CON4541 - CCM - Chapter 4 - 8
CON4541 - CCM - Chapter 4 - 8
CON4541 - CCM - Chapter 4 - 8
4. Contract Administration (refer Private Standard Form with Quantities for HK)
Contd
Topic outline
Architects Instructions ()
Written instructions ()
Oral instructions (, )
Instructions issued by Architects Representative ()
Variations ()
Valuation of Variations ()
Architect may issue instructions up to the issue of the Final Certificate (Clause 4.1)
The Architect may issue instructions that he is empowered to issue under the
Conditions to the Contractor at any time up to the issue of the Final Certificate
There are 3 ways in which Architects Instruction may be conveyed to the Contractor:
If the Architect gives an oral instruction that the Contractor believes requires a
Variation and it shall have no immediate effect until the following procedures:-
The Contractor shall confirm the oral instruction requiring a Variation in writing
within 7 days.
If the Architect has not dissented in writing within 7 days from receipt of the
Contractors confirmation, the Variation shall take effect on the expiry of the
latter 7 days.
@VTC2013 - Page 1 of 8 -
CON4541 CONSTRUCTION CONTRACT MANAGEMENT
The Architect shall then issue the written instruction for a Variation for record
purposes.as soon as possible (ASAP)
The Contractor shall comply () with Architect's Instructions which are issued
under empowered within the Conditions, i.e. with express authority ().
The Contractor may disagree that the Architect is empowered by the Conditions to
issue an instruction.
If that is the case, the Contractor may within 7 days of receipt of that instruction
require the disagreement to be resolved by settlement of dispute specified
under Clause 41.
If the Contractor does not begin to comply with the properly authorized instructions (
) within 7 days after receipt of a written notice from the Architect
requiring compliance with that instruction:
Then the Employer may employ other persons to carry out the instructed
works.
@VTC2013 - Page 2 of 8 -
CON4541 CONSTRUCTION CONTRACT MANAGEMENT
removal of materials or goods delivered on site which are not in accordance with
the Contract
nomination of subcontractors
nomination of suppliers
omit work so that it may be carried out by any other contractor or the Employer
nominate a subcontractor or supplier unless a prime cost sum has been provided
in the Contract Bills.
@VTC2013 - Page 3 of 8 -
CON4541 CONSTRUCTION CONTRACT MANAGEMENT
the removal from the Site of materials or goods and the demolition and removal
of work except where the materials or goods are not in accordance with the
Contract.
The Contractor may be instructed to carry out Variations for the following
reasons:
@VTC2013 - Page 4 of 8 -
CON4541 CONSTRUCTION CONTRACT MANAGEMENT
The Valuation of Variation is allowed in the Interim Certificates for payment and
is subject to retention. The amount valued for Variations is included in the Final
Account for the adjustment of the Final Contract Sum.
It is the Quantity Surveyors responsibility under the Contract to measure and value
work including Variations, remeasurement of Provisional Quantities, Items and
Sums.
by Contract rates
by daywork rates
Contract rates
Works of same or similar in character and is carried out under the same or similar
conditions and where Variation does not substantially change the quantities of that
work, use Contract rates in the Contract Bills to determine the valued rates
@VTC2013 - Page 5 of 8 -
CON4541 CONSTRUCTION CONTRACT MANAGEMENT
Works of same or similar in character but is not carried out under the same or
similar conditions or Variations substantially changes the quantity of that work,
use Contract rates with fair adjustment for the difference in conditions or quantity.
The word conditions shall mean physical conditions and not financial conditions.
Fair rates
Works is not the same or similar in character to any work priced in the Contract Bills
the work shall be valued at fair rates.
build up a unit rate from basic principles taking into account all factors
such as invoice cost of materials, wastage allowances, transportation
and handling cost, standard labour constants, cost of plants,
overheads and profit.
Daywork rates
Works that cannot be properly measured or valued and with prior consent of
the Architect use daywork rates included in the Contract or other means if no
dayworks rates included in the Contract.
Dayworks are intended to establish a reasonable price for any Variation (ie.
emergency works being valued in this way.
In this case, the Contractor should be very careful on the accuracy of keeping
the records of dayworks .
@VTC2013 - Page 6 of 8 -
CON4541 CONSTRUCTION CONTRACT MANAGEMENT
Clause 13.4 deals with the situation when work is not of a similar character or executed
under similar circumstances.
The contract rates will be the basis for the same, in as far as they may be reasonable, but
failing which a fair valuation is to be made.
Note : it is only necessary to prove that one of the two facets is dissimilar, i.e. (i) character
or (ii) conditions.
The onus of proof for using fair valuation lies on the shoulders of the Contractor. It is the
responsibility of the Contractor to apply for fair valuation if the Contractor finds it necessary.
(i) Character
The meaning of character should refer to the style, quality, distinctive type, sort, nature,
constitution, plus the possibility of being either good or bad. To all intents and purposes,
character must relate with quality.
For example, if a school contract was varied by building a chapel at one corner of the main
building. And the work to the chapel demanded a higher standard of workmanship and
quality of materials. This section of the work would be priced at the pro-rata rates to reflect
the difference in quality of the work required.
Another example of a contract for a factory, together with some flats for managerial staff.
The Architect by a Variation, introduced a small theatre into the Contract. The theatre was
different in character to the repetitive work of the factory or flats. The standard and class of
workmanship involved in building the theatre was different too. Therefore, this section
would also require fair rates to reflect the differences in quality required.
(ii) Conditions
The contract documents generally set out the circumstances, state or situation under which
the building operations are to be undertaken. No matter how good or bad these conditions
are.
They are the norm for the specific contract in question. The conditions of a contract are
those forecast or anticipated at the time of tendering but if subsequently these conditions
change during the contract period.
@VTC2013 - Page 7 of 8 -
CON4541 CONSTRUCTION CONTRACT MANAGEMENT
If there is a clear provable instance of change, then a variation order must be asked for by
the Contractor to distinguish the work from that payable at contract bill rates.
@VTC2013 - Page 8 of 8 -