Safety Manual New
Safety Manual New
Safety Manual New
Safety manual
1
Index
Chapter - 1
Definitions/3-11
Chapter - 2
Policy & Principles Of Safety/12-15
Chapter - 3
Safety Rules/16-37
Chapter - 4
Safety Instructions/38-100
Chapter - 5
Safety Audit/101-103
Reviewed by :
Adll S.E 1-12-15 Protection & Operation Services
Recommended by:
Chief Engineer 30-12-15 P&M, PSTCL
Approved by:
th
07-01-16 BOD's of PSTCL in 34 meeting vide U.O No-
142/BOD/34.15/PSTCL, Dated 18-01-16
2
PSTCL Safety Manual
Chapter - 1
definitions
3
1.0 DEFINITONS
1.5 Automatic-means self-acting, operating by its own mechanism when actuated by some
impersonal influence, as for example, a change in current strength.
Note: Remote control that requires personal interface is not automatic but manual.
1.6 Cancellation of Line Clearance PTW / Test-means a declaration by the person (to
whom the 'Line Clearance Permit to Work / Testing' has been issued) stating that the work
for which the permit / sanction was issued, has been suspended or completed and stating
that all temporary arrangements including men & material, earth connections have been
removed and that all men under his direct charge have been warned that it is no longer safe
to Work/Test on that equipments/apparatus and equipments/apparatus is ready for
energization/use.
1.8 Certificate-No Back Feed-A certificate by an authorized person which certifies for no
back feeding with the details of Isolation and Earthing, carried out at a remote substation in
order to achieve Safety from the EHV/HV systems and from test supplies.
1.10 Circuit Breaker-means a device, capable of making and breaking the circuit under all
conditions, and unless otherwise specified, so designed as to break the current
automatically under abnormal conditions.
1.12 Company-means a company formed and registered under the Companies Act, 1956
and includes any corporate under a Central, State or Provincial Act.
4
1.13 Competent Authority-Authority as per DOP/Company Directive authorized to
decide, implement and control the specified activities.
1.14 Competent person-A person authorized by competent authority who has sufficient
technical knowledge and/or experience of a particular branch of engineering and is
capable of carrying out a particular operation/activity to enable him to avoid danger while
working in connection therewith.
1.15 Conductor-means any wire, cable, bar, tube rail or plate used for conducting energy
and so arranged as to be electrically connected to a system.
1.17 Cut out-means any appliance for automatically interrupting the transmission of
energy through any conductor when the current rises above a predetermined amount, and
shall also include fusible cut-out.
1.18 Danger-A risk to health/life or any part of body from shock, burn or injury.
1.20 Dead-Not electrically charged, means at or about earth potential and disconnected
from any live system:
PROVIDED that an apparatus separated from a live conductor by a spark gap shall not be
deemed to be dead.
1.21 Earth-means the conductive mass of the earth, whose electric potential at any point is
conventionally taken as zero.
5
minimum 95 sq. mm copper equivalent.
b) Additional Earths-Temporary, portable Earths (e.g. Earthing rod) which are
applied after Line Clear PTW or Sanction for Test is issued and are included on an
Earthing Schedule. They are applied within an Isolated Zone in order to discharge
any induced voltage. Additional Earth shall be minimum 35 sq. mm copper
equivalent.
1.25 Earthing Schedule- A schedule indicating the Additional Earth requirements for each
stage of the work or testing. It must show the number of earths required and either describe
or show pictorially their position in the Isolated zone.
1.27 Earth Leakage-means a current, which flows to earth or to extraneous conductive parts
in a circuit, which is electrically sound.
1.28 Electrical Safety-means recognizing hazards associated with the use of electrical
energy and taking precautions so that hazards do not cause accident, injury or death.
1.29 Emergency-for the purpose of this manual means an unusual condition which exists
that endangers life and/or property.
1.31 Equipment-- Electrical and Mechanical assets used to generate, transmit and
distribute electricity working on which the safety rules apply.
1.34 General Safety-Actions required to maintain safety at place of work/testing e.g. safe
access, safe methods of work/testing and the correct use of personal protective equipments.
6
point (usually the middle wire or neutral point of transformer or generator winding) is
intentionally grounded, either solidly or through a current-limiting device (not a current-
interrupting device).
1.37 Grid Code- means code prepared by the Punjab State Electricity Regulatory
Commission (PSERC) in accordance with Transmission licensee (PSTCL).
1.39 High Voltage (HV)-A voltage above 650 and upto 33,000 volts.
1.42 Installation-means any composite electrical unit used for the purpose of generating,
transforming, transmitting, converting, distributing or utilising energy
1.43 Isolated-means disconnected from all sources of electric energy by adequate physical
separation and in a manner that disconnected contacts of the isolating switch are clearly
visible.
1.44 Isolated Zone-All items of equipment within a work/testing area for which isolation
has been achieved at all point of supply.
1.47 Key Safe-A designated lockable cabinet for the safe custody of all Safety Keys.
1.48 Line Clearance PTW Issue Officer-is a person who is authorized for ensuring that
7
controlling switches and circuits have been isolated, made dead and inoperative and that
adjacent circuits have been made safe for the work to be carried out and who is authorized
to issue the Line Clearance Permit to Work.
1.49 Line Clearance Permit to Work-means a form of declaration signed by and given by
one authorized person to another authorized person in charge of work to be carried out on
or adjacent to any electrical apparatus, mains or L.T/H.T/E.H.T lines, for the purpose of
making known such latter person exactly what apparatus, mains or lines are made dead
and earthed and safe for working and gives the description of the work required to be
carried out under such Line Clear Permit to Work.
1.53 Locked-- To secure an item of Equipment with padlocks or other devices such that it is
immobilized in the close position
1.56 Medium Voltage (MV)-A voltage between 250 and 650 volts.
1.57 Neutral Conductor-means a conductor connected to the neutral point of a system and
capable of contributing to the transmission of electrical energy.
1.58 Points of Isolation-The point at which Equipment has been isolated and where
practicable, the Isolation Point is immobilised and locked. Caution Notice shall be attached
to all Points of Isolation.
1.59 PPE (Personal protective equipments)-means devices such as helmets, rubber gloves,
rubber gauntlets, line hose, safety boots or other insulating devices, such as high voltage
detector, earth discharge rod etc. which are especially designed for the protection of
workmen.
8
removed.
1.62 Request for Line Clearance PTW -means a request made by a Competent Person or an
Authorized Person to the Shift In-Charge of the substation before undertaking construction,
repair, testing or maintenance works for issue of a specific clearance, detailing particulars
of the work, time during which the work is intended to be carried out, precautions (if any)
required to be taken to enable the Shift In-Charge of the substation to determine whether
the Line clearance PTW can be issued in conformity with the rules, requirements of service,
safety etc.
1.63 Safe Electrical Clearance-A distance of 1.5 meters minimum, which must be
maintained by linesman from the conductors or jumpers of a de-energised overhead line
which has been Isolated, Primary Earthed and a Safety Document issued, before
connection of Additional Earths under the terms of that Safety Document.
1.64 Safety Clearance-The distance from the nearest Extra High Voltage or High Voltage
exposed Conductor not Primary Earthed or from its support insulator, which must be
maintained to avoid danger
1.66 Safety from the System-Those conditions which safeguard persons carrying out the
work on a System from the dangers, which are inherent in the System.
1.67 Safety Key-The key from a unique lock (at a location) which is used for locking an
Isolating Device, Earth or Drain/Vents.
1.68 Safety Officer-as per CEA(Measures relating to Safety & Electric Supply) Regulations,
2010 Chapter II , Cl-5 (1) ; all suppliers of electricity including Generating Companies,
Transmission Companies & Distribution Companies shall designate an Electrical Safety
Officer as per the specific prescribed norms for ensuring observance of safety measures
specified under these Regulations in their Organisation for construction , operation &
maintenance of power stations ,sub-stations , transmission and distribution lines .
9
1.70 S.L.D.C. (State Load Dispatch Centre) The Centre where the operation of electricity
grids constituting the Punjab State Power System is coordinated.
1.71 Step Voltage-means the potential difference between two points on the earth's surface
separated by distance of one pace that will be assumed to be one meter in the direction of
maximum potential gradient.
1.75 System - Items of Equipments which are used either separately or in combination to
generate transmit or distribute electricity. It means an electrical system in which all the
conductors and apparatus are electrically connected to a common source of electric supply.
1.76 System Control-means System Operation under SLDC, which controls and
coordinates all switching operations of the System including issues of Line Clearance
Permit to work /test etc.
1.77 Switch-means a manually operated device for opening and closing or for changing the
connection of a circuit
1.78 Switch Gear-shall denote switches, circuit breakers, cut-outs and other apparatus
used for the operation, regulation and control of circuits
1.79 Temporary Earth-means an earth defined under 1.22 above, but applied
additionally/temporarily at the point of work on any electrical apparatus during actual
working thereon, after the issue of Line Clearance Permit to Work/Test.
1.80 Touch Voltage-means the potential difference between a grounded metallic structure
and a point on the earth's surface separated by a distance equal to the normal maximum
horizontal reach, approximately one meter.
10
generating station to another generating station or a sub-station, together with any step up
and step down transformers, switch gear and other works necessary to and used for the
control of such cables or over headlines, and such buildings or part thereof as may be
required to accommodate such transformers, switch gear and other works.
1.82 Unauthorized person-means one who is not permitted to work on electrical apparatus
except under the personal supervision of an authorized person.
1.83 Vented-Allowing a closed space to have an outlet to atmosphere so that the pressure
has equalised to atmospheric.
1.84 Visitor-means a person, other than an Employee permitted to enter a work area under
permission by the authorized person.
NOTE: All words and expressions used but not defined hereunder shall have the meaning assigned
to them in Electricity Act 2003, Indian Electricity Grid Code, Punjab Grid Code and Indian
Electricity Rules 1956 respectively assigned to them in the Electricity Act 2003 as amended up to
date, CEA (Measures relating to Safety and Electricity Supply) Regulations, 2010 and CEA (Safety
requirements for Construction, Operation and Maintenance of Electrical Plants and Electric Lines)
Regulations, 2011 and the Rules and regulations made there under, an amendment thereof, if any,
and the Rules made there under as the case may be.
11
PSTCL Safety Manual
Chapter - 2
12
2.0 POLICY & PRINCIPLES OF SAFETY
2.1 POLICY- P.S.T.C.L. recognizes and accepts its statutory and moral responsibility for
implementing safety standards and maintaining a safe working environment for all its
employees in terms of ensuring safe design, construction, operation and maintenance of
Transmission Systems in the safest possible manner along with the provision of safe
methods of work and healthy working conditions. While achieving this objective it
endeavours to ensure compliance with the requirement of I.E. Rules 1956, I.E. Act. 2003,
Grid Code, CEA (Measures related to Safety and Electricity Supply) Regulation 2010 and
Power System Safety Standards. The Policy relies on all employees, vendors and
contractors for complying with safety requirements relevant to their responsibilities.
2.1.1 It is our policy to perform work in the safest practicable manner, consistent with good
practice. The health, safety and welfare of our employees and all those likely to be affected
by our operations is the responsibility of management, and as a priority it ranks equally
with our business objectives. Adequate resources will be made available to ensure the
success of this policy.
2.1.3 The company will provide and maintain safe plant and equipment and ensure the safe
handling and use of hazardous substances. Management will provide the necessary
information, instruction and training and will ensure the competence of all employees and
contractors.
2.1.4 All employees are to be aware that, in the event of any conflict between the demands of
business and safety, they will receive management support if they reasonably choose the
safety of employees or third parties as the priority.
2.1.5 It is our policy to adhere completely to the requirements of the I.E.Rules 1956, Indian
Electricity Act 2003, CEA Regulations 2010 and Grid Code.
2.1.6 The attention of all employees is directed to this Safety Policy and Safety Manual,
which is under review / revision.
13
2.2 PRINCIPLES
2.2.1. It is well understood that electro mechanical systems used in EHV & HV
Transmission networks are designed in such a manner that during normal operations they
are safe, but have inherent dangers during mal-operations and accidents. Hence, in order to
avoid such happenings and consequent dangers, Rules and Instructions have to be framed
and implemented. Such Rules and Instructions which form the core part of this Manual
define procedures and responsibilities of operating personnel for achieving complete
safety of personnel, equipments, system and surroundings.
Safety Rules provide basic ground rules, whereas Safety Instructions lay down the
procedures as per the Safety Rules.
2.2.3 In conditions where such limiting/isolation is not possible or is not required like
during Hotline working, special instructions/procedures are applied.
2.3.1 Accident details, however trivial they may appear to be, must always be entered in the
Accident Book, copies of which are held by the SSE /Shift in-charge on site and at the
company offices. The SSE or Shift in-charge responsible for the work will ensure that each
accident book and completed reports are returned to the Safety Head. Accidents reports
will be retained for a period of at least three years.
2.3.2 The person in charge of the work must report all injury accidents or dangerous
occurrences to the Safety Head by telephone.
2.3.3 All accidents and near misses will be investigated by the Divisional Head in charge of
the work in accordance with the company accident investigation procedures and statutory
provisions. The Divisional Head will carry out investigation and submit the enquiry report
within 24 hours (in case of fatal accident) and within 48 hours (in case of non-fatal accident)
to the Safety Head. Copies of the enquiry report may be sent to the statutory authority
including Assistant Labour Commissioner, Electrical Inspector and District
Administration in prescribed form in accordance with statutory provisions.
14
operating practice and procedures that form the Company Policy, and must be strictly
adhered to by all employees.
2.4.2 Employees who wilfully violate the spirit of policy or rule or in utter disregard to
safety policy / manual / rules carry out any O&M shall be liable for disciplinary action up
to and including termination of employment.
15
PSTCL Safety Manual
Chapter - 3
SAFETY RULES
16
3.0 SAFETY RULES
3.1.2 SAFETY PRACTICES; All Safety Rules, Safety Instructions and Procedures are
mandatory. 'Safety' as a whole may be interpreted as the proper planning of work,
proper usage of safety tools, following safety procedures and exercise of good judgment
and intelligent supervision. Experience proves that majority of the accidents are
preventable. Prevention of accidents requires the whole hearted co-operation of all
employees of the Organization.
Generally capable and mentally alert employees avoid accidents. Employee consistently
not adhering to Safety practices & Rules is a liability to the Organization. He is a danger to
himself, his fellow workers, his family, the public and Corporation. Accidents DO NOT
Just Happen; accident are the results of unsafe conditions or unsafe acts or a combination
of both.
17
13. Non adoption of the practice that all light equipment and tools to be used in the
Over-head works, should be raised and lowered by means of hand line and canvas
bucket, other suitable container, and men on the ground should be with helmet &
stay clear of overhead work to prevent being struck by falling objects.
14. Using unsafe equipment or using improper tools such as dull cutting tools or
mushroom head chisels, pipe extensions on wrenches not designed for them, wrong
tool for the job, using hands instead of hand tools.
15. Casual/ non-serious approach towards work.
Unsafe Conditions which may also result in accidents include the following:-
1. Unguarded equipments such as unshielded moving parts of machines, saws, etc.
and un-barricaded floor opening, un-covered cable trenches and excavations.
2. Use of defective material such as poorly constructed scaffolding, broken ladder, torn
gloves etc.
3. Improper illumination
4. All anticipated hazards should be well intimated to all workers.
5. Power cable for lighting / air compressor / air conditioner being run together with
Common switch box and with less capacity switches.
6. Control cable and power cable running together.
7. Sacrificing safety for speed OR early completion of the work.
8. The person-in-charge of work failing to ensure himself that the power mains & the
apparatus are free from dangerous leakage or induction and has been effectively
earthed locally before permitting men to work upon it.
9. Failure to place warning boards by the person-in-charge on all switchgear before
men are permitted to work which should only be removed by the person who has
placed them. It is desirable that the person issuing the LC PTW shall place one
warning board on the switch energizing the mains for each LC PTW issued so that he
can be sure that all the LC PTW to work are returned when he has to charge the
mains.
10. Allowing a person to work above without the presence of any supervisor or co-
worker.
11. Visitors and unauthorized persons shall not be allowed to remain in the vicinity of
live mains and apparatus, unless accompanied by an authorized person whose
responsibility would be to ensure that the visitor complies with all statutory Safety
provisions.
18
Line working cannot be covered in basic Safety Rules).
3.4.1 Safety Rules and Safety instructions shall be applied when working on, or near to
items of energized / de-energized Equipments / Lines which are owned by Punjab State
Transmission Corporation Limited.
3.4.2 Equipments shall be added to and removed from a system only in accordance with an
Approved Handing over/Taking Over Procedures. This procedure will determine when
the Safety Rules and Safety Instruction shall apply, or do not apply.
3.4.3 No unauthorized person shall be allowed to enter into switching and controlling area
of substation. A signboard distinctly displaying this notice shall be provided on the gate
meant for entry in to the switching & controlling area of substation.
3.4.4 The staff should take care that the conducting material such as ladders, steel tape etc.
should not be used in the switchyard, however if it is to be used one should take care that it
should not come within the induction zone during movement of such material. Also, staff
should avoid use of umbrella in the switchyard.
3.4.5 Normally, a standard first aid box with medicines & bandages etc. available in the
market made of steel sheet shall be provided in each & every control room.
3.4.6 Temporary changes or change over made in the switchyard or control room or on the
EHV line should be displayed on the board near to the sitting arrangement of the shift in
charge till such arrangement exists.
2. DO use correct size and quality of fuse wire while replacing the blown out fuse.
3. DO ensure controlling switches are opened & locked or fuse cut outs are withdrawn
19
before working on lines.
DON'Ts
2. DO NOT replace a blown fuse until you are satisfied with the cause and you have
rectified the irregularity in the related system.
3. DO NOT disconnect a plug by pulling flexible cable when the switch is on.
5. DO NOT close any Switch/Isolator/Breaker unless you are familiar with the circuit,
which it controls and know the reason for its being kept open.
6. DO NOT work on energized circuits without taking extra precautions, such as use
of rubber gloves and gauntlets.
7. DO NOT touch or tamper with any electrical equipment or conductor, unless you
have made sure that it is dead and earthed.
8. DO NOT work on the live circuit without the specific orders of the authorized
Engineer in-charge and make certain that all safety precautions have been taken.
11. DO NOT touch an electric circuit when your hands are wet, or bleeding, cut or an
abrasion.
20
12. DO NOT use fire extinguisher on electrical equipment unless it is of proper class
and desired for use for that purpose.
13. DO NOT throw/inject water on live electrical equipment in case of fire.
14. DO NOT touch the body of electrical shock victim. Push him with a piece of dry
wood.
15. DO NOT allow visitors and unauthorized persons to touch or handle electrical
apparatus or come within the danger zone of E.H.V. apparatus.
3.5.1 Persons shall not be allowed any part of their body or objects to approach within the
following Safety Clearances exposed EHV/HV conductors, which are Live. (Except during
approved live line work):-
Rated Voltage(KV) Safety Clearance (Meters)
Upto 33 0.8
66 1.0
132 1.4
220 2.4
400 3.1
3.5.2 Following minimum safety clearance shall be maintained for bare conductors or live
parts of any apparatus in outdoor Sub-stations, excluding overhead lines of HV and EHV
installations:-
Highest system Voltage(KV) Safety Clearance (Meters)
Upto 12 2.6
36 2.8
72.5 3.1
145 3.7
245 4.3
420 10.3
3.5.3 When Points of Isolation are established and exposed conductors/parts could be
subject to EHV or HV, the only object permitted to approach within Safety Clearance shall
be Approved voltage measuring devices or Earthing Devices.
3.5.4 When Points of Isolation are established and Danger is excluded by application of
Earthing Devices, approach is allowed under an appropriate Safety Document within the
specified Safety Clearance.
21
3.6 SAFETY RULES FOR WORKING OR TESTING ON, OR NEAR TO EHV OR HV
EQUIPMENTS
3.6.1 When working or testing is to be carried out on or near to EHV/HV equipments first
the means of achieving Safety must be assessed then the EHV/HV equipments must be
identified.
3.6.2 When working or testing on the EHV/HV equipment does not require the removal of
Primary Earths, a Line Clear PTW as per Annexure shall be issued. When testing of the
EHV/HV equipment does require the removal of Primary Earths, a Test permit (TP) as per
Annexure shall be issued.
3.6.3 The Safety Document must show the Safety Precautions taken to achieve safety from
the EHV/HV system and also further precautions required to protect persons from
inherent dangers in other systems.(e.g. Purging for the removal of substances injurious to
health, venting, draining and removal of stored energy and LV/MV supplies).
3.6.4 Within any Isolated Zone, any number of LC (Line clear) PTWs may be issued.
Separate LC PTW to be issued to separate working party. LC PTW on Line bay does not
mean LC PTW on concerned line.
3.6.5 Within any Isolated Zone only one TP shall be in force at any time. No LC PTWs are
permitted at the same time when TP is in force in the same Isolated Zone.
3.6.6 If motive power supplies are made available, no other LC PTW shall be issued on the
same equipment.
3.6.7 When Danger from induced voltages could arise during the course of working or
testing, Additional Earths shall be applied. The number of these Earths and their
application must be stated on Safety Document as per relevant Safety Instruction.
3.7.1 Where reasonably practical, working on, or near to, MV and LV equipments should be
carried out with that equipment 'Dead'.
3.7.2 When working or testing is to be carried out on or near to MV/LV Equipments, then
means of achieving safety must be assessed according to relevant Safety Instruction and
also comply with the following rules:
(a) The MV/LV Equipment shall be identified.
(b) The MV/LV Equipment shall be Isolated and those Points of Isolation shall
be secured.
(c) The method of instructing how the working or testing is to take place can be
22
described either by a Safety Document or Personal Supervision.
3.7.3 When it is unavoidable to carry out working or testing on MV/LV equipment Dead,
then suitable precautions to avoid Danger must be followed and detailed in relevant Safety
Instructions.
3.8.1 When working or testing is to be carried out on, or near to mechanical equipments, the
means of achieving safety must be assessed according to relevant Safety Rules as above.
3.8.2
(a) For working or testing with the Equipments Isolated and either non-operational or with
limited restoration of motive power supplies, the Safety Document issued will be an LC
PTW.
(b) When testing of mechanical Equipment involves application of test pressures, the Safety
Document issued will be a TP.
3.8.3 When the working or testing requires the issue of a LC PTW as above, the precautions
will be specified in the Line Clear PTW and must include the following :-
(a) The mechanical equipment must be Isolated and Points of Isolation
established for the work.
(b) Further precautions taken to protect persons from inherent dangers in
mechanical systems. This must include draining, venting, purging and
removal of stored energy.
(c) Venting emissions shall be dissipated so as to avoid Danger. Where
reasonably practicable, vents shall be locked open and Caution Notice fixed.
(d) The removal of the stored energy must be carried out in a manner to contain
or dissipate that stored energy safely.
(e) Where internal access is required and the residue of the contents could cause
Danger, the mechanical equipment must be Purged and that residue
disposed of safely according to an Approved Procedure.
3.8.5 When testing requires issue of a TP according to Safety Rule as above, then the
23
procedure will be as described in relevant Safety Instruction. It is essential that the
maintenance/testing engineer properly assess the risks of testing. This procedure should
only be used when such testing is an operational necessity.
3.9.1 The operation of any Equipment to achieve Safety from the system shall never involve
pre-arranged signals or the use of time intervals.
3.11.1 Equipments shall be clearly marked with a unique code and/or description, which
must be the information used on Safety Documents and in switching instructions.
2) Wherever the foundation is being constructed on unstable earth, the workmen shall
not be permitted to enter the excavated pit unless shoring is done.
3) Only responsible and skilled employees shall be deployed for directing mobile
equipment adjacent to footing excavations.
5) The mobile equipment shall be located only on levelled earth to assure stability.
6) Sufficient care shall be taken during tower erection to see that more than the
minimum numbers of workmen are not deployed. This will minimise injury due to
exposure of falling objects on workmen, when working at two or more levels. Proper
protection such as use of helmets, safety belts etc., shall be insisted upon.
24
7) Tie ropes shall be used wherever necessary for maintaining steel sections or other
parts in position to reduce the possibility of tilting etc.
8) Adequate supports shall be provided for the tower members and sections of panels
during assembly.
9) The construction of transmission towers, erection of poles, the tools and machinery,
employed for the work shall meet the requirements of the relevant Indian Standard
Specifications and Code of Practices along with the CBIP manual on Transmission
Lines. The wire ropes, pulley blocks etc., shall be of tested quality and inspected by a
responsible employee for its fitness before commencing the work.
10) Other than the supervisory staff and such of the workmen required to guide and
assist the section being erected, no one else shall be permitted to come under a tower
being erected.
12) Wherever cranes are used for erection, the same shall be set on firm foundations. The
outriggers of the cranes shall be used wherever available. The wheels shall be locked
in position to prevent dislocation during handling.
13) Suitable tie ropes shall be used to maintain control of tower sections being raised and
positioned wherever possible and proper care shall be taken to see that they do not
create a greater hazard. The wire rope used for carrying the section shall not be
detached before the section is adequately secured.
14) The erection or maintenance work shall not be carried out during high wind,
thunderstorms or unfavourable weather condition, which would make the work
hazardous, except during emergency restoration procedures where utmost
precautions, shall be taken to avoid any accidents.
15) The Engineer in Charge shall regularly arrange to maintain all the equipment and
tools and plant in safe operating conditions.
16) Stringing of Bundle Conductor shall be carried out with T & P Machine only except
where not feasible.
17) Adequate traffic control shall be maintained wherever erection work is being
carried out at highway crossings. The permissions required from the concerned
25
authorities, such as the department of highway, police etc., shall be obtained prior to
commencement of work. Similarly, for erection work at railway crossings, the
permission of the railway authorities shall be obtained before commencing the work.
The crossing of railway tracks under power lines shall be as nearly as possible at
right angles.
18) The Engineer in Charge shall ensure the required clearances to be maintained in
moving equipment under or near the energised Lines.
20) Wherever there is a possibility of the conductor being handled coming in contact
with an energised conductor, or there is a possibility of a dangerous voltage build up
due to induction, the conductor being handled shall be grounded, unless a
provision is made to insulate or isolate the employee. If the existing line is de-
energised, a Line Clear PTW shall be .obtained and the line grounded on both sides
of the cross over. In case the Line Clearance PTW cannot be obtained the Line shall
be considered as energised for all practical purposes.
21) While executing the work of crossing over an existing Line, suitable guard
structures with rope nets shall be installed to isolate the conductors and workmen
coming within the required minimum clearances specified for the voltage and if
there is any auto-reclose installed on the energised line, the same shall be made
inoperative. In addition the line being handled shall be grounded on either side of
the cross over.
22) The conductors being strung or removed shall be kept under control by using
adequate reels, guard structures, tie Lines, or any other appropriate means to
prevent accidental contact with energised wires.
23) The guard structure shall have sufficient strength and have proper dimensions and
supported adequately.
24) The wire ropes, come-along clamps, anchors, guys, hoists shall have ample capacity
to prevent failure and accidents. The load rating specified by the manufacturers for
stringing equipment, pulley blocks and all other load bearing hardware and tools
shall not be exceeded during operations. These shall be inspected regularly and
26
replaced and repaired when damaged or when dependability is doubtful.
25) Came along clamps designed for the specific conductor range only shall be used.
During stringing or removal of conductors, no workmen shall be permitted to come
directly under overhead operations, or on the cross arms. The dead end points of the
conductors at section towers shall be adequately anchored before commencing
operations. The grounds provided to the conductor shall be maintained intact until
the conductors are hooked on to the insulators.
26) The reel handling equipment, including pulling and braking machines shall have
ample capacity, operate smoothly, and levelled and aligned in accordance with the
manufacturer's operating instructions. Reliable communication between the
operator of these machinery and the stringing operators shall be provided.
27) Each conductor shall be dead-ended at both ends before commencing stringing of
the conductor in the next section.
28) The sequence of stringing of conductors and ground wires shall strictly follow the
design conditions of erection loads considered for the structure. The method of
erection followed shall not impose loads in excess of design loads on the structure.
29) Before commencing the stringing or releasing operations of any conductor adjacent
to an energised Line, the following precautions, in addition to all the above, shall be
taken:
a. Only skilled and trained labourers competent to work on Transmission Line
construction shall be deployed for the work. The workmen should be in good
health, able bodied and normally sound mental state.
b. The possibility of dangerous voltages due to induction, particularly during
switching and fault conditions, shall be investigated and attended.
c. The tension stringing method or such other methods shall only be used,
which prevent unintentional contact between the lines being pulled and the
employee.
d. All the pulling and tensioning equipment shall be isolated, insulated, or
effectively grounded.
e. A ground rod shall be installed between the tensioning reel setup, and the
first structure in order to ground each bare conductor, sub-conductor, or
overhead ground wire during stringing operations.
f. During stringing or unstringing operations, each conductor or ground wire
shall be grounded at the first tower adjacent to both the tensioning and
pulling setup and in increments so that no point is more than 10 stringing
spans away.
g. The grounds shall be left in place till the conductor installation is completed.
h. These grounds shall be removed at the last phase of cleanup operations.
i. The grounds shall be placed or removed only with a Hot Line equipment/
27
insulating rod.
j. Conductors and ground wires shall be grounded at all dead-end points.
k. A ground shall be located at each side and within 10 feet of working areas
where conductors or ground wire are being jointed at ground level. The two
ends to be jointed shall be bonded to each other. The jointing shall be carried
out on either an insulated platform or on a conductive metallic grounding
mat bonded to grounds. When grounding mat is used, the same shall be
barricaded and an insulated walkway provided for access to the mat.
l. All the conductors and ground wire shall be bonded to the end tower where
the work is to be completed. At the dead end tower, the de-energised line
shall be grounded.
m. The grounds can be removed on completion of the work making sure that the
Line is not left open circuited at any tower at which the work is carried out.
30) The following precautions shall be taken for Hot-Line bare hand work in addition to
all other applicable precautions specified in these standards:
a. Only qualified and trained employees, trained for Hot-Line bare-hand
technique and the pertinent safety requirements thereto, shall be permitted
for the work as well as for supervision.
b. Hot line LC PTW be availed by Hot line crew engineer before commencement
of work.
c. The information of Hot line LC PTW be informed to SLDC.
d. The following checks shall be made before commencing Hot-Line bare-hand
work on energised high-voltage conductors or equipment to ensure
adequacy of tools and capability of personnel:
e. The voltage rating of the circuit on which the work is to be carried out,
f. The clearances to ground of the lines and other energised parts on which
work is to be carried out,
g. The voltage limitations of the aerial-lift equipment intended to be used.
h. The Hot Line equipment to be used shall be of proper design and tested.
i. If any automatic reclosing feature is available on the circuit breakers or
switches, the same shall be made inoperative before commencing the work
on any energised line or equipment.
j. The work shall not be carried out during thunderstorms and cloudy
atmosphere.
k. The employee shall be connected to the bucket liner of Hot Line equipment in
use through conducting shoes, leg clips or by any other suitable means.
l. Adequate electrostatic shielding for the rated voltage of the line or
equipment on which work is being carried out shall be provided to the
workmen wherever necessary or conducting clothing shall be provided.
m. Only tools and plant intended for Hot-Line bare-hand work shall be used,
and these shall be kept clean and dry.
n. The outriggers on the aerial truck shall be extended and adjusted to stabilise
the body of the truck before the boom is elevated. The body of the truck shall
be bonded to an effective ground, or barricaded and considered as energised
equipment for all purposes.
28
o. All the controls at ground level and Bucket available in the truck shall be
checked and tested to determine their proper working condition before
moving.
p. Every day, and each time, before commencing the work "arm current tests"
shall be carried out. Aerial buckets used for hot-Line bare-hand work shall
also be subjected to these tests. This test shall be carried out by placing the
Bucket in contact with an energised source equal to the voltage to be worked
upon for a minimum period of three (3) minutes and the leakage current shall
not exceed one (1) microampere per kilo-volt of nominal Line-to-Line voltage.
The work shall be suspended immediately if any indication of a malfunction
in the equipment is noticed.
q. All the aerial lifts shall have reliable controls and shall be accessible for safe
and secure operation.
r. Ground level lift control shall not be operated without the permission of the
employee in the lift, except in case of emergency.
s. The conducting Bucket Liner of Hot Line equipment in use shall be bonded to
the energised conductor by means of a reliable connection before the
employee contacts the energised part. This shall remain attached to the
energised conductor until the work is completed.
t. The adequate minimum clearance shall be maintained from all grounded
Objects and from lines and equipment at a different voltage than, to which
the insulated aerial device is bonded, unless such grounded insulated guards
cover objects or other lines and equipment. These distances shall be
maintained when approaching, leaving, and when bonded to the energised
circuit. These distance shall be in line with the prevailing standard practice
and consistent with the manufacturer's specification/guidelines.
u. The adequate minimum distances shall also be maintained between all parts
of the insulated boom assembly and any grounded parts including the lower
arm or portions of the truck, while approaching, leaving or bonding to an
energised circuit.
v. The table, comprising the minimum clearance for hot line bare handwork,
shall be printed on a plate of durable non-conducting material, mounted in
the buckets or its vicinity in such a position that the same is clearly visible to
the operator of the boom. Insulated measuring sticks only shall be used to
verify the clearances. During positioning the bucket alongside an energised
bushing or an insulator string, the appropriate minimum Line-to-ground
clearances must be maintained.
w. No conducting material longer than 0.9 meter, other than the jumpers of
appropriate length, armour rods, and tools shall be placed in the Bucket.
x. The non standard and unsafe working methods must not be allowed by the
supervisor in charge of the Hot Line crew.
y. The bucket and the upper insulated boom shall not be over stressed by
attempting to lift or support weights in excess of the manufacturer's rating.
z. The recommendations of the manufacturer of the Hot-Line equipment being
used shall be strictly followed.
29
3.13 PERSONAL PROTECTIVE EQUIPMENT (PPE)
3.13.1 GENERAL
Personal Protective Equipment (PPE) is defined as the equipment or device used by an
individual in the construction / operation and maintenance of substations, lines, power
stations, machines and equipments, during Civil works etc. which protect him from any
accidental hazard or near miss incident & ensure his safety as well as the safety of the co-
workers .
Corporation must provide required PPE of ISI mark and of reputed make for each
Workman / Engineer engaged in the construction / operation and maintenance of sub-
stations, lines, power stations, machines and equipments etc. It is also mandatory for all
Civil work site. Site Engineer/Supervisor must ensure adherence of each individual to the
guidelines regarding use of PPE at the work site. Employees shall use the PPE intended for
respective job depending upon the hazard. The PPE shall be examined by the employee
before and after its use. If any part of this equipment is found defective the employee shall
immediately bring this to the knowledge of the Site Engineer/Supervisor concerned.
The following are the minimum requirement of Safety devices & Special tools / Personal
Protective Equipment (PPE) having ISI mark to be provided.
30
stored near a source of heat, or exposed unnecessarily to direct Sun ray's/ heat. They are
best stored in protective container and should not be tied by cords or threads which
may cut it.
4) Safety harness should be properly handled. Before and after each use the straps and
ropes must be checked. Care should be taken to see that sharp tools or edges do not
cut dents and holes in it. Extra holes should not be punched as it weakens the belt. It
is best preserved in a separate case.
5) All employees shall wear clothes and footwear suitable for the work. Avoid use of
clothing with metal straps or buttons or buckles or any other metal fittings and shall
avoid hand chains or watch chains. Employees exposed to the danger of falling
material, must wear safety helmets
31
must be used by everybody, employee or authorized visitor , when entering the switchyard
of a sub-station or entering any work site .
33
ANNEXURE 1
LINE CLEAR PERMIT TO WORK (LC PTW)
Name Of Circle : .......................
Name Of Division : ------------------------------------ KV SUBSTATION------------------------------------
LC PTW No.____________ Date___________
I. REQUEST:
1. Name Of Line / Bay / Transformer :
2. Work to be done :
3. Period of LC PTW : (From) (Date/time) (To) (Date/time) .
4. Details of isolation & earthing required:
Signature
Name
Designation
Date & Time :
--------------------------------------------------------------------------------------------------------------------------
II. ISSUE:
1. Sequence of operations carried out for isolation & earthing:
i)
ii)
iii)
2. LC PTW allowed (From) (Date/time) (To) (Date/time).
3. Further precautions to be taken to achieve Safety:
Signature:
Name:
Designation (Shift In charge)
Date: Time:
Note: 1 LC PTW request to be approved by Substation In charge.
2. LC PTW to be issued to Competent person only.
3. Earthing to be done at the place of work.
nd
4. Colour codification : 1st , 2 & 3rd copy of LC PTW will be Light Pink, White &
light Yellow respectively.
--------------------------------------------------------------------------------------------------------------------------
34
III. RECEIPT
I hereby declare that I have inspected and satisfied myself that such equipment has been switched
off, isolated and earthed, where the work is to be carried out. I also accept responsibility for
carrying out work on equipment detailed on this permit and that no attempt will be made by me or
by any man under may control, to carry out work on any other equipment.
Signature :
Name :
Designation :
Date : Time:
_________________________________________________________________________________
4. CLEARANCE:
I hereby declare that all men and material have been withdrawn and warned that it is no longer
safe to work on the equipment specified in this permit and all tools and additional earths are
clear and equipment is ready for charging.
Signature :
Name :
Designation :
Date : Time:
_________________________________________________________________________________
2. SEQUENCE OF NORMALIZATION:
i)
ii)
iii)
iv)
v)
vi)
Signature
Name
Designation(Shift In charge)
Date : Time:
_________________________________________________________________________________
35
ANNEXURE - 2
TEST PERMIT (TP)
Name Of Circle : .......................
Name Of Division :_______________________ KV Sub-Station :___________________________
TP No ____________ Date ____________
I. REQUEST
1. Name of Line/Bay/Transformer:
Name Signature:
Designation Date & Time
(Shift In charge)
Note: 1. TP request to be approved by Substation In charge.
2. TP to be issued to Company Executive only
3. Earthing to be done at the place of test.
4. Colour codification: 1st, 2nd & 3rd copy of TP will be light Green, White & light
yellow respectively.
Caution: TP should not be issued if any LC PTW is pending on the same isolated zone.
___________________________________________________________________
36
III. RECEIPT
I hereby declare that I have personally inspected and have satisfied myself that such equipment
has been switched off and isolated, where the test(s) to be carried out. I also accept
responsibility for carrying out test (s) on equipment detailed on this permit and that no attempt
will be made by me or by man under my control, to carry out tests on any other equipment.
Name: Signature
Designation: Date & Time:
--------------------------------------------------------------------------------------------------------------------------
C Clearance :
I hereby declare that all men and material have been withdrawn and following exceptions are
recorded.
Name: Signature
Designation: Date & Time:
--------------------------------------------------------------------------------------------------------------------------
V. CANCELLATION OF TP
2. Sequence of Normalization
i)
ii)
iii)
iv)
v)
Name: Signature
Designation: Date & Time:
---------------------------------------------------------------------------------------------------------------
37
PSTCL Safety Manual
Chapter - 4
SAFETY instructions
38
SAFETY INSTRUCTIONS (SECTION-1)
4.1 Extra High Voltage and High Voltage SWITCHING, EARTHING and SAFETY
DOCUMENTATION PROCEDURE
4.1.1 SCOPE
This Safety Instruction explains the procedures for (i) carrying out EHV/HV switching,
earthing and isolation from other feeding points & (ii) Safety Documents issue and their
control.
4.1.2 DEFINITIONS
All definitions are Standard Definitions explained earlier (Chapter-1)
4.1.3 PROCEDURE
4.1.3.1-- When work is to be carried out on or near EHV/HV equipments the Maintenance
Engineer and the Shift In charge will assess the means of achieving safety from the system.
4.1.3.2-- When the work on the substation equipment/transmission line does not require
the removal of primary earths, then the safety document issued must be a Line Clear Permit
to Work (LC PTW).
4.1.3.4-- Within any isolated zone any number of LC PTWs may be issued at the discretion
of the Shift In charge.
4.1.3.5-- Within any isolated zone, only one TP shall be in force at any time. No LC PTWs are
permitted at the same time when TP is in force in the same isolated zone.
4.1.3.6-- After agreement has been reached between Substation Shift In-charge & the
Maintenance Engineer/Testing Engineer and the SLDC that the shutdown on the specified
substation equipment/transmission line can be availed, the Maintenance / Testing
Engineer requests the shutdown by completing all items of 'Request' part of LC PTW or TP
document. The Request must include the number of Additional Earths required. The
Request must be approved by the Substation in-charge.
4.1.3.7 The Maintenance/testing engineer will confirm with the Shift In-charge that the
shutdown can be availed and both will record that instructions in their logbook(s) together
with the message number , date and time that the instruction was given.
4.1.3.8--The Shift In-charge will carry out switching operations as per the Substation in-
39
charge. These switching operations will be recorded in the substation logbook(s) together
with message number, the date and time.
4.1.3.9-- If, during a switching operation, a piece of Equipment shows any sign of distress,
switching must cease immediately and the Shift-In charge notified. All persons must be
warned that a potential hazard exists.
4.1.3.10-- The Shift In-charge at the substation(s) where the LC PTWs or TPs are to be issued,
will record the isolation and earthing in the relevant portion of the LC PTW / TP as per
sequence of Isolation.
4.1.3.11-- The Shift In-charge will then carry out all isolation and will Lock Open those
points of isolation. When necessary, any shift in-charge at the remote end will isolate and
Lock Open all points of isolation and confirm back to this Shift In- charge. Any isolation of
the secondary side of voltage transformers and auxiliary transformers (tertiary, where
applicable) will also be carried out including locking. Caution Notices must be fixed on all
control handles on the control panel and also attached to the padlocks used to Lock Open
all points of isolation and Lock Closed all earth switches. These switching operations will
be recorded in the substation logbook(s) together with message number, date and time that
instruction was given.
4.1.3.12-- Once all Isolations including voltage transformers and auxiliary transformers
(tertiary, where applicable), has been completed (including remote ends where necessary)
and confirmation has been received that the isolation has been completed at the remote
end), earth switches are closed and Locked. These switching operations will be recorded in
the sub-station logbook together with message number, date and time.
4.1.3.13-- No Back-Feed Certificates must be obtained from all concerned stations. All
details of the No Back-Feed Certificate must be entered in the substation logbook along
with message number, date and time. The message number, date and time must be
recorded on the LC PTW / TP.
4.1.3.14-- All Safety Keys, fuses and links etc which have been used to Lock all points of
isolation and earth switches etc will be Locked in a Key Safe under the safe custody of the
Shift In-charge.
4.1.3.15-- The Shift In-charge will specify, in relevant part of the LC PTW or TP before
leaving the charge:
i) Any further precautions to be taken later by the concern holding the LC PTW or TP
to achieve Safety.
ii) The motive power supplies that can be restored for the particular work being carried
out.
iii) The use of any Additional Earths will be specified on an Earthing Schedule drawn
40
up by the Maintenance Engineer.
4.1.3.16-- The Shift In-charge will issue the LC PTW or TP to the competent person who will
retain the Safety Document in his possession until all work has been completed. The Shift
In-charge will record all the details in the substation log book and Line Clear Permit to
Work or Test Permit register.
4.1.3.17-- The Executive will sign relevant Part of LC PTW / TP (Receipt), to accept the
responsibility for carrying out the work / testing on the substation equipment /
transmission line. The Executive responsible for the work will draw up the Earthing
Schedule, if required, to show the position and use of Additional Earths.
a) In substations, Additional Earths must be applied in a similar manner to
primary portable earths, using the same earthing equipment.
b) On overhead transmission lines, Additional Earths can be applied within
Safety Clearance but not less than Safe Electrical Clearances elsewhere
specified.
4.1.3.18-- On completion of the work, the Executive will sign the Return of LC PTW or TP at
relevant parts to declare that all work/testing is completed, to describe any restrictions and
to confirm that all men, tools, plant and Additional Earths have been removed.
4.1.3.19-- The Shift In-charge will receive the cleared LC PTW or TP and record receipt in the
substation logbook and LC PTW or TP register together with date and time.
4.1.3.20 The Shift In-charge will complete relevant part of the LC PTW or TP to describe
the sequence of normalisation. He will then carry it out after consultation with SLDC &
Maintenance/Testing Engineer and Shift In-charge of remote end.
All switching operations in their substation must be recorded in the logbook together with
date and time.
41
SAFETY INSTRUCTIONS (SECTION-2)
4.2.1. SCOPE
This Safety Instruction explains the procedure to be adopted for the demarcation of
work/test areas in substations.
4.2.4. DANGERS
The main Dangers to personnel working in substation are electric shock, burns or falling
arising from --
a) The possibility of misidentifying Equipment on which it is unsafe to work, for that
on which it is safe to work.
b) Inadvertently infringing Safety Clearance.
c) Inadequate precautions to suppress or safely discharge any inducted or impressed
voltage on the Equipment
d) Improper hand and footholds
e) Improper use of personal protective equipments.
f) Sudden rush of flying insects viz. Bees, flying ants, etc.
g) Improper communication among the working teams.
4.2.5. WORKING/TESTING
4.2.5.1-- When working or testing is to be carried out on or near to Equipment in a
substation, the area demarcation is to be determined by the maintenance engineer to the
satisfaction of the Shift In-charge.
42
Safety Distance as per Safety Rules.
4.2.6.2-- Boundary marks must be clearly identifiable and easy to see. They must only be
fixed or moved by maintenance personnel under the Supervision of the maintenance
engineer and Shift In-charge.
4.2.6.4-- In general, the boundary marking must be arranged so that it is impossible for
structures supporting Equipments which are Live to be climbed from within the work area.
Where it is not possible, unsafe access to the structures must be identified by attaching Red
Danger Notices at working level before work commences.
4.2.6.5-- The boundary of the work area must be identified using red cones/self supporting
props painted in red and white bands for supporting red and white plastic chain or nylon
rope of about 12 mm diameter.
4.2.6.6-- The enclosed work/test area must be additionally identified by green cones for
Line Clear PTW and red flags in green cones for Test Permit placed 600 mm to 1 m (2 to 3ft)
inside the work area at intervals not exceeding 6 m (20ft).
4.2.6.7-- Where the work/test area is separated from adjoining areas by fixed divisions or
screens, the work/test area must be identified by green cones placed within the safe area
and visible from the outside at each point of access. The fixed divisions or screens must
remain in position during the course of the work.
4.2.6.8-- Safety Distance must be maintained at all times to Equipments on which it is unsafe
to work. This includes any overhead conductors, which pass over the work area and on
which work is not to take place.
4.2.6.9-- The demarcation equipment must be erected before issue of the LC PTW / TP. The
demarcation equipment can be removed after clearance of LC PTW / TP.
4.2.7.2-- Danger Notices must only be fixed or moved by maintenance personnel under the
supervision of Maintenance Engineer/Testing Engineer and Shift In-charge
44
SAFETY INSTRUCTIONS (SECTION-3)
4.3 TESTING OF EHV AND HV EQUIPMENTS
4.3.1. SCOPE
This safety instruction applies precautions to achieve safety from the system for personnel
during the testing of EHV/HV Equipment.
4.3.3. DANGERS
The main dangers to personnel during the course of testing are electric shocks, burns and
other injuries arising from
a) accidental contact with Live Equipment due to improper isolation or
discharge.
b) electrical energy and mechanical pressures and forces derived from testing
sources.
4.3.4.2-- Testing which does not require the removal of primary earth may be carried out
under a LC PTW.
4.3.4.3-- Testing which requires the removal of primary earth must be carried out under a
TP.
4.3.4.4-- The test area and its boundaries/limits must be identified in accordance with the
Safety Instruction's "Demarcation of Work And Testing Areas in Substations".
4.3.4.5-- Points of isolation must be maintained from all supplies other than those required
for the tests.
4.3.4.6-- The Safety Keys for those of Points of Isolation, which are required to be
maintained during the tests, must be kept in a Key Safe.
4.3.4.7-- Safety Keys, which are necessary for the tests, must be issued to the Competent
Person.
4.3.5. TESTING
4.3.5.1.-- The Authorised Person in receipt of the appropriate Safety Document is
responsible for all matters of safety concerned with the test and for the control function
45
within the test area. He may operate, or instruct others to operate Equipment within the test
area.
4.3.5.2 If specified in a TP the Competent Person may remove, replace or instruct others to
remove or replace, Primary Earths.
4.3.5.3-- Connections used for test purpose must be of adequate capacity and be easily
visible to prevent accidental access/contact.
4.3.5.4-- The Test Supply must be applied under the Supervision of the Competent Person
who has received the Safety Document.
4.3.5.5-- Equipment, which is associated with a test and likely to retain an electrical charge,
must be discharged to earth before and after the application of the test supply.
4.3.5.6-- Where a test voltage is to be applied to Equipment which has a remote end that
may become Live, then that end must be safeguarded so as to prevent Danger.
4.3.5.7-- If the remote end of the Equipment which may become Live by the test voltage is
accessible, then it is the responsibility of the Authorised Person carrying out the test to
ensure that it is cordoned off and under the control of the Person before a test voltage is
applied. It is the responsibility of that Person to ensure that no one, including himself,
approaches the Equipment unless instructed to do so by the Authorised Person in charge of
the testing.
4.3.5.8-- During testing by generator supply, the generator supply should not be utilized to
run control room appliances such as fans or tube lights unless change over switch provision
is made in Control Room.
46
PRIMARY EARTHS AND ADDITIONAL EARTHS FOR
APPLICATION IN SUBSTATIONS
NOTE : The number of Substations are as per actual no of Substations (PSTCL) plus
giving other utilities where PSTCL lines are terminated
47
SAFETY INSTRCUTIONS (SECTION-4)
4.4 SAFETY PRECAUTIONS FOR LOW VOLTAGE AND MEDIUM VOLTAGE
EQUIPMENT
4.4.1. SCOPE
This Safety Instruction applies the principles to achieve Safety for personnel working or
testing on Low/Medium Voltage Equipment.
4.4.3. DANGERS
The main Dangers to personnel working or testing on LV/MV Equipment are electric
shock or burns arising from
a) The possibility of personnel mistaking Equipment on which it is unsafe to
work for that on which it is safe to work.
b) The possibility of the Equipment being worked on accidentally or
inadvertently being made Live.
c) Dangerous voltages on open-circuited current transformer.
4.4.4.2-- A substation in-charge must carry out an assessment to determine under what
conditions the work is to take place and if a Safety Document is to be issued.
4.4.4.3-- When work is to be carried out on LV/MV Equipment, which is part of Extra High
Voltage/High Voltage Equipment, adequate precautions must be taken to achieve Safety
from the System from the EHV/HV Equipment.
4.4.4.4-- When tests are to be carried out on LV/MV Equipment which is in proximity to
exposed EHV/HV Equipment which may be Live, or become Live, the relevant
requirement of Safety Instruction "Demarcation of Work and Testing Areas in Substations."
must be met.
4.4.4.5 When work on Live Equipment required portable instruments to be used for
voltage or resistance measurements the instruments must be provided with insulated
probes.
4.4.4.6-- When working on protection or metering Equipment extreme care must be taken
48
out to open circuit current transformers. These must be short-circuited before work is
carried out.
4.4.5.3-- Points of Isolation must be established. Any fuses and links and/or Safety Keys
used to secure the points of Isolation must be retained in a Key Safe.
4.4.5.6-- Before commencing work the Competent Person must check, by means of an
Approved voltage testing device, that the LV/MV Equipment on which he is to work is not
Live. The device must be tested immediately before and after use.
4.4.5.7-- If the work is interrupted the Competent Person who is to continue the work must
check that the Equipment is not Live as in 4.4.5.6 above.
4.4.5.8-- Before commencing work on exposed LV/MV overhead conductors, which have
been isolated, in addition to proving that they are not Live, the conductors including the
neutral, must be short circuited and Earthed.
4.4.6.3-- The Competent Person who is to do the work must first remove any metallic
objects such as wristwatch, rings, wristlets, cufflinks, pendants etc.
4.4.6.4-- Where necessary to prevent injury, approved insulated tools, insulating stands,
mats or gloves, as appropriate, must be used.
49
4.4.6.5-- Only suitable test instrument with insulated test probes must be used.
4.4.6.6-- Consideration must be given to the Competent Person, if the presence of such a
person could contribute significantly to ensure that injury is prevented.Any accompanying
competent person must be trained to recognize Danger and if necessary to render
assistance in the event of an emergency.
4.4.6.7-- Before commencing work in areas where there is a possibility of the presence of
gas, which might be inadvertently ignited by electric sparks, Substation In-charge must be
consulted.
50
SAFETY INSTRUCTIONS (SECTION-5)
4.5 SAFETY PRECAUTIONS FOR ADDING/REMOVING EQUIPMETS (NEW/OLD)
TO & FROM EHV/HV SYSTEM
4.5.1 SCOPE
This Safety Instruction defines procedure to achieve Safety of personnel and/or
transmission system safety while adding/removing equipments to/from the EHV system.
4.5.2 DEFINITIONS
Additional Definitions are as follows:
Bay Equipment- Circuit Breaker, Current Transformer, Wave Trap, Control & Relay Panel
etc. which are part of the bay.
Inter Connecting Transformer (ICT)- Transformer used to step Up / step down the system
voltage.
Reactor- Line or bus reactor used for controlling the system voltage.
Maintenance Engineer- Engineer responsible for carrying out maintenance works of EHV
equipments, transmission lines & LT system.
Erection Engineer- Engineer responsible for all construction activities related to addition
of a bay.
4.5.3. PROCEDURE
4.5.3.1 Adding bay or bay equipment to EHV/HV system.
4.5.3.1.1 Bay: When new bay is to be added to existing EHV/HV system then before connecting
the same, pre-commissioning checks are to be completed first. Once pre-commissioning checks
are completed, necessary LC PTW/TP is to be requested by Erection Engineer, which should be
approved by Substation In-charge. Work of connecting jumpers etc. is to be completed taking
safety precautions as per Safety Instructions. After connecting to existing EHV system all
commissioning checks are to be performed. All control-cables, protection relays are to be
connected taking all safety precautions. Safe electrical clearance needs to be maintained during
movement of crane for carrying out erection / dismantling work.
51
4.5.3.1.2 Bay Equipment : When existing bay equipment is to be replaced by new
type/design equipment then work should be carried out only after taking safety document
i.e. LC PTW/TP duly approved by substation in charge and safety precautions are to be
taken care of.
4.5.3.2.2 Bay Equipment: When any bay equipment is to be removed from EHV/HV
system then LC PTW / TP is to be issued which should be approved by substation in-charge.
Safety precautions are to be taken during dismantling work. Bay Equipment, which is to be
removed, should be identified / isolated from rest of the system. Maintaining Safe electrical
clearance etc need to be taken care of during movement of crane for carrying out
dismantling work.
52
SAFETY INSTRUCTIONS (SECTION-6)
4.6 SAFETY PRECAUTIONS FOR EHV OVERHEAD LINES
4.6.1 SCOPE
This Safety Instruction explains the procedures for maintenance on a de-energised circuit
of an EHV transmission line. It does not provide for work on live circuits.
4.6.2. DEFINITIONS
Following Additional Definitions are applicable for these Instructions:
Earth End Clamp -The End Clamp of an Additional Earth which is to be connected to tower
members, cross arm members or a suitable earth spike driven into the ground at ground
potential.
Line End Clamp - The End Clamp of an Additional Earth which is to be connected with
conductor or jumper.
Earth Lead - A lead made of aluminium strands protected with a transparent cover for
connection between the Line End Clamp and the Earth End Clamp.
Socket - The sliding socket for holding and operating the Line End Clamp which is a part of
a Telescopic Pole or Bridging Pole.
Earthing Pole - An insulated pole with a Socket which is to be used for tightening the Line
End Clamps on to conductors or jumpers while maintaining Safe electrical Clearance.
Pole Extension - A suitable length of extended pole which is to be connected with the
Earthing Pole for achieving the Safe Electrical distance when connecting line End Clamps
to conductors or jumpers.
Trailing Earth - An Earth of sufficient length of earth lead suitable for connection between
conductor and the tower when lowering or raising conductors. This can be the form of
additional earth.
Bridging Pole - A short insulated pole with a Socket which is used for applying and
tightening Bridging Earths. First part of earthing pole can be used as bridging pole.
Bridging Earth - An earth used for bridging across insulator strings or when a conductor is
to be cut or jointed. An additional earth with line and clamp on both ends can be used as
bridging earth.
Working Phases - The conductor phase on which linesmen will carry out work.
Field Equipment Earth - Approved connections for bonding items of field and access
equipment such as scaffold, hydraulic platforms, mobile cranes, winches etc. to earth. The
earths are coloured orange to identify them from Additional Earths and are not included on
an Earthing Schedule. They shall have a minimum cross sectioned area of 35 mm2 copper
equivalent. An additional earth can be used in the form of field equipment earth.
4.6.3 DANGERS
The main Dangers when working on transmission lines are:
1) The possibility of personnel mistaking identification of the circuit on which it is
safe to work with the one that is still energised.
2) Infringing Safety Clearance before Additional Earths are applied.
3) Inadequate precautions to exclude any induced voltages present on the conductors
of fittings.
53
4) Improper use of safety equipments.
5) Effect of atmosphere / surroundings which may cause imbalance of hand and
Foot holds.
6) Imbalance state of mind.
4.6.4.1 One Responsible Officer (Supervisor/Engineer) should always be present at the site
of work.
4.6.4.2 The "CIRCUIT UNDER SHUT DOWN" as per LC PTW should be identified at the
working locations with the help of a circuit plate, name plate, location number, phase plate
or any other reliable method.
4.6.4.3 All linesmen who work on the transmission towers, conductors or fittings, shall
wear and make use of safety belts/harnesses and other safety equipments provided for
their safety and protection.
4.6.4.4 The D/C line should be provided with the colour code for the circuits. The line staff
should be clearly told about the circuit under shut-down with the colour code.
4.6.4.5 One green flag should be provided at the circuit under shut-down and one red flag at
the circuit under charged condition at the sub-station at the LA structure.
4.6.4.6 Additional Earths shall be carried on the tower in such a way to avoid any damage to
the Additional Earths. Alternatively, the Additional Earths can be carried manually by the
linemen on their shoulders.
4.6.4.7 Safe Electrical Clearance shall be maintained by all linesmen until all the Additional
Earths are correctly connected to conductors or jumpers of circuits under shut-down.
4.6.4.8 All Earth End-Clamps of all Additional Earths at the point where the lineman is
standing or sitting in order to apply the Additional Earths, shall be connected first to the
tower/cross arm member.
4.6.4.9 After connection of the Earth End Clamps with the tower/cross arm members, all
Line End Clamps shall be connected to conductor or jumper from the point where lineman
is sitting or standing. To ensure that a proper connection of the Line End Clamps with the
conductor or jumper has been made a check of the tightness by attempting to rotate the Line
End Clamps on the conductor or jumper should be made by the use of the Earthing Pole.
54
4.6.4.10 The Earthing Pole/Bridging Pole shall be kept suitably on the tower after
connection of the Line End Clamps until disconnection of all Additional Earths.
4.6.4.12 After completing the work, all tools, plant and men shall be removed from the
conductors and fittings. The last linesman shall remove the Line End Clamps from the
conductors/jumpers sitting or standing at the point of connection of these Additional
earths to the tower/cross arm side. After this, the Earth End Clamps shall be removed. This
procedure shall be repeated for the disconnection of all other Additional Earths.
4.6.4.13 On completion of work, the Additional Earths shall be carried to the ground from
the tower in gunny/suitable bags to avoid any damage to the Additional Earths. To avoid
damage, no Additional Earths should be thrown from the tower.
4.6.4.14 While coming down from the tower, the linemen will remove the red flags and the
green flags.
4.6.4.15 One number spare Additional Earth should be carried to the working tower to
provide a spare in case of any contingencies.
4.6.5.1 WORK
For work on the de-energised circuit which does not involve the disconnection or lowering
of any conductors to the ground. This scheme is to be followed during earthing for the
following works:
a) Replacement of suspension or tension insulators.
b) Any other work on a suspension or tension string.
c) Fixing/replacement of spacer or vibration damper adjacent to the
suspension or tension string.
4.6.5.2 PROCEDURE
55
4.6.5.2.1 Apply general procedures as in section 4.6.4 of this Safety Instruction.
4.6.5.2.2 Apply Additional Earths to all phases and to all sub-conductors (wherever
applicable) at the working tower of de-energized circuit.
4.6.5.2.3 As an extra safety measure, both sub-conductors of working phases (s) may be
bridged with an Additional Earth.
4.6.5.2.4 Carry out the maintenance on strings and vibration dampers as per the normal
procedure. However, if a winch is used for replacement of insulators, the winch must be
earthed by the use of a Field Equipment Earth attached to an earth spike driven into the
ground. All the pulleys used should have good electrical connection with the tower. The
pulleys should not have any insulation i.e. rubber lining etc. Adjacent towers can be
earthed instead of bridging the sub-conductors as an extra safety measures.
4.6.6.1 WORK
For work on the de-energised circuit which does not involve the disconnection or lowering
of conductors between towers to the ground. This scheme is to be followed during earthing
for the following works on tension towers:
a) Breaking or re-making jumper connections, including lowering and raising a
jumper.
4.6.6.2 PROCEDURES
4.6.6.2.1 Apply general procedures as in section 4.6.4 above.
4.6.6.2.2 Apply Additional Earths to all phases and to all sub-conductors (wherever
applicable) at the working tower of de-energised circuit on the jumpers.
4.6.6.2.3 If only one end of the jumper is to be disconnected apply Additional Earths at the
end of conductors on line side of the dead end compression joint where the jumper is to be
disconnected. If both ends of the jumper are to be disconnected for replacement / repair of
the jumper, Additional Earths must be provided at both ends of the conductors on line side
of the dead end compression joints.
4.6.6.2.4 Apply Additional Earths on all working phases and on all sub-conductors
(wherever applicable) on adjacent towers.
4.6.6.2.6 If the jumper is to be lowered to the ground disconnect the Line End Clamp of the
Additional Earth from the jumper before lowering the jumper to the ground. The
disconnected Additional Earth shall be kept suitably at tower cross arm.
56
4.6.6.2.7 Lower the jumper in such a way that Safety Clearance is maintained from all live
conductors.
4.6.6.2.8 Before any person on ground touches the jumper, it should be discharged by the
use of an Additional Earth fixed to an earth spike driven into the ground.
4.6.6.2.9 Carry out the maintenance work on the jumper as per the normal procedure.
4.6.6.2.10 Raise the jumper to the cross arm maintaining Safety Clearance to all live
conductors. Precautions shall be taken so that the jumper is not raised in the horizontal
position.
4.6.6.2.11 An Additional Earth shall be applied to the jumper before connecting it to the
dead end compression joints.
4.6.6.2.12 Connect the jumper at both ends with dead end compression joints.
4.6.7.2 PROCEDURE
4.6.7.2.1 Apply Additional Earths on all phases and on all sub-conductors (wherever
applicable) on towers at the both end of the working zone. These towers should not be more
than 10 spans apart. At tension towers within the working zone, apply Additional Earths to
the jumpers and to all the sub-conductors (Where applicable).
4.6.7.2.2 Carry out the maintenance work as per the normal procedure. While working
following safety precautions shall be taken:
(a) The men on the conductor shall always maintain Safe Electrical Clearance
from tower steel parts or any other material at earth potential at towers where
conductor is not earthed.
(b) If any tool or plant is required by the linemen on the conductors, they shall be
lifted to the working position by using a polypropylene / insulated rope /
bag.
(c) If access to any tower is required, all the conductors at that tower shall be
earthed with Additional Earths.
57
(d) If before work commences, there is a risk of thunder / lighting stroke, no
work shall be started. If during the course of the work, there is a risk of
thunder / lighting stroke, all work shall immediately stop and all men shall
return to the ground.
4.6.8 SCHEME 4 --- PAINTING OF TOWERS WHICH DOES NOT INVOLVE ANY
DISCONNECTIONS AND ANY ACCESS TO CONDUCTOR
4.6.8.1 WORK
For work on the de-energised circuit which does not require any contact with insulators,
associated fittings or conductors. This scheme is to be followed during earthling for the
following works:
a) Painting up to vertical centre line of tower towards the de-energised circuit.
4.6.8.2 PROCEDURE
4.6.8.2.1 Apply Additional Earths on all phases and on all sub-conductors (wherever
applicable) at more than 10 towers apart of the de-energized circuit. At tension towers, the
Additional Earths shall be connected to the jumpers.
4.6.8.2.2 In case only one or two towers are to be painted only the working towers need to
be earthed as per normal procedure of earthing for suspension or tension towers as the case
may be.
4.6.8.2.3 Carry out the painting work on towers as per the normal procedure.
4.6.9.1 WORK
For work on the de-energised circuit of a transmission line which involves raising and
lowering phase conductors and the fitting of repair/sleeves/joints to the phase conductors.
This scheme is to be followed during earthing for the following works:
a) Lowering of conductor at suspensions tower.
b) Raising of conductor at suspension tower.
c) Providing the repair sleeves on the lowered conductor.
d) Cutting and jointing of lowered conductor.
4.6.9.2 PROCEDURE
4.6.9.2.1 LOWERING AND RAISING CONDUCTORS
(a) Additional Earths shall be fixed on all phases of conductors and on all sub
conductors (wherever applicable) at the suspension towers and at adjacent
towers.
(b) If a manual winch is used, it shall be Earthed to the tower using a Field
58
Equipment Earth. All the pulleys used should have good electrical
connection with the tower. The pulleys should not have any insulation i.e.
rubber lining etc.
(c) Connect the rope with the conductor through Pulley at suitable places in the
tower and through winch.
(d) If scaffolding is used in the span below conductor, the scaffolding shall be
earthed by providing an earth spike.
(e) Before lowering the conductor, the Additional Earth (s) shall be removed
from that conductor and this Additional Earth (s) shall be kept suitably at the
tower.
(f) When the lowered conductor is at approx. four meters from ground,
additional earth's shall be applied from ground spike/tower on to the
lowered conductor(s).
(g) When on the ground the conductor has to be cut, bridging Earth (s) shall be
provided on both sides of cutting point with ground spike on tower legs.
Then as per working procedure, the conductor shall be cut and joined. After
jointing the conductor, the Additional Earth (s) shall joined. After joining the
conductor, the Additional Earth (s) shall be removed.
(h) The conductor(s) shall be raised upto 4 meters height from ground and
additional earth(s) shall be removed.
(i) Raise the conductor(s) up-to the cross arm level and apply the additional earths on
the conductors.
(j) On completion of work, remove all additional earths.
59
4.6.10.1 WORK
For work on the de-energized circuit of transmission line which involves lowering and
raising phase conductors and the fixing of repairs sleeves/joints to the phase conductors.
This scheme is to be followed during earthing for the following works:
a) Lowering of conductor at suspension tower.
b) Raising of conductor at suspension tower.
c) Providing the repair sleeves on the lowered conductor.
d) Cutting and jointing of lowered conductors.
4.6.10.2 PROCEDURE
4.6.11.2 PROCEDURE
4.6.11.2.1 No earthing procedure is required as no shut down is to be taken for climbing up
the Double Circuit towers.
60
4.6.11.2.2 For single Circuit towers, follow the earthing scheme- 1 for Suspension towers
and tension towers.
4.6.12.2 PROCEDURE
a) Obtain the shut down of affected circuit.
b) Provide earthing as per scheme 1 on all towers which require to be climbed.
c) Provide Additional earth's on the earth wire ends (2 Mts away from ends)
with earth spikes before starting the job for mid span joints.
d) During rigging, the pulley used at cross arm end shall be provided with
additional earth on the cross-arm. fibre round sling in place of wire rope sling
has been used for connecting the pulley.
e) Carry out repair & maintenance work on earth wire.
f) Raise the earth wire up to 4 meters height form ground and then remove
additional earth form spikes.
g) Raise the earth wire up to cross arm level.
h) Remove all additional earth's on completion of work.
4.6.13.2 PROCEDURE
4.6.13.2.1 Follow scheme of earthing procedure as per scheme 3 if inspection is being down
by trolley work.
4.6.13.2.2 Follow scheme 1 for earthing procedure in case access to any conductor point is
needed from tower cross arm.
4.6.13.2.3 Carry out minor works like tightening of bolts and nuts, fixing split pin,
relocation of vibration dampers etc.
4.6.13.2.4 Remove Additional earth after completion of inspection & minor works.
61
SAFETY INSTRUCTIONS (SECTION-7)
4.7 MOBILE ACCESS EQUIPMENT, VEHICLES, CRANES AND LONG OBJECTS IN
SUBSTATIONS
4.7.1. SCOPE
This Safety Instruction applies the principles established by the Safety Rules to achieve
Safety from the System when mobile access equipment, vehicles, cranes and long objects
are being moved or used within substations containing exposed Live EHV/HV Equipment.
4.7.2. DEFINITIONS
Following are additional definitions, which only apply to this Safety Instruction.
Field Equipment Earths- Approved connections for binding items of field access
equipment such as scaffold, hydraulic platform, mobile crane/ winches etc. to earth. The
earths are coloured orange to identify them from Additional Earths and not included on an
2
Earthing Schedule. They shall have a minimum cross section of 25 mm copper equivalent.
Long Objects - Items of equipment such as ladders, scaffold poles, ropes, measuring tapes
etc which if not controlled during handling could infringe safety Clearance.
Operator - A Person trained, assessed and appointed to use specific types of mobile access
equipment, vehicles or cranes within substations.
4.7.4. DANGERS
The main Dangers to personnel during the movement and use of access equipment,
vehicles, cranes and Long Objects in substations containing exposed Live EHV/HV
conductors are electric shock, burns or falling, arising from
a) Infringing Safety Clearance
b) Induced voltage
4.7.5.2-- The Maintenance/Testing Engineer shall ensure that the Mobile access equipment
are operated by a trained operator only.
62
4.7.6.1-- When mobile access equipment, vehicles or cranes are to be moved to and from the
safe working area and any part of this equipment in the transport position is higher than 2.3
meters from ground level, then a maintenance/testing engineer must assess the risks.
4.7.6.2-- The Maintenance/Testing Engineer must specify on site the route to be followed
with adequate protection.
4.7.6.3 -- The Maintenance/Testing Engineer may also specify when during the movement,
the mobile access equipment, vehicle or crane must be bonded to earth using Field
Equipment Earths.
4.7.6.4-- The Maintenance/Testing Engineer when deciding on the route to be taken must
also ensure that the bus bar zone protection wherever provided and adjacent circuit
protection is in service.
4.7.7.3-- The Operator must ensure that the effective use is made of any equipment
stabilizing devices or outriggers.
4.7.7.4-- The maintenance/testing engineer holding the Safety Document must consider
whether it is necessary to consult an appropriate qualified specialist (e.g. Civil Engineer) to
ensure that safe ground bearing pressure will not be exceeded. This is particularly
important where wheels, stabilizing legs or outriggers may need to be positioned over
ducts. Where necessary, load spreading device must be used.
4.7.7.5-- The recipient of the Safety Document must ensure that, as soon as practicable after
reaching the demarcated working area, a Field Equipment Earth is applied to the
equipment.
4.7.7.6-- The recipient of the Safety Document must satisfy himself that the Operator knows
what work is to be done and that the equipments controls are operating correctly.
4.7.7.7 The recipient of the Safety Document must consider whether to select a member(s)
63
of his working party as a safety observer(s). He must assess the risk in relation to the work
being done, the equipment being used, the field of vision of the Operator and the proximity
of exposed Live EHV/HV Equipment.
4.7.7.8-- The Safety Observer must use agreed signal for halting the movement of crane to
avoid danger.
4.7.7.9-- Equipment provided for personal access must be electrically bonded to the
Earthed EHV/HV Equipment as near to the point of work as practicable to provide an equi-
potential zone. This can be achieved by connecting the access equipment through a Field
Equipment Earth to the same point as the Primary Earth or Additional Earth attached to the
EHV/HV Equipment. It is essential that there is an adequate bond between the access
platform and the vehicle chassis.
4.7.7.10-- If other nearby Earthed EHV/HV connections associated with the Equipment
being worked on, are accessible from the access equipment, additional Field Equipment
Earths must be applied as in 4.7.7.9 to extend the equi-potential zone.
4.7.7.11-- At no time must any part of the equipment encroach over exposed Live EHV/HV
Equipment.
4.7.8.2 LADDERS
a) Only Approved ladders must be used which are of no greater length than is
required for the work.
b) When not in use all ladders within substations must be securely Locked to a
suitable anchorage.
c) Ladders for operational purpose must not be used without the permission of
a Shift Engineer.
d) The movement and erection of ladders must be carried out under the
Personal Supervision of Shift Engineer/Maintenance Engineer.
e) When moved in a substation ladders must be carried in a horizontal position
and as near to the ground as possible.
f) If ladders have to be moved within a defined safe working area after the
initial placement, the movement must be carried out in accordance with the
specific instructions of the Maintenance/Testing Engineer.
g) Before use, ladders provided to give access to fixed ladders which terminate
above ground level must be Locked in position by a maintenance/testing
engineer. These must remain Locked in position during the period the
64
ladders are in use.
4.7.8.3 SCAFFOLDING
a) The Maintenance/Testing Engineer must finalise on the site, the movement
route of scaffolding.
b) Subsequent movement of scaffolding to the required location must be carried
out under the Personal Supervision of the Maintenance/Testing Engineer.
c) When moved in a substation, long scaffolding components must be carried in
a horizontal position and as near to the ground as possible.
d) Before scaffolding is erected or dismantled the Maintenance/Testing
Engineer must assess the risks in relation to the proximity to exposed Live
EHV/HV Equipment.
e) Field Equipment Earths must be applied to scaffolding erected near to the
Live EHV/HV Equipment as soon as it is practicable to do so. As erection
proceeds. Field Equipment Earths must be applied as approximately 5m
(15ft) intervals, vertically and horizontally, or as determined by the
Maintenance/Testing Engineer.
f) The recipient of the Safety Document must assess the risks in relation to the
method of erection and the proximity to exposed Live EHV/HV Equipment.
He must consider whether to select a Safety Observer.
g) No bamboo/wooden scaffolding to be used.
65
SAFETY INSTRUCTIONS (SECTION-8)
4.8 EXTRA HIGH VOLTAGE / HIGH VOLTAGE STATIC CAPACITOR BANKS
4.8.1 SCOPE
This Safety Instruction applies the principles to achieve Safety including the removal of
stored energy, for personnel working on EHV/HV Static Capacitor Banks
4.8.2. DEFINITIONS
Additional Definitions are as under :
Rack - An individual framework containing capacitors connected together.
Shorting Switch - A fixed device for short-circuiting the capacitors in Racks to dissipate
stored energy safely. It may also provide a direct connection to earth.
Discharge Stick - An Approved device for the purpose of discharging any residual charge
in a capacitor.
4.8.4 DANGERS
The main Dangers to Personnel are electric shock or burns arising from
a) The discharge of electrical energy retained by the static capacitors after they
have been Isolated.
b) Inadequate precautions to guard against any induced voltages in the
conductors or associated fittings.
66
4.8.5.1 The Capacitor Bank must be Isolated, Points of Isolation established and
Primary Earths applied.
4.8.5.2 Shorting Switches, where installed on the Racks, must be closed. The control of
Shorting Switch is the responsibility of the maintenance / testing engineer.
4.8.6.2 The Maintenance Engineer requesting the Safety Document must specify the
position for application of clip-on Short Circuiting Leads and Continuity Leads. Short
Circuiting Leads and Continuity Leads must be applied to the appropriate capacitors
under the Personal Supervision of the Maintenance/Testing Engineer.
4.8.6.5 During storage and transport, capacitors must be short-circuited using at least two
complete turns, between terminals, of tinned copper wire of not less than 30 Amp fuse wire.
4.8.6.6 When the work activity requires the opening or removal of Shorting Switches and
special requirement for subsequent access to capacitors, these actions must be carried out
under the Personal Supervision of the Maintenance / Testing Engineer.
67
SAFETY INSTRUCTIONS (SECTION-9)
4.9 STATION STORAGE BATTERY
4.9.1 SCOPE
This Safety Instruction applies the principles to achieve Safety from the System for
personnel working on Station Storage Batteries.
4.9.2 DEFINITIONS
Additional Definitions as follows :
Battery Bank - All battery cells, connections and stands comprise a battery bank.
4.9.4 DANGERS
The main Dangers to personnel working on a Battery Bank are electric shock or burns
arising from
a) The possibility of personnel inadvertently shorting battery terminals.
b) Dangerous spilling of electrolyte on body.
c) Asphyxiation or suffocation due to fuming of storage battery acid.
4.9.5.2 When work is to be carried out on a Battery Bank, adequate precautions must be
taken to achieve safety from the danger of electrolyte and DC voltage.
4.9.5.3 When working on Live Equipment, required portable instruments to be used for
impedance or voltage measurement, the instruments must be provided with
Insulated probes.
4.9.5.4 When handling acid, care must be taken and personnel protective equipment like
face shield, apron, gloves etc., must be used before work is undertaken.
4.9.5.5 Proper ventilation along with water supply in washbasin shall be ensured in
the battery room.
4.9.5.6 Add ACID TO WATER, DON'T MIX WATER TO ACID while preparing
electrolyte.
68
4.9.5.8 During handling acid, sufficient quantity of water must be available.
4.9.6.2 Substation in-charge must assess the work required on a Battery Bank and decide
whether it must be carried out under
a) Line Clear Permit to Work, and/or
b) Personal Supervision
4.9.6.4 The Competent Person who is to do the work must first remove any metallic
objects such as wristwatch, rings, wristlets, cufflinks, pendants etc.
4.9.6.6 Only suitable test instrument with insulated test probes must be used.
69
SAFETY INSTRUCTIONS (SECTION-10)
4.10 SF6 GAS FILLED EQUIPMENTS
4.10.1 SCOPE
This Safety Instruction lays down procedure for working on SF6 gas filled equipments and
to protect all personnel from inherent dangers/hazards of SF6 gas.
4.10.2 DEFINITIONS
Additional Definitions are as under:
Impurities: Impurities toxic or non-toxic contained by SF6 gas filled in EHV equipments.
De-composition products: Electrical discharge decomposes SF6 gas in SF4, SF2 etc. These
are called de-composition products. In some cases sulphur-fluorine gas is also formed due
to electrical discharge.
4.10.4 DANGER
Following are the dangers while working on SF6 gas filled equipments:
a) Since SF6 gas is heavier than air, in the storage / work area in the absence of
proper ventilation there is a danger of asphyxiation (Suffocation).
b) Decomposition products e.g. Sulphur-fluoride & other toxic gases having
pungent or unpleasant odour causes irritation of nose, mouth and eyes.
4.10.5.2 The work equipment must be electrically isolated from other equipment
4.10.5.4 Using Gas evacuation trolley, SF6 gas should be taken out from the equipment and
evacuation up to about 50 mbar should be achieved.
4.10.5.5 After ensuring that total gas has been evacuated / removed then only the
equipment should be opened / dismantled.
4.10.5.6 In general, mask or other protective measures are not necessary when no
appreciable amount of dust (fluoride powder)/ odour exists. However, during internal
70
inspection of the interior parts of apparatus, personnel should take precautions to avoid
exposure to the breakdown products and suitable protective equipment like gas mask
(preferably incorporating molecular filter etc.), Industrial type goggles (SF6 gas dust can
sometimes attack the glass of goggles, spectacles etc) and rubber gloves may be used.
4.10.5.7 After completing the work on the equipment, equipment should be reassembled.
4.10.5.8 Before refilling SF6 gas, evacuation up to 6 mbar should be carried out for about 2
hours , thereafter SF6 gas should be filled in the equipment.
71
SAFETY INSTRUCTIONS (SECTION-11)
4.11 FIRE PROTECTION
4.11.1 INTRODUCTION:
Fire is a great destructive natural force. It can destroy vital stores, equipments,
accommodation and amenities. Majority of Fires are due to carelessness, ignorance, arson,
lack of discipline and failure to observe statutory and general regulations. A little
knowledge on this subject may save loss of lives and properties.
4.11.2 BASICS OF FIRE: Ordinary Fire is a chemical reaction between a fuel and oxygen in
presence of heat. In other words, it may be stated that three things are essential to initiate a
Fire viz. OXYGEN, FUEL & HEAT. A Fire cannot take place in the absence of any one of
these three factors. In extinguishing a Fire, all that is done is removal of Heat or Fuel or
Oxygen from Fire.
1) Cooling Method: The method, in which Heat of burning substance is removed, generally
by using water, is known as cooling method. Water brings the heat of substance under Fire
below the ignition temperature of substance. This method is normally applied in
extinguishing Fire of solid combustible materials. This method must not be adopted for
fighting live electrical Fire. This method is applied for extinguishing electrical originated
Fire only after ensuring the cut off of power supply.
2) Smothering Method: The method in which Oxygen is removed from burning substance
is known as smothering method. In this method oxygen is restricted to Fire by using layers
of Foam or inert gases like CO2, Nitrogen, Chlorofluorocarbon or Dry Chemical Powder or
Dry sand. Sometimes this is achieved by proper blanketing of Fire using Fire blanket or
Asbestos blanket or Aluminium blanket or other available non-combustible materials. This
method is normally used for extinguishing Fire in Flammable liquids.
3) Starvation Method: The method in which Fuel or combustible material is removed from
Fire is known as starvation method. This is achieved by removing burning substance from
the scene of Fire. Fire in pipe lines, cylinders, Tankers containing flammable liquid or gas is
controlled by closing the valves. By closing valves the Fuel or combustible materials are
isolated from Fire and thus starvation is achieved. This method is best used for
extinguishing Fire in pipelines, cylinders containing flammable liquid or gas.
72
Class A Fire. Fire in paper, wood, cotton, plastic, rubber etc. are the example of Class-A
fires. Cooling method is normally used for extinguishing Class-A Fires.
2) CLASS B: Fires involving liquids or liquefiable solids are categorized as Class-B Fire.
Fires in petrol, kerosene, diesel, oil etc. are the examples of Class B Fires. Smothering
method is normally used for extinguishing Class B Fires.
3) CLASS C: Gaseous Fires are categorized as Class C Fire. Fires in LPG, Acetylene,
natural gas etc. are the examples of Class- C Fires. Starvation method is normally used for
extinguishing Class-C Fires.
4) CLASS D: Fires in metals are categorized as Class-D Fire. Fires in Sodium, Magnesium,
Potassium etc. are the examples of Class-D Fires. A special type of powder is used for
fighting Class D Fires. There is no chance of Class-D Fire in Sub-Station.
1) The name of Fire extinguisher is written in bold capital letters on the sticker.
By name, the inside contents and discharge of Fire extinguishers can be identified. The
following are the examples of names and contents of Fire Extinguishers:
73
Difinoro Methane)
2) The information regarding suitability of Fire extinguishers is given in form of capital
letters in circle. If character 'A' is written inside the circle then it is suitable for
Class-A Fires. If characters 'B' &'C' are written then it is suitable for Class-B & Class-
C Fires.
3) The method of operation of Fire extinguishers varies from type and capacities. It is,
therefore, essential to read carefully the method of operation written on the sticker
of particular Fire extinguishers. A stepwise drawing for operation is also shown.
The date of checking and due date of refilling must be checked before the operation of Fire
Extinguisher. It must be ensured that the Fire extinguisher is well maintained and ready for
use.
1) Fire occurrence report: For reporting a Fire incidence a format has been prepared as
Appendix-A. This format covers almost all details required in preparing Fire report.
4) Vehicle and Pump Register: A format for making entries of Fire vehicle and Fire
Pumps is given as Appendix-D. A register may be prepared and entries should be
made by the Fire staff of respective Sub-Station invariably.
5) Fire Pump Test Register: Fire pumps are installed in all major Sub-Stations. A
format for keeping test record of Fire Pump is given as Appendix-E.
6) Fire Hose Test Register: A number of Fire hoses are kept at major Sub-Stations for
suction and delivery of water for fighting Fires. Periodical tests may be carried out
and the record of tests may be kept as format given as Appendix-F.
74
APPENDIX-A
FIRE OCCURRENCE REPORT
NAME OF SUB-STATION ____________________________________
12. Was outside Aid required? Give brief details of time they were informed, time they
reported, and nature of assistance rendered :
b) Equipment No. :
c) Manufacturer :
d) Type :
e) Rating :
f) Type of insulation :
g) Any other information :
75
16. What fire protection arrangement the building or equipment had? :
b) Store :
c) Building :
d) Production/revenue :
e) Miscellaneous :
f) Total :
b) During Fire :
c) After Fire :
Reported by ______________
Signature________________
Designation______________
76
APPENDIX-B
77
APPENDIX-C
FIRE-ORDER
IN CASE OF FIRE
78
APPENDIX-D
Static Run Fuel consumed Fuel balance in Tank Initial DCO Initial
Fire Officer
Hrs. Mins. Litres Departure Arrival
79
APPENDIX-E
RECORD OF TEST OF FIRE PUMPS
80
APPENDIX-F
Length:________________ Size:__________________________
Date Details of use, check, test, repair etc. with remarks Initial
81
APPENDIX-G
82
4.11.7 PROCEDURE FOR HOT WORK.
Purpose -- The purpose of safety permit for Hot work and vessel entry is to save the human
life and control the Fire hazards. This is achieved by establishing the fool proof procedure
for giving clearance of Hot-job. Any job inside Sub-Station requiring the use of following
must be covered by a safety permit. Such jobs as well operation or use of equipment, which
in the opinion of Fire Section may create a source of ignition, will be classified as "HOT
WORK". This may include the following.
a. Welding
b. Burning & cutting
c. Torches & open flames
d. Tar pots/mastic work
e. Soldering of equipments
f. Portable electrical tools & appliances
g. Forges
h. Electrical arc of any kind and any other equipment, which may create a
source of ignition.
i. Chipping
j. Sand blasting
k. Heaters
l. Hot plates
m. Operation of mobile crane near high voltage lines / equipments.
n. Any equipment, line or vessel which contain or has contained any
Hydrocarbon, corrosive or toxic material and removed from services for
discarding in and around work shop to a location where "Hot Work" is
already permitted.
Validity
a. Safety permit will remain valid for specified period of time.
b. Safety permit will become void if the work stipulated in the permit is not
started within one hour of issue of safety permit. While issuing the new
permit all tests should be repeated.
83
c) Give message of Fire to Fire Section on telephone or Loud phone or in person.
Give full and clear message of Fire.
d) If Fire is small enough for tackling by person alone, immediately attempt to
extinguish it by using nearby Fire Fighting equipments.
a) All essentially required persons will not leave place of work and continue
their functions and operate essential equipment and emergency systems till
ordered to evacuate, considering the grave danger to their personal safety.
b) The work will only stop in affected area of the building/section and in the
immediate surroundings.
c) All non-essential persons will be evacuated safely and shall muster in safe
place of assembly, earmarked on Sub-Station layout.
a) On hearing Fire Alarm, the Sub-Station Fire staff will double up to the scene
of Fire with Fire Fighting equipments and initiate Fire Fighting operations till
arrival of city Fire Brigade and later on assist Fire Staff, if required.
b) The crew on duty will mount in Fire vehicle if available. The senior most Fire
person after ensuring that all members of the crew are in the vehicle will ask
Driver-cum-operator to start the vehicle. Driver-cum-operator shall park the
vehicle at safe place in such a manner so that Fire appliance can be quickly
moved away in case it is found exposed to dangerous conditions due to Fire
of Explosion.
c) On arrival at the scene of Fire, In-charge of Fire crew shall dismount from the
vehicle and double up to scene of Fire to enquire about the details of Fire,
quickly size up the situation and instruct his men to come into action
immediately without any delay. Fire crew will immediately operate Fixed
Fire Fighting system if kept on manual or not operated as the situation
demands. Fire crew will also start laying of hose pipes or operation of
equipment or will initiate other appropriate action according to situation in
consultation with senior most engineer present.
84
5. In charge of Sub-Station:
a) On hearing the Fire alarm or on receipt of message regarding Fire in his area,
he will immediately proceed to the scene of Fire in his area.
b) He will ensure:
I. That Fire Station is informed about the Fire.
II. That Fire alarm is sounded on siren, if required and will inform Main
Gate security persons for sounding hooter.
c) He will ensure that all-important documents, precious material are salvaged
& removed to safe place with the help of his sectional staff.
d) He will decide in consultation with senior Engineer present and arrange to
switch off power/gas/air or other equipment or system if so warranted to
control the situation.
e) He will not leave the Fireplace till normal condition is established.
85
arriving at Main Gate for help to reach the scene of Fire.
f) On receipt of "ALL CLEAR" message from Head of Sub-Station, he will
sound "ALL CLEAR" siren by continuous blast of one minute.
The Fire or emergency siren will be sounded for 5 Minutes and in wavering sound as
under:
15 Seconds on-- 5 Seconds off, 5 Seconds on-- 5 Seconds off
And so on for 5 Minutes.
4. All clear siren will be sounded in continuous blast for 1 minute.
5. Fire Alarm shall be installed at Security Main Gate of the Sub-Station.
01. EMULSIFIER SYSTEM: The emulsifier system is installed in Sub-Station for fighting
Fire of higher capacity transformers. The system not only extinguishes Fire of transformer
but also cools down the transformer. The system is fixed type and installed around the top
of transformer of higher capacity. The system normally works automatically. The
emulsifier system is fitted with quartzite glass bulb inside which coloured liquid is filled.
When the temperature below the glass bulb increases the liquid inside the glass bulb
expands. At certain temperature depending upon the colour of liquid, the glass bulb breaks
and pressurized air in the pipeline comes out. As the air releases the air pressure on the
deluge valve drops down and the pressurized water enters in the water line. Thereafter
water in form of mist comes out through water projector with high velocity at different
angles. The high velocity water in form of mist penetrates into the oil tank of transformer
and generates large quantity of steam over burning oil tank. Also, small bubbles of water
are created inside the oil are converted into steam. In this way, due to deficient of oxygen
around the burning oil and cooling effect, the Fire is extinguished. The temperature
identification according to the colour of liquid inside glass bulb is as under:
ORANGE 57
RED 68
86
YELLOW 79
GREEN 93
BLUE 141
MAUVE 182
02. HYDRANT AND PUMPING SYSTEM: This is the most common system which is
installed in most of the 400 KV Substations. The system consists of a large water reservoir,
Pumps, network of water lines covering the yard area, Hydrant points, Hose pipes, Hose
Boxes etc. Water with pressure for extinguishing Fire can be tapped easily by using Fire
hoses form the hydrant points nearest to the scene of Fire. The water in the water line is fed
through centrifugal pump driven by electrical motors or by diesel engines. The pump
driven by diesel engine is useful in case of failure of power supply in the station as the diesel
engine can run on battery. The pressure switches are provided for each pump and common
header to regulate the pressure in the water line. The Jockey Pump is also provided in the
system. Therefore, the system can run automatic. The Hose boxes are provided near to the
hydrant points. Delivery Fire hoses and branches are put into the hose boxes. In case of Fire
the pressurized water can be directed on Fire by using delivery Fire hose with end
connected with branch.
03. FIRE DETECTION & ALARM SYSTEM: Normally smoke is generated before the
actual Fire takes place. By early detection of smoke the occurrence of Fire can be prevented.
If Fire has already taken place, the early detection of smoke is helpful in attacking Fire in its
incipient stage. For the detection of smoke and raising alarm, Fire Detection and Alarm
system is installed in most of the 400 KV S/S. The system consists of Smoke detectors, Heat
detectors, Main Panel, Mimic panel, Repeater Panel ,Hooter etc. The detectors connected
with the panel of the system detect smoke and heat and gives alarm in the Fire Section and
Main control room. The exact place where smoke or heat is detected is also indicated on the
panel so that exact Fire spot can be traced and necessary preventive measures can be started
immediately. Most of Fire Detection and Alarm systems are conventional type and
automatic in action. If maintained properly, the system is very useful in early detection of
Fire, which in turn confines the infinite loss of lives and properties.
87
SAFETY INSTRUCTIONS (SECTION-12)
4.12 WORK ALLOCATION TO PERSONS
4.12.1 SCOPE
The Safety Instruction sets down procedure for appointment of personnel such as
Maintenance Engineer, Testing Engineer, Shift in-charge, Substation In charge, Line In-
charge, Lead Shift In-Charge, Operator and Authorized Persons.
4.12.2 DEFINITIONS
Additional Definitions are as under:
Maintenance Engineer Engineer responsible for carrying out maintenance works of EHV
equipments, Transmission lines & LT system.
Testing Engineer - Engineer responsible for carrying out testing of protective relay, PLCC
panels and other related equipments.
Substation In-charge Engineer responsible for all operation and maintenance activities
being done/to be done in the Substation.
Line In-charge Engineer responsible for patrolling and maintenance activities nvolved
for carrying out line maintenance.
Lead Shift In-charge Shift in-charge responsible for coordinating operation activities
involved for carrying out line maintenance.
Operator Person authorized to carry out operations of EHV equipments or to use specific
type of vehicles or cranes within S/S.
4.12.3 PROCEDURES
4.12.3.1 -- Only appointed persons shall be allowed to carry out operation and maintenance
activities in substation / transmission lines.
4.12.3.2 -- Safety guidelines during O&M of S/S shall be issued by substation in charge. All
operation and maintenance activities shall be carried out under the control of Sub Station
In-charge.
4.12.3.3 -- For carrying out maintenance work, safety document (LC PTW / TP) shall be
approved by Sub Station In-charge.
88
4.12.3.4 -- Substation In-charge shall appoint Shift In-charge and Maintenance Engineer
for carrying out O&M activities in S/S. Safety document i.e. LC PTW / TP shall be filled by
Maintenance/Testing Engineer for carrying out maintenance/testing activities in S/S. LC
PTW / TP are to be approved by Substation In-charge before being issued by Shift In-
charge.
4.12.3.5 -- All operation including isolation and earthing of equipments shall be carried out
by Operator in presence of Shift In-charge.
4.12.3.6 -- After physically confirming isolation and earthing in the work area.
Maintenance/Testing Engineer shall advise authorized persons for carrying out
maintenance/testing activities. All authorized persons shall be appointed by Substation
In-charge. Maintenance/Testing Engineer shall be responsible for taking all safety
precautions during maintenance works including use of PPEs (Personal Protective
Equipment).
89
SAFETY INSTRUCTIONS (SECTION-13)
4.13.1. Every case where a person receives an electric shock whether mild or serious or
suffers an injury or burn or fatality, directly or indirectly due to electrical causes shall be
treated as an "electrical accident". The concerned jurisdictional engineer of PSTCL shall
report the same immediately to the authorized representative of Commissioner in charge
of the area within 24 hours. A copy shall also be sent to the Chief Electrical Inspector of the
Government of Punjab. This shall be followed by detailed report within 48 hours whenever
an accident occurs resulting in or likely to have resulted in loss of human life.
4.13.2. An enquiry shall be conducted into every electrical accident. It shall be completed
within a reasonable time frame, but in any case not exceeding fifteen days, to guard against
the possibility of destruction or disappearance of material evidence, to escape
responsibility. It shall be a searching probe to uncover the root cause of the accident, which
sometimes are quite difficult to ascertain. The enquiry shall not only fix responsibility for
the accident, but it is more important, to spell out steps to be taken to prevent reoccurrence
of such accidents in future.
To avoid accidents to the public, Danger Board should be provided at each location of
transmission line. Proper care should be taken for not exposing the live part to the public.
Public should be educated about the sub-stations and transmission lines to avoid
possibility of the accidents.
90
SAFETY INSTRUCTIONS (SECTION -14)
4.14.1 FIRST-AID
First aid is the first assistance or treatment given to a person for any injury or sudden illness,
with the available resources at the place of occurrence, before the arrival of an ambulance or
a qualified paramedical /medical person. It may involve improvising with facilities and
materials available at the site.
4.14.1.1 GENERAL
1. Immediately remove the patient from the source of accident or remove the cause of
injury.
2. Keep the affected person lying down in a comfortable position; his head in level
with his body. This is prevention against fainting. Never pick him up by head and
heel.
3. Severe haemorrhage must receive immediate attention, no matter what other
injuries are present.
4. If the breathing is ceased, immediate measures must be taken to restore it. The
patient should be in a position to breathe freely.
5. If the patient has received burns attend to them.
6. When the patient has fractured a bone, no attempt must be made to move the patient
until the bone has been rendered as much immovable as practicable unless life is in
danger from some other cause.
7. Treat the patient for shock.
8. Send for medical help or ambulance immediately.
9. Never give water or liquid to an unconscious patient.
10. Keep bye-standers away from the patient.
11. Don't allow the patient see his own injury.
12. Keep the patient warm. Avoid over application of external heat, but maintain
normal body temperature.
13. Air should not be blocked in place where the patient has been kept.
D : DANGER REMOVAL -- Remove the danger from the casualty or remove the casualty
from the danger.
R : RESPONSE -- Check the response of the casualty by three simple methods;
(i) Call near the patient's ear in a bit louder voice & observe the response.
(ii) Shake both the shoulders of the casualty & observe the reaction.
(iii) Give a gentle pain to the ear lobe or below the foot & observe.
A : AIR WAYS OPENING -- Lift the chin and tilt the head resulting in removal of
obstruction of air passage due to falling of tongue or any foreign body in the mouth
B : BREATHING - Check the breathing of the casualty by LOOK, LISTEN & FEEL
(i) Look for chest or abdominal movement
91
(ii) Listen for breathing sounds
(iii) Feel the air coming out of the nose or mouth
The rate of breathing per minute on an average is 18 (eighteen).
Count the breathing rate for 10 seconds, if it is other than 3 or 4, it may be abnormal.
C : CIRCULATION OF BLOOD - Check the pulse rate at the neck from CAROTID PULSE.
This pulse can be felt by placing the finger tips gently on the voice box & sliding them down
into the hollow between the voice box and the adjoining muscle.
The normal pulse rate per minute on an average is 72.
Count the breathing rate for 10 seconds, if it is other than 12 to 14, it may be abnormal.
If you assess the condition of the casualty normal from above A B C, you can put the
casualty in RECOVERY POSITION and continue observing his breathing & circulation.
If the breathing and circulation is not normal, you can immediately start ARTIFICIAL
RESPIRATION & CARDIO PULMONARY RESUSCITATION (CPR) till the normal
breathing & pulse rate is restored or till the casualty reaches the hospital. (Process of
Artificial respiration and CPR are described subsequently)
92
the vital forces of body are so exhausted that death may result.
4.14.1.4.2 Symptoms: Symptoms of shock may reflect as pale face and murmuring lips, cold
moist skin, rapid and weak pulse, shallow and irregular breathing, fall of the body
temperature, nausea and vomiting may often occur.
4.14.1.4.3 TREATMENT (IMMEDIATE):
1. Keep the patient lying on back with head low and turned to one side.
2. Loosen clothing about the neck, chest and waist and ensure free circulation of air.
Cover with rugs or coats.
3. Raise well the lower limbs
4. May apply smelling salts, if available, to the nose except in the case of head injury.
5. Use encouraging words to the patient.
6. Ensure freedom from excitement and worry and avoid unnecessary questioning of
patient.
7. Remove the patient to shelter in an airy place.
4.14.1.5 FAINTING
1. Lower patient's head between knees, loosen tight clothing around neck. If
impossible to lower victim's head, elevate his lower limbs and keep him lying down
until recovery seems assured. If unconsciousness persists, cover patient, call for a
doctor.
2. Sprinkle the face with luke warm and cold water alternately, and apply warmth to
the pit of the stomach and over the heart. Vigorous rubbing of the limbs upwards has
a stimulating effect. Smelling salts, if available, may be held to the nose.
7. GENERAL
a) In most cases of electric shock and collapse, it is the lungs and the diaphragm
that are most affected and there is a very good chance of revival by applying
quick artificial respiration & CPR in appropriate method and procedure.
Methods of artificial respiration & CPR generally used, are described below
and all employees concerned should practice themselves by practical study
and drill in the treatment for electric shock including (CPR) according to
these methods.
b) While rendering CPR, violent operations should be avoided as injury of the
internal organs may result from excessive and sudden pressures.
c) In case of severe electric shock, respiration is seldom established within an
hour, while 3 to 4 hours or more may be necessary to restore normal
breathing. It is, therefore, essential that in all cases of electric shock, where the
condition of the patient is doubtful or patient is unconscious or not breathing,
artificial respiration & CPR should be continued until death is diagnosed by a
physician.
Normal air contains 21% of oxygen along with Carbon dioxide, Nitrogen with other
poison gases amounting to 79% . During respiration process, we consume only 5% from
above 21% oxygen inhaled and exhale 16%. If forcibly we can continue to give this
exhaled oxygen to a casualty during artificial respiration he may regain normal
breathing.
97
the nose of the casualty and proceed as was carried out for the mouth to mouth respiration.
Administering CPR
1. Place the victim on his back. Make sure he is lying as flat as possible - this will
prevent injury while you're doing chest compressions.
2. Place the heel of one hand on the victim's breastbone, exactly between the nipples.
3. Place your second hand on top of the first hand, palm down.
4. Position your body directly over your hands, so that your arms are straight and
somewhat rigid.
5. Perform 30 chest compressions. Press down with both hands directly over the
Breast bone to perform a compression, which helps the heart beat. Chest
compressions are more critical for correcting abnormal heart rhythms (ventricular
fibrillation or pulse less ventricular tachycardia).
6. You should press down by about 2 inches (5 cm). Continue the process until help or
Doctor arrives
98
4.14.1.15 FIRST AID EXERCISE
1. First-aid is the basic necessity for the post accident management which is very
important for any power sector.
2. Based upon First-aid training in the field / during 5-days 'safety training' at HQ
level & the Mock Safety exercise carried on by the Safety Cell in different Grid /
work site, some important practices are to be done during the first-aid exercise in the
grid / work-site among the employees.
3. Inspection of the first-aid box whether it is properly furnished as per the list
prescribed above including its expiry date.
7. Wound management;
Dressing
Bandaging - Types of Roller bandaging
- Use of Triangular bandaging
- Type of knot with Triangular bandage
99
shifted to a nearby doctor / hospital
100
PSTCL Safety Manual
Chapter - 5
SAFETY audit
101
5.0 SAFETY AUDIT
5.1 INTRODUCTION
It is essential that the highest Safety Standards are maintained throughout the Company
and that the quality of these standards are assured by audit. The audit is to be used solely as
a means for establishing the quality of safety standards so that procedure can be reviewed
and if necessary, improved to ensure that safety practices are satisfactory throughout the
Company. It should not be seen as a means of judging an individual's performance.
5.2.2 The Safety Officer at the Circle level will personally audit at least twenty-five
substations per annum. The records are to be kept in the Circle Office, but a list of the audits
carried out by site staff and circle staff, with their results, are to be sent HOD.
5.2.3 HOD will audit all Circles for Substation or Transmission Line working situations per
annum.
5.2.4 HOD will maintain a record of all the audit results and review them annually.
5.2.5 HOD will propose Safety Rule or Safety Instruction revisions if required, based on the
review of the annual audit. These proposals will have to be agreed by Chief Engineer before
implementation.
5.2.6 The format for the audit is attached to this section as Appendix A.
102
SAFETY RULE AUDIT APPENDIX A
Substation --
Equipment --
Date of issue --
Date of audit
103
T-3