Effect of Sand Invasion On Oil Well Production A Case Study of Garon Field in The Niger Delta PDF
Effect of Sand Invasion On Oil Well Production A Case Study of Garon Field in The Niger Delta PDF
Effect of Sand Invasion On Oil Well Production A Case Study of Garon Field in The Niger Delta PDF
--------------------------------------------------------ABSTRACT-----------------------------------------------------------
The effect of sand and other BS&W invading the wellbore of an oil well has been studied using Garon field in
the Niger Delta region. Garon field has unconsolidated formation and it has been producing for more than 10
years. This study is carried out to quantify the safety and economic effect of sand invasion on well productivity
and not on the techniques in numerical models for the prediction of sand production. It tries to look out the sand
evolution, analysis of previous well test done and a survey of sand identification, results of some wells
production data and evaluation of the effect of sand invasion on subsurface and surface production facilities. In
this study, Well X17 was routed into a test separator for 3days and immediately tested for 72hours. The test
separator man way opened in other to ascertain the quantity of sand produced from the well for 72Hrs to
validate the result obtained with Clampon DSC. Also presented are the effects of sand invasion on surface
facility, choke, screen and tubing.
Keywords Well productivity, sand invasion, Wellbore, Unconsolidated formation, test separator, surface
facilities, choke, screen and tubing.
--------------------------------------------------------------------------------------------------------------------------------------------------
Date of Submission: 17-April-2015 Date of Accepted: 15-May-2015
------------------------------------------------------------------------------------------------------------ ---------------------------
I. INTRODUCTION
The probability/tendency of producing hydrocarbon from reservoirs to the surface production facilities in a safe
and economical way without the inclusion of sand is very low from a typical Niger Delta field due to the
unconsolidated nature of the formation. To maximize profit in this region, it is crucial to identify all the possible
problems that affect the productivities of the wells drilled into the reservoir and sand production is one of these
problems plaguing the production aspect of the oil industry. Moreso, geological formations that are shallow with
little or no natural adherence to hold the individual sand grains together are normally prone to sand production
but in some areas, sand problems may be encountered in high depths (Adams, 1986). To effectively control the
invasion of sand, we need to have technology to estimate accurately the initiation conditions, predict the sand
influx rate and the volume of sand production to prevent its effect on surface and subsurface production
facilities which directly impact on the oil well productivity. Oluyemi and Oyeneyin (2010) stated that the
economic, operational and safety implications of sand failures require real time efficient sand management.
Since the effect of sand on facilities is costly, Coberly (1941) noted that expenditures of this magnitude
obviously have a significant impact on profits. In spite of these costs, effective sand-control practices have
yielded oil and gas from wells that otherwise would have been shut- in.
The rationale behind sand production is that; as soon as the well begins production of fluids, depending on the
formation type and other factors, a point is reached when sand mobilization sets in. Sand production in oil and
gas wells can occur if fluid flow exceeds a certain point governed by factors such as consistency of the reservoir
rock, stress state and the type of completion used around the well, this happens when the wellbore pressure is
lower than reservoir pressure, because drag forces are applied to the formation sand sequel to fluid production.
The sand production takes place if the sand grains around the cavity is disaggregated and as the volume of sand
dislodged is deposited and accumulated on production equipment continuously, cleaning will be required to
allow for efficient production of the well. To restore production, the well must be shut-in, the surface equipment
opened, and the sand must be manually removed. In addition to the clean out cost, the cost of the deferred
production must be considered.
The design of the surface separator is to handle liquid and not sand production which essentially has no
economic value with adverse effects on well productivity and equipment. This is one of the major challenges
that is facing the petroleum industry especially the production operations in many oil fields in Nigeria whose
formation is unconsolidated and some other countries such as US gulf coast, California, Indonesia, Trinidad,
Venezuela, and Libya. If a separator is partially filled with sand, the capacity of the separator to handle oil, gas
and water is reduced. For instance, in a two phase separator (oil/water), for every 5000 barrel of liquid per day
on average is accompany by a corresponding 0.03 pptb of sand per day. It implies that at the end of say 6
months the separator must have accumulated about 5.472 pptb of sand and if this continues, an appreciable
volume of the separator designed to handle liquid must have been partially filled with sand. In Garon field used
as a case study, well X17 was routed into Test separator with the Test separator pressure set point at 20Bar. The
well was routed out of Test separator after three (3) days. The well was tested for 72Hrs at 65/64 choke size.
On the second day, test separator man way was opened in other to ascertain the quantity of sand produced from
the well for 72Hrs. results are shown in Figures 2-6.
Therefore, these causes can be lead to several problems during the life time of the wells drilled in a particular
reservoir which is a major production engineering problem. These can lead to one or more of the following
complications:
Formation damage or collapse by the flowing sand grains
Wellbore instability
Casing collapse
Impairment or failure of down hole and surface equipment
Lost production time due to shut in of the well to change damage equipment or clean the sand filled wellbore.
Work-overtime and expense to service the well and production equipment
Coiled tubing cost and possible complications
Cost of separating sand from the produced fluid
Environmental problems in the disposal of the produced dirty sand Fjaer, et al (1992)
Cost of sand disposal and control measures at the pay zone
Opposing the fluid forces are the resulting forces that act to hold sand grains in place. These forces arise from
inter-granular bonds (natural consolidation), Inter-granular friction, a gravity forces and capillary forces.
Internal pore pressure (reservoir pressure) helps support the weight of the overburden, thereby acting to relieve
some of the stress on the sand grain. Of these forces, the inter-granular bonds are the most important factor in
preventing sand production. The compressive strength of formation sand is probably the best measure of the
intergranular bond (Penberthy and Shaughnessy, 1992). If good completion and production practices are
followed, formation with a compressive strength exceeding 1000 psi will generally produce sand free. The
exception is the case where the pressure drawdown around the well is high. If the pressure drawdown is low,
however, sands with much lower compressive strength may also produce sand free. If an oil well is produced at
a desired production rate which causes the well flowing pressure to be lower than formation collapse pressure,
the formation consolidation breaks down, and sand tends to move toward the wellbore (Sanfilippo et al., 1997
and Suman et al., 1991)
It is no longer news that severe operational problems could result from the production of formation sand. These
problems range from erosion and damage of downhole and surface equipment such as valves, pipelines,
separators etc. to inhibition of production through well clogging. These issues could be mild or severe
depending on the flow rate and viscosity of the produced fluid, and the rate of production and accumulation of
fines and sand grains. Sand production costs oil companies tens of billions of dollars yearly (Wu and Tan 2005).
The failure to develop an accurate sand production models; has costs the oil and gas industry hundreds of
millions of dollars per year to either repair or reinstall affect equipment. As an oil field depletes, stress and
pressure change in the reservoir. Water and gas breakthrough may occur which result to production decline. All
these challenges have increase the propensity of sand production, limit production rates and bring forward the
abandonment time of the field, premature failure of the wellbore, improper well completion and the production
of unconsolidated formation. Also, sand may fill up the wellbore thus choking back the productivity or fills up
the process system thereby halting the production operations due to the removal of sand or even system tripping;
it erodes well equipment and facilities, causing breakdown and sometimes even blow outs. Sand production is a
major risk to safe and economical operations. Therefore, casing may collapse; increase in the pressure
drawdown along the well length as a result of high sand production. Table 1 presents some of the problems
encounter from the reservoir to surface equipment.
The sand will have the following effects on the process if not removed:
Occupy volume that is designed to assist with oil and water phase separation, thereby, reducing the
performance with increases in oil-in-water and water-in-oil concentrations on the outlets.
Blockage of vessel internals rendering them ineffective e.g. motion dampening baffles and structured
packing used on FPSOs, vane packs, water outlets etc.
Block instrument nozzles, which can lead to ineffective bulk and interface level measurement.
Stabilization of emulsions, fine particles are known to interfere with oil/water separation and
coalescence of water droplets.
Erode vessels and downstream equipment e.g. pumps and control valves that arent designed to be sand
tolerant.
Traditionally removal of the sand is a batch process. This can be carried out either by shutting down the required
vessel for manual entry to dig the sand out or sand removal internals are provided that allows the sand to be
removed without interrupting production. The results of the effect of sand production are shown in Figures 2-10.
5.00
0.00
1 3 5 7 9 11 13 Date 15 (day)
17 19 21 23 25 27 29 31
Figure 2: Sand production evolution
9.2 Analysis of previous well test done and a survey of sand identification using a thermo graphic tool
The flow of oil from the reservoir into the well bore depends largely on the differential pressure between the
producing formation and the bottom hole pressure. Sand production become more intolerable when the well
were producing up to 10ppth of sand. This resulted in a drop in the flowing bottom hole pressure (PWF). From
the production data, it was discovered that an increase in the production of oil resulted in an increase in
production of sand. Result of Garon field Well Test as at first of January March 2007 is shown in Table 2
Table 2: Summary of Garon field well test result
Well Well Head Gross Production BSW (%) Gas Production
Pressures (bar) (bbls/day) (Sm3/d)
7 18 446-1191 0.1 - 2.6 3986 - 7150
8 7 679-952 40 - 59.3 7310 - 10905
3 11 318-1037 51 - 65.5 1489 - 5993
9 6 4203-4292 40 - 48.5 10900 - 10957
11 6 2508-2822 72 - 91.7 3003 - 8987
To ascertain the results from the Clampon DSC, well X17 was routed into Test separator on the 8th of January
2015, at 2330Hrs with Test separator pressure set point at 19 Bar. The well was routed out of Test separator on
11th of January 2015, at 2330Hrs. The well was tested for 72Hrs at 65/64 choke size. On the 13th January 2015
at 0905Hrs, test separator man way opened in other to ascertain the quantity of sand produced from the well for
72Hrs. The results of the entire process are given in Figures 4 6.
9.4 Evaluation of the effect of sand invasion on subsurface and surface production facilities
The effects of sand production are nearly always detrimental to the short and/or long term productivity of the
well. Although some wells routinely experience manageable sand production, these wells are exceptional. In
most cases, attempting to manage the effects of severe sand production over the life of the well is not an
economically attractive or prudent operating alternative. If the production velocity of the fluid is great enough to
carry sand up the tubing, this sand may become trapped in the separator as seen in Figure 5, heater treater, or
production pipeline. If a large enough volume of the sand becomes trapped in one of these areas, cleaning will
be required to allow for efficient production of the well. To restore production, the well must be shut-in, the
surface equipment opened, and the sand manually removed. In addition to the clean out cost, the cost of the
deferred production must be considered. Figure 7 represents the effect of sand invasion of surface production
facility of Garon field.
One clean-out technique is to run a "bailer" on the end of slickline to remove the sand from the production
tubing or casing. Since the bailer removes only a small volume of sand at a time, multiple slickline runs are
necessary to clean out the well. Another clean-out operation involves running a smaller diameter tubing string or
coiled tubing down into the production tubing to agitate the sand and lift it out of the well by circulating fluid.
The inner string is lowered while circulating the sand out of the well. This operation must be performed
cautiously to avoid the possibility of sticking the inner string inside the production tubing. If the production of
sand is continuous, the clean-out operations may be required on a routine basis, as often as monthly or even
weekly. This will result in lost production and increased well maintenance cost. Figure 9 shows a choke that
failed due to excessive erosion.
X. CONCLUSION
The Garon field in the Niger Delta was completed and produced from unconsolidated formation which produced
sand along with crude oil. Approximately 800 litres of sand was drained and recovered from test separator.
Comparing this quantity with the previously recovered sand at 64/64 on 1 trim choke (350 litres), the current
sand quantity is higher than the former by 650 litres. Also the sand sensor reading gave a total quantity of
198.36 kg/d of sand produced for 72Hrs with choke 65/64 for the same test period which clearly indicates a
wide range of difference between the sensor and the physically recovered sand . Series of event continuous
production imposed serious damage on production equipment of Garon field. The effect as recorded in Garon
field includes the following: The erosion of choke (surface), tubing, screen, Cuts production of flow line, Loads
of treating facilities, Loss of production during work-over jobs and Loss of valuable man-hour during the period
of close-in in terms of wages, which add up to overhead cost. Thousands of dollars were spent to carry out work
over operation as well as installation of sand control measure.
REFERENCES
[1]. N. Adams, Recommended Practices for Testing Sand Used in Gravel Packing Operations. American Petroleum Institute, API
Recommended Practice 58 (RP58), March 1986.
[2]. O. A. Adeyanju and L. O. Oyekunle, Prediction of Volumetric Sand Production and Stability of Well-bore in a Niger Delta
Formation. Paper SPE 136965 presented at the 34th Annual International Conference and Exhibition, Tinapa-Calabar, August 2-7,
2010.
[3]. R. Anderson, G. Coates, S. Denoo, D. Edwards and R. Risnes, Formation Collapse in a Producing Well, The Technical Review 34, no. 3 (October 1986): 29-32.
[4]. C. J. Coberly, Selection of Screen Openings for Unconsolidated Sands, API Drilling and Production Practice, 1941.
[5]. E. Fjaer, R.M. Holt, P. Horsud, A.R. Raaen and R. Risnes, Petroleum Related Rock Mechanics. 1st edition, Elsevier Science
Publishers BV, p. 338, Amsterdam, The Netherlands.
[6]. W. L. Penberthy, and E. E. Echols, Gravel Placement in Wells, SPE Paper 22793, Journal of Petroleum Technology (July 1993), 612-
613, 670-674.
[7]. W. L. Penberthy and C. M. Shaughnessy, Sand Control, SPE Series on Special Topics, Volume 1, 1992.
[8]. F. Sanfilippo, M. Brignoli, D. Giacca and F. Santarelli. Sand Production from Prediction to Management, 1997.
[9]. G. O. Suman, R. C. Ellis, and R. E. Snyder, Sand Control Handbook, Second Edition, Gulf Publishing Company, Houston, Texas,
1991.
[10]. B. Wu, and C. P Tan, Effect of Water-Cut on Sand Production An Experimental Study. Asia Pacific Oil & Gas Conference and
Exhibition. Jakarta, Indonesia: SPE 92715, 2005.