Digital Assignment - Ii Advanced Foundation Design: Soil Nailing and Anchoring, Design Aspects and Case Studies
Digital Assignment - Ii Advanced Foundation Design: Soil Nailing and Anchoring, Design Aspects and Case Studies
Introduction
The basic concept of soil nailing is to reinforce and strengthen the existing ground b installing
closely-spaced steel bars, called "nails", into a slope or excavation as construction proceeds
from the top down. This process creates a reinforced section that is internally stable and able
to retain the ground mass. As with mechanically stabilized earth (MSE) walls, the
reinforcements are passive and develop their reinforcing action through nail-ground
interactions as the ground deforms during and following construction. Nails work
predominantly in tension but may develop bending/shear in certain circumstances. The effect
of the nail reinforcement is to improve stability by (a) increasing the normal force and hence
the soil shear resistance along potential slip surfaces in frictional soils; and (b) reducing the
driving force along potential slip surfaces in both frictional and cohesive soils. A construction
facing is also usually required and is typically shotcrete reinforced by welded wire mesh. The
steel nail bars are typically 20 to 35 mm in diameter, with a yield strength in the range of 420
to 500 N/mm2, and are typically installed into drill holes having diameters in the range of 100
mm to 300 mm and at a spacing between 1 and 2 meters. The nail lengths are typically 70 to
100 percent of the wall height. Nail inclinations are generally on the order of 15 degrees below
horizontal to facilitate grouting.
Soil nails typically consist of steel reinforcement inclusions and may be categorized on the
basis of their method of installation and degree of corrosion protection. For conventional drill
and grout nail installations, the nail grout consists typically of a neat cement grout with a water
cement ratio of about 0.4 to 0.5. Where a stiffer consistency grout is required (e.g., to centralize
the nail when no centralizers are used in a hollow stem auger installation or to control leakage
of grout into the ground such as in highly permeable granular soils or highly fractured rock), a
lower slump sand-cement grout may be used. Sand-cement grout may also be used in
conjunction with large nail holes for economic reasons.
The lowest level of corrosion protection in U.S. practice is provided by the grout alone.
Encapsulation of the bar provides the highest level of corrosion protection and is achieved by
adding a protective sheath and grouting the bars in a phased process. Corrosion protection of
the soil nail tendon can also be provided by application of a fusion-bonded, epoxy coating,
galvanization, or sacrificial steel. Chapter 7 contains detailed descriptions of the corrosion
protection techniques available for soil nails.
Facing
Shotcrete Facing consists of an initial and a final component. Soon after excavation, the
initial facing is applied on the exposed soil at each excavation lift before or after nail installation
to provide temporary stability and protection. The initial facing also receives the bearing plate
of the soil nail. The final facing is constructed over the initial facing and provides structural
continuity throughout the design life. The final facing may also include an aesthetic finish. The
initial facing most commonly consists of reinforced shotcrete. The final facing generally
consists of CIP reinforced concrete, reinforced shotcrete, or precast concrete panels.
Figure: Typical cross-section of a soil nail wall.
Reinforcement used in the shotcrete of the initial facing includes the following items: (i)
welded-wire mesh (WWM) installed over the entire excavation lift, and effectively over the
entire wall using appropriate lap splices; (ii) horizontal bars (referred to as waler bars) placed
around nail heads to add bending resistance in the horizontal direction; and (iii) vertical bearing
bars placed at nail heads to add bending resistance in the vertical direction (see Figure 2.1).
Other reinforcement options include the use of steel or synthetic fiber particularly for
temporary facing in soft or weathered rock. If the final facing consists of shotcrete, the
reinforcement in the final facing is similar to that described for shotcrete in the initial facing.
If the final facing consists of CIP or precast concrete, rebar mesh is typical.
Other Components
Connection Components The soil nail is connected to the facing through a number of
components including: nuts, washers, bearing plates, and headed-studs. The headed studs are
attached to the bearing plate and become embedded within the final facing as depicted in
Figure.
Drainage System A drainage system is installed behind soil nail walls to: (i) collect perched
groundwater or infiltrated surface water that is present behind the facing; and (ii) direct the
collected groundwater away from the wall. The drainage system commonly consists of
composite, geosynthetic drainage strips, also referred to as geocomposite strip drains. The
drainage system does not provide full coverage of the wall area, but rather covers commonly
10-20%, or more, of the excavation face, depending on the selected strip drain spacing and
commercial widths that are available.
Construction Sequence
The typical sequence of construction of a soil nail wall is described below and shown
schematically in Figure.
Step 1. Excavation. The depth of the initial excavation lift (unsupported cut) may range
between 2.5 and 7 ft, but is typically 3 to 5 ft and reaches slightly below the elevation
where the first row of nails will be installed. The feasibility of this step is critical
because the excavation face must have the ability to remain unsupported, until the nails
and initial face are installed, typically one to two days. The type of soil that is excavated
may limit the depth of the excavation lift. The excavated platform must be of sufficient
width to provide safe access for the soil nail installation equipment.
Step 2. Drilling of Nail Holes. Drill holes are advanced using specialized drilling
equipment operated from the excavated platform. The drill holes typically remain
unsupported.
Step 3. A) Nail Installation and Grouting. Tendons are placed in the drilled hole. A
tremie grout pipe is inserted in the drill hole along with the tendon; and the hole is filled
with grout, placed under gravity or a nominal, low pressure (less than 5 to 10 psi). If
hollow bars are used, the drilling and grouting take place in one operation.
B) Installation of Strip Drains. Strip drains are installed on the excavation face,
continuously from the top of the excavation to slightly below the bottom of the
excavation. The strip drains are placed between adjacent nails and are unrolled down
to the next excavation lift.
Step 4. Construction of Initial Shotcrete Facing. Before the next lift of soil is
excavated, an initial facing is applied to the unsupported cut. The initial facing typically
consists of a lightly reinforced 4-in. thick shotcrete layer. The reinforcement includes
welded-wire mesh (WWM), which is placed in the middle of the facing thickness
(Figure 2.1). Horizontal and vertical bars are also placed around the nail heads for
bending resistance. As the shotcrete starts to cure, a steel bearing plate is placed over
the tendon that is protruding from the drill hole. The bearing plate is lightly pressed into
the fresh shotcrete. Hex nuts and washers are then installed to engage the nail head
against the bearing plate. The hex nut is wrench-tightened within 24 hours of the
placement of the initial shotcrete. Testing of some of the installed nails to proof-load
their capacity or to verify the load-specified criterion may be performed before
proceeding with the next
excavation lift. The shotcrete should attain its minimum specified 3-day compressive
strength before proceeding with subsequent excavation lifts. For planning purposes, the
curing period of the shotcrete should be considered 72 hours.
Step 5. Construction of Subsequent Levels. Steps 1 through 4 are repeated for the
remaining excavation lifts. At each excavation lift, the strip drain is unrolled downward
to the subsequent lift. A new panel of WWM is then placed overlapping at least one
full mesh cell with the WWM panel above. The temporary shotcrete is continued with
the previous shotcrete lift.
Step 6. Construction of Final Facing. After the bottom of the excavation is reached
and nails are installed and tested, the final facing is constructed. Final facing may
consist of CIP reinforced concrete, reinforced shotcrete, or prefabricated panels.
Weepholes, a foot drain, and drainage ditches are then installed to discharge water that
may collect in the continuous strip drain.
Variations of the steps described above may be necessary to accommodate specific project
conditions. For example, shotcrete may be applied at each lift immediately after excavation
and before drilling of the holes and nail installation, particularly where stability of
theexcavation face is a concern. Another variation may be grouting the drill hole before
placement of the tendon in the wet grout.
Figure: Illustration. Typical soil nail wall construction sequence.
Applications of Soil Nail Walls
Overview
Soil nail walls can be used in the following roadway applications:
Roadway cuts
Road widening under existing bridge abutments
Tunnel portals
Repair and reconstruction of existing retaining structures
Hybrid soil nail systems
Shored Mechanically Stabilized Earth (SMSE) walls
The below figure shows the construction of a soil nail wall for a large cut face.
Figure: Photo. Construction of soil nail wall. Photo courtesy of Schnabel Engineering.
Roadway Cuts
Soil nailing is attractive in roadway cuts because a limited excavation and reasonable right-of-
way (ROW) and clearing limits are required (See below Figure). These factors help to reduce
the environmental impacts along the transportation corridor. The impact to traffic may also be
reduced because the equipment for installing soil nails is relatively small.
Variations in the details shown schematically in Figure 2.4 may exist, particularly to those
details related to runoff control. Some of these variations will be discussed in Drainage and
Details.
INTRODUCTION
Deep excavations and retaining structures are constructed in the city of Istanbul at different
locations of the city due to the recent demand for the construction of high-rise structures and
shopping malls having various basements. The main lithological unit of Trace Formation, i.e.
alternating layers of sandstone, siltstone and claystone are encountered during these
excavations. The lithological unit is extensively fractured. Consequently, stress relief in
horizontal direction as a result of excavations is the main potential hazard that has to be handled
with care. Istanbul is located at a very seismically active region and a major earthquake
magnitude of Mw>7.0 are expected to occur with a 65% probability within the next 30 years.
It is well known that flexible earth retaining structures in cuts as soil nailed walls offer a great
advantage under the described subsoil and seismic conditions. As a result many soil nailed
walls having various heights have been constructed recently in the city. The performances of
these walls are monitored by means of inclinometers. The displacement data for various
projects are evaluated in terms of various design parameters of the soil nailed walls and the
excavation depth. In the paper the basic guidelines for soil nailed walls in typical greywacke
formation of the city are developed for future applications.
The city of Istanbul due to its recent growth in economy caused a great attraction for the
construction of high-rise residential and office buildings. In order to obtain parking space, deep
excavations are employed to allow great number of basements below these tower structures.
The depths of the excavations commonly reach to 25-40 meters below the ground surface. The
city of Istanbul is potentially under the influence area of the Marmara Fault System, located at
the south, in the Marmara Sea, which is the western end of the North Anatolian Fault-NAF of
Turkey. After the 1999 Kocaeli and Dzce earthquakes occurred on NAF within the Marmara
Region in ap proximately 100-150 kilometers from the city of Istanbul, the structure of NAF
system in Marmara Sea attracted worldwide scientific attention. Recent studies conducted after
the 1999 Kocaeli (Mw=7.4) and Dzce (Mw=7.2) earthquakes indicated that about 65%
probability for the occurrence of a Mw>7.0 effecting Istanbul within the next 30 years due to
the existence of potential seismic gaps. (Parsons et al 2000). The encountered subsoil formation
is soft rock greywacke locally known as Trace Formation, which is lithologically alternating
sandstone, siltstone and claystones with various degree of weathering and fracturing.
Obviously, the extend of weathering and fracturing controls the mechanical properties and in
fact geological observations do well agree with the results of measurements reflecting
mechanical properties of the formation. The geotechnical modelling of formation, weathered
zones, extend of fracturing and compressibility modulus of formation are usually obtained by
means of integrated seismic survey and Menard pressuremeter testings performed within the
boreholes at various locations and depths. (Durgunoglu & Ylmaz 2007) Based on the previous
positive records of flexible earth retaining structures during earthquakes in Turkey by Mitchell
et al (2000) and Durgunoglu et al (2003), soil nailed walls in such excavations performed
within the city offer great advantage especially for the encountered subsoil and seismic
conditions. The results of the performance of walls with different heights in various sites having
the similar greywacke subsoil formation are compiled in this study. The performances of walls
are monitored by inclinometer recordings taken at certain time intervals in parallel to the
excavation at various locations. The displacement and normalized displacement (i.e.
performance ratio, Pr) data are presented together with some basic parameters of soil nailed
walls such as, height of wall (H), area per nail (S), average nail length (L), nail density (=L/S),
length ratio (Lr), bond ratio (Br) and strength ratio (Sr). As a result the values of performance
ratio for soil nailed walls together with nail density in typical greywacke formation of the city
of Istanbul are developed based on these extensive case studies as a guideline for future
applications.
Soil nailing is a very versatile excavation retaining system for deep excavations in urban areas
surrounded by major structures and infrastructures provided that limiting lateral displacements
are not exceeded. Using conventional methods of design, Federal Highway Administration
(2003) and previously developed charts for estimating lateral displacements or performance
ratio may be misleading in deep soil nailing applications Monitoring and modern numerical
analysis based design and application for such deep soil nailed walls are of primary importance.