Presentation in Workshop of Sofia
Presentation in Workshop of Sofia
Presentation in Workshop of Sofia
Arjan Jovani
Member of ALBCOLD
and Director of Dam Safety Department in KESH sh.a.
International Seminar on Water Security and Risk Management
Albania is a rich country with water. The water cachement area is 43 305 km2
There are 652 dam. 360 of them are large dams and 10 of them are very large
dams with height more than 60 m. 3 Large dams are under the construction
Mainly of Dams are used for Irrigation. 2 large dams are used for water supply and
10 of them are used for Hydroenergy.
Numbers of high dams according to their Number of high dams according to Type
Heights of Usage
2 6
10 2
76
276
348
The highest Dam is Fierza Dam with Height of 166.5 m and Volume 8 million m3
The largest reservoir created by the construction of a Dam is Fierza Dam with storage volume of
2.35 billion m3
The dams with highest risks are 5 dams on the Drini River.
Protection Measures against Erosion phenomens and sediments coming in three artificial lakes of Drini
Cascade
Preparation of new Hydrological model for Drini Basin and Installation of new modern Hydro
meteorological systems in Drini River.
Providing of safe flood management and Increase of discharges capacities in Drini Cascade
Implementation of new Bathimetry survey and preparation of new Volume Curves in 5 Artifical lakes
for hydroenergy on Drini and Mati river
Risk Analayse Study and Preparation of Emergency plans for 5 dams of Drini Cascade and 2 Dams of
Mati cascade and Banja Dam on Devolli River.
Construction of Moglica Dam on Devolli River with height H = 150 m. This is the
first very large dam in Albania with asphalt diafragm. It will be the highest dam
with asphalt diafragm in Europe
Construction of Okshtun Dam on Okshtuni river, branch Black Drini river with
height H = 64 m. This is the first large dam in Albania with RCC
II. Adaption of legal frameworks and Technical Standarts with EU Directives and ICOLD Reccomendation
V. Modernization of Monitoring Systems of very large dams in Hydroenergy and installation of data transfer system in real
time and online
VI. Installation of Monitoring Systems and improvement of Monitoring process for Irrigation dams and their infrastructure
VIII. Preperation and Implementation of new Emergenecy Plans for all very large dams with highest risks