Section 4. Particular Conditions of Contract
Section 4. Particular Conditions of Contract
Section 4. Particular Conditions of Contract
Instructions for completing the Particular Conditions of Contract are provided in italics in parenthesis for
the relevant GCC Clauses.
GCC 1.1(y) The Intended Completion Date for the 2 (Two) No. Multi-purpose Self
Propelled Inland Container Vessels shall be
18 (Eighteen) months upto the delivery date of the two vessels at Pangaon
Terminal, Dhaka.
[to be calculated from the Commencement Date]
GCC 1.1(kk) The Site is located at at the Yard of Khulna Shipyard Limited, Khulna
[it is the last date when the Contractor shall commence execution of the Works under the Contract
reasonably immediately after the Commencement Date; refer to GCC Clause 40]
[state brief summary, including relationship to other Contracts under the Project]
The 2nd phase includes L.C of the Main Engines, Propulsion systems
and Generating sets, and the bottom construction works of two vessels
upto double bottom.
The 3rd phase includes the completion of ship hulll / hull blocks of
two vessels upto deck level but without deck.
GCC 3.1 The Procuring Entitys address for the purpose of communications under this contract is :
Contact person: Engr. Abdul Gafur Sarker
Executive Engineer & Project Director
Address: BIWTC Bhaban
5, Dilkusha, C/A, Dhaka-1000
Tel: 02-9563508
Fax: 880-2-9563653
E-mail address: [email protected].
The Contractors address for the purpose of communications under this contract is :
Contact person: Mr. -------,
Managing Director.
GCC 6.1 (j) Other documents forming part of the Contract are;
1. Work plan (BAR Chart) as forming the part of the Contract (Annexure-
1).
8. In order to ensure required engine power for the proposed hull form
model testing must be carried out in any ITTC approved model testing
lab after signing the agreement. After the model testing it is found that
higher engine power required attaining the required speed Bidder will
have to supply higher power engine. (Annexure -5, RDPP pp77-78)
(b) 1 (one) copy of the negotiable, clean, on-board bill of lading marked
"freight prepaid" and 1 (one) copy of nonnegotiable bill of lading;
manufacturers/ suppliers warranty certificate (if any);
(c) copy of packing list identifying contents of each package -1 (one) copy
[list other documents viz. Schedule of other contractors, Schedule of Key Personnel, Site Investigation
Reports, relevant correspondences prior to signing of the Contract agreement etc.]
GCC 9.1 A Contractor or a Subcontractor that is a national of, or registered in, the following
countries are not eligible: ISRAEL
GCC 9.2 Materials, Equipments Plants and supplies shall not have their origin in the following
countries: ISRAEL
GCC 13.1 Possession of the Site or part(s) of the Site, to the Contractor shall be given on the
following date(s); Not Applicable (N/A)
GCC 19.1 Following Key Personnel to carry out the functions stated in the Schedule shall be
employed by the Contractor;
1. Mr. Shahidul Islam, Deputy General Mnager (D & P)
2. Mr. Amal Krishna Roy, Additional Chief Engineer & Project Director
of container vessels, KSL, Khulna
3. Mr. Golam Nobee, Executive Engineer (Project Officer of container
vessels)
4. Mr. Shafiquzzaman, Executive Engineer ( Out Door section)
[insert name(s)]
GCC 23.1 The Contractual matters between the Procuring Entity and the Contractor shall be
decided by Builder and BIWTC management
(a) The maximum deductible for insurance of the Works and of Plant and Materials is
Tk [state amount]
All risk insurance, including war risk, riots, and /or strikes shall be
acquired for 110% of the delivered cost of the goods on Warehouse to
warehouse basis.
Insurance of the container vessel shall be covered by the shipyard
insurance policy. All risk before delivery of the container vessels shall
be borne by the respective shipyards.
[the Contractor shall provide this amount at the time of Contract signing].
(b) The minimum cover for insurance of the Works and of Plant and Materials in
respect of the Contractors faulty design is Tk [state amount].
[the amount could be 110% of the value of the works, plant and materials that may be lost in a
worst case scenario].
(f) The minimum cover for insurance of other property is Ten Percent (10%) of the
contact price.
[it is the responsibility of the Contractor to obtain adequate insurance cover for such risks
recommended value 10% of contract price].
(g) The minimum cover for personal injury or death insurance:
(i) for the Contractors employees is as per the law and common practice in
Bangladesh.
(ii) and for third parties is as per the law and common practice in Bangladesh.
(iii) For the personnel (BIWTC) Tk.1.00 (one) Lac for injury & Tk.10.00
(Ten) Lac for death in the premises of KSY
Commencement Date of Works shall be as follows;
GCC 40.1
GA and Mid ship section Drawing approval date by the class and owner
which occurs later shall be considered as commencement date.
[insert different commencement dates for different parts of the Works, if deemed appropriate]
GCC 42.1 The Contractor/Builder shall submit a Programme / BAR CHART for the Works
within 07 (seven) days of signing the Contract.
[usually fifteen (15) days]
GCC 42.3 The amount to be withheld for late submission of an updated Programme is BD
Tk.10,000/- (Ten thousand).
GCC 57.1 The Defects Liability Period is Twelve (12) Months ( 365 Days)
[usually Defect Liability Period is twelve (12) months to cover at least one complete monsoon season].
GCC 66.3 The particulars of the Bank Account nominated are as follows :
[information furnished by the Contractor shall be substantiated by the concerned Bank and
authenticated by the Procuring Entity]
GCC 69.1(m) The following additional events shall also be the Compensation Events: NONE
[list events or state none ]
GCC 71.1 The Contract is not subject to price adjustment.
(b) It is mentioned here that the warranty of the container vessels shall not
cover mishandling of the equipments by the ships crews, grounding,
accident, wilful neglect of the ships crews, normal wear and tear, natural
calamities etc.
[state none if not applicable. If applicable then the proportion of Retention Money shall be equal to
the percentage-shortfall of ten (10) percent of Performance Security determined at the time of signing
the Contract. Again in case of unbalanced Tender or because of front loading, provision for Retention
Money shall not be applicable]
GCC 73.1 The amount of Liquidated Damages or in other words Delay Damages for the
uncompleted Works or any part thereof is 0.05 of ONE (1) percent of its Contract price
per day of delay.
a) The liquidated damages for the whole of the works are 0.05 of one (1)
percent per day of the final Contract price/ final bill ..
b) If the delivery time exceeds for any reason other than force majeure and
additional works the owner shall not pay slipway charge for those delay
days.
c) If the delay time is un-limited the owner reserves the right to cancel the
contract.
[usually the percent-rate of liquidated damages is set at between 0.05 and 0.10 of ONE (1) percent of its Contract
price per day of delay]
GCC 73.1 The maximum amount of Liquidated Damages for the uncompleted Works or any part
thereof is Ten percent (10%) of the final Contract price of the whole of the Works.
[ usually the total amount of liquidated damages shall not exceed ten (10) percent of the final Contract price for
the whole of the Works]
GCC 74.1 The Bonus for the whole of the Works is Zero percent (0%) of the final Contract price
per day.
The maximum amount of Bonus for the whole of the Works is Zero percent (0%) of the
final Contract price.
[if early completion would provide benefits to the Procuring Entity, this clause should remain,
otherwise state Not Applicable. The bonus is usually numerically equal to the Liquidated Damages]
GCC 75.1 The Advance Payment shall be Tk [insert amount] and shall be paid to the Contractor not
later than [insert date].
The advance payment is10% (ten percent) of the contract price shall be paid
upon submission of Bank Guarantee of equivalent amount from any schedule
Bank of Bangladesh within Fifteen (15) days from the date of signing of
contract.
[for 100 percent GoB funded procurement, advance payments are not recommended unless otherwise
specifically decided by the Government. An advance payment, if admissible, shall be made for
mobilisation, considering the nature of the works. The recommended maximum advance payment is ten
(10) percent of the original Contract price against an unconditional Bank Guarantee (Form PW3-10.)
On the contrary, advance payments may be applicable for procurements under aided projects]
GCC 77.2 The percentage for adjustment of Provisional Sums is 0% (Zero percent)
[state none, if not applicable. Usually covers the VAT, profit and overhead costs]
GCC 84.1 The date by which as-built drawings are required is [insert date]
The date by which operating and maintenance manuals are required is on the day of the
delivery of the vessel
GCC 84.2 The amount to be withheld for failing to produce as-built drawings and/or operating
and maintenance manuals by the date required is Tk 2.00 (Two) Lac
GCC 90.1 The percentage to apply to the contract value of the works not completed, representing
the Procuring Entitys additional cost for completing the uncompleted Works, is [state
percentage] percent.
[ usually between ten (10) to twenty (20) percent depending on the nature of the Works]
(a) Deadweight:
In the event that there is a deficiency in the guaranteed deadweight tonnage
determined by the class / designer, on completion of approval of final
drawings of the vessel, without any decrease in proposed container carrying
capacity at 16 M.T.(maximum) homogeneous loads per TEU, the contract
price shall not be decreased for a deficiency of the guaranteed dead weight
tonnage. However, for a decrease of container carrying capacity due to
deficiency of dead weight tonnage by any amount a sum of Tk 20.00
lac(Twenty lac) will be deducted per TEU for a maximum number of
decreases by 2 TEUs carrying capacity. The purchaser reserves the right to
rescind the contract if the carrying capacity is decreased beyond 2 TEU.
Speed :
The contract price of the vessel shall not be affected or changed if the deficiency in
actual speed is less than three tenths (3/10) of one knot below the required service
speed of the vessel as mentioned in the technical specification. Each for reductions
of 0.1 knots (maximum allowable 0.3 knots) there will be deducted of 0.5% of total
contact price. The purchaser reserved the right to rescind the contact if the the speed
is decreased beyond 0.30 knots.
If the deficiency in actual speed of the vessel is more than 1(one) knot below
the required service speed, then the Purchaser may reject the vessel(s) and
rescind the contract.
(b) Draught :
In case the actual loaded draught exceeds 3.8 meter, the Purchaser shall be
entitled to reject the vessel and rescind the contract .Shallow draft and higher
capacity vessel will be given preference.
(c) Route: The designer must consider the river conditions & others
relevant parameters of river route.
1. Dhaka to Chittagong
2. Chittagong to Dhaka
3. Dhaka to Mongla
4. Mongla to Dhaka
5. Mukterpur bridge/ Electrical tower clearance, Maximum- 18 m
(d) The designer must approve his design by the consultant BRTC,
BUET.
[ usually between ten (10) to twenty (20) percent depending on the nature of the Works]
GCC 94.2 (b) The Adjudicator jointly appointed by the parties is:
Name:
Address:
Tel No:
Fax No:
e-mail address:
GCC 94.2(b) In case of disagreement between the parties, the Appointing Authority for the
Adjudicator is the President of the Institution of Project Managers, Bangladesh.
GCC 94.3 (b) The arbitration shall be conducted in the place mentioned below;
[state name of place with location and district ]