R2 en COSIMA Process Optimization Methods
R2 en COSIMA Process Optimization Methods
R2 en COSIMA Process Optimization Methods
methods
1
This project has been funded with support from the European Commission. This presentation reflects the views only of the author, and the
Commission cannot be held responsible for any use which may be made of the information contained therein. LLP Leonardo da Vinci Transfer
of Innovation Programme / Grant agreement number: DE/13/LLP-LdV/TOI/147636
Contents
Contents .................................................................................................................................................. 2
Figures ..................................................................................................................................................... 2
Introduction............................................................................................................................................. 4
Definition of Process optimization .......................................................................................................... 4
Process optimization methods- Approaches........................................................................................... 5
BPR Business process reengineering ................................................................................................ 5
Lean Management............................................................................................................................... 5
Kaizen (CIP) .......................................................................................................................................... 6
Six Sigma .............................................................................................................................................. 6
TQM total quality management ....................................................................................................... 6
Tools - in improvement processes .......................................................................................................... 7
Mind maps ........................................................................................................................................... 7
Fish Bone ............................................................................................................................................. 9
DMAIC Define, Measure, Analyse, Improve and Control ............................................................... 11
7 Wastes ............................................................................................................................................ 12
Principle of 5 S ................................................................................................................................... 15
PDCA (Plan-Do-Check-Act/Adjust) .................................................................................................... 17
One piece flow (or continuous flow manufacturing) ....................................................................... 18
Pareto chart ....................................................................................................................................... 20
Ratios ................................................................................................................................................. 22
Spaghetti Diagram ............................................................................................................................. 28
Value Stream Mapping ...................................................................................................................... 31
Figures
Figure 1. Fishbone diagram. .................................................................................................................. 10
Figure 2. Principle of 5 S. ....................................................................................................................... 15
Figure 3. PDCA. ...................................................................................................................................... 17
Figure 4. One-piece flow manufacturing environment. ........................................................................ 19
Figure 5. Batch-and-queue manufacturing environment. .................................................................... 19
Figure 6. Pareto chart. ........................................................................................................................... 21
Figure 7. PDCA-circle. ............................................................................................................................ 22
Figure 8. The project management triangle. ......................................................................................... 23
Figure 9. Management of costs. ............................................................................................................ 24
Figure 10. Time/process potential. ....................................................................................................... 25
Figure 11. Return on investment........................................................................................................... 28
Figure 12. Spaghetti diagram example. ................................................................................................. 29
2
Figure 13. Spaghetti diagram for housing assembly. ............................................................................ 31
Figure 14. Value stream mapping of the current state. ........................................................................ 32
Figure 15. Example of a current state map (Source: Rother/Shook 2006) ........................................... 33
Figure 16. Information can initially be documented on a flip chart (see picture). ............................... 33
Figure 17. Digital (Excel) current state map. ......................................................................................... 34
Figure 18. Step-by-step mapping of the current state. ......................................................................... 34
Figure 19. Step-by-step mapping of the current state. ......................................................................... 35
Figure 20. A future state map................................................................................................................ 37
Figure 21. Balancing takt times. ............................................................................................................ 38
Figure 22. Before modifications in a value stream map. ...................................................................... 38
Figure 23. After modifications in a value stream map. ......................................................................... 39
Figure 24. Photo of train system. .......................................................................................................... 39
Figure 25. Arrival and departure times. ................................................................................................ 40
Figure 26. Mapping the current state. Record customer information.................................................. 41
Figure 27. Mapping the current state. Quick walk through to identify the sequence of the major
processes. .............................................................................................................................................. 41
Figure 28. Mapping the current state. Second walk through for to collect detailed data.................... 42
Figure 29. Mapping the current state. Add supply information. .......................................................... 42
Figure 30. Mapping the current state. Add information flow. .............................................................. 43
Figure 31. Mapping the current state. Calculating the lead times........................................................ 43
Figure 32. Mapping the current state. Example calculation. ................................................................ 44
Figure 33. Mapping the current state. Determining lead times............................................................ 45
3
Introduction
This report is a collection of different process optimization tools and approaches that can be used as
a theoretical basis to the FIS-moderators for the implementation of the FIS concept (Factory in a
Seminar room) lead by Learning Factory.
The Learning Factory will develop a pedagogic-didactic concept for the FiS within the scope of the
COSIMA-project. The Learning Factory's FiS is a business simulation programme, in which several
improvement tools (look also Tools in improvement processes) are applied.
This report can also be used as material during the train-the- trainer course This document was
produced as contribution to Work Package 2 part b) in the COSIMA project. The partners bfw
Unternehmen fr Bildung, HTL Wolfsberg, Junior Achievement, Learning Factory and Campus
Varberg have all contributed to the report.
General principles
For a long time the process optimization was considered as the task of quality management, but
today it is increasingly grown as a part of a comprehensive and integrated process management in
organizations. Process orientation and optimization as the basis of an effective type of farming is
now an indispensable part of any modern business management in order to survive in the national
and international competitive environment.
It is based on a process-oriented approach throughout the business processes. For this purpose it is
necessary to define process chains across departments instead of thinking in hierarchical department
structures.
First the present working processes have to be recorded and classified within the context of a
process analysis using process modeling. To evaluate the quality and performance of such processes
to be described, appropriate key figures (Key Performance Indicator) must be implemented. With the
aid of these obtained process descriptions a process map can be created, which provides a basis for
further optimizations.
This may affect all of the following business sectors: research and development, production, from
administration to purchasing to sales and delivery.
Ideally, the entire business processes as well as the human and material resources of such evaluation
and classification are examined in the context of an integrated e-business concept. The continuously
ongoing process optimization, which is based on such an evaluation, aimed at sustainable
improvement of the given processes without interrupting the workflow.
Well-known management concepts in this context are, for example, Business Process Reengineering
(BPR) in 1991, Six Sigma (early 90s) or Kaizen (1994), etc.
4
Process optimization methods-
Approaches
When you want to optimize a process you can do this from a variety of approaches. Below there are
a list of five common procedures, after these it follows a number of tools you can implement when
you have selected an approach that fits your process.
Business process reengineering is a business management strategy, focusing on the analysis and
design of workflows and business processes within an organization. BPR aimed to help organizations
fundamentally rethink how they do their work in order to dramatically improve customer service, cut
operational costs, and become world-class competitors.
BPR seeks to help companies radically restructure their organizations by focusing on the ground-up
design of their business processes. Re-engineering emphasized a holistic focus on business objectives
and how processes related to them, encouraging full-scale recreation of processes rather than
iterative optimization of sub processes. Business process re-engineering is also known as business
process redesign, business transformation, or business process change management.
BPR is different from other approaches to organization development (OD), especially the continuous
improvement or TQM movement, by virtue of its aim for fundamental and radical change rather than
iterative improvement.
Lean Management
Remove all forms of waste
Lean manufacturing, lean enterprise, or lean production, often simply, "lean", is a production
practice that considers the expenditure of resources for any goal other than the creation of value for
the end customer to be wasteful, and thus a target for elimination. Working from the perspective of
the customer who consumes a product or service, "value" is defined as any action or process that a
customer would be willing to pay for. With the approach to ideally design the processes and to
harmonize them in a way that they perfectly fit together. To do so, all unnecessary items are
identified and the process is designed as lean as possible. The targets: maximum efficiency, clearly
defined responsibilities, exactly described processes and processes, traceable ways of
communication.
5
Kaizen (CIP)
When things are constantly improved through many small modifications
For process optimization, kaizen or coined in Japanese is a management concept, which focuses on
the gradual improvement of processes and on the development of people so that they are able to
solve the problems and the desired results can be achieved.
Its not a project, it is a comprehensive tool and mindset to develop the business. It is used to remove
problems and capitalize opportunities for improvement. This work is driven by employees with
management support. The industry was the first to use that tool by Toyota and Sony. But it is now
also used in the service sector as medical, health and dental care, municipalities, schools, banks and
others.
Six Sigma
Quality improvement strategy focused on removing variability from a process
Is a methodology for improvement, the goal is to achieve savings by reducing the causes of defects
and variability in manufacturing and business processes. The method is used primarily by large
manufacturing companies for example in manufacturing or automotive industry in order to become
even more cost effective.
Six Sigma is a statistical method within the area of quality management with the approach define
measure analyze improve - monitor. Is frequently used in manufacturing processes to increase
the quality level. The Six Sigma methodology requires a special training for the company staff, it
means talking about the different roles that staff can fill depending on their level of education.
Six Sigma is a quality improvement strategy focused on removing variability from a process. Although
originally developed for manufacturing processes, the Six Sigma methodology has been successfully
applied to a wide range of processes. As a tool for process improvement and reduction of defects, Six
Sigma compliments Lean and is a component of many Lean programs.
6
Tools - in improvement processes
Process optimization methods provide you with the tools and techniques you will need to
successfully optimize your current processes. The programs will provide you with the knowledge,
techniques and methods that is used to optimize processes. Today you can find many different tools.
In this report we are focussing of some basic tools.
Mind maps
A diagram used to visually out like information
A mind map is a diagram used to visually outline information. A mind map is often created around a
single word or text, placed in the centre, to which associated ideas, words and concepts are added.
Major categories radiate from a central node, and lesser categories are sub-branches of larger
branches. Categories can represent words, ideas, tasks, or other items related to a central key word
or idea. Mind maps offer great flexibility and can present complex systems in a very easy to
understand format. The strategy of mind mapping are to help persons to quickly relate a central
word or concept. The mind forms associations almost instantaneously and 'mapping' allows you to
write your ideas quicker, using only words or phrases. Mind Maps help organise information. This can
allow people to develop a strategy for note-taking, creative writing, report writing, studying the easy
way, studying as a group, meetings, think tanks and can alleviate writer's block.
Example
The following guidelines for creating mind maps:
1. Start in the centre with an image of the topic, using at least 3 colours.
2. Use images, symbols, codes, and dimensions throughout your mind map.
3. Select key words and print using upper or lower case letters.
4. Each word/image is best alone and sitting on its own line.
5. The lines should be connected, starting from the central image. The central lines are thicker,
organic and thinner as they radiate out from the centre.
6. Make the lines the same length as the word/image they support.
7. Use multiple colours throughout the mind map, for visual stimulation and also to encode or
group.
8. Develop your own personal style of mind mapping.
9. Use emphasis and show associations in your mind map.
10. Keep the mind map clear by using radial hierarchy, numerical order or outlines to embrace
your branches.
This list is itself more concise than a prose version of the same information and the mind map of
these guidelines is itself intended to be more memorable and quicker to scan than either the prose
or the list.
Use
Mind maps can be used for:
1. problem-solving
2. outline/framework design
3. structure/relationship representations
4. anonymous collaboration
5. marriage of words and visuals
7
6. individual expression of creativity
7. condensing material into a concise and memorable format
8. team-building or synergy creating activity
9. enhancing work morale
Types
Reference mind maps - for keeping track of information
A reference mind map is a map that contains information organized so that you can find it again
easily. Many types of subject can be broken down and represented this way. You can start by
collecting ideas and facts, then reorganizing them into sections and subsections, so that you get a
complete overview.
- Assembling documents or reports: the topic texts will become the section headings when you
export the mind map to a word processor
- Collecting resources: capture and organize resources such as web pages, companies and
information about people
- Learning about a subject: build a mind map of information and facts to help you learn and
revise
- Keeping lists: keep track of detailed information in categories in different parts of your mind
map
8
Fish Bone
Cause and effect diagram
Fishbone, a Cause and Effect Diagram displays graphically the factors and underlying causes of a
defect or problem. A fishbone diagram, also called Ishikawa diagram, is a visualization tool for
categorizing the potential causes of a problem in order to identify its root causes. When you have a
serious problem, it's important to explore all of the things that could cause it, before you start to
think about a solution. That way you can solve the problem completely, first time round, rather than
just addressing part of it and having the problem run on and on, in this case you can use a fishbone
diagram.
The factors are drawn on lines radiating out from a central line. The completed diagram resembles a
fish skeleton hence the nickname. Cause and Effect Analysis is a mix of brainstorming and mind
mapping and it was originally developed as a quality control tool, but you can use the technique just
as well in other ways. For instance, you can use it to:
A fishbone diagram is useful in brainstorming sessions to focus conversation. After the group has
brainstormed all the possible causes for a problem, the facilitator helps the group to rate the
potential causes according to their level of importance and diagram a hierarchy. The design of the
diagram looks much like a skeleton of a fish. Fishbone diagrams are typically worked right to left,
with each large "bone" of the fish branching out to include smaller bones containing more detail.
Fishbone diagrams are used in the "analyse" phase of Six Sigmas DMAIC (define, measure, analyse,
improve, control) approach to problem solving.
Causes in the diagram are often categorized. Cause-and-effect diagrams can reveal key relationships
among various variables, and the possible causes provide additional insight into process behaviour.
Causes can be derived from brainstorming sessions. These groups can then be labelled as categories
of the fishbone. They will typically be one of the traditional categories mentioned above but may be
something unique to the application in a specific case.
9
Procedure
- Create a head, which lists the problem or issue to be studied.
- Create a backbone for the fish (straight line which leads to the head).
- Identify at least four causes that contribute to the problem. Connect these four causes
with arrows to the spine. These will create the first bones of the fish.
- Brainstorm around each cause to document those things that contributed to the cause.
Use the 5 Whys or another questioning process such as the 4Ps (Policies, Procedures, People
and Plant) to keep the conversation focused.
- Continue breaking down each cause until the root causes have been identified.
This example illustrates how a group might begin a fish diagram to identify all the possible reasons a
web site went down in order to discover the root cause.
10
DMAIC Define, Measure, Analyse, Improve and Control
DMAIC refers to a data-driven improvement cycle used for improving, optimizing and stabilizing
business processes and designs. The DMAIC improvement cycle is the core tool used to drive Six
Sigma projects. However, DMAIC is not exclusive to Six Sigma and can be used as the framework for
other improvement applications.
Define
The purpose of this step is to clearly articulate the business problem, goal, potential resources,
project scope and high-level project timeline. This information is typically captured within project
charter document. Write down what you currently know. Seek to clarify facts, set objectives and
form the project team. Define the following:
- A problem
- The customer(s)
- Voice of the customer (VOC) and Critical to Quality (CTQs) what are the critical process
outputs?
- The target process subject to DMAIC and other related business processes
- Project targets or goal
- Project boundaries or scope
- A project charter is often created and agreed upon during the Define step.
Measure
The purpose of this step is to objectively establish current baselines as the basis for improvement.
This is a data collection step, the purpose of which is to establish process performance baselines. The
performance metric baseline(s) from the Measure phase will be compared to the performance
metric at the conclusion of the project to determine objectively whether significant improvement has
been made. The team decides on what should be measured and how to measure it. It is usual for
teams to invest a lot of effort into assessing the suitability of the proposed measurement systems.
Good data is at the heart of the DMAIC process:
Analyse
The purpose of this step is to identify, validate and select root cause for elimination. A large number
of potential root causes (process inputs, X) of the project problem are identified via root cause
analysis (for example a fishbone diagram). The top 3-4 potential root causes are selected using multi-
voting or other consensus tool for further validation. A data collection plan is created and data are
collected to establish the relative contribution of each root causes to the project metric, Y. This
process is repeated until "valid" root causes can be identified. Within Six Sigma, often complex
analysis tools are used. However, it is acceptable to use basic tools if these are appropriate. Of the
"validated" root causes, all or some can be
11
- Identify how the process inputs (Xs) affect the process outputs (Ys). Data is analysed to
understand the magnitude of contribution of each root cause, X, to the project metric, Y.
Statistical tests using p-values accompanied by Histograms, Pareto charts, and line plots are
often used to do this.
- Detailed process maps can be created to help pin-point where in the process the root causes
reside, and what might be contributing to the occurrence.
Improve
The purpose of this step is to identify, test and implement a solution to the problem; in part or in
whole. Identify creative solutions to eliminate the key root causes in order to fix and prevent process
problems. Use brainstorming or techniques like Six Thinking Hats and Random Word. Some projects
can utilize complex analysis tools like DOE (Design of Experiments), but try to focus on obvious
solutions if these are apparent.
Control
The purpose of this step is to sustain the gains. Monitor the improvements to ensure continued and
sustainable success. Create a control plan. Update documents, business process and training records
as required.
A Control chart can be useful during the Control stage to assess the stability of the improvements
over time by serving as
7 Wastes
Toyota developed its production system, striving for Excellence, with a keen sensitivity to waste.
Toyota executive Taiicho Ohno (1912-1990) defined The 7 Deadly Wastes (muda).
12
5. Waste in production process
6. Useless motions
Many companies are producing more than necessary because they loose parts, products, material!
Without order, care and discipline in storage, inventories will fill all available space. Temporary
storing a batch in a non defined / dedicated area is risky, as someone could move the batch without
care nor notice In such a case, it is likely to loose its track, all ending in a waste of raw material,
energy and man power.It may lead to a double waste if the lost batch requires to produce a new one
be delivered!
Eliminating the wasted space and valuable surface by excess inventories and overproduction
is a potential improvement.
5S can be used to setup rules for storing, define space and places. These rules have to be
widely communicated so that everyone knows where is what, why and for how long. While
continuously improving the situation, the rules have to be updated and stick to the newest
state.
Are the items you are waiting for really necessary? If they're not, if they do not add value to the job
or the product, it it wise to try to eliminate them or at least reduce the waiting time and storage
distances.
Computers with plenty and poorly ordered data on hard disk drives slow down.
Did you consider directories and files as candidates for 5S?
The necessity to move and transport can be caused by the previously mentioned wastes. All
transportations may not be eliminated, but they have to be kept to the very minimum.
Looking for a pallet truck to move crates or pallets is a common occupation in the workshops. People
most often claim for more trucks, but a proper set of rules, parking areas and discipline to bring them
back after use is enough to solve availability problems.
13
4. Waste related to useless and excess inventories
In the 5S way, anything that is useless is to be eliminated. In case of inventories, the gain is the value
of the goods stored and the regained spaces, which must be dedicated preferably to value creating
activities.
Paper documents and their numerous copies, catalogues and calendars of previous years, files and
data, dry and worn out pens and pencils... all excess inventories!
Procedures and work guides which are not constantly updated are likely to let useless operations be
performed in the process. Sorting and ordering applies also in the sequences of the process and the
related documents.
This type of waste is also common in administration processes and office work. Old rules still remain
even if the causes of their creation disapeared a while ago. As long as nobody will update the set of
rules, everyone will carry on, sticking to the olds with application and discipline(!!).
6. Useless motions
Ergonomics of the work place is certainly the most popular and "visible" application of the 5S. The
layout and display of the area will follow the 5S logic, favoring availability of necessary items,
distance of reach, ease for tending...
Among useless motions, do not forget the walks to search for missing items, data, instructions,
complementary information...
Number of defects and quality problems can be directly linked to the work place state:
Assembly mistakes (parts mismatch) due to jammed work table with parts from differents models /
series
Forgotten parts in assembly, the parts could not be seen in the mess on the table
Scratches on parts by scap form the work table (burrs, dirt, parts...)
8. Waste from confusion Any missing or misinformation. Any goals or metrics that cause
uncertainty about the right thing to do.
14
9. Waste from unsafe or unergonomic work conditions - Office work conditions that cause carpel
tunnel, eye fatigue, chronic back pain, or that compromise the health and productivity of
workers in any way.
10. Waste from underutilized human potential skills, talents, and creativity. Restricting
employee's authority and responsibility to make routine decisions. Having highly paid staff do
routine tasks that don't require their unique expertise. Not providing the business tools needed
to perform and continuously improve each employee's assigned work. Not trusting your people
to stop production to stop and fix a problem (jidoka). Not trusting your people to be responsible
for the cleanliness, maintenance, and organization of their own work area. Not trusting people
with a flat organization structure of largely self-directed teams. Not expecting (and measuring)
every person to contribute to continuous improvement.
Principle of 5 S
The 5S philosophy is a way of thinking, focusing on effective work place organization, simplified work
environment, strives waste reduction while improving quality and safety.
The five S stand for the five first letters of these Japanese action words:
Meaning
Seiri Sort
Seiton Set in Order
Seiso Shine
Seiketsu Standardize
Shitsuke Systematize
Figure 2. Principle of 5 S.
Calling these principles the "5S" is a good way to remember their meaning and content.
Developed in Japan, this method assume no effective and quality job can be done without clean and
safe environment and without behavioral rules.
The 5S allow to set up a well -adapted and functional work environment, ruled by simple yet
effective rules.
5S deployment is to be done in a logical and progressive way. The 3 first S are shop floor actions,
while the 2 lasts are sustaining and progress actions.
15
It is recommended to start implementing 5S in a well-chosen pilot workshop or pilot process, and
spread to the others step by step
What is 5S?
1. Seiri - Sort
Sorting, keep the necessary in work area, dispose or keep in a distant storage area less frequently
used items, unneeded items are discarded.
Seiri fights the habit to keep things because they may be useful someday. Seiri helps to keep work
area tidy, improves searching and fetching efficiency, and generally clears much space. Seiri is also
excellent way to gain valuable floor space and eliminate old broken tools, obsolete jigs and fixtures,
scrap and excess raw material.
Systematic arrangement for the most efficient and effective retrieval. A good example of Seiton is
the tool panel. Effective Seiton can be achieved by painting floors to visualize the dirt, outlining work
areas and locations, shadow tool boards. An example of Seiton are "broom carts". As cleaning is a
major part of 5S we custom made carts to hold brooms, mops and buckets. Several carts have
specific locations and all employees can find them.
Seiton saying would be: "A place for everything and everything on its place."
3. Seiso - Shine
Cleaning. After the first thorough cleaning when implementing 5S, daily follow-up cleaning is
necessary in order to sustain this improvement. Cleanliness is also helpful to notice damages on
equipment such as leaks, breakage and misalignment. These minor damages, if left unattended, coul
lead to equipment failure and loss of production. Regular cleaning is a type of inspection. Seiso is an
important part of basic TPM; Total Productive Maintenance and Safety matter through cleanliness is
obvious.
4. Seiketsu - Standardize
Standardizing. Once the first three S have been implemented, it should be set as a standard so to
keep these good practice work area. Without it, the situation will deteriorate right back to old habits.
Have an easy-to-follow standards and develop a structure to support it. Allow employees to join the
development of such standards.
The 3 first S are often executed by order. Seiketsu helps to turn it into natural, standard behavior.
16
5. Shitsuke - Systematize
Finally, to keep first 4 S alive, it is necessary to keep educating people maintaining standards. By
setting up a formal system; with display of results, follow-up, the now complete 5S get insured to
live, and be expanded beyond their initial limits, in an ongoing improvement way; the Kaizen way.
The effect of continuous improvement leads to less waste, better quality and faster lead times.
Everyone and all types of business benefit from having a 5S program. Manufacturing and industrial
plants come to mind first, as those are the business that can realize the greatest benefits. However,
any type of business, from a retail store to a power plant from hospitals to television stations all
types of businesses, and all areas within a business, will realize benefits from implementing a 5S
program.
PDCA (Plan-Do-Check-Act/Adjust)
Definition
PDCA (PlanDoCheckAct or PlanDoCheckAdjust) is an iterative four-step management method
used in business for the control and continuous improvement of processes and products.
Example
Figure 3. PDCA.
17
Use
PDCA cycle consists of the following steps:
- PLAN: Establish the objectives and processes necessary to deliver results in accordance with
the expected output (the target or goals). By establishing output expectations, the
completeness and accuracy of the spec is also a part of the targeted improvement. When
possible start on a small scale to test possible effects.
- DO: Implement the plan, execute the process, make the product. Collect data for charting
and analysis in the following "CHECK" and "ACT" steps.
- CHECK: Study the actual results (measured and collected in "DO" above) and compare
against the expected results (targets or goals from the "PLAN") to ascertain any differences.
Look for deviation in implementation from the plan and also look for the appropriateness
and completeness of the plan to enable the execution, i.e., "Do". Charting data can make this
much easier to see trends over several PDCA cycles and in order to convert the collected data
into information. Information is what you need for the next step "ACT".
The main principle of the one-piece flow is the design of cells in the production process: Parts of the
production process and the according job tasks are arranged in sections in the so-called "cells". In the
design of cell production factory floor labor are arranged into semi-autonomous and multi-skilled
teams, or work cells, who manufacture complete products or complex components. Properly trained
and implemented cells are more flexible and responsive than the traditional mass-production line,
and can manage processes, defects, scheduling, equipment maintenance, and other manufacturing
issues more efficiently. The cells help to prevent that the task sizes for individual workers are too big
and they lose routine and exercise and so on working speed and quality. The employee starts on the
first working system of the cell and moves on with the product work system to work system of the
cell. The first and the last work station in a cell should be as close together as possible, so that the
employee can start the process anew. This is why assembly lines in cells are mostly U- or Omega-
shaped.
1
Source: Marton, Michal / Paulov, Iveta (2011): ONE PIECE FLOW - ANOTHER VIEW ON PRODUCTION FLOW IN THE NEXT CONTINUOUS
PROCESS IMPROVEMENT, s. https://www.mtf.stuba.sk/docs//internetovy_casopis/2011/1/PDF/marton_paulova.pdf (09.04.2014).
18
Figure 4. One-piece flow manufacturing environment.
There is little relationship between each manufacturing step and the steps immediately
19
upstream or downstream. This results in:
- Large amounts of scrap when a defect is found because of large batches of WIP (work/goods
in process)
- Long manufacturing lead time
- Poor on-time delivery and/or lots of finished goods inventory to compensate,
- Large amounts of WIP
Use
For implementing one-piece flow the following steps should be considered:
1.) Decide which products or product families will go into the one-piece flow cells, and
determine the type of cell: Product-focused or mixed model. For product focused cells to
work correctly, demand needs to be high enough for an individual product. For mixed model
cells to work, changeover times must be kept short; a general rule of thumb is that
changeover time must be less than one tact time.
2.) The next step is to calculate tact time for the set of products that will go into the cell. Tact
time is a measure of customer demand expressed in units of time and is calculated as
follows:
Tact time = Available work-time per shift / Customer demand per shift
3.) Next, determine the work elements and time required for making one piece. In much detail,
list each step and its associated time. Time each step separately several times and use the
lowest repeatable time. Then, determine if the equipment to be used within the cell can
meet tact time. Considerations here include changeover times, load and unload times, and
downtime. The next step is to create a lean layout. Using the principles of 5-S (eliminating
those items that are not needed and locating all items/equipment/materials that are needed
at their points of use in the proper sequence), design a layout. Space between processes
within a one-piece flow cell must be limited to eliminate motion waste and to prevent
unwanted WIP accumulation. U-shaped cells are generally best; however, if this is impossible
due to factory floor limitations, other shapes will do. For example, I have implemented S-
shaped cells in areas were a large U-shape is physically impossible.
4.) Finally, balance the cell and create standardized work for each operator within the cell.
Determine how many operators are needed to meet tact time and then split the work
between operators. Use the following equation: Number of operators = Total work content /
Tact time
Pareto chart
Definition
A Pareto chart is a bar chart, which contains both bars and a line graph, where individual values are
represented in descending order by bars and the cumulative total is represented by the line. It is
named after the Italian economist Vilfredo Pareto and finds use inter alia in statistics.
20
The purpose of the Pareto chart is to highlight the most important among a (typically large) set of
factors. In quality control, it often represents the most common sources of defects, the highest
occurring type of defect, or the most frequent reasons for customer complaints, and so on.
The left vertical axis is the frequency of occurrence, but it can alternatively represent cost or another
important unit of measure. The right vertical axis is the cumulative percentage of the total number of
occurrences, total cost, or total of the particular unit of measure. Because the reasons are in
decreasing order, the cumulative function is a concave function.
Example
Use
For using a Pareto chart the following steps should be considered:
2.) Then categories are formed, e.g. for types of error or causes or for products, customers,
products, suppliers.
3.) In addition, a quantity type must be determined by which one can clarify the effects of a
problem. The most common quantity types are the frequency of occurrence, or the cost
incidence (number multiplied by expense ratio), or the likelihood and impact.
4.) To create the Pareto diagram the percentage of each error category is determined from the
absolute frequency: Subset / Total * 100 = % Frequency
5.) Afterwards the error categories are sorted in descending order according to their importance
and then plotted on the horizontal axis from left to right. For each error category a column is
drawn, whose height corresponds to the frequency of occurrence. The columns are stacked
on one another from left to right, the result is the Pareto curve, which reflects the
accumulated percentage value.
21
Ratios
What gets measured gets done!
Figure 7. PDCA-circle.
22
Every corrective action taken must be testable and thus measurable. You can only make
meaningful changes to what you can measure.
Ratios replace assumptions with facts and make informed decisions possible in the first
place.
23
Ratios for FIS ("Factory in a Seminar Room")
Ratios help to analyse a current state and to review the effectiveness of the corrective
actions taken which then makes it possible to establish a new standard. All actions taken
should be in tune with the company goals (for example: attaining the highest possible
ROI/return on investment, making corresponding profits, etc). As depicted in the project
management triangle, the factors cost quality time are interrelated which means it is
necessary to define goals and priorities.
When conducting FIS, ratios should predominantly be chosen that are suitable for measuring
the methods used (for example CIP, Kaizen, Value Stream, etc). Consideration should be
given as to what kind of information will be available in FIS and the ratios should be able to
be calculated and analysed both easily and quickly.
The methods applied in FIS (see above) mainly address process potential. As can be seen in
the following image, the focus is on measuring and reducing the non-value adding time
(90% - 95%).
Management of costs can be covered using the ROI ratios from the DuPont method, as an
example.
24
Ratios TIME / PROCESS POTENTIAL
These ratios focus above all on the measurement/reduction of time (queue time, idle
time, on time delivery) and on measuring and increasing efficiency.
Lead time
Lead time is the period of time between the placing of an order until the item is shipped. It
includes production time, transport time and queue time.
Lead time
25
Allocation rate
The allocation rate shows the degree of process density and therefore the amount of WIP
(work in progress) and queue and idle times. The time that needs to be allocated is the
standard time for equipment (machines). It includes processing time, changeover time and
downtime.
Throughput
Throughput specifies the performance/efficiency of a process.
Employee productivity
This ratio measures the relation of productive time to attendance time in %.
Unit productivity
This ratio provides information based on the units produced relative to one employee hour.
26
Ratios - QUALITY
Quality rate
This ratio gives information about the losses that arise due to a noncompliance with
specifications that apply to the produced units.
Scrap rate
This ratio gives information about the extent of the loss made due to scrap (number of
scrapped units in %).
Rework rate
This ratio calculates the extent of losses made due to rework (amount of products in need of
reworking in %).
!
Ratios - COSTS
Return on Investment
A possible company objective may be to achieve the highest possible return on total capital.
The DuPont ROI tree helps to show which influences affect the ROI, including both income
statements and balance sheets.
27
Figure 11. Return on investment.
In FIS, the contribution margin is calculated using the net sales and the variable costs.
For the fixed costs, the FIS director makes an estimation. The fixed costs are deducted
from the contribution margin to determine the net profit.
Net sales are divided by the net profit to determine the net profit margin.
To compare this to the capital invested in FIS, the FIS director has to again make
estimations for the total assets. This makes it possible to determine the asset turnover
(net sales/total assets).
ROI is calculated using asset turnover * net profit margin.
The ROI can be increased by
- Increasing sales
- Reducing costs (variable and fixed costs)
- Reducing the invested assets.
Spaghetti Diagram
The primary goal when creating a spaghetti diagram is to detect waste in work processes.
28
A spaghetti diagram makes it possible to clearly depict types of waste, in particular the waste types
"transportation" and "motion".
In a layout of the production area, the trips made during the production process are tracked with
lines. The less productive a process flow is, the more cluttered the organisation of the lines on the
layout will be. The name spaghetti diagram comes from the fact that such plots often look like a plate
of spaghetti noodles.
Goals:
29
type "transportation". However it should be taken into account that transport is often
associated with unnecessary movement.
Advantages:
Learning to use this tool is simple and it is easy to apply. A spaghetti diagram provides a simple yet
powerful depiction of waste in a production process.
Procedure:
30
Observation period: 1 hour Date: 20 June 2010
Distance
Number Total
From Location 1 description To Location 2 description Comments [m] of trips distance
E Carton for finished products H Hand lift Hand lift retrieved 8.0 2 16.0
B Assembly table G Stock shelf - small parts Small parts supplied 5.2 3 15.6
Value stream mapping is a method which makes it possible to visually depict the current state of
production and/or assembly and to detect wastes.
The goal is to first reduce waste and to subsequently shorten the lead time or the efficiency of a
process. Value stream mapping is a tool which helps to identify the root causes of waste.
When a value stream is mapped out, material and information flows are illustrated in a clear and
transparent manner. In order to holistically improve a process, it is necessary to understand how
both flows are interrelated!
31
Step 1 Choose a product
The first step is to choose a product to be analysed using value stream mapping.
An example follows for a loader crane.
The current state of the production and/or assembly of the product is mapped using simple,
predefined symbols.
KEY German-English
Symbole fr Materialfluss = Symbols for material flow
Montage = Assembly
Fertigungsprozess = Production process
XYZ Unternehmen = XYZ company
Externe Quellen = External sources (suppliers, customers)
Sek = sec.
Min = min.
3 Schichten = 3 shifts
Datenkasten = data box icon
Mon + Mittw = Mon + Wed
Lieferung per LKW = Delivered by truck
PUSH Pfeil = PUSH arrow
Fertigwaren an den Kunden = Finished product sent to customer
The material flow is mapped "backwards", i.e. from shipping back to the receipt of goods. This makes
it possible to view the flow from the customer's perspective. This method for recording the current
situation is called value stream mapping.
32
Figure 15. Example of a current state map (Source: Rother/Shook 2006)
Figure 16. Information can initially be documented on a flip chart (see picture).
33
Figure 17. Digital (Excel) current state map.
Step-by-step mapping of the current state (Source: www.ipe-gmbh.de) [Only available in German online]
KEY German-English
3) Mapping the CURRENT state
2) Quick walk through to identify the sequence of the major processes
This step gives a broad overview of the production process. A quick walk through helps to identify the main processes (helicopter
perspective)
Kunde = customer
20,000 units/mo.
Container = 20 units
2 shifts
Stanzen = Stamping
Frsen = Milling
Schweien = Welding
Montage = Assembly
Versand = Shipping
34
Figure 19. Step-by-step mapping of the current state.
KEY German-English
4) Add supply information
Name and location of supplier
Quantity delivered / Transport unit
Delivery cycle (Delivery frequency)
Delivery type
Lieferant = Supplier
Di + Do = Tues + Thurs
5 Tage = 5 days
Versand = Shipping
The next step is to ask yourself certain key questions about where you want to be in the future and
to plot an image of an optimised, future value stream. This is called value stream design.
The map made of the current status of each assembly process serves as the basis for the analysis
phase.
Due to the amount of time it takes to collect data, we have added data from our ERP System (SAP) to
complement the classic methods for recording time and determining each buffer stock.
35
An explanation of each area of potential follows:
Made to order production at PALFINGER makes it possible for every customer to order a crane (size
& model) which suits their individual needs.
While this provides quite a considerable advantage when it comes to customer satisfaction, it also
leads to problems in production and assembly.
The range of models offered by PALFINGER ranges from standard to high end products. This leads to
substantial differences in the takt times between each workplace.
Missing parts:
Due to delivery problems with some subsuppliers, a large amount of cranes could not be completed
and had to be put into interim storage. This led to high storage costs for semi-finished products.
High inventory levels were caused by the previously mentioned missing parts and also by an
outdated push system which was used in assembly. This led to unnecessarily high buffer stock
inventories between each work cell.
Information flow:
In assembly at the moment, every assembly work place is equipped with a preview chart which gives
employees an overview of the cranes to be assembled.
36
Figure 20. A future state map.
The ideal state is depicted at the very top as the "one piece flow" which is called the "North star" here (the
North star represents a distant goal that we would like to reach in the future).
In one piece flow, every operation is given the same takt time to complete a work step and all work cells are
arranged like an assembly line which provides the following advantages:
buffers are no longer necessary
additional storage areas become unnecessary
transport and manipulation of material becomes unnecessary
In the second and third position of the graphic there are two types of pull systems. Pull means that every
workplace (work cell) sets the takt time for the next workplace. As a result, only what is truly needed is actually
produced/assembled.
Our starting point is the widespread push system. Push means that every work cell produces using all of the
raw material available to that cell, regardless of what the following work cell needs.
This inevitably leads to an unnecessary accumulation of buffer stock, to unnecessary transport and to
unnecessary manipulation of material.
Based on the future state map, actions are developed which are necessary to reach the newly defined future
state. These actions are documented, allocated and prioritised in an action plan.
A small selection of our corrective actions follow, some of which have already been implemented and others
which are to be implemented in the future.
37
Figure 21. Balancing takt times.
KEY German-English
Takt time for workplace Base frame preassembly
Normale Ausfrhung = Normal model
High End Kran = High End crane
Vorher = Before
Nachher = After
The problem with workplace different takt times as a result of offering different crane models can be
solved using supermarket pull systems.
These supermarket pull systems help to harmonise the different takt times as well as the daily
capacity requirements over a broad range of work cells. This is achieved by preassembling time-
consuming assemblies (e.g. electronic assemblies, support cylinders) on days with a lighter workload
which can then be taken out of the system on days with a heavier workload. Modular construction of
crane equipment helps us to keep the variety of components low in the supermarket systems. The
effect that this has on takt time is displayed in the diagram on the right.
Initially, 4 or 8 hours were necessary to complete a work step. With the supermarket pull system, this
difference is harmonised which means that the workplace now needs 6 hours to complete every
crane, regardless of which model.
The following images demonstrate how these modifications look digitally in a value stream map.
38
Figure 23. After modifications in a value stream map.
39
Figure 25. Arrival and departure times.
Because the train is able to tow twelvefold the load volume of a forklift, just one delivery replaces eleven
forklift runs and therefore reduces the high number of empty runs.
40
Step by step mapping of the current state
(Source: www.ipe-gmbh.de)
KEY German-English
3. Mapping the CURRENT state
1. Record customer information
Data box includes:
Customer information
Requested products
Requested quantity
Container volume
Order and shipping intervals
NOTE: For all repeated symbols, please refer to the translations on page 34 and 35
Figure 27. Mapping the current state. Quick walk through to identify the sequence of the major processes.
KEY German-English
Please refer to the translation on page 34
41
Figure 28. Mapping the current state. Second walk through for to collect detailed data.
KEY German-English
3. Second walk through for to collect detailed data / create a CURRENT state map
Add the data boxes and inventories
Record all process steps and relevant parameters:
Number of employees
Cycle time / process time
Setup time / Batch size
Number of product variations
Shifts
Container volume
Availability
Scrap / rework rate
KEY German-English
See page 35 for translations except for Tglich = daily:
42
Figure 30. Mapping the current state. Add information flow.
KEY German-English
5. Add information flow
If production is managed by a planning department, this is placed at a central position (red).
All processes that are managed by planning are mapped with an arrow.
Information (orders) that include plans from customers and/or suppliers is also shown accordingly.
Electronic data exchange is shown with an arrow that resembles lightning.
Figure 31. Mapping the current state. Calculating the lead times.
KEY German-English
6. Calculating the lead times
43
Determine Customer takt time = available operating time per unit of time / customer demand per unit of time
Determine Process lead time = (inventory before the process) x Customer takt time
Determine Overall lead time = Sum of all process lead times
KEY German-English
Example calculation (Lead time for welding)
Process lead time = 1700 units x 1 unit/min. = 1700 min. 28.3 hours 1.8 days (using 2 shifts)
Overall lead time = 5 days + 7.6 days + 1.8 days + 2.6 days + 2 days + 4.5 days = 23.5 days
44
Figure 33. Mapping the current state. Determining lead times.
KEY German-English
Determining lead times
Lead time is the time that elapses start-to-finish during the production of a product.
The lead time thus comprises the sum of all process times, idle times and queue times.
The customer takt time simultaneously defines the minimum output takt time; an output takt time under customer takt time would entail
waste in the form of overproduction. In value stream mapping, lead time is calculated in relation to customer takt time:
Lead time is therefore calculated independently from the cycle times of each process.
45