BDSLT Report
BDSLT Report
Prepared for:
Prepared by :
COPY
NO
JOB NO.
(FILENAME)
SUPPLEMENTARY
NO.
ISSUED
DATE
PREPARED BY
TESTING
PERSONNEL
4
4358
4358BD001
0 16/09/2008 CEK MNAbH
Bi-directional Static Load Test
Test Report
TABLE OF CONTENTS
1.
INTRODUCTION.......................................................................
.................................. 2
3. BORED PILE
CONSTRUCTION.......................................................................
..........3
4. LOAD TEST
PROCEDURE .........................................................................
................ 4
5. DISCUSSION OF
RESULTS............................................................................
............ 5
5.1 PERFORMANCE OF
INSTRUMENTATION ...................................................... 5
5.2 LOAD-MOVEMENT
BEHAVIOUR .................................................................... 5
6.
CONCLUSIONS........................................................................
...................................6
FIGURES
FIGURE 1
Schematic Section of Test Pile
CHARTS
CHART 1
Load Movement Curves
CHART 2
Equivalent Top Loaded vs. Settlement Curves
APPENDICES
Appendix A
Load-Movement Data
Appendix B
Construction of the Equivalent Top-Loaded
Load Settlement Curve
Appendix C
Calibration Certificates
Proposed Dr. Ir. Soekarno Bridge at Manado, North Sulawesi, Indonesia Page 1
Pile # BP4
Bi-directional Static Load Test
Test Report
1. INTRODUCTION
Soil Dynamics (M) Sdn. Bhd. (SDM) has carried out a Bi-directional Static Load Test
on a bored pile referred as pile no. BP4 at the Proposed Dr. Ir. Soekarno Bridge
at
Manado, North Sulawesi, Indonesia project on 12th September 2008.
The main objective of this load test was to proof-load the test pile to its maximum
test
load of 1,500 tonnes which is two (2) times the working load of 750 tonnes.
41.550 m from ground level (40.250 m from cut-off level). The hydraulic jack
assembly comprising of two (2) 400-tonne capacity bi-directional hydraulic jacks,
were installed at 26.813 m from ground level (25.00 m RL).
There were a pair each of tell-tale extensometers installed at the top and bottom
of the
hydraulic jacks assembly. Their movements were measured against a reference frame
constructed by the contractor. The pile top movements were also measured against
this reference frame.
Proposed Dr. Ir. Soekarno Bridge at Manado, North Sulawesi, Indonesia Page 2
Pile # BP4
Bi-directional Static Load Test
Test Report
The hydraulic jacks assembly and steel cages were jointed and lowered into the
bored
hole. The pile was concreted according to the contractors method statement.
Proposed Dr. Ir. Soekarno Bridge at Manado, North Sulawesi, Indonesia Page 3
Pile # BP4
Bi-directional Static Load Test
Test Report
pressure transducer was used to measure the pressure. The displacement transducers,
which were supported from the reference frame, were used to measured relative
movements (with respect to ground) at the designated points of measurement.
It is to be noted that the loads applied by the bi-directional hydraulic jacks act
in two
opposite directions, resisted by upper side shear above the jack assembly and by
the
combined end bearing and lower side shear below the jack assembly.
Loading and unloading were carried out in the cycle as shown in the following
schedule:
Loading
Cycle
Load Increment /
Decrement (% WL)
Effective Bi-directional
Load (tonnes)
Holding Time
L 1-0 0 0 0
L 1-1 25 188 30 mins
L 1-2 50 375 30 mins
L 1-3 75 563 30 mins
L 1-4 100 750 23 mins
UL 1-1 50 375 11 mins
UL 1-2 0 0 3 mins
It was to note that the loading was only carried out up to 100% of Working Load
(WL) and was not continued to 200% of Working Load due to the hydraulic jacks
have reached its maximum stroke of 180mm. The pile was subsequently unloaded as
per schedule above.
A millimeter scale was fixed to the reference frame, and direct readings from an
optical level to this scale were observed to check that there were no gross errors
in the
displacement transducer readings. During the duration of testing, no deflection of
reference beam was detected.
Proposed Dr. Ir. Soekarno Bridge at Manado, North Sulawesi, Indonesia Page 4
Pile # BP4
Bi-directional Static Load Test
Test Report
5. DISCUSSION OF RESULTS
5.1 PERFORMANCE OF INSTRUMENTATION
The pile head movements were measured directly using displacement
transducers mounted on the reference beam. Meanwhile, the top and bottom of
hydraulic jacks assembly were measured using displacement transducers that
were connected to telltale extensometers. Six (6) displacement transducers
were used to measure all movements at the designated points. All the
displacement transducers performed well during the duration of the test.
The maximum pile top movement was 4.8 mm and maximum upward
movement at the jack assembly was 5.3 mm. The maximum downward
movement at the jack assembly was 169.3 mm at the applied load of
375 tonne that was equivalent to the effective bi-directional load of 750 tonne
(100% WL).
The loading was not continued to 200% of Working Load due to high
settlement and the hydraulic jacks have reached their maximum stroke of
180mm.
CHART 2 shows the equivalent top loaded load movement curves as derived.
Adjustment for additional elastic compression is calculated as PL/EA where P
is the applied load, L the length, E the elastic modulus and A the cross-
sectional area.
The results show that the test pile would settle by 26.4 mm at 750 tonnes
(100% Working Load).
Proposed Dr. Ir. Soekarno Bridge at Manado, North Sulawesi, Indonesia Page 5
Pile # BP4
Bi-directional Static Load Test
Test Report
6. CONCLUSION
The bi-directional static load test that started on 12th September 2008 was
terminated on the same day. The loading was carried out to the maximum
applied load of 750 tonnes (100% Working Load).
Proposed Dr. Ir. Soekarno Bridge at Manado, North Sulawesi, Indonesia Page 6
Pile # BP4
Bi-directional Static Load Test
Test Report
LEVEL
REFERENCE
LEVEL DESCRIPTION
DEPTH
(m)
Tell-taleextensometersGL Ground Level 1.813
COL Cut-off Level 0.513
J1 Hydraulic jack assembly -25.000
(2 x 400 tonnes)
PT Pile toe -39.737
HydraulicjackassemblyHydraulichoses
FIGURE 1 -Schematic Section of Test Pile
Proposed Dr. Ir. Soekarno Bridge at Manado, North Sulawesi, Indonesia Page 7
Pile # BP4
Bi-directional Static Load Test
Test Report
Proposed Dr. Ir. Soekarno Bridge at Manado, North Sulawesi, Indonesia
Bidirectional Static Load Test on Pile No. BP4
Tested on 12th September 2008
Chart 1 -Load-Movement Plot
Unidirectional Load (tonnes)
0 50 100 150 200 250 300 350 400
-100.0
-80.0
-60.0
-40.0
-20.0
0.0
20.0
40.0
60.0
80.0
100.0
120.0
140.0
160.0
180.0
200.0
Displacement (mm)
Pile Top
Proposed Dr. Ir. Soekarno Bridge at Manado, North Sulawesi, Indonesia Page 8
Pile # BP4
Bi-directional Static Load Test
Test Report
60.0
50.0
40.0
30.0
20.0
10.0
0.0
0 100 200 300 400 500 600 700 800
Load (tonnes)
Settlement (mm)
Settlement (Rigid Pile) Settlement (Adjusted for Elastic Compression)
Proposed Dr. Ir. Soekarno Bridge at Manado, North Sulawesi, Indonesia Page 9
Pile # BP4
Bi-directional Static Load Test
Test Report
APPENDIX A
Load-Movement Data
Proposed Dr. Ir. Soekarno Bridge at Manado, North Sulawesi, Indonesia Page A-0
Pile # BP4
BIDIRECTIONAL STATIC LOAD TEST AT
Proposed Dr. Ir. Soekarno Bridge at Manado, North Sulawesi, Indonesia
1,500 mm dia Bored Pile (Pile # BP4)
Date / Time
Applied Pressure
(PSI)
Effective
Bidirectional
Load (tonne)
Actual Jack
Load (tonne)
Average Displacement (mm)
Pile Top Cell Top Cell Bottom
12/09/08 03:53 PM 0 0 0 0.0 0.0 0.0
12/09/08 03:54 PM 818 118 59 0.0 0.0 0.1
12/09/08 03:55 PM 1180 179 89 -0.1 0.0 0.0
12/09/08 03:56 PM 1203 182 91 -0.2 -0.2 -0.1
12/09/08 03:57 PM 1242 189 94 -0.2 -0.1 -0.1
12/09/08 03:58 PM 1257 191 96 -0.2 -0.2 -0.1
12/09/08 03:59 PM 1246 190 95 -0.1 -0.2 -0.1
12/09/08 04:00 PM 1240 189 94 -0.2 -0.2 -0.1
12/09/08 04:01 PM 1235 188 94 -0.2 -0.2 -0.1
12/09/08 04:02 PM 1232 187 94 -0.2 -0.2 -0.1
12/09/08 04:03 PM 1228 187 93 -0.2 -0.1 -0.1
12/09/08 04:04 PM 1226 186 93 -0.1 -0.2 -0.1
12/09/08 04:05 PM 1222 186 93 -0.2 -0.2 -0.1
12/09/08 04:06 PM 1220 185 93 -0.2 -0.2 0.3
12/09/08 04:07 PM 1219 185 93 -0.2 -0.2 0.3
12/09/08 04:08 PM 1216 185 92 -0.1 -0.2 0.4
12/09/08 04:09 PM 1215 184 92 -0.2 -0.2 0.3
12/09/08 04:10 PM 1263 192 96 -0.2 -0.2 0.4
12/09/08 04:11 PM 1271 194 97 -0.2 -0.2 0.3
12/09/08 04:12 PM 1275 194 97 -0.2 -0.2 0.4
12/09/08 04:13 PM 1275 194 97 -0.2 -0.2 0.3
12/09/08 04:14 PM 1274 194 97 -0.1 -0.1 0.4
12/09/08 04:15 PM 1271 194 97 -0.2 -0.2 0.3
12/09/08 04:16 PM 1269 193 97 -0.2 -0.2 0.3
12/09/08 04:17 PM 1267 193 97 -0.2 -0.2 0.3
12/09/08 04:18 PM 1265 193 96 -0.2 -0.2 0.3
12/09/08 04:19 PM 1263 192 96 -0.2 -0.2 0.3
12/09/08 04:20 PM 1262 192 96 -0.2 -0.2 0.3
12/09/08 04:21 PM 1261 192 96 -0.2 -0.2 0.3
12/09/08 04:22 PM 1260 192 96 -0.2 -0.2 0.3
12/09/08 04:23 PM 1259 192 96 -0.2 -0.2 0.3
12/09/08 04:24 PM 1257 191 96 -0.2 -0.2 0.3
12/09/08 04:25 PM 1256 191 96 -0.2 -0.2 0.3
12/09/08 04:26 PM 1694 264 132 -0.3 -0.3 0.4
12/09/08 04:27 PM 2031 321 160 -0.4 -0.3 0.6
12/09/08 04:28 PM 2300 365 183 -0.5 -0.5 1.1
12/09/08 04:29 PM 2374 378 189 -0.5 -0.5 1.5
12/09/08 04:30 PM 2390 380 190 -0.5 -0.5 1.7
12/09/08 04:31 PM 2374 378 189 -0.5 -0.5 1.8
12/09/08 04:32 PM 2380 379 189 -0.5 -0.5 2.0
12/09/08 04:33 PM 2382 379 190 -0.5 -0.5 2.1
12/09/08 04:34 PM 2382 379 190 -0.5 -0.5 2.2
12/09/08 04:35 PM 2383 379 190 -0.6 -0.6 2.2
12/09/08 04:36 PM 2384 379 190 -0.6 -0.6 2.3
12/09/08 04:37 PM 2386 380 190 -0.6 -0.6 2.3
12/09/08 04:38 PM 2387 380 190 -0.6 -0.6 2.4
12/09/08 04:39 PM 2385 380 190 -0.6 -0.6 2.5
12/09/08 04:40 PM 2388 380 190 -0.6 -0.6 2.5
12/09/08 04:41 PM 2388 380 190 -0.5 -0.6 2.6
12/09/08 04:42 PM 2388 380 190 -0.5 -0.6 2.6
12/09/08 04:43 PM 2386 380 190 -0.6 -0.6 2.7
12/09/08 04:44 PM 2386 380 190 -0.6 -0.6 2.8
12/09/08 04:45 PM 2388 380 190 -0.6 -0.6 2.8
12/09/08 04:46 PM 2387 380 190 -0.6 -0.6 2.9
12/09/08 04:47 PM 2386 380 190 -0.6 -0.6 2.9
12/09/08 04:48 PM 2385 380 190 -0.6 -0.6 3.0
APPENDIX B
Construction of the Equivalent Top-Loaded
Load Settlement Curve
Proposed Dr. Ir. Soekarno Bridge at Manado, North Sulawesi, Indonesia Page B-0
Pile # BP4
Bi-directional Static Load Test
Test Report
Introduction:
BDSLT can provide a good estimate of a curve showing the load versus settlement of
a top-loaded
driven or bored pile (drilled shaft) with the following assumptions, which consider
good sense and
conservative:
1.
The end bearing load-movement curve in a top-loaded shaft has the same loads for a
given
movement as the net (subtract buoyant weight of pile above hydraulic jack) end
bearing
load-movement curve developed by the bottom of the hydraulic jack when placed at or
near
the bottom of the shaft.
2.
The side shear load-movement curve in a top-loaded shaft has the same net shear,
multiplied
by an adjustment factor F for a given downward movement as occurred in the BDSLT
for
that same movement at the top of the jack in the upward direction. The same applies
to the
upward movement in a top-loaded tension test. Unless noted otherwise, a factor
F=0.95 for
compression in cohesionless soils and F=0.80 for tension tests in all soils is
used.
3.
The pile behaves as a rigid body, but include the elastic compressions that are
part of the
movement data obtained from a bidirectional static load test (BDSLT). Procedure 1
interprets an equivalent top-load test (TLT) movement curve and procedure 2
corrects the
effects of the additional elastic compressions in a TLT.
4.
The part of the shaft below the hydraulic jack (one or multi level) has the same
load-
movement behavior as when top-loading the entire shaft. The subsequent end bearing
movement curve refers to the movement of the entire length of shaft below the
jack.
Procedure 1:
Figure A shows BDSLT results and Figure B shows the construction of equivalent top
loaded
settlement curve. Each of the curves shown has points numbered from 1 to 12 such
that the same
point number on each curve has the same movement magnitude.
With the above assumptions, the equivalent curve can be constructed as follows:
Select an arbitrary movement such as the 0.40 inches to give point 4 on the shaft
side shear load
movement curve in Figure A and record the load of 2,090 tons in shear at that
movement. With the
initial assumption of a rigid pile, the top of pile moves downward the same as the
bottom.
Therefore, find point 4 with 0.40 inches of upward movement on the end bearing load
movement
curve and record the corresponding load of 1,060 tons.
Adding these two loads will give the total load of 3, 150 tons due to side shear
plus end bearing at
the same movement and thus gives point 4 on the Figure B load settlement curve for
an equivalent
top-loaded test.
Procedure 1 can be used to obtain all the points in Figure B up to the component
that moved the
least at the end of the test, in this case point 5 in side shear.
Proposed Dr. Ir. Soekarno Bridge at Manado, North Sulawesi, Indonesia Page B-1
Pile # BP4
Bi-directional Static Load Test
Test Report
Suitable hyperbolic curve fitting technique can be used for extrapolation of the
side shear curve to
produce end bearing movement data up to 12. Some judgment is required for deciding
on the
maximum number of data points to provide good fit with high correlation
coefficient, r2. Using the
same movement matching procedure described earlier, the equivalent curve to points
6 to 12 can be
extended. The dashed line shown in Figure B, signify that this part of the
equivalent curve depends
partly on extrapolated data.
If the data warrants, the extrapolations of both side shear and end bearing to
extend the equivalent
curve to a greater movement than the maximum measured (point 12) will be used. An
appendix in
this report gives the details of the extrapolation(s) used with the present BDSLT
and shows the fit
with the actual data.
Procedure 2:
The elastic compression in the equivalent top load test always exceeds that in the
BDSLT. It
produces more top movement and also additional side shear movement, which then
generate more
side shear, more compression, etc. An exact solution of this load transfer problem
requires
knowing the side shear vs. vertical movement (t-y) curves for a large number of
pile length
increments and solving the resulting set of simultaneous equations or using finite
element or finite
difference simulations to obtain an approximate solution for these equations.
The attached analysis P.6 gives the equations for the elastic compressions that
occur in the BDSLT
with one or two levels of hydraulic jacks. Analysis P.7 gives the equations for the
elastic
compressions that occur in the equivalent TLT. Both sets of equations do not
include the elastic
compression below the hydraulic jack because the same compression takes place in
both the
BDSLT and the TLT. This is equivalent to taking l3 = 0. Subtracting the BDSLT from
the TLT
compression gives the desired additional elastic compression at the top of the TLT.
The additional
elastic compression is then added to the rigid equivalent curve obtained from
Part 1 to obtain the
final, corrected equivalent load-settlement curve for the TLT on the same pile as
the actual BDSLT.
Note that the above p.6 and p.7 give equations for each of three assumed patterns
of developed side
shear stress along the pile. The pattern shown in the center of the three is
applicable to any
approximate determined side shear distribution. Experience has shown the initial
solution for the
additional elastic compression, as described above, gives an adequate and slightly
conservative
(high) estimate of the additional compression versus more sophisticated load-
transfer analyses as
described in the first paragraph of this Part II.
The final analysis p.10 provides an example of calculated results in English units
on a hypothetical
3-stage, multi level BDSLT using the simplified method in Part II with the centroid
of the combined
upper and middle side shear distribution 44.1% above the base of the bottom
hydraulic jack. The
individual centroids of the upper and middle side shear distribution lie 39.6% and
57.9% above and
below the middle hydraulic jack, respectively. Figure E compares the corrected with
the rigid curve.
Page II contains an example equivalent to that above in SI units.
Other Tests: The example illustrated in Figure A has the maximum component movement
in end
bearing. The procedures remain the same if the maximum test movement occurred in
side shear.
Proposed Dr. Ir. Soekarno Bridge at Manado, North Sulawesi, Indonesia Page B-2
Pile # BP4
Bi-directional Static Load Test
Test Report
Then we would have extrapolated end bearing to produce the dashed-line part of the
reconstructed
top-load settlement curve.
The example illustrated also assumes a pile top-loaded in compression. For a pile
top-loaded in
tension we would, based on Assumptions 2 and 3, use the upward side shear load
curve in Figure A,
multiplied by the F = 0.80 noted in Assumption 2, for the equivalent top-loaded
displacement curve.
Expected Accuracy: There are only five series of tests that provide the data needed
to make a
direct comparison between actual, full scale, top-loaded pile movement behavior and
the equivalent
behavior obtained from a BDSLT by the method described herein. These involved three
sites in
Japan and one in Singapore, in a variety of soils, with three compression tests on
bored piles (drilled
shafts), one compression test on a driven pile and one tension test on a bored
pile. The largest
bored pile had a 1.2 m diameter and a 37 m length. The driven pile had a 1-m
increment modular
construction and a 9 m length. The largest top loading = 28 MN (3,150 tons).
The following references detail the aforementioned Japanese tests and the results
therefrom:
Kishida H. et al., 1992, Pile Loading Tests at Osaka Amenity Park Project, Paper
by
Mitsubishi Co., also briefly described in Schmertmann (1993, see bibliography).
Compares
one drilled shaft in tension and another in compression.
M.B. Karkee, GEOTOP Corporation. Compares one drilled shaft and one driven pile,
both
in compression.
We compared the predicted equivalent and measured top load at three top movements
in each of the
above four Japanese comparisons. The top movements ranged from inch (6 mm) to 40
mm,
depending on the data available.
The (equiv./meas.) ratios of the top load averaged 1.03 in the 15 comparisons with
a coefficient of
variation of less than 10%. These available comparisons help support the practical
validity of the
equivalent top load method described herein.
L.S. Peng, A.M. Koon, R. Page and C. W. Lee report the results of a class-A
prediction by others of
the TLT curve from a BDSLT on a 1.2 m diameter, 37.2 m long bored pile in
Singapore, compared
to an adjacent pile with the same dimensions actually top-loaded by kentledge. They
report about a
4% difference in ultimate capacity and less than 8% difference in settlements over
the 1.0 to 1.5
times working load range comparable to the accuracy noted above. Their paper has
the title
OSTERBERG CELL TESTING OF PILES, and was published in March 1999 in the
Proceedings
of the International Conference on Rail Transit, held in Singapore and published by
the Association
of Consulting Engineers Singapore.
B.H. Fellenius has made several finite element method (FEM) studies of a BDSLT in
which he
adjusted the parameters to produce good load-deflection matches with the BDSLT up
and down
load-deflection curve. He then used the same parameters to predict the TLT
deflection curve. We
compared the FEM-predicted curve with the equivalent load-deflection predicted by
the previously
described Part I and II procedures, with the results again comparable to the
accuracy noted above.
A paper by Fellenius et. al. titled BDSLT and FE Analysis of a 28 m Deep Barrette
in Manila,
Philippines, awaiting publication in the ASCE Journal of Geotechnical and
Environmental
Engineering, details one of the comparisons.
Proposed Dr. Ir. Soekarno Bridge at Manado, North Sulawesi, Indonesia Page B-3
Pile # BP4
Bi-directional Static Load Test
Test Report
Limitations: The engineer using these results should judge the conservatism of the
aforementioned
assumptions and extrapolation(s) before utilizing the results for design purposes.
For example,
brittle failure behaviour may produce movement curves with abrupt changes in
curvature (not
hyperbolic). However, the hyperbolic fit method and the assumptions used usually
produce
reasonable equivalent top load settlement curves.
Feb, 2007
Proposed Dr. Ir. Soekarno Bridge at Manado, North Sulawesi, Indonesia Page B-4
Pile # BP4
Bi-directional Static Load Test
Test Report
Proposed Dr. Ir. Soekarno Bridge at Manado, North Sulawesi, Indonesia Page B-7
Pile # BP4
Bi-directional Static Load Test
Test Report
Given:
C1 = 0.441
AE = 3820000 kips (assumed constant throughout test)
#0= 5.9 ft
#1= 48.2 ft (embedded length of shaft above hydraulic jack)
#2= 0.0 ft
#3= 0.0 ft
.
DDDD
BDSLT
(mm)
Q#A
(MN)
Q#B
(MN)
Q#B
(MN)
P
(MN)
d
dddd
TLT
(mm)
d
dddd
BDSLT
(mm)
.
DDDD
BDSLT +
.
DDDD
d
dddd
(mm)
0.000 0 0 0 0.000 0.000 0.000 0.000
0.100 352 706 1058 0.133 0.047 0.086 0.186
0.200 635 1445 2080 0.257 0.096 0.160 0.360
0.300 867 1858 2725 0.339 0.124 0.215 0.515
0.400 1061 2088 3149 0.396 0.139 0.256 0.656
0.600 1367 2382 3749 0.478 0.159 0.319 0.919
0.800 1597 2563 4160 0.536 0.171 0.365 1.165
1.000 1777 2685 4462 0.579 0.179 0.400 1.400
1.200 1921 2773 4694 0.613 0.185 0.427 1.627
1.500 2091 2867 4958 0.651 0.191 0.460 1.960
1.800 2221 2933 5155 0.680 0.196 0.484 2.284
2.100 2325 2983 5308 0.703 0.199 0.504 2.604
2.500 2434 3032 5466 0.726 0.202 0.524 3.024
Proposed Dr. Ir. Soekarno Bridge at Manado, North Sulawesi, Indonesia Page B-8
Pile # BP4
Bi-directional Static Load Test
Test Report
Given:
C1 = 0.441
AE = 17000 MN (assumed constant throughout test)
#0= 1.80 m
#1= 14.69 m (embedded length of shaft above hydraulic jack)
#2= 0.00 m
#3= 0.00 m
.
DDDD
BDSLT
(mm)
Q#A
(MN)
Q#B
(MN)
Q#B
(MN)
P
(MN)
d
dddd
TLT
(mm)
d
dddd
BDSLT
(mm)
.
DDDD
BDSLT +
.
DDDD
d
dddd
(mm)
0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
2.54 1.57 3.14 4.71 3.37 1.20 2.17 4.71
5.08 2.82 6.43 9.25 6.52 2.45 4.07 9.15
7.62 3.86 8.27 12.12 8.61 3.15 5.46 13.08
10.16 4.72 9.29 14.01 10.05 3.54 6.51 16.67
15.24 6.08 10.60 16.68 12.14 4.04 8.10 23.34
20.32 7.11 11.40 18.50 13.60 4.34 9.26 29.58
25.40 7.90 11.94 19.85 14.70 4.55 10.15 35.55
30.48 8.55 12.33 20.88 15.55 4.70 10.85 41.33
38.10 9.30 12.75 22.05 16.53 4.86 11.67 49.77
45.72 9.88 13.05 22.93 17.27 4.97 12.29 58.01
53.34 10.34 13.27 23.61 17.84 5.06 12.79 66.13
63.50 10.83 13.48 24.31 18.44 5.14 13.30 76.80
Proposed Dr. Ir. Soekarno Bridge at Manado, North Sulawesi, Indonesia Page B-9
Pile # BP4
Bi-directional Static Load Test
Test Report
Given: C1 = 0.441
C2 = 0.579
C3 = 0.396
#0= 5.9 ft
#3= 0.0 ft
.
DDDD
BDSLT
(mm)
Q#A
(MN)
Q#B
(MN)
Q#B
(MN)
P
(MN)
d
dddd
TLT
(mm)
d
dddd
BDSLT
(mm)
.
DDDD
d
dddd
(mm)
.
DDDD
BDSLT +
.
DDDD
d
dddd
(mm)
0.000 0 0 0 0 0.000 0.000 0.000 0.000
0.100 352 247 459 1058 0.133 0.025 0.107 0.207
0.200 635 506 939 2080 0.257 0.052 0.205 0.405
0.300 867 650 1208 2725 0.339 0.067 0.272 0.572
0.400 1061 731 1357 3149 0.396 0.075 0.321 0.721
0.600 1367 834 1548 3749 0.478 0.085 0.393 0.993
0.800 1597 897 1666 4160 0.536 0.092 0.444 1.244
1.000 1777 940 1745 4462 0.579 0.096 0.483 1.483
1.200 1921 971 1802 4694 0.613 0.099 0.513 1.713
1.500 2091 1003 1864 4958 0.651 0.103 0.548 2.048
1.800 2221 1027 1907 5155 0.680 0.105 0.575 2.375
2.100 2325 1044 1939 5308 0.703 0.107 0.596 2.696
2.500 2434 1061 1971 5466 0.726 0.109 0.618 3.118
Proposed Dr. Ir. Soekarno Bridge at Manado, North Sulawesi, Indonesia Page B-10
Pile # BP4
Bi-directional Static Load Test
Test Report
Given:
C1 = 0.441
C2 = 0.579
C3 = 0.396
AE = 17000 MN (assumed constant throughout test)
#0= 1.80 m
#1= 9.14 m (embedded length of shaft above mid-jack)
#2= 5.55 m (embedded length of shaft between hydraulic jack)
#3= 0.00 m
.
DDDD
BDSLT
(mm)
Q#A
(MN)
Q#B
(MN)
Q#B
(MN)
P
(MN)
d
dddd
TLT
(mm)
d
dddd
BDSLT
(mm)
.
DDDD
d
dddd
(mm)
.
DDDD
BDSLT +
.
DDDD
d
dddd
(mm)
0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
2.54 1.57 1.10 2.04 4.71 3.37 0.64 2.73 5.27
5.08 2.82 2.25 4.18 9.25 6.52 1.31 5.21 10.29
7.62 3.86 2.89 5.37 12.12 8.61 1.69 6.92 14.54
10.16 4.72 3.25 6.04 14.01 10.05 1.90 8.15 18.31
15.24 6.08 3.71 6.89 16.68 12.14 2.17 9.97 25.21
20.32 7.11 3.99 7.41 18.50 13.60 2.33 11.27 31.59
25.40 7.90 4.18 7.76 19.85 14.70 2.44 12.26 37.66
30.48 8.55 4.32 8.02 20.88 15.55 2.52 13.03 43.51
38.10 9.30 4.46 8.29 22.05 16.53 2.61 13.92 52.02
45.72 9.88 4.57 8.48 22.93 17.27 2.67 14.60 60.32
53.34 10.34 4.64 8.62 23.61 17.84 2.71 15.13 68.47
63.50 10.83 4.72 8.76 24.31 18.44 2.76 15.68 79.18
Proposed Dr. Ir. Soekarno Bridge at Manado, North Sulawesi, Indonesia Page B-11
Pile # BP4
Bi-directional Static Load Test
Test Report
mm
mm
mm
mm
mm
mm2
tonnes/mm2
tonnes/m3
tonnes
mm
#BDSLT
(mm)
Q#A (tonnes) Q#A' (tonnes) Q#A (tonnes)
Q#A '
(tonnes)
Equivalent
Load
(P single)
(tonnes)
#
.
#0 (mm)
#
.
#1+ #2
(mm)
#TLT
(mm)
#BDSLT
(mm)
#
(mm)
#BDSLT + #
(mm)
0.00 0 0 0 0 0 0.00 0.00 0.00 0.00 0.00 0.00
-5.00 163 97 295 295 392 0.00 1.41 1.41 0.41 1.00 -6.00
-10.00 175 110 400 400 510 0.00 1.81 1.81 0.56 1.26 -11.26
-15.00 185 120 485 485 605 0.00 2.14 2.14 0.68 1.46 -16.46
-20.00 195 130 555 555 685 0.00 2.41 2.41 0.78 1.64 -21.64
-25.00 205 140 615 615 755 0.00 2.65 2.65 0.86 1.80 -26.80
Proposed Dr. Ir. Soekarno Bridge at Manado, North Sulawesi, Indonesia Page B-12
Pile # BP4
Bi-directional Static Load Test
Test Report
APPENDIX C
Calibration Certificates
Proposed Dr. Ir. Soekarno Bridge at Manado, North Sulawesi, Indonesia Page C-0
Pile # BP4