Sl. Name and Address of the Project Project Location Product Investment Employ Land Status
No in Crores ment
1 PARDINI INTERNATIONAL PVT. LTD., C- PL NO.15-A, BISCUITS - 21600 MT 8 50 0.98 Implemented
2404/5,SHREEJI HEIGHTS, SECTOR SANKALAPURA IA,
NO.46-A, PALM BEACH HOSPET, BELLARY
ROADPL.NO.1,NERUL, NAVI MUMBAI DIST.
2 JSW SEVERFIELD STRUCTURES LTD. Toranagallu Village, Fabricated Structural 234 500 65 Implemented
No.401, Deluxe Court, Sandur Taluk, Products of Iron and
R.V.Bambardekar Road, Off Station Bellary District Steel (except rolling
Road, Bandra (West), Mumbai - 400 shutters)
050
3 JINDAL SAW LTD. Vidyanagar, Shopping Sultanpur village, Steel Pipes & Coating 130.88 400 50 Implemented
Complex, Bellary Sandur Taluk, Plant
Bellary
4 SIRUGUPPA SUGARS & CHEMICALS Desanur Village, 28 MW Cogen Plant, 310.26 676 0 Implemented
LTD. No.60/1, 2nd Cross, Residency Siruguppa Taluk, 60 KLPD Ethanol Plant,
Road, Bangalore 560 025 Bellary Sugar Candy and
Beverages Plant
5 POWERNOCIKS LTD, Besides 110 KV Siruguppa Village & Poultry Based Power 70.7 75 36.89 Implemented 8 MW power
KEB Substation, Adoni Road, Taluk, Bellary Project - 12 MW capacity
Siruguppa, Bellary 583 121
6 KEJ MINERALS PVT. LTD.,NO.17,SRI TARANAGAR VIL. IRON ORE 45 70 12 implemented
RAGHAVENDRA COLONY,'D' BLOCK, SANDUR TQ. BENEFICATION PL-0.30
OPP.:MEI,YESHWANTHPUR, BELLARY DIST MTPA & PELLETS-0.15
BANGALORE-560022
7 SLR METALIKS LTD.,A-2/452, SECTOR-8, NARAYANADEVAKE 8 MW CAPTIVE 47 55 45 implemented
ROHINI, NEW DELHI-110085 RE VIL. HB HALLI POWER PLANT
TQ. BELLARY DIST.
8 JANKI CORP LTD.,NO.17/95, VISHAL SIDIGINAMOLA 15 MW CAPTIVE 48.68 195 69.03 implemented
NAGAR, ANANTHAPURA VILLAGE, BELLARY POWER PLANT
ROAD,BELLARY - 102 TQ. AND DISTRICT
9 SLR METALIKS LTD.,A-2/452, SECTOR-8, NARAYANADEVAKE SINTER FROM IRON 45 55 84.44 Unit is about to commencement
ROHINI, NEW DELHI-110085 RE VIL. H.B. HALLI ORE FINES into production
TQ. BELLARY DIST.
Sl. Name and Address of the Project Project Location Product Investme Employ Land Status
No nt in ment
Crores
1 DIVYA JYOTI STEELS LTD.,NO.12, I TARANAGAR VIL. BENEFICIATION, 9 16 0 clearance from
MAIN, I CROSS, NTI L/O, RMV 2ND SANDUR TQ. SCREENING & MOEF has
STAGE,BANGALORE - 560 094 BELLARY DIST. CRUSHING completed awaiting
for public hearing
2 DIVYA JYOTI STEELS LTD.,NO.12, 1ST TARANAGAR 100 TPD SPONGE 41.25 50 24.5 clearance from
MAIN, 1ST CROSS, NTI LAYOUT, VILLAGE, IRON PLANT WITH 6 MOEF has
DOLLARSCOLONY 2ND SANDUR TQ. MW CAPTIVE POWER completed awaiting
STAGE,BANGALORE-94 BELLARY for public hearing
DISTRICT
3 UR STEELS PVT. LTD.,HIG BLOCK 1, PLOT HALKUNDI VIL. 2X100 TPD SPONGE 48.5 160 14.15 Land purchased.
NO.7, BHAGLINGAMPALLI,HYDERABAD BELLARY TQ. AND IRON PLANT AND 8 Applied to MOEF &
DISTRICT MW CAPTIVE POWER TOR meeting.
4 RAYEN STEELS PVT. LTD.,NO.19 "GURU HARAGINADONI 10 MW POWER PL. 48 150 37.49 Consultant finalised.
NIVAS", AISHWRYA COLONY, ROAD, FROM WHR & BF Yet to start the
CANTONMENT,BELLARY - 583104 VEENIVERAPURA BOILOR FROM project awaiting for
CROSS, BELLARY CAPITIVE the raw material to
TQ. & DIST. be finalased
5 RBSSN FERROUS INDUSTRIES PVT. LTD, Hampapatna, 0.6 MTPA Iron Oxide 266.8 160 331.22
No.1499/1, P.O Box No.38, Kariganur, Vardakapur, Pellets and 18 MW
Hospet, Bellary - 583 201 Vayasapur & Thermal Power Plant
Morabinal
Villages of
Hagaribomanaha
lli Taluk, Bellary
Sl. Name and Address of the Project Product Investme Employ power Land Status
No Project Location nt in ment mw
Crores
1 ARCELOR MITTAL INDIA LTD. Kuduthini and 6 MTPA Integrated 30000 10000 4000 possession certificate is
Plaza M-6, 6th Floor, Jasola Harginadoni Steel Plant, Pig Iron, issued by KIADB for
District Centre, New Delhi 110 Village of Pallets and 750 MW 1827.60 acers of land in
025 Bellary Captive Power kudathni village for
District generation implementation of 1st
stage of the project
2 NMDC Ltd. No.10-3-11/A, VADA, Bellary 5 MTPA Integrated 9280 2500 25 5000 Land compensatation
Khanija Bhavan, Castle Hills, District Steel Plant operati distribution under process
Masab Tank, Hyderabad - 500 onal
173 175
mw
3 BRAMHANI INDUSTRIES Vijayanagar 6 Million TPA with 36000 25000 5000 compesatation
KARNATAKA LIMITED, No.123, Area 1st Phase, 1.9 distrubution from kiadb is
Veeranna Gowda Colony, Near Development Million TPA with a under progress for land
Kumaraswamy Temple, Ganesh Authority Captive Power Plant loosers THROUGH UTTAM
Nagar, Bellary 583 103 Area, Bellary of 68 MW capacity GALVA LTD.,
District
4 JSW STEEL LTD No.U 607, 6th Toranagallu Enhancement of 15131.7 6000 1150 a letter from kiadb
Floor, East Wing, Raheja Towers, Village, Installed capacity of dharwad is sent to head
M.G.Road, Bangalore - 560 001 Sandur Taluk, Integrated Steel office kiadb regarding issue
Bellary Plant from 10 MTPA of notification
District to 16 MTP & to set
up 600 MW Captive
Power Plant
5 JSW INFRASTRUCTURE LTD, Through Railway Siding and 87 366 231 for 216.29 acers pocession
No.U.607, 6th Floor, East Wing, different railway line in is handed over to to JSW
Raheja Towers, M.G. Road, Sy.Nos. of Bellary District. on 19/05/2011
Bangalore 560 001 Daroji and
Toranagallu,
Krishnanagar,
Daulathpur &
Sushilnagar
Villages
6 SWASTIK STEEL (HOSPET) PVT. Danayakanake 0.50 Million TPA 1500 362 580 The promoters have
LTD, 1st Floor, Swastik re & Integrated Steel informed that, their
Steel Building, Opp. APMC Gollarahalli Plant consultant suggested to
Complex, Hospet 583 203 Village, acquire totally 1030 acres
Hospet Taluk, of land for the project.
Bellary Hence, they are in the
District process of collecting details
of additional lands. MOEF
has conducted meeting on
23-11-2010 regarding TOR.
Applied to WRD for
allocation of water from
Tungabhadra upstream.
WRD has sought additional
information.
7 JAI RAJ ISPAT LIMITED, Plot No.8, Belagal MS Billets -0.20 150 245 30 applied for land conversion
Phase III, IDA Jeedimetla, Village, MTPA and 30 MW under 109
Hyderabad 55 Bellary Taluk Captive Power Plant
& District
8 DIVYA JYOTI STEELS LTD.,NO.12, TARANAGAR 100 TPD SPONGE 41.25 50 24.5 clearance from MOEF has
1ST MAIN, 1ST CROSS, NTI VILLAGE, IRON PLANT WITH 6 completed awaiting for
LAYOUT, DOLLARSCOLONY 2ND SANDUR TQ. MW CAPTIVE public hearing
STAGE,BANGALORE-94 BELLARY POWER
DISTRICT
9 VIC STEELS PVT. LTD.1st Floor, Toranagallu 2 MTPA Integranted 6515 4000 1976 The company is in the
Embassy Point, No.150, Infantry Village, Steel Plant and 180 process of applying to
Road, Bangalore - 560 001 Hospet Taluk, MW Power Plant KIADB for allotment of land
Bellary
10 ARADYA STEEL PVT. LTD, No.385, VADA, Bellary 1 MTPA Integrated 1500.00 362 980 Company has not yet filed
Aradhya House, K.B. Extension, Steel Plant with 140 application with KIADB for
Davangere-577 002 MW Captive Power acquisition.
Plant
11 MSP ENERGY LTD.16/S, Block-A, Kadalabalu, Beneficiation, 975.28 775 200 The company has entered
New Alipore, Kolkata 700 053 Hagaribomma Palletisation & into agreements with
nahalli, Taluk, Sponge Iron Plant farmers for purchase of 46
Bellary with 30 MW power acres out of total
plant. requirement of 200 acres.
Negotiations with the
remaining land owners is in
progress.
12 RAVINDRA TRADING & AGENCIES Bellary- 2 MTPA Iron Ore 3292 1000 650 The company has written
LTD. 7th Floor, Devchand House, Hospet Pelletisation in 1st to KIADB for acquisition of
Shiva Sagar Estate, Dr.Annie Region Phase, 6 MTPA land for the project. The
Besant Road, Worli, Mumbai Integrated Steel company is pursuing for
Plant in 2nd & 3rd mining lease.
Phase
13 VSL MINING COMPANY PVT. LTD. Nandibandi 1st Phase 1 MTPA 2510 724 255 clearance from MOEF has
No.12, I Main, I Cross, NTI Village, Beneficiation, completed awaiting for
Layout, RMV Extension, 2nd Hospet Taluk, Pelletisation of 0.75 public hearing
Stage, Bangalore 560 094 Bellary MTPA 2nd
Phase 1 MTPA
Steel Plant
14 UR STEELS PVT. LTD.,HIG BLOCK HALKUNDI 2X100 TPD SPONGE 48.5 160 14.15 Land purchased. Applied
1, PLOT NO.7, VIL. BELLARY IRON PLANT AND 8 to MOEF & TOR meeting.
BHAGLINGAMPALLI,HYDERABAD TQ. AND MW CAPTIVE
DISTRICT POWER
15 SUPRA STEEL & POWER PVT. i SPONGE IRON 2X50 45.84 225 18.5 Existing 2 X 50 TPD Sponge
LTD.,PLOT NO.7, 4TH CROSS, - 4 MW CAPTIVE Iron Plant. Land purchased
NANDA SCHOOL ROAD, POWER PLANT for expanding it to 4 X 50
VIDHYANAGAR WEST, BELLARY - Captive Power Plant.
583104
16 SBQ STEELS LTD, 6/13 North VADA Bellary Integrated Steel 1200 1500 300 Company will file the
Avenue, K.P. Puram, Chennai District Plant 0.5 MTPA application to KIADB for
600 028 with 60 MW captive acquisition. Company has
power plant sought change of location.
17 CONCAST INFRASTRUCTURE PVT. VADA, Bellary High Grade Iron Ore 738.65 339 100 The company has identified
LTD, No.21, Hemant Basu Sarani, District Pellet Plant 1.2 alternate land in Achanur
5th Floor, Suite Nos.511 & 512, Million TPA and Halluru Villages of
Kolkata 700 001 Bagalkot districts. The
subject to be placed before
SHLCC for change of
location.
18 HANUMAN INFRA ENERGY PVT. Ayyanahalli 70 MW Thermal 345 245 50 Made agreements with the
LTD, No.136, Tarihalli, Near Bus Village, Power Plant landowners, Deputy
Stand, NH 13 Road, Mariyamman Commissioner issued
Hanumanahalli, Hospet Taluk, ahalli Hobli, permission U/s 109 to
Bellary District 583 222 Hospet Taluk, purchase 50 acres of land.
Bellary Company has purchased 27
District acres, but, for the balance
23 acres they are unable to
register due to title
problems and have
requested KIADB to acquire
and allot the same for the
project.28(1) notification is
under progress
19 BALAJI COKE INDUSTRY PVT. LTD, Vijayanagar Low Ash 212 172 100 Will file the application to
No.12, Ho-Chio-Minh Sarani, Flat Area Metallurgical KIADB for acquisition
No.2B, 2nd Floor, Kolkata 700 Development 2,40,000 TPA Coke
071 Authority with 20 MW Waste
Area, Hospet Heat Recovery
Taluk, Bellary Power Plant
District
20 HOSPET COKE AND ENERGY PVT. Vijayangara Low Ash 212 172 100 Will file the application to
LTD, Hospet Coke and Energy Area Metallurgical Coke KIADB for acquisition
Pvt. Ltd, 2A, Ganesh Chandra Development of 2,40,000 TPA &
Avenue, 4th Floor, Room No.7, Authority 20 MW Waste Heat
Kolkata 700013 (VADA), recovery Power
Bellary Plant
Sl. Name and Address of the Project Project Product Investment Employ Land Status
No Location in Crores ment
1 BHUSHAN STEEL LTD., F-Block, 1st Gadiganur 6 MTPA Integrated 27928 20000 4000 Wild life clearance is
floor, International Trade Tower, Nehru Village of Steel Plant with 600 pending before Vice
Place, New Delhi 110019 Bellary MW Co gen. Chairman, Wildlife
District Society, Karnataka.
And for the company
alternative land is
been shown yet
awaiting for the
response from the
company