Substation Layout
Substation Layout
Substation Layout
PLANNING ASPECTS:
400kV
TG Beam at 15 m with peak 23m
TSP Beam at 23m with peak 30 m
G5 Beam at 15m (Twin Moose)
GSP Beam at 23m
220kV
TA Beam at 11m
TB Beam at 11m & 17.5m
TC Beam at 11m & 17.5m with peak 22m
G1 Beam at 11m (Single Moose)
G2 Beam at 11m (Twin Moose)
G3 Beam at 17.5m (Single Moose)
Typical dimensions between
equipments
400 kV 220 kV 132 kV 66 kV
CB&ISO 10.5 m 6.5 m 3.75m 3m
ISO&CT 7m 4m 2.5 m 2m
CB&CT 7m 3m+road+5 m 2.5 m 2m
Placement of
AC driven main pump
DG driven stand-by pump
Jockey Pump
Air Vessels
AC Distribution Board cum pump control panels
Fire Water Tank
Miscellaneous
Placement of
LT Station (ACDB, DCDB, Battery Bank &
Battery Chargers)
Diesel Generator Set with AMF Panel
Security hut
Office Buildings
Other residential buildings
Gas Insulated Substation (GIS)
GIS in POWERGRID
POWERGRID is constructing 132kV, 220 kV & 400
kV GIS substation
Construction of 800 kV GIS is under consideration
Technical Advantage of GIS
All equipments are compact in size and enclosed in
SF6 gas with metallic enclosure
Area requirement of GIS is approx. 20% of
conventional AIS
Lesser structures & foundation works; Hence less
execution time
Costlier than AIS
Bus Bar Switching Schemes
Factors dictating choice of bus switching scheme
1) Reliability
No Power interruption during Bus fault
2) CB Maintenance
No Power interruption during CB maintenance. Taking
out CB for maintenance shall be easy
5) Ease of Extension
Extension of Bus bar necessary to take care of future
expansion. Power interruption during such extension
works.
6) Cost
Optimal techno-economic solution
Bus Switching Schemes
Single Main Bus Scheme
with sectionaliser & without sectionaliser
Single Main & Transfer Bus Scheme
Double Main Bus Scheme
Double Main with by-pass isolator Bus scheme
Double Main & Transfer Bus Scheme
One & Half Breaker Bus Scheme
Double bus two breaker Scheme
Ring Bus Scheme
SINGLE BUS SCHEME
400 KV BUS-I
I
4989A 41089A 41889A 4589A 4489A 4689A
4989AE 41089A 41889A
E E
4589AE 4489AE 4689AE
4952 41052 41852 4552 4452 4652
1000- 1000- 1000- 1000- 1000- 1000-
500/1A 500/1A
41089B 500/1A 500/1A 500/1A 500/1A
4989BE 41889B 4589BE 4489BE4789T2 4689BE
CONTROL
220 KV BUS-I I
2189A 2289A 2289B 2789A 2389A 2889A 2489A 2589A 2689A 2989A 21089A 21189A 21289A
2189B 2789B 2389B 2889B 2489B 2589B 2689B 2989B 21089E 21089B 21289B
2252 21189B
1 21189E 21289E
2189E1 2289E1 2789E1 2389E1 2889E1 2489E1 2589E1 2689E1 2989E1 1
1000- 1
2152 500/1A 2752 2352 2852 2452 2552 2652 2952 21052 21152 21252
BUS
21089E
COUPLER 21189E 21289E
1000- 2
2789E2 2389E2 2889E2 2489E2 2589E2 2689E2 2989E2 2 2
500/1A 21089T 21289T
2789L 2389T 2889L 2489L 2589L 2689T 2989T 21189T
1000- 21089E
2189E2 500/1A 3 21189E 21289E
2789E3 2389E3 2889E3 2489E3 2589E3 2689E3 2989E3 3 3
1000- 1000- 21089C 1000-
2189C 2789C 2889C 2489C 2589C 2689C 2989C 21189C 21289C
2389C 500/1A 500/1A 500/1A
220 kV 220 kV ICT-I BAY 220 kV 220 kV 220 kV ICT-I I ICT-I I I 220 kV 220 kV ICT-I V
TBC BAY PSEB-I I I PSEB-IV PSEB-I PSEB-I I BAY BAY Switchyard Fencing Jagraon-I Jagraon-II BAY
Small Scale
industry
TO BE
DISMENTELED
Small Scale
industry
TO BE
DISMENTELED
Small Scale
industry
TO BE
DISMENTELED
MOGA SUBSTATION AUGMENTATION OF EXISTING TRANSFORMATION CAPACITY - INSTALLATION OF ICT-IV AND ASSOCIATED BAYS
400 KV 400 KV 400 KV
SPARE 400 KV 400 KV 400 KV
JALANDHAR-I JALANDHAR-II KISHENPUR-II
KISHENPUR-I BHIWADI-I BHIWADI-II
250 MVA
ICT-IV
63 MVAR 63 MVAR
LINE LINE
REACTOR REACTOR
400 KV BUS-I
400 KV BUS-II
CONTROL
ROOM
Existing
BUS COUPLER Conductor Bus
220 kV
TBC BAY
63 MVAR
63 MVAR
LINE
LINE
41289RE
REACTOR
41589RE
13 REACTOR 3 41589L 41989LE
41452 41489B 41489R
41689T1E
4189BE1 4389T1E 41589BE 41789B
41489BE 4289BE1 LOCATION 41789BE
OF 41989BE 42089T2E
41289BE 15 BHIWADI I & 17
II 19
14
41252 4152 1 2 4252 41552 ( PROPOSED ) 41752 41952
12 4189AE1 4289AE2
42189AE
41489AE 41289AE 41589AE 41789AE 41989AE
41489A 41289A 4189A 4289A 41589A 41789A 41989A 42189A
4189AE2 400 KV BUS-I 4289AE2
400 KV BUS-II
4589A
4989BE 41089BE 4589AE 4489BE 4689BE
CONTROL
41189T1E
4489B
4989B 41089B 4889T1E 7 4689B
ROOM
4789T1E
41189T1 41889BE 4852 4789T2
4589L
4489L
41152
41889C
4989C 41189T2 41089C 4889T2 4889T1 4752 4789T1 4689C
1 MVA 41089CE 41889CE 4689CE
4989CE 33/0.433
kV 4589LE 4489LE
250 MVA
250 MVA 250 MVA 250 MVA ICT-IV
ICT-I ISOL:KEP ICT-II ICT-III
2989B
D
2989A
2189A 2189B 2189B 2389A 2889A 2489B C 21089A 21189A 21289A 21289B
2189E1 2 2789E1 2389E1 2889E1 2489E1 2989E1
21089E1
21089B 21189B
21289E1
2589E1 2689E1 21189E1
2189E1 7 3 8 4 5 6
2152 1 BUS COUPLER
2252
2752 2452 9 2952 21052 21152 21252
2389E2 235 2/889E22852
2789E2 2552 2652 21189E2
2 2489E2 2589E2 2689E2 21089E2 21289E2
2789L 2389T 2889L 2489L 2689T 2989E2 21089L 21189L
2789E3 2889E3 2589L 2989T 21289T
2189E2 2389E3 2689E3 2989E3 21089E3 21189E3 21289E3
2489E3
2189C 2789C 2389C 2889C 2589C 2689C 2989C 21089C 21189C 21289C
220 KV TRANSFER BUS 2489C
ICT-I BAY ICT-II BAY ICT-III BAY
220 kV
TBC BAY
220 kV 220
PSEB-III
220 kV 220 kV 220 kV 220 kV 220 kV KV
PSEB-IV PSEB-I PSEB-II Switchyard Fencing PSEB-V PSEB-VI ICT-
IV
SINGLE LINE DIAGRAM OF 220kV DMT SCHEME
400 KV BUS-I
400 KV BUS-II
4989A 41089A
4989AE 41089AE
4952 41052
1000-500/1A 1000-500/1A
4989BE 41089BE
41189T1E 41189T2E
4989B 41089B
1000-500/1A 1000-500/1A
41189T1
41152 41089C
4989C
4989CE 41089CE
220 KV BUS-I
220 KV BUS-I I
2189E2
2389E3 2489E3 2689E3
220 kV ICT-I I
ICT-I BAY PSEB-I BAY
SINGLE LINE DIAGRAM OF 220kV DMT SCHEME WITH 245kV CT RELOCATED
400 KV BUS-I
400 KV BUS-II
4989A 41089A
4989AE 41089AE
4952 41052
1000-500/1A 1000-500/1A
4989BE 41089BE
41189T1E 41189T2E
4989B 41089B
1000-500/1A 1000-500/1A
41189T1
41152 41089C
4989C
4989CE 41089CE
220 KV BUS-I
220 KV BUS-I I
2189E2
2389E3 2489E3 2689E3
220 kV ICT-I I
ICT-I BAY PSEB-I BAY
CABLE TRENCH
INTRODUCTION
Devices used to get the replica of primary voltage which
shall be suitable for measuring instruments and
protective relays.
No. of cores as per requirement
CVTs used generally above 220kV for economic reasons -
also obviates need for separate coupling capacitor for
PLCC
Pre Commissioning Tests of CT
Polarity Test
Magnetization Curve Test
Ratio Test
Primary Current Injection Test
Secondary Current Injection
Test