Berkeley Associates
Sub-Consultants:
ILF Pakistan (Pvt) Ltd. ESUPAK, UET, Lahore NCEG, Peshawar HEC Peshawar
300 MW Balakot Hydropower Project
Feasibility Study Report
Executive Summary
LIST OF VOLUMES
EXECUTIVE SUMMARY
VOLUME - 1 MAIN REPORT
VOLUME - 2 DESIGN CRITERIA (CIVIL, ELECTRICAL, MECHANICAL)
VOLUME - 3 TOPOGRAPHIC AND HYDROGRAPHIC SURVEY REPORT
VOLUME - 4 HYDROLOGY AND SEDIMENTATION STUDIES REPORT
Vol. 4-1/2 - Report
Vol. 4-2/2 - Annexure
VOLUME - 5 NEO-TECTONIC AND SEISMIC HAZARD ANALYSIS
VOLUME - 6 GEOLOGICAL AND GEOTECHNICAL STUDIES
EXECUTIVE SUMMARY
1 INTRODUCTION
Balakot Hydropower Project (HPP) is one of the series of hydropower
development projects launched by PHYDO (Pakhtunkhwa Hydel Development
Organization), Government of Pakhtunkhwa (KP). The objective of the proposed
hydropower scheme is to generate and add cheap energy to the system in order
to meet the current shortfall and increasing demand of electricity in the region
through economical and sustainable means.
Montreal Engineering Company (MONENCO),a Canadian Consulting Engineering
Organization, identified three hydropower projects on Kunhar River, namely Naran,
Suki Kinari and Patrind in 1984. Balakot HPP was identified in 1995, under the
study Identification of Hydropower Potential in Kaghan Valley by Sarhad Hydel
Development Organization (SHYDO) with the technical collaboration of the
German Agency for Technical Cooperation (GTZ) as a 190 MW HPP. The project
envisaged a 140 m high dam with a 4.5 km long intake tunnel and an
underground powerhouse. The dam axis was, identified 9 km upstream of Balakot
town, headrace tunnel on the left bank and the powerhouse near the confluence
of Sangarh nullah with Kunhar River.
PHYDO carried out ICB in 2011 for the selection of Consultant to carry out
detailed Feasibility Study of the Project. As a result of competitive bidding, the
Consortium of Consultants led by Mirza Associates Engineering Services (Pvt.)
Ltd. (MAES) and consisting of ILF Beratende Ingeniere ZT GmbH, Innsbruck,
Austria and Berkeley Associates, Pakistan, had been selected for implementation
of the Feasibility Study of Balakot HPP. The Consultants carried out services for
eighteen months and prepared this bankable Feasibility Study Report of the
Project.
The Study has resulted in a project size of 300 MW with an excellent economic
rate of return. Table -1 presents the salient features of the Project. Balakot dam
and powerhouse have been proposed on the 9 km stretch of the intermediate part
of 20 km reach of Kunhar River from Paras to Sangarh Village. The dam site on
Kunhar River is 03 kilometer downstream of Paras village, and 17 km upstream of
Balakot town main bridge. The powerhouse is to be located on the left bank of
Sangarh nullah confluence with Kunhar River, 1 km upstream of Dabrain village
and 8 km upstream of Balakot main bridge. The whole project layout including the
headrace tunnel is proposed on the left bank of Kunhar River. (Drawing BLK-CS-
GEN-DWG-001).
Table - 1: Salient Features of the Project
HYDROLOGY (DESIGN FLOWS)
Catchment area at dam site 1952 km2
Mean annual flows 87.3 m3/s
Design discharge 154 m3/s
Design flood (10,000 Year Flood) 5312 m3/s
Probable maximum flood 5702 m3/s
Maximum flood level 1290 m.a.s.l
300 MW Balakot Hydropower Project
Feasibility Study Report
Executive Summary Page -2
RESERVOIR
Reservoir length 4,500 m
Reservoir area 0.555 km2
Max. reservoir operating level 1288 m.a.s.l
Min. reservoir operating level 1283 m.a.s.l
Reservoir capacity at 1288 m.a.s.l 12.606 MCM
Reservoir capacity at 1283 m.a.s.l 10.040 MCM
DAM STRUCTURE
Dam height above riverbed and Foundation level 78 m, 24 m
Dam crest level and length 1293 m.a.s.l, 250 m
Dam Type Concrete gravity
DIVERSION TUNNEL
Length of diversion tunnel 400 m
Size of tunnel (W x H) 10 x 12 m
SPILLWAY
Gated surface spillway
Number and type of gates 5 (Five), Radial gate
Gate Size 10.5 m x 12 m
Discharge capacity 5745 m3/s
Spillway crest / sill level 1276.0 m.a.s.l
LOW LEVEL OUTLETS/ FLUSHING SLUICES
No. of outlets 3 (Three)
Gate type Vertical lift gate
Gate size (W x H) 4x5m
Discharge capacity 1721 m3/s
Sill level of flushing sluices 1217.0 m a s l
POWER WATERWAYS
POWER INTAKE
Type Lateral intake
No. of gates 1 (one)
Gate size (W x H) 8x8m
Deck elevation 1293.0 m.a.s.l
Sill level of intake racks 1264.0 m.a.s.l
LOW PRESSURE HEADRACE TUNNEL
Diameter 8.0 m
Length 8420 m
SURGE SHAFT
Diameter 12 m
Height 80 m
300 MW Balakot Hydropower Project
Feasibility Study Report
Executive Summary Page -3
The survey had been carried out in one uniform system of co-ordinates and
elevations using S.O.P. Benchmark at Batrasi as datum. All survey work was then
duly verified through GPS.
Following scales with contour interval of 2m have been adopted for the survey
maps of the project:
I. Reservoir area, Headrace Tunnel / Channels, Access Roads 1:2000
II. Dam Site and Intake Area 1:500
III. Surge Tank, Pressure Tunnel/Penstock,
Powerhouse and Tailrace 1:1000
IV. Project Layout 1:25,000
The terrestrial survey has been carried-out for the three (3) alternative project
layouts conceived and selected for field work at the Inception Stage and covers all
the above mentioned project components.
For the inaccessible areas of the tunnel alignments, topographic maps have been
developed with the help of high resolution Digital Elevation Models (DEM), ortho-
rectified with ground survey.
Hydrographic survey was carried out and longitudinal profiles of the relevant
stretch of Kunhar River were prepared.
3 HYDROLOGY AND SEDIMENTATION STUDIES
The Project has a catchment area of 1952 Km2 up to the dam site. Mean annual
flows estimated for the Garhi Habibullah stream gauging station, dam site and
powerhouse site are 102.3, 87.3 and 94.1cumecs, respectively.
The recommended flood magnitudes corresponding to 10,000 year return period
for the dam and powerhouse sites are computed as 5312 and 5745 cumecs,
respectively. The computed PMF at the dam site is 5702 cumecs.
Average annual total sediment inflow to the dam site is 2.714 MCM (2201 AF).
Average annual trapped sediment load at the dam site is 1.1 MCM (892 AF).
Optimum discharge to carryout efficient flushing of the reservoir is computed as
150 to 350 cumecs, with flushing duration of 11.25 to 2.5 days, depending on the
flow available and amount of deposited sediments. The life of the reservoir can be
enhanced to about 40 years with appropriate flushing operations once a year
during June or July, and annual monitoring of sediment delta. Construction of Suki
Kinari reservoir would further extend the life of Balakot reservoir from 40 to 50
years. Further enhancement in life of reservoir can be achieved, by adopting
appropriate watershed management measures.
Dam breach analyses for PMF shows that the generated flood peaks between the
dam and powerhouse sites indicate no chances of flooding of the downstream
settlements.
4 NEO-TECTONIC AND SEISMIC HAZARD ANALYSES
The region encompassing the Balakot HPP is highly complex in terms of its
tectonic set up.
The estimated seismic hazards in terms of peak ground acceleration (PGA) with
10% probability of exceedance in 50 years i.e., 475 year return period as
300 MW Balakot Hydropower Project
Feasibility Study Report
Executive Summary Page -5
computed by different workers for Kaghan, range between 0.09 and 0.7 with the
recommended value as 0.38.
Kashmir Earthquake (2005) of M 7.6was the major event in Kaghan valley. This
earthquake generated very high isoseismal MMI intensities of XI at Balakot, while
intensities as high as VII were recorded near Naran and VI at Batakundi.
Based on the standard MMI to PGA conversion models, the intensities generated
by this earthquake yield PGAs of 0.8-0.9 for the project site.
4.1 Seismic Design Parameters Based on Deterministic Seismic Hazard
Assessment (DSHA) Approach
According to ICOLD (2010), DSHA is used for assessment of Maximum Credible
Earthquake (MCE), and PGA values for both 50-percentile (median) and 84-
percentile (mean plus one standard deviation) are listed.
For the dam site, at GMPE with 84-percentile value, seven of 12 identified faults
are capable of generating PGA >0.5g. The maximum PGA is expected from
Panjal Fault (Segment 4) that passes close to the dam site with a value of 0.71g.
For the powerhouse site, at GMPE with 84-percentile value, 5 of 12 faults
(Balakot-Bagh Fault, Panjal Fault VI, Kaghan Fault, Indus-Kohistan Seismic Zone,
and Combined Balakot-Bagh-Indus Kohistan Seismic Zone) generate PGAs >
0.7g,which is close to PGA generated by the Balakot-BaghFault in the M 7.6 2005
Kashmir Earthquake. Therefore, for the Project, MCE is defined by a ground
motion of 0.79g.
4.2 Seismic Design Parameters Based on Probabilistic Seismic Hazard
Assessment (PSHA) Approach
Ground motion parameters for return periods from 200 to 10,000 years for
appropriate selection as the MDE design parameters corresponding to PGAs of
0.24 to 0.74g for the dam and 0.24-0.73g for the powerhouse have been included.
However, considering the seismic history of the Balakot area, it is recommended
that the ground-motion parameters for the MDE may be selected for 1000 year
return period as a minimum and 10,000 year as the maximum.
The OBE may be expected to occur during the lifetime of the structure. No
damage or loss of service is allowed. It has a probability of occurrence of about 50%
during the service life of 100 years. The return period is taken as145 years
(ICOLD 2010). The OBE ground motion parameters are estimated based on
PSHA. For the Project 150 year return period has been recommended for
selection of the OBE ground-motion parameters, which corresponds to 0.24g for
the project.
5 GEOLOGICAL AND GEOTECHNICAL STUDIES
The field work for the Project comprised surface geological mapping including
scan line surveys, geophysical survey using seismic refraction method, drilling of
boreholes, coring and logging, performance of permeability and water pressure
tests and excavation of test pits at potential construction material sources.
A total of 20 scan line surveys and 7 profiles of seismic refraction survey, were
carried out at the dam/ intake area, headrace tunnel, powerhouse etc.
300 MW Balakot Hydropower Project
Feasibility Study Report
Executive Summary Page -6
For collection of the soil/ rock samples and to perform in-situ tests,22 boreholes
were drilled at the proposed structure locations, with total drilling depth of 2768 m.
Test pits were also excavated at various structure locations for verification of the
extent of overburden and physical inspection of its nature at the site. Some other
pits were excavated in prospective borrow areas for evaluation of the construction
materials i.e. coarse as well as fine aggregate, and cohesive material.
Suitability of the potential construction material sources has been examined
through laboratory testing of representative samples.
The project area is located in rocks belonging to Murree Formation of early
Miocene age, which consists of sandstone and siltstone, mudstone/shales and
lenses of conglomerates. These rocks are exposed at the dam and powerhouse
areas in alternate beds. Structurally, the formation shows a high degree of
compression in the form of tight folding with repeated faulting and fracturing.
On the basis of observed RQD values, the bedrock can be classified as Very
Poor to Excellent with a very wide range of core recovery from 0 % to 99 %.
In the light of data collected and analyses carried out, the rock mass design
parameters were determined for various components of the project, and used for
evaluating the stability as well as foundation design parameters for the various
structures. For the underground structures i.e. headrace tunnel, surge shaft,
powerhouse caverns and tailrace tunnel, stability analyses and design of support
systems have been carried out.
6 DESIGN CRITERIA (CIVIL, ELECTRICAL AND MECHANICAL)
A design criteria is necessary for setting out the guidelines/ basis of all designs
and field operations necessary for preparing the Feasibility Report. The design
criteria document for Civil, Electrical and Mechanical works has been prepared,
which covered all the aspects of design and field operations.
7 PROJECT LAYOUT STUDIES
The Consultants identified two alternative dam sites in addition to the previously
identified site by PHYDO/GTZ(Drawing BLK-GE-DWG-001).Based on the
parameters for screening viz: good topographical, hydrological and geological
conditions and minimal environmental issue etc, the dam site selected is located 2
km upstream of Kewai nullah confluence. At the selected dam site, the valley
sections are narrow at the upstream cofferdam, downstream cofferdam, diversion
tunnel, main dam, plunge pool and power intake area.
Two powerhouse sites (P-1B, P-1C) in addition to and in close vicinity of the site
identified by PHYDO/GTZ were investigated, which indicated poor geological
structure along the depth, and were rejected as unsuitable for underground
powerhouse. An alternative powerhouse site P-2 some 2.5 km upstream of
Sangarh village was found to have better geological structure for the surge tank,
pressure shaft and the underground powerhouse. Necessary investigations were
conducted to confirm the location of the underground structure at the powerhouse.
The selected layout has relatively smaller dam, longer tunnel and a reservoir with
adequate storage for daily peaking.
300 MW Balakot Hydropower Project
Feasibility Study Report
Executive Summary Page -7
energy, for years 1998 (average year), 1992 (wet year) and 2001 (dry
year), is 1212.38, 1653.12 and 743.64 GWh respectively.
9 DAM AND OTHER HYDRAULIC STRUCTURES
Hydraulic analysis and sizing of the Project structures, has been carried out to the
feasibility level for the following structures:
a. Main Dam
b. Power intake structure on the left bank of the river
c. Low pressure headrace tunnel
d. Surge tank
e. Steel lined vertical pressure shaft
f. High pressure tunnel/penstocks
g. Underground powerhouse with transformer cavern.
h. Free flow tailrace tunnel
9.1 Main Dam
A concrete gravity dam has been planned and designed to pass PMF flood of
5702 cumecs (Drawing BLK-CS-GEN-DWG-012).Five (5) overflow spillway bays,
each having opening of 10.5 m height and10 m width, equipped with hydraulically
operated radial gates for flood discharge are set at the crest level of1276 m.a.s.l.
The dam crest (roadway/bridge deck) level is at El: 1293m.a.s.l. Three (3) circular
bottom outlets of diameter 5.0 m will be provided near the riverbed with the bottom
at El: 1217 m.a.s.l. for sediment flushing. The river bed level at dam axis is 1215
m.a.s.l. and the bedrock is encountered at EL. 1205 m.a.s.l. Height of the main
dam from river bed is 78 m.
9.2 River Diversion Scheme
The river diversion works consist of the following components:
a. Rock fill coffer dam with impervious core and crest level at 1230 m.a.s.l at
the upstream side.
b. Rock fill coffer dam with impervious core and crest level at 1227 m.a.s.l at
the downstream side.
c. A D-shaped diversion tunnel with arch section of 5 m radius and 393 m
long.
9.3 Power Intake Structure
A 3-bay intake structure with trash racks has been proposed for passing the
design discharge. A rectangular 8.0 m wide 8.0m high control gate equipped with
upstream sealing has been provided.
9.4 Low Pressure Headrace Tunnel
Headrace tunnel has been optimized by considering different diameters for the
design discharge with the following parameters:
a. Manning- Stickler coefficient (shotcrete) 60
b. Tunnel slope 0.11 %
c. Shotcrete lining thickness 0.100.3 m (as per conditions)
d. Concrete lining 0.3 m
The optimized dia. of low pressure headrace tunnel is 8.0 m and it is 8420 m long.
300 MW Balakot Hydropower Project
Feasibility Study Report
Executive Summary Page -9
system. The system has been found to be strong enough to stay stable and
recovers with fast damping, and therefore passed the transient stability checks.
11 ENVIRONMENTAL AND SOCIAL IMPACT ASSESSMENT STUDIES
The broad objective of ESIA studies is to assess the beneficial and adverse
impacts of the project implementation on the environment including physical,
biological and socio-economic parameters and to mitigate the adverse impacts.
The Project area of the reservoir is under, agriculture, range land with a good
number of forest and fruit trees, mixed shrubs and rough grasses.
There are no industries in and around the project area; therefore, noise pollution is
generally below the EPA limit of 65 dB (A). The air quality in the area is also good.
The environmental and ecological water releases downstream of the dam will be
1.5 cumecs and 3.0 cumecs in winter and summer respectively. In addition to this,
water ranging from 1.60 to 3.10 cumecs in winter and 5.3 to 18.5 cumecs in
summer will also be added through the downstream streams and nullahs.
The flora existing in the Project as well as study areas falls under moist sub-
tropical pine forests generally called Chir forests.
Fauna of the tract consists of mammals, reptiles, amphibians and birds. Some of
the most colourful and beautiful fowls like Monal pheasants and Kaleej are found
in the surrounding mountains.
Archaeological/ historical sites in the reservoir and powerhouse areas do not exist.
The population of the Project area is a mixture of Punjabi, Kashmiri and Pathan.
The major language of project area is Hindko, while Urdu and English are also
used by educated class of the area.
In the Project area, no proper medical facilities exist. Only one dispensary and
some private medical stores are available in Paras village.
Majority (76%) of the female respondents do not take part in any activity except
household chores and livelihood earning is the responsibility of males.
The reservoir of the Project will permanently occupy 127.5 acres of land. Out of
this land, only 23 acre land is irrigated agricultural land whereas 31, 49.5 and 24
acres of land is grazing, barren and under infrastructure respectively. In addition,
area of 10 acre will be occupied for residential colony near the powerhouse site.
In the reservoir area, 4663 trees (1642 forest and 3021 fruit) are being impacted.
There will be no danger to large wildlife with the execution of the project as they
live in forest areas, which are located at higher altitude.
There will be positive impact on the birds and the fowl communities as a suitable
habitat will be formed for this community with the creation of the reservoir.
Construction of the project will result in the creation of job opportunities, better
potential for business, transport and tourism development.
During construction, environmental monitoring will be done for air quality, noise
and vibration, drinking water quality, sewage effluent, solid waste, explosive
material used, hazardous/toxic materials and their proper disposal, flora/fauna,
excavated material and traffic handling system etc.
300 MW Balakot Hydropower Project
Feasibility Study Report
Executive Summary Page -12
Due to the construction of the project, 164 houses are being affected, which will
require resettlement or compensation. In addition to this, 116 different types of
commercial infrastructure is also being affected due to the reservoir.
All the owners of the land and land based assets will be resettled or compensated
according to the D.C. rates or the rates assessed by the Committee constituted for
this purpose by the D.C. The survey revealed that more than 71.4 % of the
affectees favored cash compensation. A Grievance Redressal Committee (GRC)
is proposed, which will look into all the grievance cases.
The project environmental and resettlement cost amounts to Rs.1100.8 million.
PHYDO will be responsible for the overall implementation of environmental
mitigation measures and the RAP through its Project Director and field offices,
with the collaboration of district government departments.
12 COST ESTIMATES
The cost estimates for the various works including Infrastructure Development and
Site Installations, Civil, Hydro-Mechanical, Hydraulic Steel, Electrical& Substation
have been prepared. These costs include estimates for Environmental Mitigation
Program.
The unit and lump sum prices were adopted after doing the total cost rate analysis
for various items, comparing and escalating the unit prices for certain items
available from other on-going or recently completed similar projects.
Table - 2 presents summary of cost estimates. These estimates do not include the
financial Costs of US$ 17.61 Million.
Table - 2: Summary of Cost Estimates
Total
Sr. Year
Description CostM. US Year 1 Year 2 Year 3 Year 4
No 5
$
A Infrastructure development, Mitigation and Preparatory works
1 Mobilization and Demobilization 14.42 7.21 0 0 0 7.21
Infrastructure & Technical facilities
including Access Roads, Water
2 supply & Drainage and Power 7.21 7.21 0 0 0 0
supply to Residential colonies at
Dam and Powerhouse sites
Camps and Housing During
3 9.38 9.38 0 0 0 0
Construction
Reservoir Slope Stabilization and
4 2.88 0.46 0.55 0.61 0.61 0.66
Construction Difficulties costs
Sub Total A 33.89 24.26 0.55 0.61 0.61 7.87
B Civil Works
1 Coffer Dams and Diversion Tunnel 11.17 6.7 4.02 0.44 0 0
2 Dam and Plunge pool Excavation 68.64 0 37.75 26.43 4.47 0
3 Power Intake 10.67 0 9.6 1.06 0 0
4 Low Pressure Headrace Tunnel 117.44 17.61 31.71 42.28 25.83 0
5 Surge Shaft 0.54 0 0.05 0.49 0 0
300 MW Balakot Hydropower Project
Feasibility Study Report
Executive Summary Page -13
Total
Sr. Year
Description CostM. US Year 1 Year 2 Year 3 Year 4
No 5
$
6 Pressure Shaft 1.32 0 0.13 1.19 0 0
7 High Pressure Tunnel 0.59 0 0 0 0.59 0
8 Penstocks 0.17 0 0 0 0.17 0
9 Powerhouse 25.16 0 16.35 8.81 0 0
10 Tailrace Tunnel 18.01 0 11.71 6.3 0 0
Sub Total B 253.71 24.31 111.32 87 31.06 0
C HSS, Mechanical and Electrical Works
1 Hydraulic Steel Structures 23.76 0 4.75 10.69 8.32 0
2 Powerhouse Mechanical Works 45.54 0 0 11.38 34.15 0
3 Powerhouse Electrical Works 54.94 0 0 0 43.95 10.99
4 Switchyard Works 48.62 0 0 0 48.62 0
5 Transportation 10.89 0 3.81 4.03 2.5 0.54
Sub Total C (FIT and E&C Costs
183.75 0 8.56 26.1 137.54 11.53
included)
D Environmental And Valley Development
1 Valley Development And Uplift 28.94 6 6.94 6 5 5
Environmental Mitigation
2 11 1.76 2.09 2.31 2.31 2.53
Measures
Sub Total D 39.94 7.76 9.03 8.31 7.31 7.53
Sub Total A+B+C+D 511.29 56.33 129.46 122.02 176.52 26.93
Management Consultants
E 33.77 5.1 8.44 8.44 8.44 3.35
Engineering and Supervision
F Contingencies 24.11 4.33 6.27 3.14 5.79 4.58
Miscellaneous (Insurance,
G Performance Bonds and 9.65 1.74 2.51 1.25 2.32 1.83
workman Compensation etc.)
Sub Total A to G 578.82 67.5 146.68 134.85 193.07 36.69
PHYDO Expenses,
H Administration, Counterpart 29.33 5.28 7.63 3.81 7.04 5.57
Staff and Misc Costs
Allowance for greater risk and
I 11.73 2.11 3.05 1.53 2.82 2.23
uncertainties
Total Cost of the Project A to I 619.88 76.36 157.72 139.05 202.37 44.5
J Duties 7.79
Grand Total 627.67