ESTIMATE

NAME OF WORK: Construction Of RCC Bridge No.-4/2 on Choto Athiabari to Bordoulguri Borachuba
[Refer APWD SOR FOR RR For 2016-17 & quantity estimation ]

BRIDGE PROPER
Sl Item of work Cl. No. of Unit Qty
No. MORT & Hs
specification
1 2 3 4 5
1/16. Labour for dismantling all members of the timber bridge (except RM 15.00
53 piles) and stacking them at suitable places as directed (all
members will be under custody of the contractor till taken over
by the Department.) scarfing and joining piles 25cm to 30cm dia
dressed to heartwood 90cm. In length including supplying, fitting
and fixing with 2 nos. of 50mm x 10 mm MS FI clamps and
16mm dia MS bolts and nuts etc. complete as directed
(Refer to quantity estimation)

2/11. Earth work in excavation of foundation of structures as per 304 Cum 129.44
1,1) drawings & technical specifications, including setting out,
construction of shoring and bracing, removal of stumps and other
deleterious matter, dressing of sides and bottom and back filling
with approved material.
I. ordinary soil
A. manual means
(a) without dewatering
(ii) up to 3m depth

3/16. Bored cast-in-situ M35 grade R.C.C. pile excluding 1100,1600 & metre 242.78
89 A reinforcement complete as per drawing and technical 1700
specification and removal of excavated earth with all lifts and
lead upto 1000m.(Pile diameter-1000mm)
(N) without plasticiser

4/16. Levelling course for pile cap 1100 & 1700 Cum, 8.19
96
5/16. Pile load test on single vertical pile in accordance with 1100 Ton 145.82
94 IS:2911(Part-IV).
a). Initial and Routine load test.
6/16. Cement concrete for reinforced concrete in pile cap complete as 1100,1500 & Cum 113.52
94 per drawing and Technical Specification. Including steel 1700
(i) shuttering formwork
(N) without plasticiser
A. RCC grade M25
(i) Using Concrete Mixer

7/16. Supplying, fitting and placing un-coated TMT bar reinforcement 1600 MT 31.35
97 in foundation complete as per drawing and technical specification
(b) with TATA make TMT rebar.
8/16. Plain/Reinforced Cement concrete, in Substructure complete as 1500,1700, Cum 63.30
103 per Drawing and Technical Specifications and steel shuttering 2200
formwork.
(N) without plasticiser
E. RCC Grade M 25
1.Height up to 5.0 m

Case I : Using Concrete Mixer


(Refer to quantity estimation)
9/16. Supplying, fitting and placing TMT bar reinforcement complete Section 1600 & MT 4.97
104 in substructure complete as per drawing and technical 2200
specification
(b) with TATA make TMT rebar.

10/1 Back filling behind End wall of abutment,wing wall & return 1600 & 2200 Cum 94.80
6.10 wall complete as per Drawing and Technical Specification
7 (B) Sandy materials
11/1 Providing weep holes in Brick masonry/Plain/Reinforced each 20.00
6.10 concrete abutment, wing wall/return wall with 100 mm dia AC
6 pipe, extending through the full width of the structure with slope
of 1V :20H towards drawing foce. Complete as per drawing and
Technical specification.

12/1 Supplying, fitting and fixing in position true to line and level 2000 &2200 CuCm 80640.00
6.11 elastomeric bearing conforming to IRC:83 (part-II) section IX
2 and clause 2005 of MoRTH specifications complete including all
accessories as per drawing and Technical specifications.

13/1 Furnishing and placing reinforced / Prestressed cement concrete 1500,1600 Cum 78.00
6.11 in superstructure as per drawing and Technical Specifications. & 1700
5 Including steel shuttering formwork.
(N) Without plasticiser
B. RCC Grade M 25
Case - I : Using Concrete Mixer
ii) For T-beam and alab
(a) Height upto 5m

14/1 Supplying, fitting and placing TMT bar reinforcement in 1600 MT 12.08
6.11 superstructure including splicing complete as per drawing and
6 technical specifications
(b) with TATA make TMT rebar.

15/1 Providing and laying cement concrete wearing coat M 30 grade 1800 Cum 11.36
6.11 including reinforcement complete as per drawing and Technical
8 Specifications

16/1 Construction of pre cast RCC railing of M30 Grade in situ with 2703,1500, RM 47.80
6.12 20 mm nominal size aggregate, true to line and grade, tolerance 1600 & 1700
0 of vertical RCC post not to exceed 1 in 500 center to center
spacing between vertical post not to exceed 2000 mm leaving
adequat space between vertical post for expansion, complete as
per approved drawings and technical specifications.

17/1 Providing and and laying of a strip seal expansion joint catering 2607 RM 15.00
6.13 to maximum horizontal movement upto 70mm, complete as per
4 approved drawings and standard specificatons to be installed by
the manufacturer / supplier or their authorised representative
ensuring compliance to the manufacturer's instructions for
installation.

18/1 Drainage spouts complete as per approved drawings and 2705 Each 10
6.12 technical specifications.
3
19/1 Painting Two Coats on New Concrete Surfaces 1701 sqm 110.90
0.5 Painting two coats including primer coat after filling the surface
with synthetic enamel paint in all shades on new, plastered /
concrete surfaces as per drawing and Technical Specification
Clause 1701

Sub total of Bridge Proper (A)=


PROTECTION WORK
20/1 Providing and laying pitching on slopes laid over prepared filter 1302 Cum 90.21
4.5 media including boulder apron laid dry in front of toe of
embankment complete as per drawing and technical
specifications
A. Stone/Boulder

21/1 Providing and laying filter material underneath pitching in slopes 1302 Cum 54.12
4.6 as per drawing and technical specifications.
22/1 Providing and laying boulders on river bed for protection against 1301 Cum 184.44
4.1 scour with stone boulders weighing not less than 40 kg each
complete as per drawing and Technical specification .without
wire crate

Sub total of Bridge Protection (B)=


Grand Total (A+B)=
Say,
ordoulguri Borachuba

Rate Amount
(in Rs.) (in Rs.)

6 7.00
850.00 12750.00

71.00 9190.00

11694.00 2839069.00

5776.00 47305.00

330.00 48119.00

7514.00 852989.00

72065.00 2259238.00
7982.00 505261.00

72169.00 358606.00

1948.00 184664.00
191.00 3820.00

1.15 92736.00

9014.00 703092.00

70685.00 853875.00

14137.00 160596.00

2193.00 104825.00

13139.00 197085.00

8615.00 86150.00

46.00 5101.00

f Bridge Proper (A)= 9324471.00


1325.00 119522.00

1332.00 72092.00

1325.00 244385.00

ridge Protection (B)= 435999.00


Rs. 9760470.00
Rs. 9760470.00
ESTIMATE

[Refer PWD SOR FOR RR For 2016-17 & quantity estimation ]

BRIDGE PROPER
Sl Item of work Cl. No. of Unit Qty
No. MORT & Hs
specification
1 2 3 4 5
1/16. Labour for dismantling all members of the timber bridge (except RM 15.00
53 piles) and stacking them at suitable places as directed (all
members will be under custody of the contractor till taken over
by the Department.) scarfing and joining piles 25cm to 30cm dia
dressed to heartwood 90cm. In length including supplying, fitting
and fixing with 2 nos. of 50mm x 10 mm MS FI clamps and
16mm dia MS bolts and nuts etc. complete as directed
(Refer to quantity estimation)

2/11. Earth work in excavation of foundation of structures as per 304 Cum 129.44
1,1) drawings & technical specifications, including setting out,
construction of shoring and bracing, removal of stumps and other
deleterious matter, dressing of sides and bottom and back filling
with approved material.
I. ordinary soil
A. manual means
(a) without dewatering
(ii) up to 3m depth

3/16. Bored cast-in-situ M35 grade R.C.C. pile excluding 1100,1600 & metre 242.78
89 A reinforcement complete as per drawing and technical 1700
specification and removal of excavated earth with all lifts and
lead upto 1000m.(Pile diameter-1000mm)
(N) without plasticiser

4/16. Levelling course for pile cap 1100 & 1700 Cum, 8.19
96
5/16. Pile load test on single vertical pile in accordance with 1100 Ton 145.82
94 IS:2911(Part-IV).
a). Initial and Routine load test.
6/16. Cement concrete for reinforced concrete in pile cap complete as 1100,1500 & Cum 113.52
94 per drawing and Technical Specification. Including steel 1700
(i) shuttering formwork
(N) without plasticiser
A. RCC grade M25
(i) Using Concrete Mixer

7/16. Supplying, fitting and placing un-coated TMT bar reinforcement 1600 MT 31.35
97 in foundation complete as per drawing and technical specification
(b) with TATA make TMT rebar.
8/16. Plain/Reinforced Cement concrete, in Substructure complete as 1500,1700, Cum 63.30
103 per Drawing and Technical Specifications and steel shuttering 2200
formwork.
(N) without plasticiser
E. RCC Grade M 25
1.Height up to 5.0 m

Case I : Using Concrete Mixer


(Refer to quantity estimation)
9/16. Supplying, fitting and placing TMT bar reinforcement complete Section 1600 & MT 4.97
104 in substructure complete as per drawing and technical 2200
specification
(b) with TATA make TMT rebar.

10/1 Back filling behind End wall of abutment,wing wall & return 1600 & 2200 Cum 94.80
6.10 wall complete as per Drawing and Technical Specification
7 (B) Sandy materials
11/1 Providing weep holes in Brick masonry/Plain/Reinforced each 20.00
6.10 concrete abutment, wing wall/return wall with 100 mm dia AC
6 pipe, extending through the full width of the structure with slope
of 1V :20H towards drawing foce. Complete as per drawing and
Technical specification.

12/1 Supplying, fitting and fixing in position true to line and level 2000 &2200 CuCm 80640.00
6.11 elastomeric bearing conforming to IRC:83 (part-II) section IX
2 and clause 2005 of MoRTH specifications complete including all
accessories as per drawing and Technical specifications.

13/1 Furnishing and placing reinforced / Prestressed cement concrete 1500,1600 Cum 78.00
6.11 in superstructure as per drawing and Technical Specifications. & 1700
5 Including steel shuttering formwork.
(N) Without plasticiser
B. RCC Grade M 25
Case - I : Using Concrete Mixer
ii) For T-beam and alab
(a) Height upto 5m

14/1 Supplying, fitting and placing TMT bar reinforcement in 1600 MT 12.08
6.11 superstructure including splicing complete as per drawing and
6 technical specifications
(b) with TATA make TMT rebar.

15/1 Providing and laying cement concrete wearing coat M 30 grade 1800 Cum 11.36
6.11 including reinforcement complete as per drawing and Technical
8 Specifications

16/1 Construction of pre cast RCC railing of M30 Grade in situ with 2703,1500, RM 47.80
6.12 20 mm nominal size aggregate, true to line and grade, tolerance 1600 & 1700
0 of vertical RCC post not to exceed 1 in 500 center to center
spacing between vertical post not to exceed 2000 mm leaving
adequat space between vertical post for expansion, complete as
per approved drawings and technical specifications.

17/1 Providing and and laying of a strip seal expansion joint catering 2607 RM 15.00
6.13 to maximum horizontal movement upto 70mm, complete as per
4 approved drawings and standard specificatons to be installed by
the manufacturer / supplier or their authorised representative
ensuring compliance to the manufacturer's instructions for
installation.

18/1 Drainage spouts complete as per approved drawings and 2705 Each 10
6.12 technical specifications.
3
19/1 Painting Two Coats on New Concrete Surfaces 1701 sqm 110.90
0.5 Painting two coats including primer coat after filling the surface
with synthetic enamel paint in all shades on new, plastered /
concrete surfaces as per drawing and Technical Specification
Clause 1701

Sub total of Bridge Proper (A)=


PROTECTION WORK
20/1 Providing and laying pitching on slopes laid over prepared filter 1302 Cum 90.21
4.5 media including boulder apron laid dry in front of toe of
embankment complete as per drawing and technical
specifications
A. Stone/Boulder

21/1 Providing and laying filter material underneath pitching in slopes 1302 Cum 54.12
4.6 as per drawing and technical specifications.
22/1 Providing and laying boulders on river bed for protection against 1301 Cum 184.44
4.1 scour with stone boulders weighing not less than 40 kg each
complete as per drawing and Technical specification .without
wire crate

Sub total of Bridge Protection (B)=


Grand Total (A+B)=
Say,
Rate Amount
(in Rs.) (in Rs.)

6 7.00
850.00 12750.00

71.00 9190.00

11694.00 2839069.00

5776.00 47305.00

330.00 48119.00

7514.00 852989.00

72065.00 2259238.00
7982.00 505261.00

72169.00 358606.00

1948.00 184664.00
191.00 3820.00

1.15 92736.00

9014.00 703092.00

70685.00 853875.00

14137.00 160596.00

2193.00 104825.00

13139.00 197085.00

8615.00 86150.00

46.00 5101.00

f Bridge Proper (A)= 9324471.00


1325.00 119522.00

1332.00 72092.00

1325.00 244385.00

ridge Protection (B)= 435999.00


Rs. 9760470.00