Impact of Load Uncertainty Modeling On The Reliability of Power Systems Using Sequential Monte Carlo Simulation
Impact of Load Uncertainty Modeling On The Reliability of Power Systems Using Sequential Monte Carlo Simulation
effect. That why a data of one year hour by hour is needed either flow is performed using Gauss Seidel numerical method. Then
from history or forecasted data. The change will be investigated the voltage profile is checked to see either the load is supplied
from the load and transmission lines sides, that why a power or not. If the voltage is whiten the limit, the whole tie sets are
flow solution is needed. The source will be assumed to be checked to make sure at least one of them is not overloaded
sufficient and reliable all the time since the study focuses only otherwise the load will be considered not supplied. The final
on the distribution systems. The load will be counted as step is to count how many time the states are changed in the
unavailable if one of two conditions is happen; even if the whole process to find the frequency of each load.
voltage profile is less than allowable limit or the whole tie sets
lines between the source and the load are exceeded their IV. RESULTS AND ANALYSIS
capacity. The complete algorithm is shown in fig. 1.
The study will be conducted in a simple system with known
Start parameters obtained from Saadat's book [6]. The system has
three buses and two loads as shown in fig. 2 and table I. One
load will assume to be residential and the other commercial and
Get Data the load data has been modeled as described on [5] as equation
(1) and fig. 3.
t=1
L(t) = Pw Pd Ph (t) (1)
L1(t)*RN
The reliability indices of the component will be taken from
RBTS [4] as shown in table I.
yes
Isolate that RN>Pr?
Component
100% Reliable
no Power Supply
Power Flow
yes
Vi>Vmin? U=U+1
Line 2 Line 1
no
Line 3
yes
Itie>Imax?
no
no L2 L1
f=f+1 s(t)=s(t-1)?
yes
Fig. 2. The single line diagram of the studied system
t=t+1
The capacity of the lines will be assumed to be apple to supply
no the load at N-1 contingency. The supply bus is assumed to be
t=8760? 100% reliable and can supply the load all the time. Load 1 and
Load 2 are connected to bus 2 and bus 3 respectively. The load
yes flow is done in 10 iterations since the system has only 2 load
End buses and bus 1 assumed to be slack. While the MCS is
simulated up to 1000 times where each time represents one year
and at the end the average of all those years is taken. Using
Fig. 1. One year simulation flowchart Monte Carlo Simulation the load indices are calculated as seen
in table II and fig. 3-5.
In the first step the data is gathered including system
connection, impedances, thermal limits, failure rates, rapier
times, load profile/forecast for one year and mean standard
deviation of the normal destitution. After the simulation started
the load is multiplied with random number (RN) obtained from
normal distribution. Then another RN obtained from uniform
random distribution is compared with probability to fail (Pr) to
isolate the component from the system at that hour. Then a load
3
4.00
One Day Load Shape
3.00
1.1
R_L1 2.00
Load (pu)
VI. REFERENCES
Fig. 3. Unavailability of the two loads with different standard deviation
[1] M. Benidris, J. Mitra, "Composite power system reliability assessment using
5.00 maximum capacity flow and directed Binary Particle Swarm Optimization,"
North American Power Symposium (NAPS), 2013 , vol., no., pp.1,6, 22-24
4.00 Sept. 2013
3.00
f_L1 [2] R. Billinton, D. Huang, "Effects of Load Forecast Uncertainty on Bulk,"
2.00 IEEE Transactions on Power Systems., Vol. 23, No. 2 May 2008
f_L2
1.00 [3] A. K. Basu , S. Chowdhury and S. P. Chowdhury , D. Ray, P. Crossley,,
0.00 "Reliability study of a micro-grid power system," Universities Power
Engineering Conference, 2008. UPEC 2008. 43rd International, vol., no.,
0.20 0.10 0.05 Ref. pp.1,4, 1-4 Sept. 2008
Fig. 4. Failure rate of the two loads with different standard deviation
4