23 Letter 66kv Equipment
23 Letter 66kv Equipment
23 Letter 66kv Equipment
To,
The Engineer
M/s N K Consortium,
4th Floor, Pragati Maidan,
Metro Station Building,
New Delhi-110001, India
Kind Attn: Mr. Ken Nishino (Project Director, NKC)
Dear Sir,
Sub: 2x25 kV Traction System for Rewari Makarpura (Vadodara) section of WDFC Phase-1 (ICB
No.: EM P-4) Part reply to comments on Equipment Sizing Report & approval of 66kV
Equipment for use in Traction Substation.
Ref: 1. SUBM/SLT4/NKC/EMP-4/DGN/GEN/232 Dated 22.11.2016
2. NKCs Letter- L-NKC-SLT4-PMC-1612-38 Dated 27.12.2016
3. SLT4/NKC/EMP-4/DGN/GEN/2017/1069 Dated 11.09.2017
4. SLT4/NKC/EMP-4/DGN/GEN/2017/1208 Dated 14.10.2017
5. NKCs Letter- L-NKC-SLT4-PMC-1710-50 Dated 30.10.2017
In response to Engineers observations vide 5 above, Kindly find SLT-4s response against the
comment for equipment referred under Sr. 5 for your perusal and issue of NONO.
A B C D
S. Item RDSO
Remarks (Complies to RDSO Specification)
No. Description Specification
1. Between Secondary of Scott Transformer and
Primary of Auto Transformer at TSS locations,
manual Isolators of 66kV rating are to be
66kV Double ETI/PSI/122 (3/89)
1 installed as per NKCs Drawing No. EMP4/PS/202
Pole Isolator Rev.1 (April-90)
in Volume-V (1/4), enclosed.
2. So you are requested to approve 66kV Double
Pole Manual Isolator as per RDSO specification.
Please accord your approval for procurement of PSI Equipment mentioned in column-B as per RDSO
Specifications mentioned in column-C of above table for use in the entire EMP4 project.
Thanking You,
Yours faithfully
For Sojitz L&T Consortium
Page 2 of 2
A Sojitz-Larsen & Toubro Consortium