Chapter 12 - Superstructures: MG Latimer 12.1 Scope
Chapter 12 - Superstructures: MG Latimer 12.1 Scope
Chapter 12 - Superstructures: MG Latimer 12.1 Scope
MG Latimer
12.1 SCOPE
In the first portion of this chapter six common types of bridge decks are dealt with, each having
particular features which need to be considered and monitored. Attention is drawn to these features,
and additional explanatory information is provided where necessary. To assist monitoring staff in the
execution of their duties, the guidance presented for each deck type is arranged under separate
headings for “planning” and “construction”.
The second portion of the Chapter deals with general aspects of construction which are of particular
relevance to bridge superstructures.
As the name suggests, solid slab decks comprise of a solid section, without beams or voids. This type
of deck is commonly used in the construction of short span bridges and culverts, and is illustrated in
Photo 12.1.
The construction of solid slab decks is usually straight-forward and uncomplicated, and the formwork
is very simple to construct. Reinforcement layouts seldom result in congested areas, and the
placement of concrete should therefore present no difficulties. Concrete volumes may be large.
Photo 12.1: Soffit of cast in-situ concrete slab deck. Note untidy
construction joint line and surface blemishes.
Superstructures 12-1
12.2.2 Planning
The following points should be considered when planning the construction of solid slab decks:
• The exposed surface area of the concrete deck is usually large, and rainfall during
concreting can therefore present serious problems. Expected weather conditions should
be checked in advance and on the day of the pour.
• Plan for the possibility of plant breakdown or delays in the supply of concrete (lights
required?)
• Consider suitable positions and details for emergency construction joint in case these are
required.
NOTE
• The arrangements to achieve the required level Planning should include the
control, surface finish, and curing must be planned control of personnel access and
and agreed. movement on the deck. N.B.
Ensure that parapet starter bars
• Under unfavourable weather conditions (wind, heat)
are not disturbed or used as
some concrete mixes may be prone to plastic
hand-holds during placement
shrinkage cracking. Re-vibration of the concrete is
and finishing of the concrete
recommended.
(this is detrimental to
• Check that the provision of drip moulds at the edges anchorage and bond of the
of the deck has not been overlooked. reinforcement).
12.2.3 Construction
The standard monitoring items contained in Chapter 6 Formwork, 7 Reinforcement and 8 Concrete are
applicable. Monitoring staff should in addition pay particular attention to the following during
construction:
(a) Thick slabs impose heavy loads on formwork, falsework and falsework supports. The
construction and performance of these elements therefore deserve special attention.
(b) When pouring large volumes of concrete ensure that the supply rate is not excessive as this
leads to loss of control over the placing and compaction of the concrete.
(c) Accurate setting out and alignment of parapet starter bars is of the utmost importance. These
bars must not be disturbed during concrete placement and finishing.
(d) Check for signs of settlement cracks, and if noticed ensure revibration to eliminate these.
(e) Level control, surface finish, and curing.
Superstructures 12-2
12.3 VOIDED SLAB DECKS
Photo 12.2: Voided slab deck under construction. Tie down straps not yet installed.
12.3.2 Planning
When void formers are incorporated within concrete slab decks, both contractor and monitoring staff
should ensure that they have a sound understanding of the forces acting upon the formers, straps and
formwork during concreting. Major difficulties can arise when these forces are not satisfactorily
provided for, sometimes requiring that the entire deck be demolished and reconstructed. It is therefore
essential that the arrangement be properly designed and that the formers be sufficiently rigid, sealed
and tied down before casting the concrete.
The following points should be considered when planning the construction of voided slab decks:
(a) Tie-down of formers to resist buoyancy. Ensure that tie-down devices are:
• Properly designed.
• Tied to bearers below formwork.
• Adequately distributed along the length of the formers.
Superstructures 12-3
• Applied in a manner which will not deform or damage the formers.
• Provided with sleeves/cones to enable the ties to be removed/cut back to ensure adequate
cover to all steel. The arrangement must enable the concrete surface to be neatly repaired
and finished off.
(b) The provision of drainage holes at the low points in all void formers.
(c) Concrete should be placed and compacted in layers rather than “full depth” in order to
reduce buoyancy forces.
(d) The placement sequence and procedure must be planned and tightly controlled to ensure that
concrete below the formers is well compacted and that no cold joints develop.
(e) Ensure adequate, but not excessive, concrete supply rate.
(f) Falsework and formwork can be subjected to heavy loading.
(g) Deflection and settlement of the formwork and falsework.
(h) Large volumes of concrete may result in long concrete pours, extending into hours of
darkness. Consider the need for lights.
(i) Standard deck items (refer 12.2.2 (e)):
12.3.3 Materials
(a) Have adequate robustness and will not deform under the action of buoyancy forces and the
tie-down strapping.
(b) Will not deteriorate or soften when wet.
(c) Can resist the forces they will be subjected to.
(d) Are adequately braced to maintain their shape.
(e) Are sealed to prevent ingress of water or grout.
(f) Have adequate drainage outlets at their low points.
Superstructures 12-4
12.3.4 Construction
The standard monitoring items contained in Chapter 6 Formwork, 7 Reinforcement and 8 Concrete are
applicable. Monitoring staff should in addition pay particular attention to the following during
construction:
Cast in-situ beam and slab decks comprise of deck slabs supported by cast in-situ beams. The beams
provide the strength and stiffness required for the span, and enable the slab to be relatively slender and
economical to construct. The number of beams utilised is dependent upon several factors, such as the
width of the deck and the slenderness of the beams.
Formwork for cast in-situ beam and slab decks is more complicated than that required for solid or
voided slab decks.
12.4.2 Planning
The following points should be considered when planning the construction of cast in-situ beam and
slab decks:
(a) The design of the falsework and formwork must cater for the substantially differing load
intensities of the beam and slab portions.
(b) Casting procedure and sequence.
(c) To assist compaction of concrete in beams, the leading face of the pour should not be steeply
inclined.
(d) The concrete in the region of the web-slab junction should be re-vibrated to close settlement
cracks which tend to form at these positions. The timing of the re-vibration is critical to the
success of this exercise. Refer to Figure 12.1.
(e) Standard deck items (refer 12.2.2 (e)):
Superstructures 12-5
• Re-vibration of concrete to eliminate the possibility of settlement cracks and plastic
shrinkage cracking.
BEAM
12.4.3 Construction
The standard monitoring items contained in Chapter 6 Formwork, 7 Reinforcement and 8 Concrete are
applicable. Monitoring staff should in addition pay particular attention to the following during
construction:
Precast beam and slab decks are similar to cast in-situ beam and slab decks, but utilise precast beams
to support the deck slabs. Refer Photo 12.3 and 12.4. During concreting of the deck slab, the
formwork is usually supported by the precast beams, requiring that the precast section alone be
designed to carry the combined weight of both beam and slab.
Superstructures 12-6
Photo 12.3: Precast T-beams erected on pier.
Photo 12.4: Soffit of beam and slab deck (with transverse diaphragms)
Occasionally, designs may require that the beams be temporarily propped until the slabs have been
cast and have gained strength. Under these conditions the self weight of the slab only acts on the
structure when the props are removed, and is therefore carried by the composite (combined) beam and
slab section.
Slender precast concrete slab panels or fibre-cement boards are sometimes used as permanent slab
soffit formwork.
Superstructures 12-7
A variation of this deck type is the contiguous beam deck, in which the beams are butted against one
another to obtain a flat soffit. Refer Photo 12.5. This is commonly employed on bridges over
electrified railway tracks in order to minimise work above the exposed electrification.
12.5.2 Planning
The following points should be considered when planning the construction of precast beam and slab
decks:
Superstructures 12-8
(k) Bedding material at bearings.
(l) If permanent slab soffit formwork panels are used:
• Ensure adequate tolerance on seating area. Note that the beam spacings may vary slightly,
and that beams may not be perfectly straight. Note also that sunlight can cause lateral
temperature differentials and curvature.
• Ensure that panels are secured and cannot be displaced.
• Ensure panel seating detail incorporates a grout seal.
12.5.3 Materials
When permanent formwork panels are utilised it is advisable to consult with the bridge designer to
ensure that the details and materials are acceptable. Monitoring staff should ensure that the strength
and stiffness of the panels are adequate, and that the necessary concrete cover is obtained.
12.5.4 Construction
The standard monitoring items contained in Chapter 6 Formwork, 7 Reinforcement and 8 Concrete are
applicable. Monitoring staff should in addition pay particular attention to the following during
construction:
Superstructures 12-9
(g) Compaction and re-vibration at diaphragms to prevent settlement cracks.
(h) Control of concrete slab thickness.
(i) Control of cover to reinforcement.
(j) Level control, surface finish, and curing.
Concrete box girder decks utilise a section comprised of one or more hollow boxes (usually
rectangular or trapezoidal in shape). In its most common form, the deck has a single box (Photo 12.6
and 12.7) with cantilever slabs, but for wider bridges, the box is often subdivided into two or more
cells.
This type of deck has high torsional stiffness, and the presence of both top and bottom slabs provides
capacity for both sagging and hogging moments.
When constructing cast in-situ concrete box girder decks, the lower slab and webs are usually cast
first, followed by casting of the top slab a few days later.
Superstructures 12-10
Photo 12.7: Trapezoidal shaped box deck. Note textured surface finish
obtained using tongue-and-grooved timber.
12.6.2 Planning
The following points should be considered when planning the construction of concrete box girder
decks:
Superstructures 12-11
(m) Standard deck items (refer 12.2.2 (e)):
12.6.3 Construction
The standard monitoring items contained in Chapter 6 Formwork, 7 Reinforcement and 8 Concrete are
applicable. Monitoring staff should in addition pay particular attention to the following during
construction:
(a) Congested areas: ensure sufficient space for concrete placement and compaction.
(b) Check on concrete placement and compaction at web/bottom slab junction.
(c) Check level of bars at the top of the webs and slab as this can be critical in achieving the
required finished level of the roadway.
(d) Accurate setting out of parapet starter bars.
(e) Cleanliness of beam reinforcement before casting
top slab. WARNING
Keep a close watch over
(f) Check below deck during casting to identify compaction in the region of the
possible leakage of fines. web/bottom slab junction. Note
(g) Control of concrete slab thickness. that there is often a tendency to
undervibrate this area as the
(h) Control of cover to the reinforcement in the top vibration increases the flow of
slab. concrete from the web into the
(i) Compaction and re-vibration at diaphragms to bottom slab. Undervibration results
prevent settlement cracks. in poor compaction, particularly if
prestress tendons are present.
(j) Level control, surface finish, and curing.
Twin spine beam decks utilise two spine beams to carry the deck slab. Refer to Fig 12.2. The beams
and slab can be constructed from either reinforced or prestressed concrete.
The spine beams commonly comprise of solid concrete sections, but often utilise void formers to
reduce their cross-sectional area and increase their efficiency.
Superstructures 12-12
Figure 12.2: Twin spine beam deck.
12.7.2 Planning
The following points should be considered when planning the construction of twin spine beam decks:
(a) Falsework and formwork supporting the spine beams may be subjected to heavy loading.
(b) Deflection and settlement of the falsework and falsework supports.
(c) Precamber requirements.
(d) To assist compaction of concrete in the spine beams, the leading face of the concrete pour
should not be steeply inclined.
(e) Ensure that all concrete will be thoroughly compacted. Note that some locations may be
difficult to compact due to high concentrations of prestressing and reinforcement.
(f) The concrete in the region of the web-slab junction should be re-vibrated to close settlement
cracks which tend to form at these positions. The timing of the re-vibration is critical to the
success of this exercise.
(g) Surface preparation required at construction joints.
(h) Standard deck items (refer 12.2.2 (e)):
12.7.3 Construction
The standard monitoring items contained in Chapter 6 Formwork, 7 Reinforcement and 8 Concrete are
applicable. Monitoring staff should in addition pay particular attention to the following during
construction:
(a) Congested areas: ensure space for concrete placement and compaction.
(b) Check level of top slab bars, to ensure that the specified cover is obtained.
Superstructures 12-13
(c) Accurate setting out of parapet starter bars.
(d) Check below deck during casting to identify possible leakage of fines.
(e) Control of concrete slab thickness.
(f) Control of cover to reinforcement in the top slab.
(g) Level control, surface finish, and curing.
The importance of advance planning for the construction of bridge superstructures cannot be over-
emphasised. Monitoring staff should ensure that they are in possession of all construction drawings
and specifications, and that these are clearly understood. They are advised to actively engage with the
contractor to ensure that the necessary method statements and proposals are prepared and submitted
timeously.
Advance planning meetings between the monitoring staff and the designer can be very helpful, as
these present an opportunity to obtain clarifications and to communicate matters of importance.
Planning should consider all aspects of the construction, including falsework and formwork, casting
sequence, construction joint positions, bearings, movement joints, recesses, drainage ducts etc.
Possible requirements for approvals from railway or other authorities, and advance testing or
component approvals should not be overlooked.
The construction of bridge superstructures almost always involves working at height, and safety
aspects related to the provision of adequate safety railings, access ramps and ladders must receive the
necessary attention.
Special consideration should be given to access arrangements when working over water, and to
ensuring that both environmental and safety requirements are satisfied.
When working over roadways suitable protection measures must be put in place to safeguard motorists
or pedestrians below.
Refer Chapter 3.
The geometry of bridge superstructures is often complex, and setting out calculations and checks may
need to take account of varying crossfall, vertical and horizontal curvature, and the effects of the “tilt”
of box sections and beam webs.
Formwork levels should allow for the deflection of supporting beams or girders, as well as the
bedding-in and elastic shortening of falsework supports.
Superstructures 12-14
12.8.4 Precamber and Casting Sequence
On all but the most elementary structures it is advisable to consult the design office to confirm and if
necessary obtain approval for precamber requirements.
Reinforced concrete members usually require upward precamber to allow for downward elastic and
creep deflection. Prestressed members usually require downward precamber to allow for upward
elastic and creep deflection.
In instances where the superstructure being cast is carried by temporary girders which will deflect
under the weight of freshly cast concrete, consideration should be given to the affect that this
deflection will have on any concrete which is setting or has already set. Such concrete is prone to
cracking, as it is no longer able to deform to accommodate the changing profile caused by the
deflection. It follows that the ability of the concrete to tolerate this deflection without distress is
dependent upon the rate and sequence of casting, as well as the time at which the concrete starts to set.
An obvious further consideration is the flexibility of the supporting girders, which should be contained
within acceptable limits. These aspects should be carefully considered, and guidance obtained from
the design office where necessary.
12.8.5 Falsework
The contents of Chapter 6 : Falsework, Formwork and Concrete Finish are applicable and should be
referred to.
The following items have particular relevance to the falsework to superstructures, and should not be
overlooked:
In general, when prestressing is applied to members carried by rigid supports, the members lift off the
supporting formwork when the prestress loading is applied. When this occurs the weight of the
concrete is immediately transferred from the formwork onto the member itself, counteracting the
upward forces imposed by the applied prestressing. This behaviour enables member stresses to be
contained within acceptable limits.
However, when members are cast on formwork supported by very tall scaffolding towers or flexible
beams/girders, the elasticity of the support influences the above behaviour, and the weight of the
concrete may be only partially transferred onto the prestressed member. Unless this behaviour is
properly evaluated and accounted for, tensile stresses at the top of the member may exceed allowable
values causing cracking of the member.
Superstructures 12-15
It is therefore essential that monitoring staff are alert to the potential for such situations and consult
with their design office regarding the necessary evaluations.
12.8.7 Formwork
The contents of Chapter 6 : Falsework, Formwork and Concrete Finish are applicable and should be
referred to.
The following items have particular relevance to the formwork to superstructures, and should not be
overlooked:
(a) Bridge superstructures are usually very visible and special attention should therefore be paid
to the quality of finish, uniformity of colour and texture etc.
(b) Monitoring staff should be on the lookout for variations in the quality, texture and surface
finish of timber formwork used to form visible concrete faces. Note that the surface colour
and texture of concrete cast on “first-use” timber often differs from that of “second or third-
use” timber. This effect can result in a very “patchy” appearance.
(c) Formwork boards or panels for visible faces should be arranged in a pleasing and regular
pattern. The formwork material and panel layout should be discussed and approved well
before formwork material is ordered and delivered to site.
(d) If tongue-and-grooved timber formwork is used the concrete surface should be left “as
struck” (no rubbing).
(e) Formwork (particularly timber formwork) should be treated with care in order to prevent
damage during handling or fixing of steel reinforcement. Reused formwork should be
regularly inspected for possible defects.
(f) Note that dust, dirt and contaminants from rusting reinforcement can lead to staining of the
concrete surface. The cleanliness of horizontal formwork to exposed surfaces should
therefore be monitored, and the long term storage of reinforcement on formwork should be
discouraged.
(g) Pay special attention to the fixing, neatness and alignment of chamfer strips in all prominent
locations such as the edges of decks.
NOTE
(h) Poorly constructed construction joints can be very unsightly. Ensure that the provision
Pay attention to alignment, fixity of soffit formwork, of drip grooves near the
provision of grout seals etc. edges of decks is not
(i) Ensure that local overloading of formwork does not occur. overlooked (consult with
the design office).
12.8.8 Concreting
The contents of Chapter 8 : Concrete are applicable and should be referred to.
Superstructures 12-16
(d) Provision of sufficient experienced “finishers” to operate the screed rails and complete the
surface finishing.
(e) Consider and plan for unfavourable weather conditions (rain, wind, cold, heat). Deck
concrete should not be poured when there is a likelihood of rainfall during the casting and
setting period.
(f) Planning for possible equipment failure, concrete supply problems (availability of lights?),
emergency construction joints.
(g) Compaction at congested locations.
(h) Monitor possible leakage of fines at soffit, panel joints etc.
(i) Possible need for revibration of concrete to prevent plastic shrinkage cracking, especially
during hot or windy conditions.
Planning and construction should consider the importance of obtaining the correct deck levels,
recognising the permissible tolerances. The actual levels achieved should be checked after concreting,
as deviations from the specified levels may require that remedial work be carried out and that the
parapet levels be amended. Refer Item 12.8.13 below.
12.8.10 Curing
The contents of Chapter 8 : Concrete are applicable and should be referred to.
Prior to stressing, prestressed concrete members usually have limited resistance to cracking as these
members are young and often contain only small quantities of steel reinforcement. It is therefore not
advisable to allow the application of prestressing to be unnecessarily delayed. The design office
should be consulted for advice in situations where requirements are not specified on the drawings or in
the specifications.
12.8.12 Parapets
Parapets are probably the most visible of all bridge components, and are often viewed from close
range. Even minor blemishes and defects are therefore easily noticed. It follows that special attention
should be paid to the quality of construction, including both alignment and finish.
Superstructures 12-17
Monitoring staff should pay attention to:
(a) Provision for joints, cover plates, lighting ducts and supports etc.
(b) Both horizontal and vertical alignment MUST be very good.
(c) Correct setting out of parapet starter bars is of great importance (errors can result in lack of
cover).
(d) Concrete cover must be tightly controlled (lack of cover can in time lead to unsightly stains
and concrete spalling - both unacceptable on parapets).
(e) Chamfers, edges, alignment etc. must be carefully checked before concreting.
(f) Monitor surface finish achieved, surface blowholes etc. and take prompt action to rectify any
problems.
(g) Curing.
Superstructures 12-18
and low spots may require local asphalt levelling layer. In severe cases, a cementitious
screed may need to be applied.
(e) Concrete surface cleaning and tack coat.
(f) Monitoring the application of the tack coat to ensure that kerb/parapet is not contaminated.
(g) Approval of compaction equipment to be used on bridge deck (the operation of vibratory
compaction equipment on the deck should not be permitted, unless special circumstances
require this and the designer’s approval is obtained).
(h) Monitoring the operation of compaction equipment to ensure that kerb/parapet edges are not
chipped or damaged by steel wheels of rollers.
(i) Compatibility of materials where asphalt is in contact with sealants (isolation membranes
may be required if the materials are not compatible).
There are numerous important points to consider and monitor. These include:
Superstructures 12-19
INDEX TO APPENDICES
NOTE
For formwork, reinforcement, concrete,
prestressing, etc., the standard check-lists apply.
Superstructures 12-20
APPENDIX 12A
SUPERSTRUCTURES CHECK LIST
CONSTRUCTION MONITORING CHECKLIST
PROJECT NO. / NAME: .......................................................................................................................................
INSPECTOR’S NAME(S): ....................................................................................................................................
STRUCTURE: ........................................................... ELEMENT: ..............................................................
STATUS
ACTIVITY AND DETAILS SIGNED DATE
A B C D E F
1. ACCESS
1.1 For personnel
1.2 Control and exclusion
1.3 Traffic arrangements
2. SAFETY
2.1 Compliance with OHS & Const Regs
2.2 Safety screens, catch nets
3. FALSEWORK, FORMWORK &
CONCRETE FINISH
3.1 Chapter 6 checklist completed
3.2 Levels
3.3 Screed rails & surface finish
3.4 Temporary support requirements
3.5 Precamber
4. STEEL REINFORCEMENT
4.1 Chapter 7 checklist completed
4.2 Accurate setting out of parapet starter bars
5. CONCRETE
5.1 Chapter 8 checklist completed
5.2 Casting sequence
5.3 Revibration to close settlement cracks
6. PRESTRESSING
6.1 Chapter 9 checklist completed
6.2 Effect of elastic support
7. ANCILLARY COMPONENTS
7.1 Bearings installed correctly
7.2 Drainage pipes, ducts, attachments
7.3 Provision for expansion joints
STATUS INCLUDES
A Contractor's submission received C Inspected / Tested E Approved / Rejected
B Engineer's appraisal D Compliance Verified F Signed Off
CCP : Contractor's Competent Person
Note: Indicate N/A under Status if not applicable
Mechanically Stabilized Earth Walls And Patented Earth Retaining Systems 12-1