G+2 Residential Building 266 Days Fri 01-12-17 Sat 06-10-18
G+2 Residential Building 266 Days Fri 01-12-17 Sat 06-10-18
E B M E B M E B M E B M
0 G+2 Residential Building 266 days Fri 01-12-17 Sat 06-10-18
Page 1
ID Task Name Duration Start Finish February March April
E B M E B M E B M E
12 1.9.2 Slab and Beam 8 days Fri 16-02-18 Sat 24-02-18
Reinforcement
13 1.9.3 Concrete Casting 2 days Mon 26-02-18 Tue 27-02-18
Page 2
ID Task Name Duration Start Finish March April May June July August September October Novembe
B M E B M E B M E B M E B M E B M E B M E B M E
24 1.11.5 Over head Structures 10 days Fri 20-04-18 Tue 01-05-18
25 2 Finishing and MEP Schedule 142 days Mon 02-04-18 Thu 13-09-18
Page 3
ID Task Name Duration Start Finish April May June July August September October
M E B M E B M E B M E B M E B M E B M E
36 2.2.1 Block Work 25 days Tue 01-05-18 Tue 29-05-18
Page 4
ID Task Name Duration Start Finish April May June July August September October
M E B M E B M E B M E B M E B M E B M E
48 2.3.4 Wooden fixtures 20 days Mon 25-06-18 Tue 17-07-18
Page 5