Wefix Construction Services Incorporated: (Weekly Activity Report)

Jenelyn M. Arbuis was assigned as an OJT at the WeFix Construction Services Incorporated NGCP 138 kV-69 kV Substation Project in Brgy. Awang Opol, Misamis Oriental. Over the course of the week, activities at the project site included safety training, trench excavation, control building formwork and reinforcement, drainage installation, slope protection, fencing, roadwork, and materials testing. Administrative tasks such as payroll processing and report writing were also performed. The substation will distribute power to local electric cooperatives upon completion.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
107 views4 pages

Wefix Construction Services Incorporated: (Weekly Activity Report)

Jenelyn M. Arbuis was assigned as an OJT at the WeFix Construction Services Incorporated NGCP 138 kV-69 kV Substation Project in Brgy. Awang Opol, Misamis Oriental. Over the course of the week, activities at the project site included safety training, trench excavation, control building formwork and reinforcement, drainage installation, slope protection, fencing, roadwork, and materials testing. Administrative tasks such as payroll processing and report writing were also performed. The substation will distribute power to local electric cooperatives upon completion.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
You are on page 1/ 4

WeFix Construction Services Incorporated

(Weekly Activity Report)

Name: ARBUIS, JENELYN M. Project: Opol 138kV-69kV Substation


Position : OJT Location : Brgy. Awang Opol, Misamis Oriental

We were accepted at WeFix Construction Services Incorporated and were assigned at different
field on a rotational basis. I and my partner was assigned at NGCP 138 kV-69 kV Substation
Project. This station will be a distributor of power to Cepalco and Moresco. The following were
activities observed last week:

Day 1 (Tuesday, April 14/2015)

Safety Management Awareness


Site Visit (NGCP OPOL)

Day 2 (Wednesday, April 15/2015)

Tool Box Meeting


- this meeting elaborates the safety measures need to observed in the
workplace.
Cable Trench
-Layout (surveying the elevation)
Control Building
Slab
-Installation of Reinforcement
-Setting Forms for Blockouts(for electrical purposes)

Wall
-Installation of CHB
-Plastering/Finishing
Drainage
-Excavation
- Installation of Culverts
Riprap
- Excavation(slope protection)
- Installation of Boulders on the Prepared Slope
-Pouring of Concrete Mix
Fence / Perimeter
-Installation of Reinforcements for wallfooting & columns
- Installation of CHB & Reinforcement for wall

Day 3 (Thursday, April 16/2015)


Cable Trench
-Layout
-Installation of Reinforcement
Control Building
Slab
-Installation of Reinforcement
Wall
- Installation of CHB
-Plastering/Finishing
Drainage
-Excavation
-Placing of Culverts
-Setting forms for Junction Box/
-Installation of Reinforcement for Junction Box
Riprap
-Preparation for Slope/Excavation
-Placing of Boulders on the Prepared Slope
-Pouring of Concrete Mix
Fence / Perimeter
-Installation of Spikes
-Placing of CHB & Reinforcement for wall
Road
-Compaction of Base Course
-Pouring of Concrete
Steelworks
-Fabrication of trusses
Testing of materials
- Delivering Sample Cylinders to NGCP 138 kV Substation (Mindanao
Material Testing Laboratory, Villanueva Mis. Or.)

Day 4 (Friday, April 17/2015)


Cable Trench:
-Installation of Reinforcement
-Finishing/Plastering
Control Building
Slab
-Installation of Reinforcement
Wall
-Placing of CHB
-Plastering/Finishing
Drainage
- Installation of Culverts

-Sealing of Culverts using Mortar/Concrete


Riprap
- Installation of Boulders on the Prepared Slope
-Pouring of Concrete Mix
Fence / Perimeter
-Installation of Spikes
-Installation of CHB & Reinforcement for wall

Day 5 (Saturday, April 18/2015)


Office Works
-organizing/paper cutting workers pay roll slip
-checking papers
- writing weekly report
-visiting warehouse and familiarizing materials

GOOD DAY