Bca 2
Bca 2
Bca 2
CHILLERS
BUILDING NAME: APPLICATION #:
BUILDING ADDRESS:
General Notes:
1. This is a generic test procedure for chillers. If the complexity, configuration, or other aspects of a specific project
require substitute tests or additional tests, explain on the comments sheets, and attach the additional test
procedures and field data. Attach all relevant functional performance verification sheets, and always attach the final
signed and dated procedure certification page.
2. In all test sections, circle or otherwise highlight any responses that indicate deficiencies (i.e. responses that don’t
meet the criteria for acceptance). Acceptance requires correction and retest of all deficiencies, as defined in each
test section under “Criteria for Acceptance” or “Acceptance”. Attach all retest data sheets. Complete the Deficiency
Report Form for all deficiencies.
3. This Commissioning Procedure does not address fire and life safety or basic equipment safety controls.
4. To ensure that this Commissioning Procedure will not damage any equipment or affect any equipment warranties,
have the equipment manufacturer’s representative review all test procedures prior to execution.
DESCRIPTION CHILLER #
Manufacturer
Model #
Serial #
Refrigerant Type
INSTALLATION VERIFICATION:
Instructions: Under each unit write "Y" for yes, "N" for no, "NA" for not applicable, or a number to refer to any needed
comments. If other information is requested such as voltage or frequency, write the appropriate values. “Accessories”
includes chilled water and condenser water pumps, cooling towers, etc. It does not include air handling systems or
secondary pumping systems.
Criteria for Acceptance: Items #1 - 13 require answers of “Y” (or “NA”, where relevant) except where other criteria
are noted.
Caution: Only qualified personnel familiar with the operation of the installed chillers, and the hazards involved, should
adjust, operate, test, and/or service the equipment. The commissioning agent should become familiar with the
installation, operation, and maintenance manuals prior to starting commissioning work. Failure to observe proper
safety precautions could result in damage to equipment, severe bodily injury, and/or loss of life.
DESCRIPTION CHILLER #
14.
15.
Chiller-____:
Evap. water temp. in
Evap. water temp. out
Cond. water temp. in
Cond. water temp. out
Chiller-____:
Evap. water temp. in
Evap. water temp. out
Cond. water temp. in
Cond. water temp. out
CHILLER #
/ /
1. Chiller FLA, design / / / /
/ /
22. Chiller amps, measured / / / /
44.
45.
CHILLER #
26. Chiller appears to meet load (no complaints)
7.
8.
I certify that the data and test results as recorded herein are accurate.
file:\msoffice\winword\docs\scl\cxproc\chlrqas.pro