Investment Project Management Sample

The document provides information about allocating tasks, resources, and timelines for an investment firm's project to evaluate company XYZ. It includes: 1) A table outlining the primary and secondary assignments for portfolio managers, associates, and analysts across three tasks over three weeks. 2) Instructions to create a responsibility matrix, resource Gantt chart, and resource loading chart from the table.

Uploaded by

Shaneel Prasad
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
301 views9 pages

Investment Project Management Sample

The document provides information about allocating tasks, resources, and timelines for an investment firm's project to evaluate company XYZ. It includes: 1) A table outlining the primary and secondary assignments for portfolio managers, associates, and analysts across three tasks over three weeks. 2) Instructions to create a responsibility matrix, resource Gantt chart, and resource loading chart from the table.

Uploaded by

Shaneel Prasad
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 9

1

MGT 250. Project Management

Assignment 2

1) The following table shows the allocation of work assignments and


resources needed for an investment firm to make a decision on investing
in company XYZ.

Task A Task B Task C


Profolio Managers Week 1(S) - Week3 (P)
Associates - Week 1 (P) Week2 (S)
Analysts Week 1 (P) Week 2 (P) Week2 (S)
(P)=Primary (S)=Secondary
Resource Speadsheet
Resource Week 1 Week 2 Week 3
Profolio Manager 1 1
Associate 1 2
Analyst 2 5
Note: figures in spreadsheet are person-weeks of effort

a) Create Responsibility Matrix


b) Create Resource Gantt Chart
c) Create Resources Loading Chart

2015 University of Management and Technology 1


2

Ans:
a) Responsibility Matrix:
RESOURCE WEEK 1 WEEK 2 WEEK 3

PORTFOLIO
MANAGER

ASSOCIATE

ANALYST

2015 University of Management and Technology 2


3

2015 University of Management and Technology 3


4

Resources Loading Chart:

2015 University of Management and Technology 4


5

Building a swimming pool


Task Worker Category Person # of Elapsed Materials
Days Workers Time (days) ($)
Excavate Machine Operator 6 2 0 1,500.00
Frame the walls Masons 8 4 0 800.00
Install Internal Plumbing Plumber 4 2 0 700.00
Install Electricity Electrician 2 2 0 500.00
Pour concrete Masons 4 2 4 2,000.00
Install pump and filter Plumber 1 1 0 3,000.00
Total 8,500.00

Category Wage Rate $/Day


Electrician 200.00
Mason 160.00
Machine Operator 120.00
Plumber 200.00

a) Create a Gantt chart from the work breakdown structure.


b) Create a PERT/CPM network showing the interdependencies of the different activities. How long will the project take?
(Note: Dont forget to take elapsed time into account.)
c) Using the information in your Gantt chart, as well as the information on wage rates and cost of materials, put together a
budget showing planned total expenditures for the project

2015 University of Management and Technology 5


6

2015 University of Management and Technology 6


7

Gantt chart:

2015 University of Management and Technology 7


8

PERT:

2015 University of Management and Technology 8


9

Duration:

Shortest path duration: 19 Days


Time elapsed= 4 days
Total time= 19+4= 23 Days

Budget:

Excavate= Workers + material = (120*2)*6 + 1500 = $2940

Frame the wall: Workers +material = ($160*4)*8 + $800 = $ 5290

Install Internal plumbing = ($ 1600+ $700) = $2300

Install electricity $1300

Pour Concrete $3290

Install pump and filter $3200

Total cost: $18,322

2015 University of Management and Technology 9