Estimation
Estimation
Estimation
1 Brick work
outer wall 1 66.63 0.75 9
internal wall 1 20.07 0.33 9
total
Deduction
Door1 1 4 0.75 7
Door 2 1 3.5 0.75 7
window 1 6 0.75 4.5
Total
Total
2 Pcc for RCC
column 8 9.33 1 0.75
beam 1 237.83 0.75 1
slab
staircase 1 23 3.5 1.5
Total
3 Reinforcement
column
16mm dia bar 8*4 9.33
12mm dia bar 0 0
Beam
16mm dia bar 4 237.83
12mm dia bar 2 237.83
slab
0.02%of pcc
for staircase 0.025% of pcc for rcc
total
4 plastering work
outer wall 1 85.84 9
inner wall 1 85.38 9
staircase 1 35.33 9
total
5 punning work
floor area 1 367
Quantity
449.7525
59.6079
509.3604
21
18.375
20.25
59.625
449.7354
55.98
178.3725
178.5
120.75
533.6025
121.3658536585 kg
80.9105691057 kg
257.810298103 kg
128.9051490515 kg
357.5567054154
241.8765948398
1188.4251701739
772.56
768.42
317.97
1858.95
367
ABSTRACT
S.NO Description of item Quantity unit
1 Brick work 449.73 cu ft
2 Pcc for RCc 533.6 cu ft
3 reinforcement 835.99 kg
4 plastering 1858.95 sq.ft
5 punning 357 sq.ft
1cu.ft=0.0283 m3 0.028353
size of brick=230mm*110mm*55mm
thickness of mortar joint =10mm
so ,size of brick with mortar =240mm*120mm*65mm
No. of brick required =1/0.24*0.12*0.065
= 534.188 _534nos for 1m3
adding 5% wastage =1.05*534 nos
560.7
similarly, for 12.72 m3
7123.2
for 12.72 m3 , 7124 nos brick are required
volume of mortar required=12.72-7124*(0.23*0.11*0.055)
2.806954 m3
adding 30% of extra material
therefore, total volume of ingredients required for cement mortar
2.80+30/100*2.80
3.64
total part of mix =1+6
7
cement required=1/7*3.64
748.8 kg/m3
748.8/50 bags
14.976 bags
sand=6/7*3.64
3.12
w/c=0.5
w=0.5*748.8
374.4 ltr
materials quantity
no of bricks 7124
cement 15bag
sand 3.12m3
water 375 ltr
volume of pcc=15.10m3 (1:1.5:3)
for pcc,50-55% of extra material is required due to the reduction of volume during mixing ,losses of material during
therefore, total volume of concrete required=1.5*15.10 m3
22.65 m3
total part of mix proportion=1+1.5+3
5.5
cement required= 1/5.5*22.65
c=4.11*1440kg/m3
5918.4 kg
118.368 bag
119 bag
Total volume of sand required
1.5/5.5*22.65
6.177273 m3
coarse aggregate
3/5.5*22.65
12.35455 m3
assume w/c ratio=0.5
w/c=0.5
or, w=0.5*5918.4
2959.2 ltrs
water required= 2960 ltrs
material Quantity
cement 13bag
sand 3m3
water 512ltr
12.72m3 brickwork (1:6)cement mortar
ng ,losses of material during mixing and transportation
for brick work
materials quantity
no of bricks 7124
cement 15bag
sand 3.12m3
for pcc
materials required Quantity
cement 119bag
sand 6.117m3
aggregate 12.55 m3
for plastering
material Quantity
cement 13bag
sand 3m3
Reinforce ment
12mm 588.992
8 mm 599.433
1188.425 KG