Katy Freeway Corridor Flood Control Study
Katy Freeway Corridor Flood Control Study
Katy Freeway Corridor Flood Control Study
EXECUTIVES~ARY
There are a number of drainage and flood control problems in the Buffalo Bayou
watershed, including problems with the Addicks and Barker reservoir systems. Of primary
concern is the fact that the reservoirs do not function as originally intended which translates into
increased risk of flooding upstream of the reservoirs and less protection downstream. As
development continues behind the reservoirs, there is the potential to expose as many as 25,000,
homes and businesses in the reservoir fringe areas to flooding.
, Buffalo Bayou has its own problems in that the reservoirs do not completely protect
downstream development along the bayou from flooding. Due to the unique environment of the
bayou, it is not practical to increase its flood control capacity, and land for flood control storage
is generally not available. In addition, many of the tributaries which drain to Buffalo Bayou from
the riorth are generally inadequate, environmentally sensitive, and capacity cannot be increased
due.to potential flooding imp~cts on Buffalo Bayou. Land development along the tributaries also.
makes storm water detention storage infeasible.
There are a number of. possible ways to address the reservoir system Is inadequacies,
including: controls on upstream development; modifications within the reservoir; increasing
reservoir outfall capacity (to Buffalo Bayou or elsewhere); living with the problem and the
potential damages.
One of the more promising possibilities involves the creation of additional reservoir outfall
capacity by building a closed conduit .s ystem (culverts) down the Katy Freeway corridor. The
Texas Department of Transportation has purchased the adjacent railroad corridor and is currently
reviewing the transportation needs of the combined corridor from the Brazos River to downtown
Houston. Major reconstruction of the freeway system would provide a unique opportunity to
include a flood water conveyance system that could address many if not all of the Buffalo Bayou
system Is drainage and flood control problems. The box culverts along the corridor could .allow
increased discharge from the reservoirs, intercept increased runoff from tributaries of Buffalo
Bayou, divert flood waters from Buffalo Bayou, and provide drainage and flooding impact
mitigation for the highway project.
A conceptual review of the system shows that it may work and would cost several hundred
million dollars ($325 to $400 million). The potential flood control problems are severe enough
to consider this magnitude of project, and the major trans~ortation construction in the Katy
Freeway corridor presents a unique, once-in-a-lifetime opportunity to consider this type of flood
control option. To determine if a conduit system under the freeway is justified, it needs to be
evaluated against other options.
... ;
Katy Freeway Corridor Flood Conrrol Sn1dy
INTRODUCTION
The Harris County Flood Control District (HCFCD) has completed a. preliminary
investigation to assess the technical merits of constructing a large flood control bypass conduit
within the Katy Freeway right-of-way from the Addicks and Barker Reservoirs to a discharge
point near downtown Houston. The primary reason for constructing a bypass conduit is to
increase reservoir outlet capacity and drain the reservoirs more efficiently. Secondary reasons
include providing flood relief to those areas located north of the Katy Freeway in the Buffalo
Bayou watershed, reducing flood flows on Buffalo Bayou, and protecting Buffalo B3:you from
environmentally damaging reservoir discharges.
, Over the past several years, the concept of constructing a flood control bypass conduit
within the Katy Freeway/railroad right-of-way has been discussed. The concept recently surfaced
again during a series of public information meetings for the Texas Department of Transportation Is
(TxDOT) Major Investment Study (MIS) of the Katy Freeway corridor. TxDOT is currently
conducting a MIS to assess future transportation needs for a 40-mile section ofiH-10 from the
Braios River to downtown Houston. Alternative transportation plans are being developed an~
screened considering transportation needs to the Year 2020. The MIS will culminate with
selection and recommendation of a transportation plan for implementation. TxDOT's current
schedule is to begin major construction of the new IH-10 transportation facilities in Year 2001.
Problem Statement
.
The primary flood threat facing the citizens of west Harris County and west Houston comes
from the inability to drain the Addicks and Barker reservoirs in an efficient manner. The
maximum flood pool levels of the Addicks and Barker reservoirs extend far beyond the limits of
the government owned land. There are currently 6,000 structures and more than 8,000 acres
within the reservoir "fringe" areas between the limits-of the government owned land and the extent
of the Addicks and Barker maximum flood pools. While 6,000 is a large number, projected
growth rates for west Harris County could easily increase the number of structures in the fringe
to 25,000 or more. Delineations of the Addicks Reservoir and Barker Reservoir fringe areas are
shown in Appendix A.
The addition of gates to the reservoirs I original uncontrolled outlet design, and the
necessarily restrictive gate operations criteria used by the Corps of Engineers has limited the
ability to empty the reservoirs in an efficient manner. Under the original design of the reservoirs
with free outflow conditions, it would have taken a storm of unusually large magnitude to .threaten
properties not acquired by the federal government. However, under current conditions wi.th the
addition of gates and the restrictive operations criteria, it no longer takes an extreme storm. Just
a wet period, consisting of a series of "normal" frequent storms (like the rainy period between
November 1991 and June 1992) is enough to "ratchet" reservoir levels upward and severely flood
private properties.
;
Katy Freeway Corridor Flood Control Sn1dy
Flooding problems also exist downstream of the reservoirs. Buffalo Bayou has an
extensive flood plain due to limited flood carrying capacity. Flood control alternatives to address
flooding along Buffalo Bayou are limited due to the desire to preserve the bayou's unique
environmental characteristics, and the scarcity of available land for siting traditional detention
basins. Flood carrying capacities of the tributaries located to the north of Buffalo Bayou are also
inadequate. Like Buffalo Bayou, there are not many feasible flood control alternatives to solve
tributary flooding because of limited available land for detention, environmental concerns, and the
inability to increase tributary capacities without transferring the flood problems downstream to
Buffalo Bayou.
Several alternatives (and combinations thereof) in addition to the Katy Freeway Corridor
bypass conduit can be imagined to address the flood problems associated with the reservoirs.
Some of these include:
Increasing flood releases from the reservoirs by changing the gate operations and
providing for increased outflows to Buffalo Bayou;
Adopting a flood warning and evacuation plan for reservoir fringe properties;
While all of these are potentially feasible ideas, providing additional reservoir outlet
capacity by way of a Katy Freeway corridor bypass conduit is really the only alternative that
addresses the secondary flood problems existing in the Buffalo Bayou watershed. Constructing
the Katy Freeway corridor conduit would provide opportunities to be environmentally sen~itive,
while addressing inadequate reservoir outlet capacity, problems along Buffalo Bayou, and the
inadequacies of the northern tributary' drainage system.
Is the Katy Freeway corridor bypass conduit the "right plan?" Does it make sense to build
urban transportation and flood control infrastructure within one corridor? The answers to these
questions will come from a full scale feasibility level study. A feasibility level study is needed to
screen all of the alternatives, and develop the best flood control plan for implementation. A
unique opportunity currently exist to coordinate construction of a flood control conduit with
construction of the Katy Freeway transportation facilities, but the aforementioned questions need
to be answered. The time to conduct a feasibility study is now, while coordination with TxDOT
is still possible.
Study Area
Figure 1 illustrates the study area for this investigation which includes: the Addicks
Reservoir watershed (136 square mile drainage area), the Barker Reservoir watershed (130 square
miles), and the Buffalo Bayou watershed (101 square miles). The study area is located generally
in west Harris County, however, portions of the Addicks Reservoir watershed extend into adjacent
Waller County, and portions of the Barker Reservoir watershed extend into Waller and Fort Bend
counties.
The Buffalo Bayou watershed is heavily developed (approximately 80%) and encompasses
primarily incorporated jurisdictions including the Memorial Villages, and portions of the City of
Houston. In contrast, the Addicks and Barker watersheds are considerably less developed
(approximately 30%) and are primarily unincorporated.
-
The Corps of Engineers was given Congressional authorization to construct the Addicks
and Barker reservoirs as part of the Buffalo Bayou and Tributaries, Texas Project by the Rivers
and Harbors Act of June 20, 1938. The authorization was prompted by the devastating flood
events of 1929 and 1935. The intent of the authorization was to construct a project to protect the
City of Houston and the Houston Ship Channel. Part of the authorization provided for
construction of the Addicks and Barker dam facilities, a channel project to enlarge and straighten
Buffalo Bayou downstream of the reservoirs to a point where a diversion canal would convey flood
waters to Galveston Bay, and a levee along Cypress Creek to block overflows into the Addicks
Reservoir watershed. The detailed plan was approved in 1940. Construction of Barker Reservoir
was completed in 1945. Addicks Reservoir and the 7.4 miles of outlet channel were completed
in 1948. The diversion canal and the levee along Cypress Creek were never constructed.
Each reservoir was intended to have five outlet conduits (four ungated and one gated) with
a total combined uncontrolled design flood discharge of 15,700 cubic feet per second (cfs). The
reservoirs were originally designed to remain dry most of the time, and not store water for
prolonged periods.
The federal government acquired property for the reservoir projects at an elevation three feet
above the pools that would have been produced had the 1935 storm event been centered over each
of the reservoir watersheds. This resulted in land acquisitions 5.9 feet below the maximum flood
control pool of Addicks Reservoir, and 8.7 feet below the maximum pool of Barker Reservoir.
The purchase of_land in this manner created a zone of land or "fringe" area upstream and
adjacent to the reservoirs that was not purchased by the federal government but, could indeed flood
given the height of the dams relative to these upstream areas. At the time, potential inundation of
the fringe areas caused little concern and was viewed as an acceptable low risk for the government
to incur. Since the fringe areas were primarily either agricultural land or undisturbed prairie land,
the government presumed that damages resulting from inundation would be minimal.
Existing Conditions
Today, conditions are quite different. To begin with, the Corps of Engineers have added
gates to all of the outlet conduits at both Addicks and Barker Dams to regulate reservoir discharges
into Buffalo Bayou. The Corps dev~loped and currently use a gate operations criteria to determine
how much and when to open the gates. The criteria takes into account reservoir conditions (quantity
of inflows to the reservoirs and the rate at which the reservoir pools rise), flooding conditions
downstream along Buffalo Bayou, and predicted conditions from weather forecasts. During dry
weather conditions, the Corps will release a maximum flow of 2.000 cfs measured at .Piney P0int
Road. During wet weather conditions. when rain is forecasted to occur. the gates are closed. The
;
Ka!Y Freeway Corridor Flood Conrrol Study
gates remain closed until flow conditions in Buffalo Bayou and weather forecast permit reservoir
releases.
The addition of gates and the restrictive operation criteria to limit reservoir discharges causes
water to be stored in the reservoirs for longer durations than the original designers ever intended.
There is now cause for concern about the prolonged pending time in the reservoirs and with the fact
that the maximum pool levels of both reservoirs extend far beyond the limits of the government
owned land. There are ~,600 acres of land and approximately 6,000 structures within the fringe areas
of Addicks and Barker reservoirs. The fringe area adjacent to Addicks Reservoir encompasses 4,000
acres of land with approximately 5,000 structures, while the fringe area adjacent to Bar~er Reservoir
encompasses 4,600 acres of land with approximately 1,000 structures.
Flooding of fringe area structures and properties from high reservoir pool levels would be
different than the type of riverine flooding typically experienced in this region. Flood levels would
not recede over the course of several hours like typically experienced with flooding from channels,
in fact, fringe area properties could be inundated for an extended period because of the restrictive
gate operations criteria. The types of problems encountered due to the inability to draw the reservoir
pools down would be much more severe than those that occurred when the reservoirs reached record
levels in March 1992. Not only would public park and transportation facilities be severely impacted
from prolonged storage of water, but structures, including homes would also be impacted. As it was,
the closure of State Highway 6 during a 10-day period in early March 1992 affected 37,000 vehicles
per day. "'
Considering the original design of the reservoir and outfall facilities and the project's remote
rural location; the land acquired by the government was probably an adequate amount, and potential
flooding of the fringe areas was probably an acceptable low risk. However, some 50 years later, with
the addition of gates and the restrictive operations criteria to limit reservoir discharges and the
substantial amount of urban developments now occurring in both the fringe areas and throughout
both of the watersheds, the project's original design parameters and assumptions are severely
outdated and invalid.
Table 1 is a summary of physical data for Addicks and Barker reservoirs. Among other
pertinent data, Table 1 shows the limits of the government owned land in terms of surface area. The
federal government owns 12,460 acres at the Addicks Reservoir site and 12,060 acres at the Barker
Reservoir site. However, the limits of the maximum pool for Addicks and Barker reservoirs are
16,423 acres and 16,739 acres, respectively. Figure 2 is a graphic illustration of critical reservoir
levels.
;
Katy Freeway Corridor Flood Conrrol Sn1dy
TABLE 1
Addicks and Barker Reservoir Data
R irs
Addicks Barker
;
Katy Freeway Corridor Flood Conrrol Smdy
Figures 3 and 4 show the relative amount of storage volumes (converted to inches of runoff
from the watershed) for some of the critical reservoir levels. For example, approximately 12 inches
of runoff from the Barker watershed are required to reach the limits of the government owned land,
and 30 inches of runoff are needed to reach the maximum pool level. The record level for Barker
occurred from a net accumulation of 10 inches of runoff over a three month period. Similarly,
Figure 4 demonstrates relative amounts of storage volumes for Addicks Reservoir.
Reservoir Analysis
An analysis was conducted to illustrate how storage levels in the reservoirs fluctuated over
the period from December 1, 1991 through June 30, 1992. Figures 5 and 6 demonstrate the
reservoirs' storage volume fluctuations in terms of inches of runoff. The amount of water stored in
the reservoirs reached record levels in early March 1992 (March 6 for Barker and March 9 for
Addicks). The figures illustrate that over a two-week time frame beginning in mid-December, runoff
resulting from a number of small rainfall events filled Barker to a storage volume equivalent to about
six inches of runoff, and Addicks to a storage volume of about eight inches of runoff. Once the
reservoirs were filled to this capacity, subsequent "normal" and frequent rain storms coupled with
the restrictive gate operations criteria "ratcheted" the amount of water in the reservoirs upward until
record capacities and pool levels were reached in early March.
It is conceivable and not hard to imagine that a single storm event could have a catastrophic
impact to several thousand people in the reservoirs and the fringe areas. But, it's just as important _,
to realize that a rainy season consisting of several "normal" rain storms (like the period from
December 1991-March 1992) could be just as catastrophic because of the ratcheting effect. When
the reservoirs store water for extended periods, fringe area properties are at greater risk from
additional normal rains or a moderate single event pushing reservoir pools upward to damaging
levels.
To illustrate this, an analysis was conducted to demonstrate and compare flood conditions
that would have occurred in the reservoirs from, first, a period of multiple normal rain storms over
the Addicks and Barker watersheds, and second, from centering a large single event storm system
over the watersheds. The December 1991 to mid-March 1992 storm period (including the event of
March 4, 1992, which was actually centered 10-miles to the east of Addicks and Barker reservoirs)
was analyzed to simulate the effects on the reservoirs from multiple storms. The October 15-18,
1994 storm event, which was actually centered 20-miles to the north of Addicks and Barker
reservoirs, was used to simulate the effects of a large, single event storm system.
Assumptions were made regarding overflows from. the Cypress Creek watershed to the
Addicks Reservoir watershed and the available reservoir storage capacities at the start of each storm.
The analysis assumed that no overflows occurred from Cypress Creek to Addicks Reservoir, and that
the reservoirs were empty at the onset of the October 1994 storm. For the multiple event storm
analysis, simulating the December 1991 to mid-March 1992 storm period, actual reservoir pool
levels were used.
Results of the analysis indicate that either storm system centered over the Addicks and Barker
watersheds would have caused pool levels to surpass record flood levels and severely impact several
thousand people and several public facilities in both the reservoirs and the fringe areas. The results
of the analysis are shown in terms of reservoir pool levels on Figure 2 (labeled "shifted storm;'), and
shown in terms of resulting storage volumes on Figures 3 and 4. Tables 2 and 3 provide a
comparison between the levels that resulted from the actual storm events and the levels that would
have occurred had the storms been centered over the Addicks and Barker watersheds.
For the multiple storm scenario analysis using the December 1991 to mid-March 1992
rainy period and centering the March 4, 1992 storm event 10-miles to the west of where it actually
occurred, Addicks Reservoir would have reached a pool level 3.8 feet higher (Elevation 104.4)
than its record level-(Elevation 100.6) and Barker Reservoir would have reached a pool level 2.3
feet higher (Elevation 98.2) than its record level (Elevation 95.9).
For the single event storm scenario analysis centering the October 1994 storm system over
the Addicks and Barker watersheds (20-rniles to the south of where it actually occurred), Addicks
Reservoir would have reached a pool level 10.7 feet higher (Elevation 111. 3) than its record level
and Barker Reservoir would have reached a pool level 8.4 feet higher (Elevation 104.3) than its
record level.
The analysis indicates that storm events typical of the Gulf Coast region, coupled with the
inability to empty the reservoirs in a timely manner because of restrictive gate operations, can
cause reservoir pool levels to:
rise over the course of several days from a large single storm event; and
be ratcheted upward over several months from a series of "normal" frequent rain
events.
;
Katy Freeway Corridor Flood Control Smdy
TABLE2
ANALYSIS OF MARCH 4, 1992 STORM
(MULTIPLE EVENT STORM SCENARIO)
Reservoir
Addicks Barker
TABLE3
ANALYSIS OF OCTOBER 15-18, 1994 STORM
(SINGLE EVENT STORM SCENARIO)
Reservoir
Addicks Barker
Existing Conditions
There are several constraining factors related to flood control and drainage in the Buffalo
Bayou Watershed downstream of the reservoirs. To begin with, Buffalo Bayou is subject to flooding
even without the influence of reservoir discharges. The large drainage area combined with limited
channel capacity, results in a 100-year flood plain covering approximately 3,000 acres and affecting
about 3,000 structures.
The watershed is divided by the Katy Freeway corridor transpottation facilities . Historically,
storm runoff from the northern sections of the watershed drained relatively unimpeded to Buffalo
Bayou by way of several major tributaries including Turkey Creek, Rummel Creek, Soldiers Creek,
and Spring Branch. As the watershed developed and the Katy Freeway corridor transportation
facilities (freeway lanes, frontage roads and railroad) were built, culverts and drainage structures
were constructed to bridge the tributaries. Today, stream capacities and drainage structures do not
meet current desired levels of service and storm water drainage from north of the transportation
corridor to Buffalo Bayou has become restricted.
The area located to the north of the Katy Freeway and railroad right-of-way has a number of
flooding and drainage problems. The flood control options for this area are limited. Detention
--... basins are used throughout Harris County to store flood waters in areas without adequate channel
capacity. In the case of Spring Branch and adjacent communities north of the Katy Freeway,
detention basins are not practical alternatives due to the scarcity of available vacant land.
Channelization is also a typical flood control measure used to efficiently convey storm water away
from areas that flood. However, in this case, channelization of the northern tributaries without
. mitigating detention would merely transfer the flooding problems downstream toward and/or to
Buffalo Bayou.
Environmental Aspects
Many natural processes take place along the riparian corridor of Buffalo Bayou. The fluvial
geomorphological process or the bayou's desire to equalize water flow and sediment transport is no
exception. There are numerous bank failures along Buffalo Bayou due to the fluvial process.
Erosion of material at the toe of the side slopes and the transport of stream bed material cause bank
failures to occur in several different modes.
One theory faults sustained reservoir discharges for some of the bank failures. Water levels
in Buffalo Bayou due to reservoir releases are typically much higher than normal base flow levels.
The sustained higher water levels tend to kill vegetation making the banks of the bayou more
susceptible to erosion. Bank saturation at higher than normal water levels and the drawdown effect
as reservoir releases are lowered, have the potential to weaken the structural integrity of the channel
banks causing failures to occur. While reservoir discharges are not the only factor influencing the
erosion process, the ability to consistently maintain the bayou's normal base flow level would sustain
vegetation growth resulting in more stable slope conditions.
. _ . /- 0
;
Katy Freeway Corridor Flood Control Sn1dy
The conceptual plan derived during this preliminary investigation is illustrated on Figure 7.
The plan consists of a conduit structure extending approximately 12 miles from the reservoirs to an
outfall or discharge point near downtown Houston. Figure 7 shows the conduit outfall point at
White Oak Bayou, but other alternative outfall points, like at the Ship Channel, may be feasible. The
structural configuration consists of multiple box structures buried underneath the Katy Freeway
transportation facilities. Two alternative structures were sized for discussion purposes, and it was
found that either 8- 12-foot by 12-foot boxes or 6 - 14-foot by 14-foot boxes would be adequate to
convey reservoir discharges of about 8,000 cfs (approximately one-half of the Corps' original outfall
design capacity for the ungated reservoir outlets). An optimization analysis would need to be part
of a full feasibility study to determine the conduit size that would be appropriate.
Operation of the reservoir-conduit flood control system would likely be required and is a
factor that needs to be considered. Reservoir releases would be made after the threat of downstream
flooding has passed. That is, after the tributaries north of Buffalo Bayou have drained, and after the
downstream outfall channel has receded. Between periods of reservoir releases, the conduits would
be used to provide volume (approximately 200 acre-feet for each 12-foot by 12-foot box structure)
for storm water storage.
an inlet design for the conduit to provide a safe means to capture reservoir
discharges;
a way to intercept some of the lateral drainage cha1U1els and re-route others to
provide drainage and flood control outfall to the areas north of the Katy Freeway
transportation facilities;
avoiding adverse impacts to the rece iving channel and areas downstream; and
disposal of the excess material left over from the excavation operation .
Preliminary estimates suggest a construction cost for the bypass conduit on the order of
$325 million. The cost estimate takes into account labor and materials for construction of the
bypass structure, excavation, sub grade and foundation preparation, backfill, and 10% for
engineering. The estimate does not specifically account for utility relocations; transportation
facility relocations; lateral channel modifications; or inlet, outlet, and receiving channel features.
Additionally, the estimate does not specifically account for the cost savings of constructing the
bypass conduit in conjunction with construction of the transportation facilities. A detailed cost
estimate is needed for consideration of all these factors and should be part of a full scale
feasibility level study.
An economic analysis is also needed to quantify all the flood damage reduction benefits,
but it is conceivable that under existing conditions in the reservoir fringe areas, on the average of
$10,000 of damage per structure and per flood occurrence (or $60 million total per flood
occurrence) could be prevented by constructing the bypass conduit. Future damage reduction
benefits would increase as the fringe area develops and could easily reach the $250 million to $300
million total level per flood occurrence assuming 25,000 structures ultimately occupy the fringe
area. Other benefits to consider include preventing closures of transportation facilities (mainly
State Highway 6, but also Eldridge Parkway, Clay Road, Barker Cypress Road, and Westheimer
Parkway), and flood damage reduction in the Buffalo Bayou watershed.
t',
The Addicks and Barker reservoirs-Buffalo Bayou flood control system has never been
constructed to completion, and because of this, Buffalo Bayou lacks adequate outfall capacity to
convey unregulated reservoir discharges. The addition of gates to the outlet conduits and the
restrictive operations criteria cause prolonged storage of water, thus, increasing the risk of flooding
to reservoir fringe area properties. Buffalo Bayou has an extensive 100-year flood plain, and there
are several flooding and drainage problems throughout the Buffalo Bayou watershed, including those
areas located north of the Katy corridor transportation facilities.
This investigation concludes that construction of a bypass conduit offers an opportunity to:
drain the reservoirs faster, reducing extended risk to fringe area properties; .
address the drainage and flooding problems in the areas of the Buffalo Bayou
watershed located north of the Katy Freeway corridor transportation facilities;
reduce flooding on Buffalo Bayou because the tributaries draining from the north
could be intercepted; and
- eliminate and/or reduce the need to structurally modify Buffalo Bayou to increase
conveyance capacity.
Because major reconstruction of the Katy Freeway corridor transportation facilities presents
an opportunity to address the inadequacies of the reservoirs as well as many of the flooding problems
throughout the Buffalo Bayou watershed, it is recommended that a full scale feasibility study be
conducted now to evaluate all the options and select the best flood control alternative for
implementation, while coordination with TxDOT' s construction schedule is still possible.
4
-...
e
..-
I 8
AD DICKS
BRAYS
, BAYOU
SBIF"l'ED STORM:
.._...._ OCTOBER 1994
0 ..... .. 11
SHIF"l'ED STORM:
OCTOBER 1994
BARKER AD DICKS
RESERVOIR RESERVOIR
71.1'
0 ................ 7
35
~ 30
~"
p-.. 25
~~
0 ~
~& 20
rll~
t!J II
<~ 15
=i
o.!!
E-t'"" 10
UJ
5
0
RECORD 100-YR LIMIT OF MA.XDIUM SHIFTED SHIFTED
3/6/92 GOVERNMENT POOL STORM STORM
LAND 10/94 3/92
35
li1 30
~"
t;-.c 25
..:~'0
0 a
~i 20
lil'O
t!J
< liD
15
~i
os
Eo"" 10
rn
5 ..
0
RECORD lOOYR LIMIT OF MAXIMUM SHIFTED SlllP'TED
3/6/92 GOVERNMENT POOL STORM STORM
LAND 10/94 3/92
FIGURE 4
j l
( (
10 -- - - - - - - -- - - -- - ---.------ -
""\ .
A \
,
A .-
'V\1'~ \
I' ~f'v\u
, \~ ...
J y'~ '\
l \
\ ,.,.,....__
~
2
'\
~
I
\
\
.,
rv '--"J
0
DEC JAN FEB MAR
DATE
APR MAY JUN
' JUL
10
9
~
~'"'
t:Jt
~ 0
0 ~
8
7 - - - - - t - -- -- - - - + -- - - ----1-
r
--'"---1-------1-------1-------1
>~
~~
0 Ill
6
6
1"'\n. rv-v". .~ \
<~
= 4
0
DEC
,-v
--~~--~---~---~--~'~
MAY JUN
I \ ' JUL
DATE
KATY FREEWAY CORRIDOR
FLOOD CONTROL STUDY
HARRIS COUNTY FLOOD CONTROL DISTRICJl'
PLANNING DEPARTMENT
ADDICKS RESERVOIR
STORAGE VOLUME
DECEMBER 1991 JULY 1992
4 / 01 /96
kl:\ l:fco\ r raph.d r FIGURE 6
1 0 1 a
:MAXIMUM POOL
FLOOD PLAIN
.
. r--- ..
I
r ._:-~
. -~~-
'.,
~ ~
I .
- r.
CONCEPTUAL PLAN
4/29/96
klc\l:f<:o\IIOdar...dt FIGURE 7
ao
E 6!0 ~~ =
0
=
z 0
~ ~~ z
. zm f!i~
)
t= ~ < <
::s fJ;1 rn o . E-4 0~ ~
~
~
~ ~
0 fJ;1
('!) e ~
=
~
~
t.Q
,:QfJ;:I
=~
:so
0 . .....
Z
=
~
~ ZE-4 ~
~ ~
0
~ rn 0
.....
~~ ~ ia e
rn E-4 t.Q
t:r.1
..:I ~ <
~ ~ =
Et =Et
13;1
~ t.Q
0
13;1
<
0
r:z:!i
e:Qt.Q ~~ ~
~
.....
fll
110
.A - ~- 110
100 ( !\) . A A
L .j . .
"
. 100
,..m
" "\, ~ .
....,... ~ ,.
~ ~
90 ~- MA'l'
~ .90
. .'<~
-~
.1-10
I'- \ ~
,.
8.0 .
- ....
- . .
'
.80
u-
R ..14'~ y_., Jl
-'~-~
~... w~
v ~
Mlr'T' RR
70.
lnRAINH:;~
IJnor.....
~.
.....
\1 . \ CROSS.ING
STRU<~URES - r--1 ~
60
50 50
. 40
Bn 1
O;!kJOR
30
. 470' RO.W.
. 10
CONCEPTUAL CBOSSSECTION
35000 30000 25000 20000 15000 10000 5000 000
. :
z ~
~~
~~
~~
UJ~
~0
uz
~~
0~
~~
. \..,_.
(, : I
( (
..
BARI<ER RESERVOIR
FRINGE AREA MAP
15600 Special Considerations for FEMA Public Assistance Projects
Lesson 3: Hazard Mitigation
Content Overview
The information below elaborates on what you heard and saw in the video portion of this lesson.
Hazard Mitigation
As stated earlier, hazard mitigation can be defined as any action of a long-term, permanent nature that
reduces the actual or potential risk of loss of life or property from a hazardous event.
0 elevating a structure.
0 strengthening existing foundations, floors, and walls to withstand stress.
0 making utilities, structural components, and contents resistant to damage.
FEMA has two primary hazard mitigation programs: Public Assistance hazard mitigation (known as
Section 406 mitigation) and the Hazard Mitigation Grant Program (also known as Section 404
mitigation.) The numbers refer to the relevent sections of the Stafford Act. The objective of both
programs is to prevent future loss of property and lives.
It is helpful to understand the similarities and differences between the two types of mitigation. There
will be times when you will need to work closely with mitigation personnel or be asked by applicants to
explain these similarities and differences.
Examples of Section 406 mitigation include (but are not limited to):
0 Seeding
0 Floodproofing buildings
0 Construction of low-level rig dikes
0 Abandonment
0 Use of flood-resistant materials
0 Use of shields, flood barriers, or sealants at doors and windows
0 Installation of hurricane shutters
0 Elevation of mechanical equipment and utilities
0 Elevation of the building
0 Installation of anti-backflow devices on floor drains
0 Floodproofing of utilities
0 Placement of utilities on bridges instead of channel bottoms
0 Encasing utilities or constructing low head dams for protection
0 Installation of flapgates on storm sewer outlets
0 Elevation of controls and motors at lift stations
0 Use of submersible pumps
0 Use of shields or sealants
0 Floodproofing of bridges and culverts
0 Clear spans instead of multispans
0 Low water crossings instead of bridges
0 Installation of cut-off walls or headwalls on culverts
0 Increasing hydraulic capacity
0 Flared end sections
0 Use of disaster-resistant materials
0 Abandonment or consolidation
0 Lower abutment footings
0 Use of tie-downs on bridge decks
0 Installation of jump spans instead of replacement of embankments
D Redune the risk: 0f future damage, ha!idshipt loss., or sutffeting as-a result of major disasters by
providing substantial financial support to implement cost-effective, post-disaster state and local
hazard mitigation measures.
D Provide funding for mitigation measures identified through the post-disaster hazard mitigation
plan required of state and local governments as a condition of receiving federal assistance.
The objectives of the program are to encourage state and local governments to:
D Identify and implement cost-effective mitigation measures that will reduce future disaster
losses.
D Coordinate mitigation needs with existing state and federal efforts.
JO Capitalize on previous mitigation planning efforts to maximize the financial opportunities
available.
PROGRAM GUIDELINES
The Hazard Mitigation Grant Program is available following a disaster declaration. The program. is
anaged by the state. Applicants, primarily local governments and non-profits, put together projects
'" and submit them to the state. The state prioritizes the projects based on its Hazard Mitigation Plan,
ranks them, and recommends them to FEMA for funding, if so desired. FEMA does a final eligibility
determination, an environmental review, and a benefit-cost analysis to ensure cost-effectiveness.
The amount of funding is based on the federal expenditures during the disaster response and recovery.
The federal share of the grants cannot exceed 15 percent of the total federal expenditures.
FEMA may contribute up to 75 percent of the costs approved for funding. The state and/or local cost
share, which must be not less than 25 percent, may be met with cash or in-kind contributions.
- ELIGIBLE PROJECTS
Types of projects that are eligible include: