EXECUTIVE SUMMARY

CONCESSION NAME : JAYAKHISMA GLOBE INDONESIA


Nama Konsesi : Jayakhisma Globe Indonesia
MINING STATUS : IUP Operasi Produksi
No. 540.1/K.531/HK/VIII/2011
Status Perijinan : IUP Operasi Produksi
No. 540.1/K.531/HK/VIII/2011
AREA SIZE : 4.800 Ha
Luas Area : 4.800 Ha
MINE LOCATION : Tanjung Mangkalihat, Kabupaten Kutai Timur, Province Kalimantan Timur.
Lokasi Tambang : Ds.Tanjung Mangkalihat, Kec. Sandaran, Kab. Kutai Timur, Prop. Kalimantan
Timur
HOW TO GET THERE : Through Balikpapan Tanjung Redeb (Capital city of Berau) by air takes 40
minutes then continue from Tanjung Redeb Biduk biduk by road is
approximately 5 hours. From Biduk biduk, by speed-boat traveling along the
beach coastal delta (towards the Kutai Timur direction) , takes around 40
minutes. Arriving at the concession village, called Tanjung Mangkalihat.
Ke lokasi Tambang : Dari Balikpapan ke Tanjung Redeb (Berau), memakai pesawat dengan waktu
tempuh 40 menit. Dari Tanjung Redeb ke Biduk-Biduk lewat darat memakan
waktu sekitar 5 jam. Dari Biduk-biduk menuju ke lokasi konsesi tambang
memakai speed/ perahu membutuhkan waktu 40 menit.
DRILLING AREA : 300 Ha
Luas Area Pengeboran : 300 Ha
RESERVE ANALYSIS : In 300 Ha found 3,000,000 Metric Tons (Reserve)
Analisa Cadangan : Dalam 300 Ha didapatkan jumlah cadangan sebesar 3.000.000 MT
STRIPPING RATIO : 1 : 5 maximum
Rasio Penambangan : 1 : 5 maksimal
CALORIFIC VALUE : From 5,300 Kcal/Kg (ADB) up to 6,200 Kcal/kg (ADB),
Average 5,600 Kcal/Kg (ADB).
Nilai Kalori : Dari 5.300 Kcal/Kg (ADB) s/d 6.200Kcal/Kg (ADB).
Dengan rata-rata kalori adalah 5.600 Kcal/Kg (ADB)
DEPOSIT : Estimated to be 12 million tons up in the whole concession
Jumlah Deposit : Diperkirakan sebanyak 12 juta MT
OUTCROP : Many outcrop be find there
Singkapan : Banyak singkapan ditemukan di lokasi
HAULING DISTANCE : From Mining pit to crushing + stockpile area min. 3 km and max 10 km.
Jarak Hauling : Dari mulut Tambang ke stokpile crusher minimal 3 km dan maksimum 10 km
TRANSSHIPMENT : Since the jetty is facing the open sea thus the distance for transshipment is
less than 1 miles to safe open sea anchorage at Tanjung Mangkalihat,
Sandaran, Kutai Timur, Kalimantan Timur
Jarak Pengapalan : Karena lokasi pelabuhan/jetty berada di tepi laut maka jarak pengapalan dari
jetty ke kapal besar berlabuh sejauh 1 mile
VILLAGE : Only 1 village in the mining concession area around 3 km from pit.
Desa : Hanya ada 1 desa di dalam area konsesi Tambang, sekitar 3 km dari pit.
INFRASTRUCTURE : Hauling road available, with maximum 3 km to the crushing + stockpile area &
0.5 km to the jetty area. There is area found for stockpile + crushing as well
as jetty around 5 ha with one crushing facility (planned) with the output
capacity of 500 tons/hour or 150,000 tons/month. There are some area now
ready to work.
Infrastruktur : Jalan hauling tersedia dengan lebar 15-20 meter, dengan jarak sepanjang 3 km
ke stokpile dan 0,5 km ke jetty. Area stokpile seluas 5 Ha terdapat fasilitas
crusher dengan kapasitas 500 MT/jam atau 150.000 MT per bulan.
VICINITY AREA : Not mining company in the area yet.
Area Sekitar : Belum ada perusahaan tambang yang beraktifitas di sekitar konsesi.
BARGE VOLUME : No minimum barge size, maximum size to be used is 320 ft
(no restriction on the water draft).
Volume Tongkang : Tidak ada batasan dengan ukuran volume tongkang maksimal 320 ft.

CONCLUSION : JGI is a concession type with prime location on the edge of the Sulawesi sea.
The transshipment and hauling costs are considered low. Therefore, once
deposit is confirmed, this mine is very low cost operation.
KESIMPULAN : JGI adalah sebuah konsesi dengan kondisi lokasi yang bagus yang menghadap
ke laut Sulawesi (open sea). Transhipmen dan jarak hauling dengan biaya
rendah, demikian juga dengan jumlah cadangan yang pasti.

COMMERCIAL BUSSINES : Joint Operation system with Total Down Payment is USD 3.5 Million. Royalty
Fee is USD.15/MT, (FoB Barge) all in exclude Government Royalty (Sale Tax
Royalty).
Komersial Bisnis : Kerjasama dengan sistem Join Operasi dengan uang muka sebesar USD 3.5
Juta sekitar Rp. 40 Milyar.
Fee royalty keseluruhan sebesar USD 15/MT, FoB Tongkang, tidak termasuk
pembayaran fee penjualan ke pemerintah.

Note/Catatan :
1. Uang muka merupakan bentuk pinjaman yang akan dikembalikan kepada mitra kerja dengan
pemotongan pada setiap pengapalan sebesar USD 4/MT atau sesuai kesepakatan.
2. Uang muka yang diberikan akan dipakai untuk keperluan pekerjaan di lapangan seperti pembebasan
lahan, penyelesaian infrastruktur termasuk jalan dan fasilitas pelabuhan serta biaya eksplorasi
lanjutan (drilling, mapping dan topografi)
3. Nilai Royalty Fee sudah termasuk fee KP/owner, jalan hauling, pembebasan lahan, comdev., dana
taktis, crushing dan loading.
4. Perijinan Clear and Clean akan diterbitkan selambat-lambatnya 2 bulan setelah kontrak kerjasama
dengan mitra ditandatangani.
5. Pembayaran Uang muka pada saat penandatanganan kerjasama dilakukan.
6. Penyelesaian infrastruktur selambat-lambatnya 45 hari setelah penandatanganan kerjasama.
7. Penambahan fasilitas pelabuhan dan pemuatan/loading seperti Conveyor akan dilihat berdasarkan
produksi dan penjualan.
8. Kontraktor tambang berjanji setelah peralatan masuk ke lokasi akan mulai berproduksi dan dalam
bulan pertama bisa coal getting sekurang-kurangnya 15.000 MT s/d 20.000. Dan pada bulan-bulan
selanjutnya akan menambah produksi sampai dengan minimal 50.000 MT secara kontinyu.