G+2 Residential Building 266 Days Fri 01-12-17 Sat 06-10-18

This Gantt chart outlines the schedule for constructing a residential building with 3 floors over 266 days from January 2017 to October 2018. It is divided into 3 main sections - the structural schedule, finishing and MEP schedule, and final finishing. The structural schedule involves tasks such as excavation, laying the foundation, slab work and column erection for the ground, first, and second floors over 130 days. Then the finishing and MEP schedule involves tasks such as block work, plastering, flooring and fixtures installation for the 3 floors over 142 days. Finally, the project concludes with 20 days of final finishing and handing over the building.

Uploaded by

premsai555
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
62 views5 pages

G+2 Residential Building 266 Days Fri 01-12-17 Sat 06-10-18

This Gantt chart outlines the schedule for constructing a residential building with 3 floors over 266 days from January 2017 to October 2018. It is divided into 3 main sections - the structural schedule, finishing and MEP schedule, and final finishing. The structural schedule involves tasks such as excavation, laying the foundation, slab work and column erection for the ground, first, and second floors over 130 days. Then the finishing and MEP schedule involves tasks such as block work, plastering, flooring and fixtures installation for the 3 floors over 142 days. Finally, the project concludes with 20 days of final finishing and handing over the building.

Uploaded by

premsai555
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 5

ID Task Name Duration Start Finish December January February March

E B M E B M E B M E B M
0 G+2 Residential Building 266 days Fri 01-12-17 Sat 06-10-18

1 1 Structural Schedule 130 days Fri 01-12-17 Tue 01-05-18

2 1.1 Mobilisation of Resources 10 days Fri 01-12-17 Tue 12-12-17

3 1.2 Surveying and Marking 5 days Thu 07-12-17 Tue 12-12-17

4 1.3 Excavation 25 days Wed 13-12-17 Wed 10-01-18

5 1.4 Laying of foundation 25 days Mon 25-12-17 Mon 22-01-18

6 1.5 Plinth Beam 5 days Thu 18-01-18 Tue 23-01-18

7 1.6 Column Erection 10 days Sat 20-01-18 Wed 31-01-18

8 1.7 Backfilling 5 days Sat 27-01-18 Thu 01-02-18

9 1.8 Grade Slab 2 days Fri 02-02-18 Sat 03-02-18

10 1.9 First Floor Slab 20 days Mon 05-02-18 Tue 27-02-18

11 1.9.1 Slab Shuttering 15 days Mon 05-02-18 Wed 21-02-18

Task External Milestone Manual Summary Rollup


Split Inactive Task Manual Summary

Project: G+2 Residential Building Milestone Inactive Milestone Start-only


Date: Sat 02-12-17 Summary Inactive Summary Finish-only
Project Summary Manual Task Deadline
External Tasks Duration-only Progress

Page 1
ID Task Name Duration Start Finish February March April
E B M E B M E B M E
12 1.9.2 Slab and Beam 8 days Fri 16-02-18 Sat 24-02-18
Reinforcement
13 1.9.3 Concrete Casting 2 days Mon 26-02-18 Tue 27-02-18

14 1.10 Second Floor Slab 25 days Wed 28-02-18 Wed 28-03-18

15 1.10.1 Column Erection 10 days Wed 28-02-18 Sat 10-03-18

16 1.10.2 Slab Shuttering 15 days Tue 06-03-18 Thu 22-03-18

17 1.10.3 Slab and Beam 8 days Sat 17-03-18 Mon 26-03-18


Reinforcement
18 1.10.4 Concrete Casting 2 days Tue 27-03-18 Wed 28-03-18

19 1.11 Terrace Floor Slab 29 days Thu 29-03-18 Tue 01-05-18

20 1.11.1 Column Erection 10 days Thu 29-03-18 Mon 09-04-18

21 1.11.2 Slab Shuttering 10 days Wed 04-04-18 Sat 14-04-18

22 1.11.3 Slab and Beam 7 days Tue 10-04-18 Tue 17-04-18


Reinforcement
23 1.11.4 Concrete Casting 2 days Wed 18-04-18 Thu 19-04-18

Task External Milestone Manual Summary Rollup


Split Inactive Task Manual Summary

Project: G+2 Residential Building Milestone Inactive Milestone Start-only


Date: Sat 02-12-17 Summary Inactive Summary Finish-only
Project Summary Manual Task Deadline
External Tasks Duration-only Progress

Page 2
ID Task Name Duration Start Finish March April May June July August September October Novembe
B M E B M E B M E B M E B M E B M E B M E B M E
24 1.11.5 Over head Structures 10 days Fri 20-04-18 Tue 01-05-18

25 2 Finishing and MEP Schedule 142 days Mon 02-04-18 Thu 13-09-18

26 2.1 Ground Floor 100 days Mon 02-04-18 Thu 26-07-18

27 2.1.1 Block Work 25 days Mon 02-04-18 Mon 30-04-18

28 2.1.2 MEP Wall Conduits 10 days Wed 25-04-18 Sat 05-05-18

29 2.1.3 Plastering 15 days Tue 01-05-18 Thu 17-05-18

30 2.1.4 Wooden fixtures 20 days Mon 07-05-18 Tue 29-05-18

31 2.1.5 Painting 20 days Fri 18-05-18 Sat 09-06-18

32 2.1.6 False Ceiling 25 days Wed 30-05-18 Wed 27-06-18

33 2.1.7 Flooring 25 days Sat 16-06-18 Sat 14-07-18

34 2.1.8 MEP Fixtures 15 days Tue 10-07-18 Thu 26-07-18

35 2.2 First Floor 100 days Tue 01-05-18 Fri 24-08-18

Task External Milestone Manual Summary Rollup


Split Inactive Task Manual Summary

Project: G+2 Residential Building Milestone Inactive Milestone Start-only


Date: Sat 02-12-17 Summary Inactive Summary Finish-only
Project Summary Manual Task Deadline
External Tasks Duration-only Progress

Page 3
ID Task Name Duration Start Finish April May June July August September October
M E B M E B M E B M E B M E B M E B M E
36 2.2.1 Block Work 25 days Tue 01-05-18 Tue 29-05-18

37 2.2.2 MEP Wall Conduits 10 days Thu 24-05-18 Mon 04-06-18

38 2.2.3 Plastering 15 days Wed 30-05-18 Fri 15-06-18

39 2.2.4 Wooden fixtures 20 days Tue 05-06-18 Wed 27-06-18

40 2.2.5 Painting 20 days Sat 16-06-18 Mon 09-07-18

41 2.2.6 False Ceiling 25 days Thu 28-06-18 Thu 26-07-18

42 2.2.7 Flooring 25 days Mon 16-07-18 Mon 13-08-18

43 2.2.8 MEP Fixtures 15 days Wed 08-08-18 Fri 24-08-18

44 2.3 Second Floor 100 days Mon 21-05-18 Thu 13-09-18

45 2.3.1 Block Work 25 days Mon 21-05-18 Mon 18-06-18

46 2.3.2 MEP Wall Conduits 10 days Wed 13-06-18 Sat 23-06-18

47 2.3.3 Plastering 15 days Tue 19-06-18 Thu 05-07-18

Task External Milestone Manual Summary Rollup


Split Inactive Task Manual Summary

Project: G+2 Residential Building Milestone Inactive Milestone Start-only


Date: Sat 02-12-17 Summary Inactive Summary Finish-only
Project Summary Manual Task Deadline
External Tasks Duration-only Progress

Page 4
ID Task Name Duration Start Finish April May June July August September October
M E B M E B M E B M E B M E B M E B M E
48 2.3.4 Wooden fixtures 20 days Mon 25-06-18 Tue 17-07-18

49 2.3.5 Painting 20 days Fri 06-07-18 Sat 28-07-18

50 2.3.6 False Ceiling 25 days Wed 18-07-18 Wed 15-08-18

51 2.3.7 Flooring 25 days Sat 04-08-18 Sat 01-09-18

52 2.3.8 MEP Fixtures 15 days Tue 28-08-18 Thu 13-09-18

53 3 Final Finishing and Handing 20 days Fri 14-09-18 Sat 06-10-18


over

Task External Milestone Manual Summary Rollup


Split Inactive Task Manual Summary

Project: G+2 Residential Building Milestone Inactive Milestone Start-only


Date: Sat 02-12-17 Summary Inactive Summary Finish-only
Project Summary Manual Task Deadline
External Tasks Duration-only Progress

Page 5