DMRC Ph-Iii Sod 1
DMRC Ph-Iii Sod 1
DMRC Ph-Iii Sod 1
SCHEDULE OF DIMENSIONS
STANDARD GAUGE (1435 mm GAUGE)
INTRODUCTION
The dimensions given in this Schedule of Dimensions are to be observed in all works
on 1435 mm gauge (STANDARD GAUGE) and 3200 mm wide Rolling Stock, unless
prior sanction has been obtained from the Railway Board through the Commissioner of
Metro Railway Safety to execute works which infringe this Schedule of Dimensions
The Under Ground system may be with a Circular Tunnel or Rectangular Box or of any
other suitable shape while Elevated system may be with suitable Over Ground
Structures such as Viaducts. Both, Under Ground and Elevated systems shall have
suitably designed Ballastless (DFF) Track. For depot, the track may be
ballasted/ballastless.
The Schedule of Dimensions (SOD) has been divided into five chapters as under
1
CHAPTER-I
GENERAL
1.1.1 Minimum distance, centre to centre of tracks without any structure between
tracks for tangent (straight) track for:
1.2 CURVES
1.2.1 Minimum radius of curves (horizontal)
Check rail/Restraining Rail shall be provided on curves on main line where radius
is 190m or less. Check rail/Restraining Rail shall not be mandatory for curves in
depots, yards and non-passenger lines where speed is less than 25Kmph. The
clearance between check/restraining rail and running rail shall be suitably
decided by metro.
1.3 GRADIENTS
(ii) The gradient will be compensated for curvature at the rate of 0.04% per
degree of curve.
2
Note:
1.4.1 Minimum horizontal distance from centre of track to any structure for heights
above rail level on level/constant grade tangent track shall be as under:
3
(b) Elevated and At-Grade Sections
Height from rail level Horizontal distance from C.L. of track
(i) Upto 65 mm 1585 mm
(ii) 65 mm to 200 mm 1585 mm increasing to 1745 mm
(iii) 200 mm to 305 mm 1745 mm increasing to 1771 mm
(iv) 305 mm to 880 mm 1771 mm increasing to 1903 mm
(v) 880 mm to 1095 mm 1903 mm
(vi) 1095 mm to 1130 mm 1903 mm increasing to 1938 mm
(vii) 1130 mm to 2030 mm 1938 mm
(viii) 2030 mm to 3300 mm 1938 mm decreasing to 1875 mm
(ix) 3300 mm to 3736 mm 1875 mm decreasing to 1540 mm
(x) 3736 mm to 6250 mm 1540 mm
i) Extra allowance shall be provided for curves as laid down at para 1.7.
ii) The term structure covers any item including light ones like ladders,
isolated posts, cables etc. erected alongside the track.
iii) Minimum lateral clearance for OHE masts for tangent track shall be 2150
mm from Centre line of nearest track.
iv) For passenger platform refer to para 2.2.1 to 2.2.3 of chapter 2.
4
clearance of 320 mm from 25 KV live parts conforming to the stipulations in
chapter-4 of this SOD.
Refer to Figure No. DMWSG-2, for Structure Gauge for outside stations on level
or constant grade tangent track.
Note:
Extra allowance shall be provided for curves as laid down at para1.7
1.6.3 At-Grade Sections
The Structure Gauge (Fixed Structure Line) has been arrived at by allowing
minimum clearance of 150 mm to Kinematic Envelope and minimum electrical
clearance of 320 mm from 25 KV live parts, conforming to stipulations in chapter
4 of this SOD.
Refer to Figure No. DMWSG-2, for Structure Gauge for outside stations on level
or constant grade tangent track.
Note:
Extra allowance shall be provided for curves as laid down at para 1.7
5
(B) Allowance for Super elevation
(a) Under Ground (Box structures), Elevated and At-Grade Sections
The lean L due to Cant at any point at height h above rail level is
given by:
L = Ca x h/g (all in mm)
For values of Structure Gauge (E1) for inside of a curve with cant effect
only, (as shown in Figure No. DMWSG-4), refer to:
(i) Appendix -3(TNL) for Under Ground Sections
(ii) Appendix -3 for At-Grade and Elevated Sections
(b) Circular Tunnels
In the case of Circular Tunnel, the cant is provided by raising the outer rail
and suitably shifting the centre of the Circular Tunnel towards inside of
curve and upwards. This has same effect as assuming rotation of the
Circular Tunnel about mid point of top of inner rail resulting in shift of
Tunnel centre laterally towards inside of curve and also vertically upwards.
The Rigid OCS shall also be rotated with the tunnel so as to be along
the centre line of canted track.
For values of horizontal and vertical shifts of centre of Circular Tunnel
for different values of cant, refer to Appendix-4 and Figure No.DMWSG-3
6
(B) Allowance for Super elevation
(a) Under Ground (Box structures), Elevated and At-Grade Sections
The lean L due to Cant at any point at height h above rail level is
given by:
L = (-) Ca x h/g (all in mm )
-ve sign indicates relief due to cant or reduction in clearance
required.
Note:
Full relief for lean due to cant (Ca) is to be taken into account only for calculation
of track spacing without any structure between tracks. In case there is a structure
adjacent to track, relief for lean is to be taken into account only if the cant
provided is greater than 50 mm and shall be limited to a value = (Ca - 50) x h/g.
Values of Structure Gauge (F1) on outside of curve with cant effect only (as
shown in Figure No.DMWSG-4), refer to:
i) Appendix 3(TNL) for Under Ground Sections
ii) Appendix 3 for Elevated and At-Grade Sections
(b) Circular Tunnels
In the case of Circular Tunnel, the cant is provided by raising the outer rail
and suitably shifting the centre of the Circular Tunnel towards inside of
curve and upwards. This has same effect as assuming rotation of the
Circular Tunnel about mid point of top of inner rail resulting in shift of
Tunnel centre laterally towards inside of curve and also vertically upwards.
The Rigid OCS shall also be rotated with the tunnel so as to be along
the centre line of canted track.
For values of horizontal and vertical shifts of centre of Circular Tunnel
for different values of cant, refer to Appendix-4 and Figure No.DMWSG-3
(C) Allowance for vertical curve (vertical throw)
The provisions at para 1.7.1 (C) above shall be applicable in this case
also.
7
i) (E + F),
ii) T1 (Extra lateral allowance due to curvature on inside of curve)
iii) T2 (Extra lateral allowance due to curvature on outside of curve)
iv) Minimum clearance between adjacent Kinematic Envelopes
stipulated is as under:
a) 200 mm for Under-Ground Sections
b) 300 mm for Elevated and At-Grade Sections.
Where,
E is the distance from vertical axis of centre line of canted track to canted
Kinematic Envelope on inside of curve at a height h (from rail level) for a
given cant (Figure No. DMWSG-4A) and
F is the distance from vertical axis of centre line of canted track to canted
Kinematic Envelope on outside of curve at a height h (from rail level) for a
given cant (Figure No. DMWSG-4A).
Notes:
i) The value of F, calculated from the formula at Figure No.DMWSG-4A
includes full relief due to cant.
ii) The sum of 'E' and 'F' for same height (which are with cant effect only),
shall be the maximum of values calculated for various heights from rail
level.
For values of E, F, T1 and T2, refer to the Appendices as shown below:
8
Notes:
a) The values of E1 and F1 for a given cant Ca, shall each be the maximum of
values at different heights of structure from rail level. In case the cant
provided is greater than 50 mm on inner track, the value of F1 shall be for the
cant of (Ca-50) mm. In case the cant provided is 50 mm or less on inner
track, the value of F1 shall be for ZERO cant.
b) Minimum track spacing, so worked out with a structure between the adjacent
tracks as per para 1.8.2 shall not be less than that calculated as per para
1.8.1 for tracks without any structure between adjacent tracks.
For values of E1, F1, T1 and T2, refer to the Appendices as shown below:
1.10 WALKWAYS
Note: Extra allowances shall be provided for curves as laid down at para 1.7
(i) Maximum and minimum heights of walkway on curves are above inner rail.
(ii) No structure, other than signaling and minor signaling equipment post, shall
be permitted within the minimum width of walkway.
(iii) Minimum clearance to walkway at the nearest edge from Kinematic Envelope
shall be 100 mm for Underground sections and 150 mm for Elevated and
Surface (At Grade) sections.
(iv) Walkway should be used by Metro Inspection Groups only in non-operation
periods and for evacuation of passengers in emergency.
9
be provided inside the track so that it permits less sway of coach towards
tunnel wall in case of derailment.
(b) Lateral Clearance between the running rail and the derailment Guard shall be
210 30 mm. It shall not be lower than 25mm below the top of running rail
and should be clear of the rail fastenings to permit installation, replacement
and maintenance.
Note:-
In case of single track tunnels, the derailment guards shall be provided:
(i) Entry of tunnel: 200m from tunnel portal outside the tunnel to 50 m inside
the tunnel.
(ii) Exit of tunnel: 50m from inside of tunnel portal to 200m outside the tunnel.
(iii) In the curved track having radius 500 m or less including transition portion
but excluding locations where check rail is provided.
(iv) Covering locations of all important installations e.g. location of any
substation or hazardous structures inside the tunnel etc., damage to which
in the assessment of Metro Rail administration can result into serious loss
of life or/and infrastructure as a result of derailment in tunnel.
The above is subject to the condition that metro railway shall carry out the risk
assessment analysis for derailment in tunnels and ensure that the
maintenance practices in the maintenance manual are as per the risk
assessment mitigation plan.
10
1.12.5 The way side signaling, wherever provided, in addition to ATP, on temporary or
permanent basis, will be so located that proper visibility to the driver is ensured.
1.12.6 The corridor when fully functional will also have way side signaling as well as
train protection by ATP. The way side signaling should be so located near the
masts so that the proper visibility to the driver is ensured considering the
alignment.
1.12.7 No workmen / Equipment are allowed between vehicle and structure gauge
during operation of trains.
1.13.1 In case of at grade section, the track is expected to be on the surface and
passing through populated areas and there are chances of people passing
through the track. Considering this fact to prevent the people to access the
track, the sections will be robustly fenced.
1.13.2 As the track will be open to the climate, temperature variation will take place in
the track, which may require patrolling of the section during extreme winter and
summer for this purpose, provision shall be made for visual inspection from the
walk way on the outside of each track permitting safe walking for patrolmen
during service hour.
1.13.3 The speed of trains shall be restricted to 40kmph on platform when wind speed
is more than 70kmph but less than 90kmph. When wind speed exceeds
90kmph, the train movement shall be halted. Stationary trains shall not be
started till wind speed is below 90kmph
11
CHAPTER - 2
STATION
2.2 PLATFORMS
2.2.1 Maximum horizontal distance from centre of track to face of passenger platform
coping
(i) For Elevated/At Grade section 1680 mm
(ii) For Underground section 1670 mm
2.2.2 Minimum horizontal distance from centre of track to face of passenger platform
coping
(i) For Elevated/At Grade section 1670 mm
(ii) For Underground section 1660 mm
Notes:
a) Platform faces shall be flared away smoothly from the centre line of the track
at either end for a distance of 1500 mm beyond passenger area/ at Platform end
so as to give from centre of track a minimum dimension :
1795 + 5 for Under Ground Stations
1785 + 5 for At-Grade and Elevated Stations
b) For additional clearance for platforms on curves, refer to para 2.7.
Maximum Minimum
(a) At-Grade1085 mm 1075 mm
(b) Elevated/Under Ground. 1095 mm 1085 mm
12
Notes:
b) The structure on the platform is treated as isolated if the length along the
platform length is 2000 mm or less. Any structure having a length exceeding
2000 mm is treated as continuous structure. The clocks/mirrors/CCTV
screens etc shall not be considered structures and shall be located at a
minimum horizontal distance of 1000 mm from platform edge/coping with
minimum height of 2000 mm from top of platform.
Note:
Except for check rails of ordinary and diamond crossings, or wing rails and point
rails of crossings leading to snag dead ends, or such parts of signalling gear as
are required to be actuated by the wheels, no gear or track fittings shall project
above rail level for a distance of 229 mm outside and 140 mm inside the gauge
face of the rails.
2.5.3 Minimum clerance between switch rail and stock rail at heel 52 mm
of Switch Rail
2.5.4 Maximum clearance of wing rail at nose of crossing 44 mm
2.5.6 Minimum clerance between toe of open switch and stock rail. 160 mm
2.5.7 Minimum radius of curvature for slip points, turnouts and 190 metres
crossover roads.
2.5.8 On main lines, the turnouts and diamond Crossings shall be of the following types
or flatter:-
a) 1 in 9 type turnout 300 m radius
b) 1 in 7 type turnout 190 m radius
c) Scissors cross-over of 1 in 9 type consisting of 4 turnouts and 1 diamond
crossing
d) Scissors cross-over of 1 in 7 type consisting of 4 turnouts and 1 diamond
crossing
2.5.9 On depot lines, the turnouts and diamond Crossings shall be of the following
types or flatter-
14
b) Scissors cross-over of 1 in 7 type consisting of 4 turnouts and 1 diamond
crossing
c) 1 in 7 derailing switches/ 1 in 7 type symmetrical split turnout
Note:
a) The above restrictions shall not apply to moveable diamond crossings
b) There must be no change of superelevation (of outer over inner rail)
between points 18 metres outside toe of switch rail and nose of crossings
respectively, except in the case of special crossing leading to snag dead-ends
or under circumstances as provided for in item 2.6 below
2.5.11 Minimum length of tongue rail: 9000 mm
15
2.7 ADDITIONAL CLEARANCE FOR PLATFORMS ON CURVES
Note:
(i) As the minimum radius of horizontal curve for station platform line is 1000
metres, there will be no superelevation and gauge widening at stations on
passenger platform lines.
(ii) Platforms located in curves shall be fitted with a gap filler wherever
necessary to maintain the minimum stepping distance of 75 mm. The gap
filler shall be of elastic nature and flexible to allow train contact.
16
CHAPTER 3
ROLLING STOCK
Note:
Fittings on the end of a vehicle, such as step iron, brake/ drainage pipes, electrical
connection, cable or boxes, vestibule or gangway, fairings etc. need not be kept
within the prescribed maximum permissible length of the car body, but may project
beyond the end of body to a reasonable extent.
Note:-
# A tyre or an attachment to a wheel or sand pipes or Wheel/ Track Lubrication Nozzle
in line with the wheel may project below the minimum height of 50mm from a distance of
51mm inside to 216mm outside of the gauge face of the wheel.
17
5. Incline of Tread / Wheel Profile RDSO SK 91146/UIC S1002
6. Wheel
a) Maximum wheel gauge back to back distance 1361 mm
b) Minimum wheel gauge back to back distance 1358 mm
18
3.2 LOCOMOTIVES AND ENGINEERING SERVICE VEHICLES
Other items of rolling stock, viz shunting locomotives, OHE maintenance and
inspection cars, emergency re-railing van, track machines, etc., used on Delhi
Metro System (where these cars would be plying) will conform with the
Kinematic Envelope of the Passenger Electric Multiple Units as shown in Figure
No DMWSG-1(TNL) for Under Ground sections and Figure No. DMWSG - 1 for
Elevated and At-Grade sections.
19
CHAPTER 4
Note: Wherever electric traction is in use, special precautions must be taken to maintain
following clearances:
Note:
(a) Location of level crossing from the exit point of the tunnel will take into
consideration the OHE height of 4318 mm at the tunnel exit and the
permissible contact wire gradient.
(b) In the Depot deck portion, where Rigid OCS is provided and the track is
Ballastless, the Electrical clearances laid down at paras 4.1.1 to 4.1.4
shall be applicable.
(c) For location of rigid OCS in circular tunnel with canted track, refer to para
1.7.1(B)-b and 1.7.2 (B)-b.
(d) It shall be ensured that environment level inside the tunnel is controlled
suitably so that no extra air clearance, over and above the minimum
separation prescribed in para 4.1.3 and 4.1.4 on account of pollution, fog
etc. is required.
4.1.2 Stagger of Rigid OCS Conductor in Tunnels shall not be more than
(a) On Straight .. 200 mm
(b) On Curves 300 mm
4.1.3 Prescribed minimum clearance between live parts of contact lines and bodies of
structures.
Air clearance between bodies of structures and live un-insulated parts of contact
lines, feeders and current collectors for 25 KV shall be as per IEC 60913 as
under:
20
*in exceptional cases and considering operating in climatic conditions (Ref: IEC
60913)
4.1.4 Prescribed minimum clearance between live parts of contact lines and
bodies of vehicles
Minimum Air clearance between bodies of vehicles and the live un-insulated
parts of the contact line or feeders for 25 KV
The Kinematic Envelope for the underground system with Ballastless track is
shown in Figure DMWSG1(TNL) The pantograph adopted should be such that
its actual half KE width does not exceed 820 mm and 980 mm at the top and
bottom respectively in pantograph raised condition for a contact wire height of
4318 mm to fulfill electrical clearance as per item 4.1.3
Note: These limits would not apply to special locations like insulated overlaps
and out of run wires.
4.2.1 Minimum vertical distance between any live bare conductor (overhead equipment
or pantograph) and any earthed structure or other bodies (rolling stock, over
bridges, signal gantries etc.)
Note:
A minimum vertical distance of 340 mm shall normally be provided between
rolling stock and contact wire to allow for a 20 mm temporary raising of the tracks
during maintenance. Wherever the allowance required for track maintenance
exceeds 20 mm, the vertical distance between rolling stock and contact wire shall
correspondingly be increased.
4.2.2 Minimum lateral distance between any bare live conductor(over head equipmentor
pantograph) or any earthed structure or other bodies ( rolling stock, over bridges,
signal gantries etc.)
21
Condition For Flexible OHE
(i) Long duration (Static) 320 mm
(ii) Short Duration (Dynamic) 220 mm
4.2.3 Height of contact wire:
Minimum height from rail level to the underside of live Conductor wire.
i) Under bridges,in tunnels and in ramp area (transition length from tunnel to
elevated corridor) . 4318mm
ii) In the open .. 5000 mm
iii) At level crossings .. 5500 mm
iv) In running and carriage sheds wherever staff are
expected to work on the roof of rolling stock. .. 5200 mm
Note:
a) For the movement of over- dimensional consignments if any, the height
specified under 4.2.3 (i) above, shall be increased by the difference
between the height of the consignment contemplated and 4.41 metres. In
case such an over-dimensional consignment is moved at speeds not
exceeding 15 kmph and is also specially escorted by authorized DMRC
staff, the derived height of contact wire may be reduced by 50 mm.
b) On curves, all vertical distances specified in items 4.2.3 above, shall be
measured above level of the inner rail, increased by half the super-
elevation.
4.2.4 Maximum variation of the live conductor wire on either side of the centre line of
the track under static conditions:
iii) On straight .. 200mm
iv) On Curves .. 300mm
Note: These limits would not apply to special locations like insulated overlaps
and out of run wires.
The Kinematic Envelope with the size of Pantograph adopted, shall be within the
Kinematic Envelope shown at Figure No. DMWSG 1
22
Chapter- 5
PLATFORM GATE
Note:
(a) Assumed plus/minus 300 mm stopping accuracy.
(b) Platform gates at stations on curves shall be considered separately taking
into account the additional clearance as per Appendix-5.
(c) Platform Gates are considered as designated railway operational structures.
Therefore, platform gates may infringe the structure gauge, but does not
infringe the station kinematic envelope and having minimum clearance of 10
mm from kinematic Envelope to Platform Gate.
23