Project Work (B.e) PDF
Project Work (B.e) PDF
Project Work (B.e) PDF
LINK PRODUCTION
A THESIS
BACHELOR OF ENGINEERING
In
MECHANICAL ENGINEERING
By
R.SUNDARAMOORTHY (01107404098)
GUIDED BY
ANNA UNIVERSITY
TRICHIRAPPALLI-620 024
NOVEMBER - 2010
DEPARTMENT OF MECHANICAL ENGINEERING
ANNA UNIVERSITY
NOVEMBER-2010
BONAFIDE CERTIFICATE
held on _________________________
2
ACKNOWLEDGEMENT
3
TABLE OF CONTENTS
TITLE PAGE NO
CHAPTER 1 - INTRODUCTION
1.1 INTRODUCTION 7
1.2 NECESSITY OF THE PROJECT 7
1.3 AIM OF THE PROJECT 10
1.4 PRINCIPLE USED IN THE WIRE FORMING 10
4
CHAPTER 5 CONSTRUCTION OF FIXTURE AND
PRODUCTION OF LINKS IN THE
DEVELOPED METHOD
5
LIST OF FIGURES
Page No
INTRODUCTION
1.1 Introduction
Heavy Alloy Penetrator Project is also engaged in the production of IFD items
namely, BOX-H2A Components for the use of military service even though its major
product is the anti tank kinetic energy projectiles.
Some of the components which includes in the assembly of BOX-H2A are
Catch Assembly, Hinge Assembly and Link for Handle. In the above three
components a rectangular shaped wire product will be used as a sub- unit. This
project deals with the simplified method to get the rectangular shape in the wire. The
wires which will be used in the production of links (rectangular shaped wire products)
for the Catch Assembly and Hinge Assembly have the diameter of 4.06 mm. But, for
manufacture the component of Link for Handle, a 3.15 mm diameter wire will be
used.
7
1.3 Aim of the Project:
This project strives to achieve highest Customer satisfaction level and to
achieve annual supplies as per laid down targets in conformance with the customers
requirements.
This Project helps the production in the following ways:
(1) It can maximize the production and so the target can be reached in short period
of time.
(2) The manufacturing cost of link components can be reduced.
(3) The human work involvement in the manufacturing the link components
can be reduced.
(4) It can ensure the consistency in the quality of the product.
When a wire is fed in between a revolving element and a flat surface roller
which may cushioned by the help of tension springs, the wire will get the shape of
rolling flat surface and feed in to front side.
10
CHAPTER-2
\
2.1 First stage of production
The mild steel wire from the roll condition is utilized for make
the links after involved it in to the several stage of operations. In that the first stage of
operation is given below:
The required diameter wire from the roll is first straightened and cut
to the required length for make the link. This operation is carried in a straightening
and wire cutting machine. The straightening of the wire can be obtained by the
rotation of two meshing pulleys those having a groove over its periphery on its outer
surface.
When the pulleys are rotating, the wire will be fed in between the
grooves. So the wire got straightened stage and also feed in to the front side. In the
front side one cutter having the vertical movements, cut the wire to the required
length during its downward stroke. The cutter got its movements from a cam operated
drive unit. The required length of cut wire for make the links are collected in a basket.
Then the basket is transferred to the first pressing machine, where the
first stage in the link formation will be takes place.
11
2.3 Third stage of operation
The first form stage links are converted in to the final shape in the
second press in this stage of operation. Here also one hydraulic press having 5 tons
capacity is used for the forming. The die and punch used in this press ensure the final
shape of link as the output. Here also suitable safety provisions are required for the
operators.
The links in the final shape obtained from the second press are collected
in a basket and then they are transferred to the welding spot for carrying the welding
operation at the edges of the links for further assemble work of the links to make the
Hinge Assembly.
12
CHAPTER-3
3.1.1 Planning
In this stage, the causes of problems which affect the production rate in the
old method are discussed with the help of elements of cause and effect diagram. The
main elements involved in the diagram are Man, Machine, Material and Method.
The first element Man involves the operators who operate the machines
and the presses. Here, the skill of the operators in operating the machines and the
presses are thoroughly checked and improved by giving better training and facilities.
The Machine includes the straightening and cutting machine and the two
numbers of Hydraulic Presses. Those are maintained in good operating condition by
the replacement of necessary spare parts.
The third element Material involves the mild steel wire used for the
production of link components. The hardness of the mild steel wire is maintained in
the required range.
After found the variations in the causes from all the above elements are
in satisfactory level, then only the Method of producing the link was involved in to
modification.
14
3.2.2 Selected new method
In this method, two lathes are utilized for manufacture the link
components. One lathe is used for formation of the link, whereas the other lathe is
used for cut the links separately from the coil of link which was produced in the first
lathe.
The first lathe is used for the rotation of the mandrel, which forms the
wire in the link shape over its surface. The second lathe is used for the rotation of a
plate cam, which actuates the cutter blades by a lever drive arrangement for cut the
links from the coil of link. The complete detail of this method is given in the
forthcoming chapters.
The drives for the mandrel rotation can also be got from a motor through chain
and sprocket or belt and pulley arrangement.
Because the speed of the mandrel may not be a changeable, it can prefer the
chain and sprocket arrangement for drive the mandrel. So, the use of lathe may be
eliminated.
But the existence of slip in the belt drive arrangement due to the development
of load during the coiling and cutting times, this method was not preferred for the
outcome.
The trial run for produce the links are carried out in this stage. The
necessary adjustments in the moving parts, for example, position of guide roller and
wire feeder, speed of the lathe, guide tubes height, actuation of the cam pin over the
lever, the cutting action of the scissor and etc, are thoroughly checked and adjusted
according to the condition to give required link output.
Link
Production
Act Planning
Check Do
This fixture arrangement is used to make the wire formation in the desired
size and shape of our requirement. The mandrel takes the main role in the wire
formation .Because, when the forming operation the wire will roll over the
rectangular surfaces of the mandrel.
17
4.1.3 Wire Feeder
It consists of a base frame with four legs. The top side of the base frame is
welded with a flat plate in the middle portion. One number vertical shaft of 50 mm
diameter made in stainless steel is mounted in the flat plate through bearings.
The flat plate also welded with a circular frame to support the coiled wire.
The vertical shaft can be rotated by the pulling motion developed over the wire by the
rotation of lathe spindle.
This is an arrangement of two levers and one of them is operated by the cam
unit which will be fixed in the spindle of the lathe .The another lever having cutting
edge on one side is fitted rigidly with the fasteners in a vertical support. The vertical
support is fixed on the cross slide. The cutting edges of the scissors are made with
hardened nature so as to prevent the earlier damage of the cutter.
23
4.2.2 Plate Cam
One short lengthened pin is welded on the other Face of the plate
eccentrically from the middle. This pin acts like a toggle, to actuate the lever of the
link cutting scissor. During cutting operation, each revolution of the plate cam gives a
link, by the above actuation of the toggle over the lever of the scissoring unit.
35
CHAPTER 5
Among the three cylinders, two cylinders are fitted in the fixture in vertical
axis at top and bottom, facing the rollers towards the spindle axis.
But one cylinder is fitted horizontally facing its roller towards the axis of
the spindle. The chuck holds the circular portion of the rectangular ended mandrel.
The pipe guide arrangement mounted over the tail stocks base plate after
the removal of the tail stock center arrangement. The pipe guides axis must be
adjusted in the way that should be matched in line with the spindle axis.
The wire feeder should be kept in opposite to the cross slide, in the back
side of the lathe as enable to supply the wire to the mandrel. Before the link
formation process the coil should be loaded over the wire feeder unit.
38
5.1.2 Link Cutting
Here the fixture carries the levers of the scissoring arrangement and the total
fixture is mounted over the bed of the second lathe. The lathe spindle holds the set of
plate cam arrangement.
The tray at the bottom of the bed should be placed in proper place to enable
to collect the links.
Initial set up
The mandrels back end should be hold with the Chuck .The use of the
three jaw chuck will ensure the self centering of the mandrel.
The wire having the required cross sectional diameter is loaded around the
vertical shaft of the feeder unit. The one end of the wire is pulled and kept in the slot
of the side face of the mandrel.
40
Formation of link
By the slow rotational adjustment of the spindle the wire can be brought in
between the roller and the mandrels flat surface. The further spindle rotation gives a
pulling force on the wire in the coil and also makes the defined rectangular formation
in the wire over the mandrel.
The link cutting scissor is mounted over the cross slide of the second lathe.
The scissor having two levers and one of its lever is operated by the projected pin of
the cam plate. The cam plate is held in the spindle.
When the coil of link length is manually introduced in between the two
edges of the scissor, the link is cut off one by one by the scissor for each actuation of
its one lever by the cam pin. The speed of introducing the coiled link in to the scissor
for cutting them may change from operator to operator.
So, the speed of the lathe must be changed depends upon the operator. For a
highly trained person, the speed of the lathe running at normal speed is suitable. But,
for the new operators, running the lathe at a slow speed can give the better results.
The reason for the above that, a trained person Can quickly introduce the
coil in between the cutting levers, according to the quicker actuation of the lever
occurred due to high spindle speed. But, a lesser skilled operator, may struggle for
this quicker response.
The links which are cut off from the link length are collected at the bottom
tray and the further works on that is carried on.
43
CHAPTER-6
Time for setting the cut wire in the die /100 numbers =1 hour
-------------------
Total hours require for produce 100 numbers of links = 2-30
--------- - -----------
Developed method
But, the total time require for produce 100 numbers of links will equal to the
Time taken by the coiling machine and cutting machine for produce 100 numbers of
links.
44
So, the total time /100 links = (10+5) minutes
= 15 minutes
Normally, the standard man hours (SMH) given for 1 number of link is 0.001 hour
is used for calculating the output hours of an operator.
Developed method,
For 1 hour of Input Hour,
The employee can get = Number of links produced in one hour X SMH
= 1200 X 0.001
=1.2 hour as the Output Hour.
So, it is well known that, an employees output hours (which is relates with
the production) must be equal to or more than his input hours (relates with his
attendance in duty). Then only he can get his basic salary or profit respectively.
So, clearly it can be understood that, an Employee can get more benefits by the
use of the developed method.
In another way, the developed method also helpful to the management to reduce
the SMH (standard man hours) of the link component and thereby they can ensure
only the basic Pay to the employees. So, the Employers/Management can get benefits
by use of the developed method.
45
6.3 Comparative study
The graph shows the relationship between the rate of production over the
entire life of the link producing machines in the old and new methods.
The line 1-2 represents the production rate in the new method over the
life of its machineries. It will be known that at the initial period of life of the
machineries in the new method can able to produce more components by the way of
increasing production rate. But in forthcoming life of the same machines, the rate of
production may be decreased due to the reason of maintenance works in the sliding
parts of the forming fixture due to the breakdown. It is denoted by the steeper slope in
the line 1-2 in the graph.
But in old method, because of the less output from the hydraulic press the
rate of production may be less and it is represented by a line 3-2 in the graph. The
line 3-2 represents the rate of production in the old method over the life of its
machineries. Because of the hydraulic presses may able to give an approximately a
constant production rate, the 3-2 line is drawn nearly horizontal in the graph.
Consider the point at 2 both the lines may meet and the corresponding
life of the machines is approximately 4 years and the production rate may be same in
both the methods. The area under the both the lines3-2 and1-2gave the total
quantity of the links produced in the corresponding methods.
It is clearly understood that the new method gives more quantity of links
compared with the old method.
46
6.3.2 Cost of production versus Life of the machineries
The graph shows the relationship between the two methods when
comparing the cost of production over its life of machines.
At one of the point the cost of production of both the methods are
same in a same life of year. When cumulatively comparing the total cost of
production in that particular year (say at 6) the cost of new method is somewhat
higher than the old one.
48
CHAPTER 7
(1) Elimination of hydraulic press in the developed method, gives the following
benefits
The inventory cost can be reduced due to the elimination of the press. The
maintenance cost can also be reduced due to this press elimination.
(2) The spare parts requirement is less compared with the Hydraulic press.
Benefits can obtain by the operators in the following ways,
Because of the increase of the production rate, the operators can expect more
profits from the management.
The operators can escape from the mental stress in the developed method
compared with the old method in the production of the link components.
(3) Even less skill is enough for the operators. The operators may require to do
minor corrective works in the settings of the machine and it also not required
always.
50
(4). Benefits by the management point of view,
Quality of the product is ensured always in this method. More out come is one
of the important beneficial to the management. Reduction in the rejection of the
products, increase the quantity of the production. Management can challenge
with the other competitors who are supplying the similar products, by giving
good quality of the products to the customers.
The previous method of link formation requires more man power. But this
developed method requires less man power. It is because of the developed method has
less steps of operation in comparison with the previous method.
It can be got different size of links by simply change of the mandrel. But in
previous method, obtaining of each size links, require separate punch, die and fixture
arrangement.
So, Setting of tool in the developed method can be done in few minutes and it
also nothing but simple replacement of mandrel and spring pressure adjustment in the
roller.
Maintaining the uniformity of jobs in size and shape reduces the rejection level
of products and that ensure the quality.
51