Big Stuff Delivering The RAPID Project
Big Stuff Delivering The RAPID Project
Big Stuff Delivering The RAPID Project
Presentation by:
KC Low
Head, Corporate Strategy
& Business Development
Johor Port Berhad
Johor Port Berhad
A Multi Purpose Port with 24 dedicated Berths for different Cargo Types and hosts a total of 4.9 km of berthing space.
Handles Container, Edible and Non-Edible Liquid Bulk, Dry Bulk, Break Bulk and specialized Project Cargo.
Total area of 1,000 acres, 660 acres of which are designated as Free Zone.
Johor Port Water Limits
>40
EPC PACKAGES
>200
UIO SUBCONTRACTORS &
>60,000
MANPOWER
~350Million
PROJECT MANHOURS
PROCUREMENT PACKAGES AT PEAK
EXECUTED
CONCURRENTLY
PIC / RAPID
x 3,500What are the QUICK
Football Fields
logistical
FACTS challenges
x9
for
PETRONAS Twin Towers
a project
Electrical & Instrumentation Cable
20,000 km
of this scale?
Structural Steel
North Pole 160,000 mt
384,550
1,000,000 351,307
SHLO
HLO
By RAIL (KM)
Johor Port to
Pengerang
Overhead pipe rack at KM5. 5 Toll Plaza Cahaya Baru at KM8.5 / E22 Flyover at KM28.4 by land
(Jalan Pekeliling Pasir Gudang) Toll Plaza Penawar at KM50
Sg Johor Bridge at KM40 Electricity & Telekom hanging Small town, villages & schools along
cables at KM60 road to RAPID site at KM50 - KM70
Road Challenges & Obstacles
Route distance is around 144 KM
Skudai Flyover at KM17 Taman Perling flyover at KM25 Lima Kedai flyover at KM30
Overall Logistics Challenges
Logistics Risk Analysis
Identified Risks
HSSE issues
Breakdown of a Siemens cargo truck resulted in a 8 km traffic congestion
Main MOLF readiness
HSSE issues
Feeder
Barge
PSA JPB MOLF
Ramunia
Vessel
------------- RAPID Site
MOLF
Vessel Setapa
PTP Barge Shipping Agent
Online transaction through Port System
Vessel (VCS and MSS) for:
Overseas On Dock / Off Dock Vessel Clearance
Berth Application
Forwarding Agent
Online transaction through Custom & Port
System (MPTS) for:
Cargo Clearance
Vessel / Barge Handling operation management
Site Area Plan
MOLF
Ramunia
MOLF
Setapa
MOLF Ramunia & MOLF Setapa
MOLF Ramunia has ceased operations as of July 2017 and all Solid Product Jetty
Barges / RORO Barges / Vessels are now being redirected to MOLF
Setapa.
MOLF Setapa will be converted into a Solid Product Jetty to cater for
the future exportation of the petroleum products from the PIC /
RAPID.
Presentation by:
Peter Roland
Managing Director
BBC Chartering Japan
RAPID BBC Chartering
1 year development
Cargo Type
18%
39%
30%
13%
Heavy Lift
Range 85-400mts (Cold box 400mts)
No specific issue
RAPID BBC Chartering
Conclusion
BIG STUFF : Delivering The RAPID Project
Presentation by:
Mike Schoofs
General Manager, Regional Project Division
deugro (Singapore) Pte Ltd
RAPID deugro group
Initially supported the FEED stage with various transport and feasibility studies, as well as budgetary pricing
Since then involved with various EPC packages within the project for Arabian, Japanese, Korean, Taiwanese
and Thai EPC contractors
Packages handled:
Steam Cracker Complex
Utilities for Steam Cracker Complex
Residue Fluid Catalytic Cracking-, LPG Treating-, Propylene Recovery and Caustic Neutralization Units
Amine Recovery, Sulfur Recovery, Sour Water Stripping, Liquid Sulfur Storage
Successfully executed shipments of more than 500000 FRT in total with Heavy Lifts up to 350 tons
RAPID deugro group
Heavy Lifts: 04 x Spent Catalyst Hoppers = L 45.02 x W 8.09 x H 8.72 m @ 348.0 tons each
02 x Fresh Catalyst Hoppers = L 40.37 x W 7.27 x H 7.87 m @ 185.9 tons each
03 x Drums up to = L 23.23 x W 7.89 x H 8.62 m @ 141.4 tons each
06 x Drums up to = L 19.85 x W 5.93 x H 7.97 m @ 87.0 tons each
Cargo readiness and project schedule made it necessary to ship all cargo on one vessel
Floor Space:
Weather Deck : 3067 sqm
Tween Deck : 2275 sqm
Tank Top : 1344 sqm
THANK YOU!!!