COST PLANNING
WHAT???
COST PLAN IS NOT AN ESTIMATE
REPRESENTATION OF THE ESTIMATED COST IN A STRUCTURED FORMAT
OR IS AN ANALYSIS OF A CLIENTS PRE-DETERMINED BUDGET SUM WITHIN
WHICH THE DESIGN MUST PROGRESS
ALLOWS PRE-CON COST CONTROL & CON COST MGT
PROCESS??
BUDGET - INCEPTION & FEASIBILITY
OUTLINE COST PLAN - OUTLINE PROPOSALS
SCHEME DESIGN COST PLAN - SCHEME DESIGN
CONTINUOUS COST CHECK - DETAIL DESIGN
DEFINITIONS.??
1. BUDGET
TOTAL EXPENDITURE AUTHORISED BY EMPR
MAXIMUM COST THAT CAN BE EXPENDED
INFORMATION REQD:-
PROJECT PARTICULARS (LOCATION/AREAS/STOREYS)
GEN STATEMENT OF QUALITY & SPECIFICATION
LIKELY BASIS - TOTAL COST PER m OR FUNCTIONAL UNIT
USE HISTORICAL DATA ADJUSTED FOR JOB PARTICULARS
GENERATED FROM COST ANALYSES OF PAST PROJECTS OF SIMILAR TYPE
2. OUTLINE COST PLAN
DETAILS COST TARGETS FOR MAIN ELEMENTS OF A BUILDING WITH APPROX
ELEMENTAL QUANTITY
OBJECTIVE = SET OCST TARGETS FOR MAIN ELEMENTS
AS DESIGN DEVELOPS, TARGETS ARE CHECKED AND ADJUSTMENTS MADE
PROVIDE OPPORTUNITY FOR PRELIMINARY CONSIDERATION OF LCC
INFO REQD:-
OUTLINE DWGS INDICATING ALTERNATIVE PROPOSALS
EMPRS BRIEF RE QUALITY / SPECIFICATIONS
METHODS :-
LIKELY BASIS = APPROX ELEMENTAL QUANTITIES / ELEMENT COST
USE HISTORICAL DATA ADJUSTED FOR PARTICULARS
COMPARE WITH SIMILAR PREVIOUS PROJECTS
3. SCHEME DESIGN COST PLAN
DESIGN PROPOSALS SELECTED, OUTLINE DWGS EMERGE
INFO INCLUDE SECTION & ELEVATION, FINISHES, PLANS
DETAILS COST TARGETS FOR ALL OR MOST OF THE ELEMENTS
OBJECTIVES;
SET OUT DISTRIBUTION OF RESOURCES DESCRIBED BY SCHEME DSN
SET COST TARGETS FOR ALL ELEMENTS