EPCC Toxic Release Shelter Upgrade

This document outlines 7 payment milestones for a contract to improve the toxic release shelter and HVAC system at a central control room building. It includes: 1) 10% payment upon submitting guarantees and insurances 2) 20% payment upon completing basic and detailed engineering design 3) 20% payment upon delivering all procured equipment 4) 15% payment upon completing installation work at the control room 5) 15% payment upon testing and achieving performance standards 6) 10% payment upon completing additional instrumentation work 7) 10% payment upon testing additional instrumentation and submitting final documents

Uploaded by

Takrimi Ismail
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
40 views1 page

EPCC Toxic Release Shelter Upgrade

This document outlines 7 payment milestones for a contract to improve the toxic release shelter and HVAC system at a central control room building. It includes: 1) 10% payment upon submitting guarantees and insurances 2) 20% payment upon completing basic and detailed engineering design 3) 20% payment upon delivering all procured equipment 4) 15% payment upon completing installation work at the control room 5) 15% payment upon testing and achieving performance standards 6) 10% payment upon completing additional instrumentation work 7) 10% payment upon testing additional instrumentation and submitting final documents

Uploaded by

Takrimi Ismail
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
You are on page 1/ 1

EPCC IMPROVEMENT OF TOXIC RELEASE SHELTER (HVAC ASSOCIATE TRS ACCORIES) AT CENTRAL CONTROL ROOM BUILDING (CCR) ASEAN

BINTULU FERTILIZER SDN BHD


CONTRACT NO: SMSO/ABFSB/2015/0012
PAYMENT MILESTONE

6. UPON
5. UPON SUCCESSFUL COMPLETION OF 7. UPON SUCCESSFUL
1. UPON COMMISSIONING AND INSTALLATION COMMISSIONING AND ACHIEVEMENT
SUBMISSION OF ACHIEVEMENT OF PERFORMANCE WORK AT OF PERFORMANCE TEST, ISSUANCE OF
BANK GUARANTEE TEST, ISSUANCE OF INITIAL ADDITIONAL INITIAL ACCEPTANCE (IA) AND
AND INSURANCES 2. UPON THE COMPLETION 3. UPON THE DELIVERY OF ACCEPTANCE (IA) AND INSTRUMENT SUBMISSION OF FINAL DOCUMENTS CUMULATIVE PREVIOUS TO DATE
FROM OF BASIC AND DETAIL ALL PROCURED EQUIPMENT 4. UPON COMPLETION OF SUBMISSION OF FINAL MARSHALLING FOR WORKS AT ADDITIONAL CLAIMABLE CLAMMABLE CLAIMABLE
ID ACTIVITIES CONTRACTOR ENGINEERING DESIGN WORK TO ABF SDN BHD INSTALLATION WORK AT CCR DOCUMENTS FOR WORKS AT CCR ROOM INSTRUMENT MARSHALLING ROOM TOTAL WTG PROGRESS % PROGRESS % PROGRESS %

1 (%) WTG Per Item 10% 20% 20% 15% 15% 10% 10% 100%

2 Current Progress (%) 10% 20% 20% 0% 0% 0% 0% 50% 50% 20% 20%
WTG Per Item

Claim for
3 Milestone No.
3

4 50% 20% 20%