Operation and Maintenance of Boilers: Prepared by
Operation and Maintenance of Boilers: Prepared by
Operation and Maintenance of Boilers: Prepared by
of Boilers
Everett B. Woodruff
Herbert B. Lammers
Thomas F. Lammers
Prepared By
Zahid Hussain
FFBL Power Company Limited Karachi
@Buckman Laboratories Asia Pacific
The procedure to be followed in the operation and maintenance of a
boiler plant depends to a large extent on its size, type of combustion
equipment, operating pressures, steam requirements, and other factors
pertinent to the specific plant. There are, however, standard practices
that any operator should follow to ensure safe, continuous service and
efficient operation. This chapter is intended to assist the operator in
the correct use of the equipment, to recognize unsatisfactory conditions,
and to take the necessary corrective measures before dangerous, costly
emergencies develop.
Fluidized bed boilers have become popular in the burning of waste
fuels and of those fuels which are difficult to burn by other combustion
methods. As a result, the operating characteristics of fluidized bed
boilers are discussed in this chapter. Although detail designs do vary
between suppliers, the general features for operation apply to all
designs.
Combined cycle and cogeneration plants have become the primary
power plant additions in recent years. Even though these facilities
burn natural gas, as compared with more complex solid-fuel-fired
power plants, the heat-recovery steam generators (HRSGs) require
special maintenance attention to ensure high reliability and long life.
These general requirements are discussed in this chapter.
All operators should be trained properly and should follow the operating procedures of the equipment
manufacturers. These procedures are
developed using the experience gained by the manufacturer from many
operating plants, and they should be modified as required based on
the operating experience and specific operating philosophy of the plant. 7.1 Boiler Startup
The necessary steps to be taken before placing a boiler in service
depend on whether it is new, has been out of service a long time for
repairs, or has been down for only a few days. New boilers and those
on which extensive replacements of pressure parts have been made
must be given a hydrostatic test before being placed in service. Such a
test consists of filling the boiler completely with water (being careful
to vent all the air) and developing a pressure 112 times the design
pressure. In order to prevent fouling and corrosion, demineralized
and deaerated water should be used whenever possible. Before the
test is applied, a final inspection is made of all welding. Connections
for flanged safety valves are usually blanked, and welded safety
valves are closed with an internal plug. The water temperature must
be at least as warm as the temperature of the air in the boiler room
and in no case less than 70F. A 750-psi pressure boiler would be
hydrostatically tested at 750 1.5 1125 psi. During hydrostatic
testing, constant load supports for steam piping should be used in
accordance with the manufacturers instructions for the additional
loads imposed by the water required for hydrostatic testing.
As part of the hydrostatic test procedure, maintenance and operations should review a checklist of major activities to
ensure that the
unit is operational. These activities should include the following for
the particular boiler design involved:
1. Have all tubes been expanded in accordance with the tube-expanding procedure?
2. Have all welds been completed in accordance with the welding
procedures? Have welds been stress relieved and nondestructive
tested?
3. Following the test, have all gags, blanks, or hydrostatic plugs been
removed from the safety valves and any other blanks that have
been used to isolate the boiler?
4. Have all ASME code requirements been met?
New boilers, and even those on line, can accumulate a deposit of oil,
grease, and paint and must be cleaned by boiling out with an alkaline
detergent solution. This boilout can be accomplished with a combination
of trisodium phosphate (Na3PO4) and disodium phosphate (Na2HPO4).
The use of caustic NaOH and/or soda ash (Na2CO3) is not recommended.
Chemical cleaning of a superheater and reheater is not necessary for
initial operation. However, these systems should be given a steam blow,
where high-velocity steam is used to blow any debris from the inside
surfaces of the system.
W
(h Q
g
hH
)f
100
where W steam flow (lb/h)
Q fuel flow (lb/h)
H heating value of fuel (Btu/lb)
h
g
heat content of steam (Btu/lb)
h
f heat content of feedwater (Btu/lb)
Example A boiler generates 50,000 lb/h of steam and burns 4880 lb of
coal per hour having a heating value of 13,700 Btu/lb. The steam is 150
psig, dry, and saturated, and the feedwater is 220F. What is the boiler
efficiency?
Solution Heat content of 150 psig, dry and saturated steam (h
g
) 1195.6
Btu/lb (see the steam tables in Appendix C). Heat content of 220F feedwater
(h
)f
188.1 Btu/lb.
Boiler efficiency 100
75.35%
Loss due to the water that may be formed during the combustion