Greeff Maintenance (2009)
Greeff Maintenance (2009)
Greeff Maintenance (2009)
Albert Greeff
25081439
in the
University of Pretoria
Pretoria, South Africa
November 2009
Why build a Model?
i
Abstract
ii
Contents
Abstract ii
1 Introduction 1
1.1 Background of BHP Billiton . . . . . . . . . . . . . . . . . . . . . 1
1.2 Introduction of the Problem . . . . . . . . . . . . . . . . . . . . . 2
1.2.1 Klipspruit Colliery . . . . . . . . . . . . . . . . . . . . . . 2
1.2.2 Warranty Service . . . . . . . . . . . . . . . . . . . . . . . 2
1.3 Project Aim . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3
1.4 Simulation Modelling . . . . . . . . . . . . . . . . . . . . . . . . . 4
1.5 Project Question . . . . . . . . . . . . . . . . . . . . . . . . . . . 4
1.6 Project Methodology . . . . . . . . . . . . . . . . . . . . . . . . . 5
1.7 Document Structure . . . . . . . . . . . . . . . . . . . . . . . . . 5
2 Literature Review 6
2.1 Maintenance Scheduling . . . . . . . . . . . . . . . . . . . . . . . 6
2.1.1 Breakdown of Maintenance . . . . . . . . . . . . . . . . . 6
2.2 Technique . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 8
2.3 Conceptual Simulation Model For Maintenance Systems . . . . . 8
2.3.1 Input and Maintenance Load . . . . . . . . . . . . . . . . 9
2.3.2 Planning and Scheduling . . . . . . . . . . . . . . . . . . . 9
2.3.3 Sub Models . . . . . . . . . . . . . . . . . . . . . . . . . . 10
2.4 Generic Klipspruit Colliery . . . . . . . . . . . . . . . . . . . . . 11
3 Data Preperation 14
3.1 Conceptual Model . . . . . . . . . . . . . . . . . . . . . . . . . . 14
iii
3.1.1 Method . . . . . . . . . . . . . . . . . . . . . . . . . . . . 14
3.1.2 Normal Day-time Service . . . . . . . . . . . . . . . . . . 15
3.1.3 High-Priority Service . . . . . . . . . . . . . . . . . . . . . 16
3.1.4 Availability of Parts . . . . . . . . . . . . . . . . . . . . . 16
3.1.5 Quality Control . . . . . . . . . . . . . . . . . . . . . . . . 16
3.1.6 Breakdowns . . . . . . . . . . . . . . . . . . . . . . . . . . 16
3.1.7 Earth Moving Equipment . . . . . . . . . . . . . . . . . . 17
3.1.8 Theoretical Model . . . . . . . . . . . . . . . . . . . . . . 17
3.1.9 Earth Moving Equipment Process . . . . . . . . . . . . . 18
3.2 Computer Model . . . . . . . . . . . . . . . . . . . . . . . . . . . 18
3.2.1 Creation . . . . . . . . . . . . . . . . . . . . . . . . . . . . 19
3.2.2 Service Decisions . . . . . . . . . . . . . . . . . . . . . . . 20
3.2.3 The Mine . . . . . . . . . . . . . . . . . . . . . . . . . . . 20
3.2.4 Workshop Queueing Conditions . . . . . . . . . . . . . . . 21
3.2.5 Workshops . . . . . . . . . . . . . . . . . . . . . . . . . . 24
3.2.6 Breakdowns . . . . . . . . . . . . . . . . . . . . . . . . . . 25
3.2.7 Availability of Parts . . . . . . . . . . . . . . . . . . . . . 25
3.2.8 Resource Scheduling . . . . . . . . . . . . . . . . . . . . . 26
3.3 Output . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 27
3.4 Influential Factors . . . . . . . . . . . . . . . . . . . . . . . . . . 27
5 Conclusion 32
A Appedix A - Figures 33
B Appendix B - Arena 36
Bibliography 37
iv
List of Figures
v
List of Tables
vi
Chapter 1
Introduction
1
1.2 Introduction of the Problem
One of the most important parts of buying an EME is acquiring an after sale
agreement that includes a warranty for the equipment, which is only applicable
to an EME if a service is conducted every 250 worked hours. The supplier offers
a lenient gap of 50 hours for the service to be conducted before the warranty
becomes obsolete.
2
Service Scheduled Hours Duration of
Numbers of Machine Service(Hours)
1 250 5
2 500 5
3 750 4
4 1000 8
5 1250 4
6 1500 5
7 1750 4
8 2000 48
The warranty is of fundamental importance to the mine, thus the Earth Moving
Machine (EMM) will be relieved of working duty if it approaches the 50 hour
gap deadline. The service time differs depending on the amount of hours that
an EME has worked. The different times for services are shown in table 1.1.
3
ductive and thus increase the productivity of the mines individual output. The
optimisation can be done by integrating the data of the Middelburg mine with
the Arena simulation program to find a optimal solution. A more productive
maintenance program results in less vehicles to queue and this will in turn result
in a bigger workforce on site, as well as equipment warranties that last longer
due to better scheduling of work.
If simulation is optimal and the workshop does not deliver sufficient results,
mathematical optimization should be used to determine the amount of services
to be outsourced in order to create a profitable workshop that contributes to
the efficiency of the mine.
4
1.6 Project Methodology
By executing the projects aim, the main deliverable is a working simulation
model of the EME workshops which is applicable to the Klipspruit colliery. The
document will show different scenarios of the workshop, of which changes will
be made to assigned number of bays and working hours.
The EMEs will only be affected by the service time, the amount of bays (assigned
to different types of EMEs) and unavailability of parts. Areas which are not
considered but may have an influence on the real-life situation is man-power
availability, working enthusiasm and travel time from the mine to workshop.
It should also be noted that the simulation study only focuses on the tyre based
vehicles as this is the type which has the greatest possibility to create bottle
necks. When the simulation is finished track based vehicles will be integrated
into the simulation to verify the decisions regarding the variable aspects.
Assuming that each week has five working days, of which all are worked every
week, and two days for a weekend (where only the mine is operational and not
the workshop) the simulation follows a fairly trivial flow. Entities are created
and move towards the mine. This is a seven day schedule and entities are only
directed towards the workshop when their service is due. After the workshop is
completed the entities return to the normal schedule of working on the mine.
The simulation will use mathematical distribution to determine the time values
for each process. These distributions are computer generated with the time-
study values as inputs.
5
Chapter 2
Literature Review
6
factor that determines productivity. Studies have shown that without mainte-
nance scheduling productivity of workers reached an estimated average of 40
percent. Due to this fact certain maintenance policies exist, which are covered
in the next section(Paz and Leigh, 1994).
Maintenance Policies
2. Policies for reducing the severity of failures are further devided into:
7
2.2 Technique
Due to the complexity that the Klipspruit model leads to when using mathe-
matical programming, simulation modelling will be used. Simulation modelling
will provide the opportunity to reconstruct the model towards a more complete
and optimized answer. Mathematical scheduling will require a program that
uses complicated mathematics to obtain an answer that requires editing.
The simulation model can also be repeated with different inputs and will require
that the optimal situation be determined by inspection. The amount of differ-
ent factors that constrains a mathematical programming problem can cause
this amount of optional answers to exceed a million. Thus, with the use of a
generic model for maintenance systems that is reviewed in the following section,
the Klipspriut Collieries maintenance problem will be solved using simulation
modelling.
maintenance load
maintenance resources
8
Maintenance interacts with many different areas of a business whether support-
or main-function. Figure 2.1 (page 10) indicates how maintenance interacts
with its own support functions as well as how maintenance interacts with the
rest of the organisation. The maintenance function has a continuous feedback
and improvement function in maintenance planning as well as in its interaction
with the rest of the organisation. It is also important to take note of the priority
listing of entities which serves as a constraint.(Duffuaa et al., 2001)
Maintenance scheduling is divided into different sections, of which the critical
areas are analysed.
9
2.3.1 Input and Maintenance Load
1. The maintenance load is the starting point of this process. The first
step differs, depending on whether the type of maintenance is planned
or unplanned. The crew size, mix and priority are known for planned
maintenance as well as the entitys priority. The same data is generated
for the unplanned maintenance with a probability distribution.
4. The job ordered is prepared and scheduled if the resources are available.
10
Planned Maintenance Unplanned Maintenance
Maintenance Load
Crew mix, size and trade Generate crew mix, size and
Schedule job
Execute job
11
6. The quality of the job is checked by using the quality module. If the
quality of the job does not meet the required standard the entity is sent
back for the job to be repeated. The data is recorded for performance
measures(Duffuaa et al., 2001).
The tools and equipment as well as materials and spares are sub models of the
base of the simulation. These modules check the availability of the specifc area.
If this item or area is not available, the execution of the model is delayed until
it becomes available.
The quality module is also a sub model but if the quality is not up to standard
the entity is redirected to be serviced again. This process is displayed in Ap-
pendix A.
Performance measures are put in place to analyse the system and to ensure that
continuous improvement occurs. The performance measure can be divided into
three parts, namely:
Maintenance effectiveness
Maintenance administration
12
Chapter 3
Data Preperation
3.1.1 Method
The first step in creating the conceptual model is to obtain enough information
from the management of the colliery to get an overview of the current oper-
ations. The current practises were understood by conducting site visits and
conducting interviews with the designers and the engineers working on the col-
liery.
A baseline for the conceptual model was constructed and approved by the man-
agement. The baseline was refined and improved through prolonged research
and brainstorming(Snyman,2008).
The output of the simulation will identify congestion of entities at key areas.
Some of these areas are the normal day time- and high-priority services, quality
control, breakdowns and parts availability.
13
Start
Construct the simulation model Specification of variables, parameters, decision rules and
probability distributions.
Specify values of variables and Determination of starting conditions and run length
parameters
Propose changes
Stop
(Snyman, 2008)]
This area is the collierys main workshop and all earth moving equipment is
scheduled to move through this workshop. The workshop runs on ten-hour
shifts where operations commence daily at 5 am. The 10 hour shifts will be
extended until the last service of the day is completed.
EMEs (Earth Moving Equipment) are flagged every 250 hours to advance to
the workshop in order to undergo a mandatory warranty service. These services
vary in length from 4-, 5-, 8- to 16 hours.
The warranty of the EME allocates a 50 hour gap for the services to be com-
pleted. If EMEs approach the workshop and the queue for that current day is
full they are transferred back to the mining pit to continue work and will then
be called in for service the following day. If the EMEs are not serviced before
14
the gap is reached they are removed from active service and are placed on a
high-priority waiting list to be serviced.
These high priority EMEs will be serviced before any of the normal day time
services are performed. The high priority service is conducted within the same
workshop as the normal day time service.
Due to human error and deviations from planned situations, parts for services
are not always available. In this case the servicing of the EME that is queued for
service is placed on halt while the unavailable parts are delivered. The EME for
servicing which is delayed, does not occupy a bay, thus service of other EMEs
continues as scheduled.
To keep the mine working at an efficient rate the quality of a sample of the ser-
vices should be inspected. If the quality of the sample does not meet acceptable
standards the services have to be repeated. A vehicle that fails the quality test
is not marked as high priority, due to its ability to work if there is still time
remaining on the warranty gap. Therefore, the destination of a vehicle which
fails the quality test depends on the amount of hours that the vehicle has been
in use.
3.1.6 Breakdowns
15
and resource allocation in the workshops. Breakdowns do not have their own
allocated workshops, thus these repairs are also done in the normal day-time
service workshops. The field service is not done within a workshop so the delay
only impacts the relevant EME and not the rest of the mine.
Only certain amount of the EMEs that are delivered for servicing are critical
to the working environment and the efficiency of the mine. These EME will be
referred to as the critical load, while the rest of the EMEs will be referred to as
the mass load.
The simulation will mostly deal with the critical load as its services and down-
time impacts on the efficiency of the mine. The model simulates the tyre based
EMEs as these are the largest in number.
As the efficiency of the mine is determined by the amount of coal that the
colliery can produce, the efficiency of the EMEs will be the determined by the
amount of coal that can be transferred in a certain time frame. To ensure that
the workshop contributes to the efficiency of the mine it has to service vehicles
in the shortest possible time and highest quality manner possible in order to
avoid congestion in the workshop.
To ensure that our model mirrors reality as closely, possible time studies will
have to be done on the following aspects:
16
unavailability of parts
quality-test failure
For the purpose of this study, a tallied hour rate will be used for the tyre-,
lubrication- and mechanical services. This rate will be the assigned rate of 4-,
5-, 8- or 16 hours.
The time it takes one EME to travel between the mine and the workshop is not
taken into account as the mine and the workshop is situated very close to one
another.
17
Creation Assign start up Due for Assign service Maintenance
values service? time Process
3.2.1 Creation
All the entities are created in 12 different create nodes which are combined into
one module on Figure 3.2. Different quantities of tyre-type vehicles are created,
of which the Caterpillar 777 has the most entities. The quantity of each entity
can be seen in Table A.1 in Appendix A.
The entity will move towards an assign node. There are two attributes assigned
to each entity namely:
Worked hours: All the EMEs will be assigned a value from a mathematical
distribution in order to determine the amount of hours that the EME has
already spent on the mine. All attributes are assigned in values between
0 and 250, representing the number hours prior to the first mandatory
service.
The assumption that EMEs have different work levels has to be made in
order to exclude poor resource utilisation and to bring the model closer
to reality.
18
3.2.2 Service Decisions
All the entities that have been created are sent through a decide node. The de-
cide node has two directions, according to the parameters that were assigned
by the previous module, to which the entities are sent. The EME can be sent
to the mine or to the workshop in order to be serviced. Table 3.1 on page 18
depicts the parameters for which an entity is sent for service.
If the worked hours for the EME fall between the stated values and the service
level is as indicated then the entity will be directed to the workshop, otherwise
it will be directed to the mine.
The simulation for the mine is very trivial and forms part of the model as a sub
model. As the entities enter the sub model, labelled Daily Work Process (Fig-
ure 3.2 page 18), they arrive at a process node, which determines the amount of
work that the EME does that particular day. This is done by using a random
distribution. There is no queue at this process.
Following the process node is an assign node to update the worked hours at-
tribute. The amount of hours that the EME spent on the mine is added to this
attribute. The EMEs exit the sub model and approach the breakdown decide
node.
This node decides if a breakdown occurred. This choice is made by probability
19
- in other words, it is achieved by analysing historical data. If the EME suffers
a breakdown it is moved to the breakdown sub model. Alternatively it is sent
back to the Service Decide-node.
If the entitys attributes fall within one of the parameters specified in Table 3.1
(page 19), the EME will move towards the workshop to be serviced.
The assign nodes, labelled Assign Service time, introduce a new attribute
towards the entity, mainly the service duration. The value assigned to this
property depends on the level of service (from level 1 to level 8) that the entity
requires. The service duration varies between four hours and two days. Table
1.1 (page 3) indicates the different service durations.
The assign nodes connect to a sub model labelled Maintenance Process. Figure
3.3 (page 21) provides a view of the layout of this sub model. There are mainly
three different results that can occur as entities move through this sub model.
There is only one set of requirements to enter an entity into this queue. The
first node is a decide node which determines the total value of all the service
times in the queue of all the workshops. If this value is more than 10 the entity
will bypass the first workshop-option, as the queue for that day is already full
and the entity will not be service on that particular day. To enter the Normal
Day workshop queue the sum of the value must be less than ten.
Another decide node follows, which stipulates that the time of arrival must be
between 5am and 3pm to enter the Normal Day workshop queue, thus the entity
arrives in the given window.
The final decide node that the entity must pass in order to enter the specific
workshop determines whether the current day falls on a weekday as the workshop
is not active on weekends. If the entity complies with this parameter it will be
included in the Normal Day workshop queue. Table 3.2 (page 22) summarises
the conditions for entry into the Normal Day queue.
20
Is Is Queue Is it a Required Normal priority
M.P
workshop length < weekday? parts Maintenance is
open? 10? available? done
21
Wait for parts
High-Priority Queue
There are three ways of entering this queue. As the entity arrives at the first
decide node the sum of the service times of the queue length can be less than
10 to send it to the next decide node, which depends on the time at which the
entity arrives at the workshop - this can also be in the time window. If the
entity enters the final decide node either on a Saturday or on a Sunday the final
condition will be true (if this was a weekday it would be identical to the first
case and it would qualify for the normal week day queue).
Meeting the above conditions will send the entity to the decide node named
Warranty expire node. This node examines the amount of time that is left on
the warranty gap before it becomes obsolete. If the value is less than 20 the EME
is taken out of service and placed in the high priority queue. This workshop
will service its load before servicing the normal work day load. Therefore the
entity should have a gap value of less than 20 hours to access this queue.
The second and third sequences of conditions to enter the high priority queue
are listed in Table 3.3 (page 23). An entity must be directed away from the first
workshop and should have a gap value of less than 20 hours.
The three conditions that were stipulated for the high priority queue are the
same conditions that the entity has to meet in order to bypass all the queues
and continue work on the mine. The only difference is that the warranty gap
should be in excess of 20 hours. The warranty expire decide node will send the
entity back to the mine. Table 3.4 (page 24) summarises these conditions.
22
Condition Yes or No
First Condition
Queued entities service time less than 10 hours? Yes
Arrival time between 5 a.m. and 3 p.m? Yes
Arrival on Saturday or Sunday Yes
Worked hours within 20 hours of the expire value? Yes
Second Condition
Queued entities service time less than 10 hours? Yes
Arrival time between 5 a.m. and 3 p.m? No
Worked hours inside 20 of the expire value? Yes
Third Condition
Queued entities service time less than 10 hours? No
Worked hours within 20 hours of the expire value? Yes
3.2.5 Workshops
The entities will enter the workshop and will be serviced according to the service
duration attribute that is assigned to them. As there are only two workshops
(starting model) the high-priority queues load will be serviced first and then
the normal day-load. If the entity receives a two day service the process will
be reset and the scheduled services will be repeated from one to eight at the
appropriate time.
3.2.6 Breakdowns
When an EME leaves the mine and the breakdown decide node indicates that a
breakdown has occurred the entity would move to a sub model labelled Break-
down workshop.
Figure 3.4 (page 25) displays a flowchart of the sub model. The first module is
a decide module that uses a random distribution to indicate if the repair can be
done in the field or if the entity should be sent to the workshop.
If field service can be performed a hold entity is put in place to delay the entity
under review. For this service no resource that is of importance is used.
23
Conditions Yes or No
First Condition
Queued entities service time less than 10 hours? Yes
Arrival time between 5 a.m. and 3 p.m? Yes
Arrival on Saturday or Sunday Yes
Worked hours inside 20 of the expire value? No
Second condition
Queued entities service time less than 10 hours? Yes
Arrival time between 5 a.m. and 3 p.m? No
Worked hours inside 20 of the expire value? No
Third condition
Queued entities service time less than 10 hours? No
Worked hours within 20 hours of the expire value? No
When the entity has to go to the workshop, the highest priority is assigned to
the entity and it is placed in the relevant queue. When the entity is repaired no
value changes are made to any of the attributes as it was not a warranty based
service.
Before an entity moves into a queue the necessary parts for repair should be
available. With the use of a decide node, which uses a random distribution,
parts availability is checked. If the parts are not available the servicing of the
entity is delayed until the parts arrive. This is applicable to the Normal Day
queue, the High Priority queue and the Breakdown queue, as well as to field
service.
The workshop entities run on two schedules, namely Normal Day schedule and
Graveyard schedule. On a Normal Day schedule two workshops are available
from 5am to 3pm or until the work load for the day is completed. This schedule
24
Should EME Required High priority
B.P be brought to B.P
parts Maintenance is
workshop for
service? available? done
3.3 Output
The simulation model for the Klipsruit Colliery runs for a year. When the
simulation is complete, statistical data is generated, at which point entity-,
queue- and resource data is available. The most important data gathered is:
25
the amount of entities taken out of service due to warranty expiry
The desired output of the model should minimise all of the above mentioned
values. The EMEs should move through the workshop while minimising the
length of the queue. The High Priority queue should not take any entities out
of service due to warranty issues and parts availability should improve.
The factors that in influence the model that take the form non-variable data
are:
service times
resource availability.
26
Chapter 4
The Klipspruit Colliery will first be simulated in the way that management
proposed the implementation of the maintenance workshop. This simulations
results will be compared to other simulations of the collierys working with
different variable data, which will provide management with a few different
options, as they should decide what is feasible. Arena simulates the colliery
for a year and this simulation is repeated ten times in order to generate an
acceptable average.
27
4.2 Distribution of Bays
Of the forty EMEs on the Klipspriut Colliery twelve are track-based and the
rest are tyre based - thus, a different distribution of work bays is the next sim-
ulation that will be investigated. If the simulation has a distribution of 3:1 for
tyre based EMEs the average waiting time in the queue is less. The workshop
has a through put of 392 entities, of which 157 are high priority and will be re-
moved from the mine. This is more than the management proposal but overall
it proves an improvement of productivity for the workshop.
Due to this change the mine increased the amount of shifts that workers worked
with 33 percent which will lead to more coal being mined, and to a more prof-
itable organisation. The increase in shifts that the mine operates on is the
reason why the number of High Priority entities increased.
The one bay of track EMEs will cause a small amount of drag but the system
will be more efficient with the bays divided in the same ratio as that of the
EMEs.
With the workshop running 16 hour shifts it will have to be divided into two
shifts. This will result in bigger salary expenses but the average waiting time for
a service will be lower than the current design. A massive 393 services occurred
during the year of which only 57 were high priority services. The number of
shifts that were worked during the year were 6960, which is less than the three
bay simulation.
This option results in increased expenses but proves a feasible productivity.
28
4.3.2 Weekend Work
The mine is currently working on a 24-hour shift, seven days a week, while the
maintenance workshop is only working 10 hours a day five days a week. If the
workshops are extended to seven days a week the improvement to throughput
is conciderable. A total of 476 entities are serviced of which only 19 is removed
from service and 136 are sent back to the mine without service. This equals
a productivity increase of 78%. The mine will have a 12% increase in shifts
compared to the management proposal.
By extending the work through weekend it is important to remember that ad-
ditional cost such as over time payment for maintenance workers will have to
be included in the budget.
If the weekend work is extended to 16 hour shifts, the model will be more
productive but the expenses increase more than the productivity does.
29
Chapter 5
Conclusion
30
Appendix A
Appedix A - Figures
31
Quantity Mode Description
2 D11T Track Type Tractor
1 D10T Track Type Tractor
3 PV275 Overburden Drills
2 EMC720 Atlas Copco EMC 720 Drill Rig Coal Drill
1 834H Wheel Dozer
4 993k Wheel Loader(Front end Loader)
12 777F Off-Highway Truck(Haul Truck)
2 16M motor Grader
1 422 Backhoe Loader
1 988H Tyre Handler
1 988H Cable Realer
2 246B Bobcat
1 CAR740 Water Tanker
2 CAT740 Diesel Tanker
2 Massey Ferguson Tractor
1 UE 150 Tonne Lobed
1 CAT IT 14 G Integrated Tool Carrier
1 CAT TH 414 Telescopic Handler
32
Q
R form U (0;1)
r < Pq
End
33
Appendix B
Appendix B - Arena
Arena uses generic flow chart modules to illustrate the process that is simulated.
The EMEs in the simulation are entities and they move between modules or
nodes. These entities are created in a Create-module. This module can edit the
distribution in which entities are created, the time between entity arrival and
the names of the entities.
The entity would then move from the creation node to the module connected
to it. This can be any module except a Dispose-module. The dispose module
is used to take the entity out of the simulation - this is normally the final part
of the simulation. The current simulation doesnt use a dispose node as all the
vehicles stay on the mine and it is important to update a vehicles properties
regarding the model as its time spent on the mine increases.
A decide node is used to execute decisions. This can be done either by chance
or by condition. The decide node consists of the ability to provide the user with
two or more options.
In the simulation of the Klipspruit colliery an assign node follows the create
node. An assign node has the ability to assigns entity pictures, attributes, vari-
ables and the type of entity.
A process model is one of the most important modules in the simulation model
as this is the module that uses resources to process the entities. The dura-
tion, resource and delay type can be assign. A schedule to determine the re-
sources working hours can be defined and the amount of resources utilised can
34
be changedcite.
The hold entity is nearly the same as the process entity due to the fact that it
occupies the entity for a specified period of time. This time delay value can be
changed. A Record node captures the data, at a specified point in the model.
All the above mentioned modules are shown in Figure3.
35
Cre a te tri p l e 7 s ta rt u p v a l u e s 1
0
1 2 6 s e rv i c e s
Cre a te fro n t e n d
loader s ta rt u p v a l u e s 2
s erv ic e or no s erv ic e
0
3 5 7 s e rv i c e s
Cre a te m o to r g ra d e r Else
s ta rt u p v a l u e s 3 wo rk s h o p fo r n o n
b re a k d o wn s
0
4 s e rv i c e 0
Cre a te wh e e l d o z e r s ta rt u p v a l u e s 4
0
pit
c re a te b a c k h o e
loader s ta rt u p v a l u e s 5 8 s e rv i c e
0 0
36
Cre a te ty re h a n d l e r s ta rt u p v a l u e s 6
0
0
Tr ue wo rk s h o p fo r
Break down b re a k d o wn s
Cre a te wa te r ta n k e r s ta rt u p v a l u e s 7
0 0
0 Fals e
Cre a te 1 d i e s e l
ta n k e r s ta rt u p v a l u e s 8
DeepSA (2008). A celebration of the south african mining industry. Deep SA,
pages 124125.
Snyman, V. (2008). Sasol Crude Oil Pipeline study. PhD thesis, University of
Pretoria.
37