0% found this document useful (0 votes)
3K views93 pages

CRP & Sas

The document provides technical specifications for the design, manufacture, supply, testing and commissioning of relay panels and substation automation systems (SAS) for 765kV and 400kV substations. It outlines requirements for the cabinet construction, including dimensions, degree of protection, testing requirements, material thickness. It also specifies the painting process, required accessories, circuit distribution and isolation components, panel wiring details and termination requirements. All work must be approved by TANTRANSCO and is aimed to satisfy their standards for reliable and safe operation of substation equipment.

Uploaded by

balaeee123
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
3K views93 pages

CRP & Sas

The document provides technical specifications for the design, manufacture, supply, testing and commissioning of relay panels and substation automation systems (SAS) for 765kV and 400kV substations. It outlines requirements for the cabinet construction, including dimensions, degree of protection, testing requirements, material thickness. It also specifies the painting process, required accessories, circuit distribution and isolation components, panel wiring details and termination requirements. All work must be approved by TANTRANSCO and is aimed to satisfy their standards for reliable and safe operation of substation equipment.

Uploaded by

balaeee123
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 93

SECTION 22

TECHNICAL SPECIFICATION FOR RELAY PANELS WITH SAS

1. General

This specification requires the design, manufacture, FAT, supply inclusive of


insurance, transport and delivery to site, testing and commissioning of SAS, Control
& Relay panels for 765 kV and 400 kV and other associated equipments. The
equipments shall be capable of working satisfactorily in the intended environmental
conditions and suitable for satisfactory performance for the application.

The manufacturer of Relay panels and SAS equipments offered by the bidder is
subject to approval of TANTRANSCO.

All necessary material and works towards field interface of Control & Relay
panels to the switchgears, CTs, PTs, power supply equipment, communication
equipment, SAS (As applicable) etc. are in the scope of the bidder.

All the testing and commissioning of the Control & Relay panels and SAS
Equipments shall be carried out by engineers authorized /certified by the original
equipment manufacturer of SAS with the witness of the concerned TANTRANSCO
P&C engineer and the completion of all the works should be to the satisfaction of
TANTRANSCO.
All the relevant files such as ICD, SCD,SSD,CID etc shall be updated in the
relevant devices and provided in soft copy in CD and in a Spare HDD (Spare HDD
to be supplied in the spares for SAS) to the concerned Protection & Communication
engineer of TANTRANSCO.

2. Cabinet for Relay Panel:

a) Construction:

Free standing simplex type, Metal enclosed with swing frame to house the devices
and an outer glass door. The gland and plate assembly shall be vermin proof. The
panel shall be designed for wiring access from front of the C&R panel
Cable entries to the panel shall be from the bottom. The design of the interior of
the panel shall allow sufficient access to the terminals of all devices for removal

551

and repair. The design shall ensure that the heat generated by various apparatus
mounted in the panel shall not affect the performance of any of the devices.
Dimension : Depth x width x height : 800 x 800 x 2312 (or more
including base frame) in mm
Degree of protection : IP-41 as per IEC 60529 / IS 12063
Tests : All type tests and routine tests prescribed in IS/IEC
60947 Low- voltage Switchgear and Control gear
standards shall be performed on the complete panel
assembly.
Thickness of metal : Minimum 3mm for planes housing the devices and for
bottom plates. Minimum 2mm for all other sides.
Swing frame :
Play of Swing frame :120 degree or above capable of opening in the
opposite direction to glass door.
No of hinges : 3nos (minimum)
Door stopper : 1 No.
Protective Glass door : Splinter proof and transparent tempered glass of
minimum thickness 3mm.
Bottom plates : Knock slots shall be provided in the bottom plates
for facilitating cable entry at site.
b) Painting :
i) All sheet steel work shall be phosphated in accordance with IS-6005
ii) Oil, grease, dirt, swart, rust and scale shall be removed by adopting proper
cleansing procedure.
iii) After phosphating and thorough rinsing, the phosphate coating shall be
sealed with application of two coats of ready mixed stoved type zinc
chromate primer. The first coat shall be flash dried while the second coat
shall be stoved.
iv) After application of primer, two coats of finishing synthetic enamel paint
shall be applied, each coat followed by stoving
v) The colour of the panel shall match with the existing panel colour of
subject station and normally of following choice for new station.
Exterior - stoved enamel grey

552

Interior - stoved enamel white


Bus frame - stoved enamel black
Finish - glossy surface treatment shall be done as per BIS.
In case power coating painting is adopted then the minimum thickness of
paint shall be 70 microns and subject to the approval of TANTRANSCO.
c) Accessories :
A Door Stopper shall be provided with each door to hold it in the open position
at an angle/angles as specified for each type of panel.
Door handle shall be provided with padlocking facility.
Each cabinet is to be provided with removable type lifting eyes or lifting beams
installed on the top.
Adequate ventilation openings in the form of louvers shall be provided. The
ventilation louvers shall be vermin proof and shall be provided with removable
filters or removable wire mesh to minimize ingress of dust.
Labels to be provided at front and rear of the panel for each device.
Name plate to be provided on the top of each panel on front , Large and bold
name plates shall be provided for circuit/ feeder designation
Name plate and labels shall be made of non rusting metal or 3 ply lamicoid.
Name plate shall be black with white engraving lettering.
Typical label size : Width: 1.5cm; length : as per the length of the inscription;
the letter size : 0.75cm.
Panels shall have base frame with smooth bearing surface, anti vibration strips/
pad made of shock absorbing materials shall be placed between panels and base
frame.
All doors, removable covers shall be gasketted all around with neoprene
gaskets.
Necessary cable gland should be fitted. Cable gland plates fitted on the bottom
shall be connected to the earthing of panel/station through a flexible braided
copper conductor rigidly.
Each panel shall be provided with space heater rated for 230V single phase
A.C. supply with controlling thermostat.
All equipments in the panel shall be mounted and completely wired to the
terminal blocks ready for external connection. The spare contacts shall also be

553

wired upto the terminal block.


Each panel shall be provided with the interior fluorescent lights of sufficient
illumination capacity controlled by door limit switch.
A 240V single phase, 3 pin A.C. socket 15/5A with switch 1 No.
Accessories required for fixing the panel such as foundation bolts and nuts
shall be provided along with a panel.
DC voltage of the panels:- As per station DC supply voltage.
d) Circuit distribution and isolation :
i) Each C&R panel shall be provided with necessary arrangements for
receiving, isolating and tripping on fault of AC and DC supplies for various
control of signaling, lighting and space heaters.
ii) Each of the distribution circuits and incomer circuits of the AC auxiliary
supply and DC auxiliary supply shall be provide with MCBs such as to ensure
selective clearance of sub circuit faults.
iii) MCBs should be of suitable rating with auxiliary contact for trip indication
which shall be wired to SAS for alarm alert.
iv) Potential circuit for metering and relaying shall be protected by fuses.
v) All fuses shall be of HRC cartridge type conforming to IS 13703 mounted on
plug in type fuse bases. All accessible live connection of fuse base shall be
adequately shrouded.
vi) Fuse shall have operation indications for indicating blown fuse condition.
vii) Fuse carrier shall have imprints of fuse rating and voltage.
viii) Removable links should be provided at the output of each relay for trip
output and reclose output. Adequate space shall be left between fuse units
when arranged adjacently.
e. Panel wiring:
i) Wire type :
Single core multi strand copper conductor wires with PVC insulation of FRLS
and shall be flame, vermin, and rodent proof. 1100V grade for CT,PT
circuits. 600V/1100V Grade for other circuits.
ii) Flexible wires shall be used for wiring of devices on moving parts such as
swinging panels or panel door.
iii) Wire size :

554

4 Sq.mm for Auxiliary AC supply circuits.


2.5 Sq.mm for CT circuits, Earthing circuits and DC Auxiliary supply wiring.
1.5 sq.mm for PT Circuits and all other circuits.
Higher size wires for all of the above mentioned circuits is applicable if
required as per engineering requirement.
iv) Panel wiring shall be securely supported, neatly arranged, readily accessible
and connected to equipment terminals and terminal blocks. Wiring gutters
and troughs shall be used for this purpose. All wiring shall be made without
splices
v) Cables/wires shall be uniformly bunched and tied by means of PVC belts and
carried in PVC carrying troughs. The position of the PVC carrying troughs and
having bunch of wires shall not give any hindrance for fixing or removing relay
casing, switches etc.
vi) Wire termination shall be made with solder less crimping type and tinned
copper lugs, which firmly grip the conductor. Insulated sleeves shall be
provided at the wire terminations.
vii) Engraved core identification plastic ferrules marked to correspond with panel
wiring diagram shall be fitted at both ends of each wire.
viii) The wire number shown on the wiring shall be in accordance with IS 5578.
ix) All wires directly connected to trip circuit breaker or device shall be
distinguished by addition of red colour unlettered ferrule.
x) Interconnection to adjacent panels shall be brought to a separate set of
terminal blocks located near to the slots or holes to be provided at the top of
the panel. Arrangements shall be made for easy connections to adjacent
panels at site and wires for this purpose shall be provided and bunched
inside the panel.
xi) Bus wires shall run at the top the panels. The terminal blocks for the wires
shall be with isolating links.
xii) The terminal blocks used shall be minimum 600V (For other circuits) /1000V
(for CT & PT circuits) grade and have 10A continuous rating, moulded piece,
complete with insulated barriers, stud type terminals washers nuts and lock
nuts suitable for operation with a tubular box spanner or screw driver.

555

xiii) Terminal blocks shall be arranged in vertical formation at an inclined angle


with sufficient space between terminal blocks with minimum of 150mm for
easy wiring.
xiv) Terminal blocks shall include a white fibre marking stripe with clear plastic,
slip on/clip on terminal covers. Marking on terminal strips shall correspond
to wire number and terminal number on the wiring diagrams.
xv) There shall be minimum clearance of 250mm between the first row of
terminal blocks and the associated cable and plate or panel side wall.
xvi) At least 20% of total terminal shall be provided as spare for further
connections and these spare terminals shall be uniformly distributed on all
terminal blocks.
xvii) For CT termination, links terminal blocks to be used shall have links for
disconnection and connect type with plugging in facility for testing purposes.
For VT termination, links terminal blocks to be used shall have links for
disconnection and plugging in facility for testing purposes.
xviii) Wiring is preferable with the following colour code.
PT supply : Red, yellow, blue for phase and black for neutral.
CT circuits : Red, yellow, blue for phase and black for neutral.
DC circuit : Grey for both positive and negative.
230V AC circuits : Black for both phase and neutral.
Earthing : Green.
xvii) Lugs : Solder less crimping type, Tinned copper lug. Ring type (Generally for
termination on devices).
f. Earthing
i) All panels shall be equipped with bus securely fixed along the inside base of
the panels. When several panels are mounted adjoining to each other, the
earth bus shall be made continuous and necessary connectors and clamps
for this purpose shall be included in the scope of supply.
ii) The size of the earth bus shall be made of 25mmx6mm tinned copper flat.
iii) The earth of the substation will be 40mm diameter MS rods, provision shall
be made on the earth bus bars of the end panels for connecting to the earth
grid. Necessary terminal clamps and connectors shall be included in the
scope of supply.

556

iv) All metal case of the relays, instruments and other panel mounted devices
shall be connected to the earth bus by independent copper wires of size not
less than 2.5 sq.mm. The colour code of the earthing wire shall be green.
Earthing wire shall be connected on the terminals with suitable clamp
connectors and soldering shall not be permitted.

3.TRIVECTOR METER:

The tri-vector meter shall be AC static micro-processor based ABT type tri-vector
energy meters, DLMS (Category-B) compliant, suitable for availability based tariff
application. The meter should be capable to record and display Active, Reactive
and apparent energy and maximum demand for 3 phase 4 wire as well as 3 phase
3 wire AC balanced/ unbalanced loads without effecting the accuracy for a power
factor range of zero (lagging), unity and zero (leading) for export and import as per
the requirement given in this specification. The meter shall be capable to measure
in all the four quadrants. The meters measurement of metering values such as
Volatge,current,frequency,energy etc shall be based on true rms measurements.

3.1STANDARDS APPLICABLE

Sl.No. Standard No. Title

1 IS 14697 1999 AC static transformer operated


Watt-hour and VAR-hour meters
With latest amendment
for class 0.2s and 0.5s.

2 CBIP technical report no. 304 Specification for AC static


with latest amendment (only for electricity energy meters
Magnet compliance)

3 IEC 62053-22 with latest AC static Watt-hour meters for


amendment active energy, class 0.2 s.

5 IS-9000 Basic environmental testing


procedures for electronic and
With latest amendment
electrical items.

6 IS 15959 DLMS Companion Standard (ICS)

557

Meters matching with requirements of other national or international standard


which ensure equal or better performance than the standards mentioned above
shall also be considered. When the equipment offered by the bidder conforms to
standards other than those specified above, salient points of difference between
standards adopted and the standards specified in this specification shall be clearly
brought out in the relevant schedule and copy of such standards along with their
English translation shall invariably be furnished along with the offer.

Further, CMRI (Common Meter Reading Instrument) shall confirm to CBIP


Technical report no.88 with latest amendments.

3.2 TECHNICAL PARAMETERS

The energy meter shall be indoor type connected with the secondary side of
outdoor current and voltage transformers.

Supply system:

Rated Voltage : 63.5 Phase to Neutral

110 V Phase to Phase

Rated current : 1 Amps / 5 Amps

System frequency : 50 Hz +/- 5%

Earthing system : Solidly grounded

Accuracy : Class 0.2S.

Actual primary values wherever applicable shall be programmable in the meter as per the
CT and PT value of the installed CTs and PTs.

3.3 GENERAL TECHNICAL REQUIREMENTS

3.3.1 The meter should be micro processor based 3 phase 4 wire type suitable
for connection to 3 phase 4 wire as well as 3 phase 3 wire system.
3.3.2 The meter shall compute the active energy and load import; active energy
and load export from the substation bus bars during each successive 15 minute
integration period block and store it in its non volatile memory.

558

3.3.3 The metering system shall normally operate with the power drawn through
the PT secondary voltage.

3.3.4 The meter shall be capable of withstanding surges and voltage spikes as
per IS that occur in the PT & CT circuits of EHV switch yards by providing
necessary isolation and/or suppression system built in the meter.

3.3.4 The active energy measurement shall be carried out on 3 phase 4 wire
principle with accuracy as per class 0.2S of IEC 62053-22. The meter shall
compute the active energy import and export and average frequency during each
successive 15 minute block and store in its memory along with its sign. It shall
also display on demand the active import and active export during the previous 15
minutes block. The values may be displayed directly in secondary quantities.

3.3.5 Further the meter shall continuously integrate and display on demand the
cumulative active energy import and export from the substation up to date and
time of meter reading. The cumulative active energy import and export reading
at each midnight shall be stored in the meter memory for last forty-five (45) days
and shall be reported at Base Computer Software (BCS) end. Separate registers
shall be maintained for active energy import and export.

3.3.6 The average frequency (Hz) of previous 15 minute block shall be displayed
on demand in the metering system.

3.3.7 The meter shall continuously compute the average of the RMS values
(fundamental only) of the 3 lines to neutral PT secondary voltage as the
percentage of 63.51 V and then display the same on demand.

3.3.8 The meter shall compute the reactive power (VAR) on 3 phase 4 wire
principle with accuracy as per IEC 60687-2000 and integrate the reactive
energy algebraically in two separate registers, one for the period for which
RMS voltage is higher than 103%(Reactive High), and the other for the
period for which the RMS voltage is below 97%.(Reactive Low). When
lagging reactive power is being sent out from the substation bus bars,
reactive registers shall move forward. When reactive power flow is in the
reverse direction, reactive registers shall move backwards. The Nett KVARH

559

for voltage high (103%) & Nett KVARH for low voltage (97%) both shall be
displayed.

3.3.9 Further, the reactive energy shall also be available as four different energy
registers for viewing at BCS and on meter display:

a) Reactive energy lag while active energy import (Q1)


b) Reactive energy lead while active energy import (Q2)
c) Reactive energy lead while active energy export (Q3)
d) Reactive energy lag while active energy export (Q4)
3.3.10 Each metering module shall have a built in calendar in clock, having
an accuracy as per IS standard. The calendar and clock shall be
correctly set at the manufacturers works. Current date (day-month-year)
and time (hour-minute- seconds) shall be displayed on the front display
section on demand. Clock adjustment shall be possible at site using the
common meter reading instrument (CMRI) with proper security it shall
be possible to set the clock with BCS clock.

An automatic back up for continued operation of the offered meters clock


and calendar shall be provided through a long life battery capable of
supplying the required power for at least 2 years under meter un-powered
conditions. The offered meters shall be supplied duly fitted with the battery
that shall not be required to be changed for at least 10 years as long as total
VT interruption does not exceed two years.

3.3.11Each meter shall have a unique identification code (serial number), which
shall be marked permanently on the front as well as in its memory.
3.3.12 Each meter shall have a non volatile memory in which the parameters as specified
in this specification shall be stored. The non volatile memory shall retain the data
for a period not less than 10 years under un-powered condition; battery backup
memory shall not be treated as NVM.
3.3.13 All meters shall be totally identical in all respects except for their unique
identification codes. They shall be totally sealed with no possibility of any
adjustment at site except for clock correction.

560

3.3.14 The meters shall safely withstand the usual fluctuation arising during faults
in particular, VT secondary voltage 115% of rated voltage applied continuously
and 190% voltage of rated for 3 seconds and CT secondary current 120% of rated
current applied continuously and 20 times of maximum current applied for 0.5
seconds, shall not cause any damage to or the mal-operation of the meters.
3.3.15 The meter should be user configurable for all the parameters at site using
the toolsprovided for the meter.
3.3.16 Power factor Range:

The meter shall be suitable for full power factor range from zero (lagging) through
unity to zero (leading). The meter shall work as an active energy import and
export and reactive (lag and lead) energy meter. The energy measurement should
be true four quadrant type.

3.3.17 Power Supply Variation:

The meter shall be suitable for working with following supply variation

Specified operating range - 0.8 to 1.15 Vref.

Limit range of operation - 0.7 to 1.2 Vref.

Frequency - 50 Hz 5%.

3.3.18 Accuracy:

Class of accuracy of the meter shall confirm to 0.2S as per the relevant standard.
The accuracy should not drift with time.

Each of the meter supplied should be tested and certified for accuracy from a NABL
recognised laboratory in India.

3.3.19 Power Consumption:

i)Voltage circuit: The active and apparent power consumption in each voltage
circuit including the power supply of meter at reference voltage, reference
temperature and reference frequency shall not exceed 1.5 Watt per phase and 8
VA per phase respectively.

561

ii)Current Circuit: The apparent power taken by each current circuit at basic
current, reference frequency and reference temperature shall not exceed 1 VA per
phase.

3.3.20 Starting Current:

The meter should start registering the energy at 0.1% ln at unity power factor.
Maximum Current:
The rated maximum current of meter shall be 120% of basic current (Ib).
3.4 GENERAL AND CONSTRUCTIONAL REQUIREMENTS

3.4.1 Meters shall be designed and constructed in such a way so as to avoid


causing any danger during use and under normal conditions. However, the
following shall be ensured:

a) Personnel safety against electric shock

b) Personnel safety against effects of excessive temperature

c) Protection against heat & spread of fire

d) Protection against penetration of solid objects, dust and water

3.4.2 All the material and electronic power components used in the manufacture
of the meter shall be of highest quality and reputed make to ensure higher
reliability, longer life and sustained accuracy.

3.4.3 The meter shall be designed with application specific integrated circuits. The
electronic components shall be mounted on the printed circuit board using latest
Surface Mount Technology (SMT).

3.4.4 All insulating materials used in the construction of metering module


shall be non-hygroscopic, non-ageing and of tested quality. All parts that are likely
to develop corrosion shall be effectively protected against corrosion by providing
suitable protective coating.

3.4.5 The meter shall be suitable for being connected through test terminal blocks
to the voltage transformer having a rated secondary line to neutral voltage of
110/3 V and to current transformers having a rated secondary current of 1A as
562

per requirement. Necessary isolation and suppression shall also be built-in, for
protecting the meters from surges and voltage spikes that occur in the VT and CT
circuits of extra high voltage switchyards.

3.4.6 Each meter shall have test output devices (visual) for checking the accuracy
of active energy (Wh), reactive energy (VARh) or apparent energy (VAh)
measurement using a suitable test equipment. This device shall be suitable for use
with sensing probe used with test benches or reference standards. The test output
device shall have constant pulse rate ie pulse/unit (KWh, KVARh) and its value
(Meter constant) should be indelibly printed/ appropriately mentioned on the rating
plate.

3.4.7 The metering system shall conform to the degree of protection IP 53 in the
normal working condition of IS12063/1EC529 for protection against ingress of dust,
moisture and vermin.

3.4.8 The meter base, meter cover, terminal block (as applicable) shall be made of
unbreakable, high grade, fire resistant, non-inflammable and good quality suitable
material to ensure safety. The manufacturer shall clearly indicate the material used.

3.4.9 The terminal block and the meter case shall be designed such that it ensures
reasonable safety against the spread of fire and shall not be ignited by thermic
overload of live parts in contact with them.

3.4.10 All terminals for CT and VT connections shall be arranged at the lower/
back side of the meters. Terminal shall have a suitable construction with barriers
and cover to provide a safe and secure connection of CT & VT wires.

3.4.11 The metering system shall be compact in design. Entire design and
construction shall be capable of withstanding stresses likely to occur in actual
service and rough handling during transportation. The meter shall be convenient to
transport and immune to shock and vibrations during transportation and handling
as per the relevant standard. Meter shall have the capability and facility to
compensate for errors of external measurement transformers i.e. CT and VT

563

3.5 SEALING OF THE METER:

Reliable sealing arrangement shall be provided for meter to avoid fiddling by


unauthorized persons.

1. The meter cover shall have at least 2 sealing sources sealing


arrangement should be accessible from front only.
2. Separate sealing arrangements shall be provided for terminal
cover.
3. Sealing arrangement should be suitable for application of
poly carbonate seals.
4. The manufacturer will provide his own seals on each meter
before dispatch.
3.6 MARKING OF METER:

The marking on every meter shall be in accordance with IS 14697-1999.


Every meter shall have name plate beneath the meter cover such that the name
plate cannot be accessed without opening the meter cover and without breaking
the seals of the meter cover and the name plate should be marked indelibly.
The basic markings on the meter name plate shall be as follows:
i. Manufacturer's name and trade mark and place of manufacture.
ii. Type designation
iii. Number of phases and wires
iv. Serial Number
v. Month and year of manufacture
vi. Reference voltage & Frequency
vii. Rated secondary current (Basic current & Maximum current)
viii. Principal unit(s) of measurement
ix. Meter constant (Impulse/unit KWh/KVARh)
x. Class index of meter
The marking shall be indelible, distinct & readable from outside the meter.
3.7 Connection Diagram and Terminal Markings:

The connection diagram of the meter shall be clearly shown for 3 phase 4 wire
system as well as 3 phase 3 wire system, on inside portion of the terminal cover

564

and shall be of permanent nature or suitably pasted in meter. The meter terminals
shall also be marked and this marking should appear in the above diagram. In
case of any special precautions need to be taken at the time of testing the meter,
the same may be indicated along with the circuit diagram.

3.8 SALIENT FEATURES:


The metering system shall have the following additional salient features:
3.8.1 It shall be possible to check the healthiness of phase voltages by displaying
all thevoltages on the display of the metering system.
3.8.2 The meter shall work accurately irrespective of phase sequence of the mains
supply.
3.8.3 The meter should remain powered up and functional even when either of
any twophases or anyone phases along with neutral is available to the meter.
3.8.4 The meter shall continue to record accurately as per prevailing electrical
conditions even if the neutral of potential supply gets disconnected.
3.8.5 The metering system shall be provided with adequate design to ensure
compliance to CBIP Technical Report No.304 (with latest amendments) for
external magnetic influence criteria (AC electro magnet or DC magnet).
3.8.6 It shall not be possible to change the basic meter software by any means in
the field. Moreover critical events like time set, MD reset operation, and tariff
change shall be logged by the meter. Such events shall be logged in roll over mode
for up to twenty numbers.
3.9 Display of Measured Values:

3.9.1 The measured value(s) shall be displayed through Liquid Crystal Display
(Alpha numeric LCD backlit) section of metering system.

3.9.2 It should be possible to easily identify the single or multiple displayed


parameters through legends/ unit on the metering system display.

3.9.3 The register shall be able to record and display starting from zero, for a
minimum of 1500 hours, the energy corresponding to rated maximum current at
reference voltage and unity power factor. The register shall not roll over in
between this duration.

565

3.9.4 Any interrogation/ read operation shall not delete or alter any stored meter
data.

3.10 Meter Serial Number:


In addition to providing serial number of the meter on the name plate, the meter
serial number shall also be programmed into meter memory for identification
through CMRI meter reading print out. The meter serial number shall also be made
available on the metering system display on selection of appropriate option.

3.11 Display, Load survey capability and billing point requirements:


The meter shall be capable of recording 15 minutes average of the following
parameters for at least last 45 days and shall display the following parameters on
suitable selection through push button:
1. Date & Time
2. Imp WH
3. Exp WH
4. Imp Varh lag Q1
5. Imp Varh Lead Q2
6. Exp Varh Lag Q3
7. Exp Varh Lead Q4
8. Voltage RN
9. Voltage BN
10. Voltage CN
11. AVG Frequency
The meter shall be capable of recording 15 minute average of the following
parameter for last 45 days
1. Date & Time
2. Imp WH
3. Exp WH
4. Imp Varh lag Q1
5. Imp Varh Lead Q2
6. Exp Varh Lag Q3
7. Exp Varh Lead Q4
8. Imp MD KW
566

9. Exp MD KW
10. AVG Volt Ph A
11. AVG Volt Ph B
12. AVG Volt Ph C
13. AVG Current Ph A
14. AVG Current Ph B
15. AVG Current Ph C
16. AVG Frequency
17. Net VARh High
18. Net VARh Low
15-minute average of the above parameters shall be available for last forty five
(45) days. It shall be possible to select either demand or energy view at the BCS
end. The load survey data shall be made available in the form of bar charts as well
as in spread sheets at the metering PC end. The Base computer software shall
have the facility to give the complete load survey data both in numeric and graphic
form. All the 96 blocks shall be recorded for data indication on block day and no
supply period also shall be recorded .

3.12 Billing Parameters:


All billing parameters shall be transferred to billing registers; the parameter shall be

Active energy import


Active energy export
Apparent energy while active import .
Apparent energywhile active export.
Cumulative Reactive energies for the voltage high condition.
Cumulative Reactive energies for the voltage low condition.
3.13 DAILY MIDNIGHT PARAMETERS:

The meter shall store following end day parameters for last forty five (45)
days at 00:00 hrs.

1. Mid night Cum Imp WH (T)


2. Mid night Cum Exp WH (T)
3. Mid night Cum Varh High (V>103%)
567

4. Mid night Cum Varh Low (V<97%)


5. Mid night Cum Imp VARh Lag Q1
6. Mid night Cum Imp VARh Lead Q2
7. Mid night Cum Exp VARh Lag Q3
8. Mid night Cum Exp VARh Lead Q4
Other requirement as per CEA regulation

Above billing data, load survey data, anomaly information and


instantaneous parameters data shall be retrievable through the meter's
communication port through a common meter reading instrument (CMRI)
using DLMS protocol as well as transferred (down loaded) to a metering PC
to get complete details for view and print. It should be possible to export
the data so collected into (common data format). The supplier will provide
necessary facilities for the same in the base computer resident software.
The necessary base computer software (BCS) for this purpose shall be
provided with complete details.

3.14 TOD (Time of day registers):

The meter shall have TOD registers for active energy import and export, apparent
energy import and export and apparent MD import and export. Maximum eight
time of day registers for each energy and MD can be defined. It shall be possible to
program number of TOD registers and TOD timings through software/CMRI with
multilevel password security system and authenticated transaction.

3.15 Maximum Demand (MD) Registration:


The meter shall continuously monitor and calculate the average demand (Active
and Apparent) during the integration period set and the maximum, out of these
shall be stored along with date and time when it occurred in the meter memory.
The maximum demand shall be computed on fixed block principle. The maximum
registered value shall also be made available in the meter reading. The integration
period shall be set as 15 minutes it shall be capable to change to other integration
period (30/60 minutes), if required, through suitable high level software /MRI as an
authenticated transaction.

568

3.16 Maximum Demand Reset:


The meter should have any of the following MD resetting options:
(i) Auto reset of MD at predefined date and time shall be provided.
(ii) Resetting through meter reading Instrument or computer capable of
communicating with the meter with explicit password protection. The
manufacture shall provide a software module specifically for resetting
MD through MRI/Computer.
(iii) Manual via common MD reset button.

3.17 Data communication capability:


The metering system shall have multiple communication ports for local
reading and remote communication facility.
3.17.1 The meter shall be provided with a galvanically isolated optical
communication port. (Such as IEC, PACT, ANSI etc) with removable cover and with
locking arrangement so that it can be easily connected to a MRI / laptop for data
transfer.
3.17.2 The optical communication port shall, be compliant to DLMS protocol and,
also have a sealing provision.
3.17.3 In addition to the optical port, the meter shall be provided with one
communicationport either of Ethernet port IEC61850 protocol or RS-485 port with
open protocol (MODBUS)for integration with the sub-station automation system to
facilitate real time data acquisition of metered values and access of stored
metering records.
3.18 Real time clock:
3.18.1 The meter offered should have a real time clock and calendar based on a
quartz crystal with a battery totally independent of power supply.
3.18.2 A lithium maintenance free battery of long life (minimum ten years) shall be
providedfor operation of time clock. It should be possible to select the various time
zones forvarious seasons of the year through suitable software built into the
electronic register.
3.18.2 The accuracy of the clock shall not be less than 5 minute in a year or better.
3.18.3 It should be possible to reset Real Time Clock of the meter through a
manually triggered command from Base Computer Software.

569

3.18.4 The clock of the trivector meter should be synchronised with the GPS clock
of the SAS.
3.19 Self Diagnostic Feature:
The meter shall be capable of performing complete self diagnostic check to monitor
the circuits for any malfunctioning to ensure integrity of data in memory location all
the time. The meter shall have indications/ display for
unsatisfactory/nonfunctioning/malfunctioning of the following:
a) Time and date and
b) Non volatile memory failure indication
c) Low Battery indication at BCS
Above indicationshould be made available at BCS end also.
While installing the meter, it should be possible to check the correctness of CT/VT
connection to the meter and their polarity from the functioning of the meter for
different voltage injections with the help of vector phasor diagrams. For this
purpose suitable software for field diagnosis of meter connections with the help of
MRI should be supplied.
The details of malfunctioning of time and date shall be recorded in the meter
memory.
3.20 Anomaly detection features:
The meter shall have features to detect the occurrence and restoration of, at least,
the following common ways of anomaly:
a) Missing potential: The meter shall be capable of detecting and recording
occurrences and restoration of missing potential (1 phase or 2 phases)
which can happen due to intentional/ accidental disconnection of
potential leads.
b) CT polarity reversal: The meter shall be capable of detecting and
recording occurrences and restoration of CT polarity reversal of one or
more phases.
c) Current and voltage unbalance: The meter shall be capable of detecting
and recording occurrences and restoration of unbalance of current and
voltage. Snap shots (numerical values) of phase wise voltages, phase
wise active currents, phase wise power factors and energy (active
energy) readings shall be provided with the above specified events.

570

d) Last hundred (100) events (occurance+restoration), in total, shall be


stored in the meter memory on first in first out basis.
e) There shall be four separate compartments for logging of different type
of anomalies:
Compartment No.1 20 events of Missing Potential

Compartment No.2 20 events of CT Reversal

40 events for Voltage Unbalance,


Compartment No.3
Current Unbalance

20 events of Feeder Fail and Power


Compartment No.4
On/Off

Once one or more compartments have become full, the last anomaly event
pertaining to the same compartment shall be entered and the earliest (First one)
anomaly event should disappear. Thus, this manner each succeeding anomaly
event shall replace the earliest recorded event, compartment wise. Events of one
compartment/category should overwrite the events of their own
compartment/category only.

4. ANNUNCIATORS:

i) The announciator unit shall be microprocessor based and field configurable.


An automatic self supervision system to monitor the functioning of the
annunciation system shall be provided with a means to alert the operator.

ii) The annunciations facia shall be provided with flasher, hooters


and bell for separate indication of tripping alarm/non-tripping
alarms. All the panels shall have the inter connection for accepting the
alarm but the reset shall be from the individual panel.

ii) The display in the announciator unit shall be High density LED type or
cluster LED type.

iii) Trip and non-trip discrimination shall be made in the fascia. For example
all trip fascia shall have red colour and non trip fascia white colour.

571

iv) A test, accept and reset push button facilities shall be provided for testing
the annunciation unit.

v) The annunciator unit should conform to the applicable parts of the IEC
60255/ Equivalent for type tests and routine tests.

vi) The annunciator unit shall be equipped with 230VAC/220VDC redundant


power supply modules.

5. General requirements for Numerical protection relays

i) Technology shall be based on numeric type.

ii) Equipped with Event recorder. Events storage shall be sufficient for the
application. minimum 200 events of storage is preferable and with a time stamp
resolution of 1ms.

iii) Equipped with fault recorder to record in digital oscillography of instantaneous


values of all the relevant analog channels during faults and disturbances. Trigger
criteria and record length (pre-trigger and post trigger record length) for the
recorder should be user configurable. Storage capacity for Disturbance and fault
record storage shall be sufficient for the application.
Trigger criteria shall be user configurable to be triggered by any of the hardwired
inputs and outputs as well as virtual inputs and outputs , boolean logic, under/over
threshold levels of relevant analog channels etc. The sampling rate of fault recording
shall be preferably 24 samples/cycle or higher.
iv) Relay casings shall have a degree of protection of IP 50 for relay enclosure,
IP50 for relay facia as per IEC 60529 or equivalent.
v) Time stamping of events shall be of resolution of 1ms.

vi) Equipped with Two optical Ethernet ports at the rear of the numerical
relayforparallel redundancy (in compliance to IEC-62439-3) in networking on
IEC 61850 Protocol.The above referred 2nos Ethernet ports shall also be used
for time synchronization using SNTP protocol with guaranteed resolution of
1ms.

572

IEC 61850 protocol with type test certification/report for compliance with relevant
parts of IEC 61850. The compliance shall include :
- Model implementation conformance statement (MICS)
- Protocol implementation conformance statement (PICS)
vii) Equipped with communication port (USB or RS232 or Ethernet port) for relay
configuration, Data and records retrieval. It shall be possible to carry out firmware
updates of the numeric relay through internet connectivity free of cost.
viii) Equipped with self monitoring feature during start up and always while in
service. A relay fail alarm should be available in dry contact type alarm output. A
relay healthy indication shall be provided. The numeric relay shall be provided with
diagnostic tools with which it shall be possible to identify and display all the
defective modules of the relay.
ix) Provided with the necessary software tools for complete configuration of the
protection relay, record retrieval, data retrieval. All firmware updates to the
numeric relays shall be feasible to be effected with download of files from
the manufacturers website free of cost.
x) Suitable to operate with the auxiliary DC supply voltage available in the sub-
Station (Nominal aux supply Voltage is 110V DC or 220V DC as per station DC
supply voltage.)
xi) Provision for display of alarms with LED/ LCD/Graphic display. The LEDs shall
be user programmable to any of the hardwired inputs and outputs as well as
virtual inputs and outputs.
xii) Support multiple relay settings for protection. The numeric relay should be
provided with a facility for settings file comparison. Facility should be provided to
view the abstract of adopted settings features of the relay.
xiii) All configuration files, data and records of the protection relay shall be stored
in a non- volatile memory and shall not be lost on absence of dc supply.
xiv) The relays should be suitable for testing with universally acceptable testing kit.
xv) The relay should be equipped with user configurable opto isolated Binary
inputs and potential free binary outputs as required for the specific
application. Numeric relays with non-programmble binary Inputs,
non-programmable binary outputs, non-programmable are not
acceptable.

573

xvi) Where ever the numerical relay is connected to the 3phase VTs, the relay

should be equipped to display the angle of vectors with respect to A phase


voltage vector i.e Va angle=0 deg (Voltage vector of phase B and C with
respect to Phase A ) similarly current vector angle of phase A,B and C with
respect to voltage vector A for relay connected to 3 phase CTs.
xvii) All relays shall have screw type terminations for wiring terminations.
xviii) Thermal with stand capabilities:
3x In - Continuously
100x In - 1 Second
40x In for 3 second
xix) Equipped with Trip rated binary output contacts specifically for tripping with
Minimum of 4nos for 3-phase breaker application and 6nos for 3x1-ph breaker
applications. The rating of trip rated contacts shall be:
Make and carry continuously : 6 A , 300V.
Make and carry for 0.2 secs : 30A.
Breaking capacity for DC : 75W.
Breaking capacity for DC (when L/R is within 40 m sec) : 30 W.
- For alarm contacts:
Make and carry continuously : 4A DC/AC
Make and carry for 0.2 secs : 30A DC , 300V.
Operating time shall be less than 10ms for output contacts.
xx) Standards for type tests and routine tests compliance.
a) The numerical relay shall conform to the following standards with latest
amendments:

- IS 8686 in general with impulse Impulse Voltage Withstand Test and


High Frequency Disturbance Test as per Class III of this standard.

- IS 3231 (Relevant parts) / IEC 60255

- IEC 60255-22-2 : ESD

- IEC 60255-22-3 : Radiation susceptibility test

574

- IEC 60255-22-4 : Fast transient interference

- IEC 60255-21-2 : Shock test

- IEC 60255-21-1 : Vibration test

- IEC 60255- 11 : Alternating component (Ripple) in DC auxiliary


energizing quantity.

- Environmental performance requirements :

IEC 60255-1 : Operating temperature range

IEC 60255-1 : Storage temperature range

IEC 60068-2-30 : Humidity

b) In particular the following type tests should be complied.

a. Power Input:

i. Auxiliary Voltage

ii. Current Circuits

iii. Voltage Circuits

iv. Indications

b. Accuracy Tests:

i. Operational Measurd Values

ii. Currents

iii. Voltages

iv. Time resolution

c. Insulation Tests:

i. Dielectric Tests

ii. Impulse Voltage withstand Test


575

d. Influencing Quantities

i. Limits of operation

ii. Permissible ripples

iii. Interruption of input voltage

e. Electromagnetic Compatibility Test:

i. 1 MHZ. burst disturbance test

ii. Electrostatic Discharge Test

iii. Radiated Electromagnetic Field Disturbance Test

iv. Electrical Fast transient Disturbance Test

v. Conducted Disturbances Tests induced by Radio Frequency Field

vi. Magnetic Field Test

vii. Emission (Radio interference level) Test.

viii. Conducted Interference Test

f. Function Tests:

i. Indication

ii. Commands

iii. Measured value Acquisition

iv. Display Indications

g. Environmental tests:

i. Cold Temperature

ii. Dry Heat

iii. Wet heat

iv. Humidity (Damp heat Cycle)

v. Vibration

vi. Bump

576

vii. Shock

c) All acceptance and routine test as stipulated in the relevant standards


should be carried out by the supplier in presence of TANTRANSCOs
representative without any extra cost

6. Electro-mechanical Relays:

i) All relays shall confirm to IS: 3231

ii) Unless otherwise specified all auxiliary relays and timers shall be
supplied in non-draw out cases / plug in type modular cases.

7. RELEVANT REFERENCE STANDARDS:


IS/IEC 60947 Low-voltage Switchgear and Control gear
IS 3231 electrical relays for power system protection
IS 8686 static protective relays
IEC 60529 Degrees of protection procured by enclosures (IP code 31).
IS 1248 & IS 2419 indicating instruments
IS 0722 energy meters, control switches (LV switching devices for
control and auxiliary circuits)
IEC 60687 /IS 14697 AC static transformer operated watthour and Var-hour meters.
IS 0337,0337-1 -do-
IS 0297(part 1-3) Dimensions for the mechanical structures of the
482.6mm (19)series
IS 6875 control switches (LV switching devices for control and aux. circuits)
IS 0005 Colour for ready mix paints
IS 1554(part I) PVC insulated cables upto and including 1000 volts
IS 3842(part I-VII) application guide for protection
IS 6005 code of practice for phospating iron and steel
IES 602555-1-0 electrical relays all-or-nothing elec. relays.
IEC 60255-3,5,6,7,8,10,11,12,13,16 electrical relays for various specifications
IEC 60255-21-2,3
IEC 60255-22-1,2,3,4 electrical relays vibration and disturbance etc.
IEC 60255-23 electrical relays contact performance
IEC 61850-3 EMI Immunity and environmental compliance(Electrical utility substations)

577

IEC 61850 All applicable parts of this standard certified by KEMA/ reputed
laboratory. Including type test certification/report for :
- Model implementation conformance statement (MICS)
- Protocol implementation conformance statement (PICS)
Note : For standards other than IS mentioned above, the equivalent or better IS
standards may be complied.
8. PROTECTION FOR 765 kV / 400 kV LINES/FEEDERS:
MAIN-I & MAIN II DISTANCE PROTECTION:
The numeric distance protection relays shall comply with the following
requirements.
1. The numerical distance protection relays shall comply with the specification for
general requirements for numerical protection relay as furnished in this
document.
2. The numeric relays shall be equipped with sufficient binary output contacts for
trip outputs, alarms, spare and for the protection scheme implementation.
3. The numeric relay shall be suitable for operating with Nominal PT input of
110V~ phase to phase, 63.5V ~ phase to ground, CT input of 1A.
4. Main-1 and Main-2 distance protection relay should be of different
manufacturer.
5. Equipped with the following built in protection functions:
21 : Distance protection
a. The distance protection relay shall have following maximum operating time
(including trip relay time, if any) under given set of conditions and with CVT
being used on line (with all filters included)
For Source to Impedance 4 15
ratio:
Relay setting 10 2
(Ohms)
Fault Locations (as % of 60 60
relay setting)
Fault resistance (Ohms) 0 0
Maximum operating time 40 for all faults 45 for 3 ph. Faults & 60
(Milliseconds ) for all other faults
b. There shall be a minimum of 3 forward and 1 reverse selectable distance
protection zones.

578

c. Have six independent loop measurements system to cater phase to phase


and phase to ground faults
d. Polygonal characteristics for phase to phase fault and polygonal
characteristics for phase to earth fault. In case of polygonal characteristics X
and R or Z and R should be independently settable.
e. Have an impedance setting range of 0.05 Ohm 120 ohm
f. have a requisite independent continuously variable time setting with range
0-3 sec
g. Have a resetting time of less than 40 millisec.
h. have facility for zero-sequence compensation for earth fault on all zones of
measuring element
i. suitable for single and three phase tripping
j. Have cross polarization, assure 100% directional sensitivity for
unbalance
fault and memory for balanced faults.

k. Have built in fault locator with following features.


a) Shall display the fault location either in percentage of line length

or in actual distance in kilometer based on reactance setting.

b) Shall have an accuracy of +/-3% or better and watch dog output.

98 : Fuse failure detection for single, two and three phases

The scheme shall incorporate necessary precaution in measurement to block


the distance protection. However, during blocking period the relay shall have
over current protection facility for fault detection. zero sequence voltage
detection for VT fuse fail detection shall be used so that the relay does not
maloperate on system ground faults

50/27 : SOTF

25 : synchro check function

50BF : LBB Function

579

79: Built in auto reclose function with single shot, single phase (3phase for
110kV) reclose with adjustable dead time setting of 0.1sec to 1sec, and with
adjustable reclaim time of 1 to 250sec.

27/59 : Under voltage/ over voltage protection element. This protection element
should have two independent stages.

50N/51N IDMT directional earth fault relay with adjustable setting range of 10 to
80% with characteristic curve for normal inverse, very inverse and extremely
inverse of both IEC and IEEE curves.

DR : Disturbance recorder with minimum 8 analog and 12 digital inputs and with
minimum memory capacity to store at least 8 disturbance records with each record
of minimum 10 cycles.

Event recorder

Load encroachment discrimination facility to prevent false tripping due to


encroachment of heavy loads.

Stub protection.

6. The distance protection function shall be provided with the following


functionalities,
features:
68 : power swing blocking protection

The power swing shall be detected by rate of change of impedance with suitable
characteristics. The blocking shall have continuously adjustable time delay with
setting range of not less than 2sec or shall have feature to block the tripping as
long as it exists. The relay shall have feature to unblock during fault. It shall be
explained how blocking is effected during power swing for phase to earth fault,
phase to phase faults and three phase faults. In each case the relay shall have
feature to unblock in the event of actual fault and with facility to block each
distance zone independently.

85 : Communication aided schemes PUTT, POTT, Blocking, weak infeed and


current reversal logic.
580

46BC : Broken conductor detection


7. Provided with metering function of class 1.0 accuracy or better and user
programmable display.
8. Equipped with sufficient numbers (minimum is 16 nos; Minimum 12 nos for
110KV) of programmable of opto isolated Binary inputs and sufficient numbers
(minimum is 20 nos, Minimum 16 nos 110KV) of programmable potential free
binary outputs with wetting voltage for digital inputs to be field programmable to
48V / 110V / 220V DC.
9. The minimum number of LEDs shall be 14 nos, In case Graphic display is
provided then atleast 4 nos LEDs shall be provided for important alarms.
10.The relay should be equipped to display the angle of vectors with respect to A
phase voltage vector i.e Va angle=0 deg (Voltage vector of phase B and C with
respect to Phase A ) similarly current vector angle of phase A,B and C with respect
to voltage vector A.
9. DIRECTIONAL O/C &E/F RELAY:

The relays shall be of numerical type

1. The numerical distance protection relays shall comply with the specification for
general requirements for numerical protection relay as furnished in this
document.
2. The numeric relays shall be equipped with sufficient digital output potential free
contacts for trip outputs, alarms and for the protection scheme implementation.
3. The numeric relay shall be suitable for operating with Nominal PT input of
110V~ phase to phase, 63.5V ~ phase to ground, CT input of 1A.
4. Features and characteristics.
Current settings :
O/C Phase fault setting : 20 to 200 % of rated current in at least 1% steps
E/F setting : 10% to 80 % of rated current in at least 1% steps.
Time multiplier : 0.05 to 1.0 in steps of 0.01 for phase fault and earth fault
settings.
Definite Time Delay : 0.05 to 20 Sec. in steps of 0.01 sec.
Drop out to pick up ratio : > 95%.

581

Inverse Characteristic : Normal Inverse (3 Sec, 1.3 Sec), Very Inverse &Extremely
Inverse of IEC curves. ( Curves should be Selectable at site)
Characteristic curves and settings shall be separately selectable for phase fault and
earth fault.
High set Instantaneous Unit :
O/C : 50 % to 2500 % of rated current in steps of 50% or lesser step size.
E/F : 50 % to 500 % of rated current in steps of 50% or lesser step size.
Current settings o/c 50 to 200% & E/F 10 to 80% in convenient steps

Time multiplier settings 0 to 1 with a resolution of 0.01sec.


Have built in IDMT directional O/C and E/F relay with characteristic curve for
normal inverse, very inverse, extremely inverse of both IEC and IEEE curves
Directional element
P.T voltage : 110 V A.C
Phase fault : + 90 deg to -90 deg
E/F fault : + 90 deg to -90 deg
Equipped with in built 50LBB function.
Zero sequence voltage shall be based on 3-phase voltages.
5. Relay shall be provided with Event record & Fault record as stated below:
Storage and display of at least 100 event records with date and time stamp.
Storage and display of at least 16 fault records comprising information of Fault
element (R/Y/B/Earth) , Type of fault, Value of fault in true rms Amps.
6. Relay shall be provided with LED Indications for :
i) Protection healthy or In service
ii) Pickup
iii) Trip operated
iv) High set operated
v) Phase O/C operated
vi) Earth O/C operated
Note : Individual indication of hand reset type shall be provided for each O/C, Earth
fault element & each high set element.
10. BUS-BAR PROTECTION for 765 kV/ 400 kV :

Redundant (1+1) numerical Bus Bar protection scheme for each bus

582

system for 400kV as well as 765kV shall be provided. The scheme shall be
engineered so as to ensure that operation of any one out of two schemes
connected to main faultybus shall result in tripping of the same. Each of the
redundant numerical bus bar protection scheme shall comply to the
following requirements.
1. The numerical bus bar protection relays shall comply with the specification
for general requirements for numerical protection relay as furnished in this
document.
2. Bus bar protection relay shall be of numerical low impedance type,
distributed architechture and shall have operate and restraint
characteristics. The distributed Numerical based bus bar protection scheme
shall comprise a central unit and peripheral units all of which communicate
in real time through a high speed fiber optic communication link.
3. Each Bus Bar protection scheme shall comply to the following requirements.
(a) have maximum operating time up to trip impulse to trip relay for all types
of faults of 25 milli seconds at 5 times setting value.
(b) Operate selectively for each zone of bus bars for all types of faults i.e Phase
to phase , Phase to ground faults including high resistive faults.
(c) Give hundred percent security up to 63 KA fault level for 400KV. be
stable for through fault condition up to 50KA fault level.
(d) incorporate continuous supervision of CT secondarys against any possible
open circuit and if it occurs, shall render the relevant zone of protection
inoperative after a time delay and initiate an alarm. However facility to
unblock CT supervision in case of actual fault occurring in the bus shall be
provided.
(e) be phase segregated triple pole type and provide independent zone of
protection. If bus section is provided, then each side of the bus section shall
have separate set of bus bar protection scheme. The bus section breaker
and bus coupler breakers shall be covered by overlapping bus bar protection
scheme of respective buses.
(f) shall include one overall check zone protection in addition to single/multiple
zones specified.Incorporate check zone feature for each phase and clear
zone indication. The check zone shall be without any switching. Also check

583

zone shall not over stabilize during internal fault due to unequal source &
load distribution.
(i) include provision for protection IN/OUT for each zone and check zone.
(j) be transient free in operation.
(k) includes continuous DC supply supervision.
4. The numeric relay shall be suitable for operating with CT inputs of 1A
(nominal). The secondary of the CT shall be directly connected to the Bus
bar relay without the aid of external auxiliary CTs. Ratio correction shall be
possible with through the relay configuration tools itself.
5. the relay must have harmonic rejection and shall not operate on second and
third harmonics. Second harmonic rejection ratio 2:1 minimum, third
harmonic rejection ratio 40 :1 minimum.
6. the high speed electrically reset high speed tripping relays (96) for tripping
each bay breakers on actuation of bus bar protection shall be on respective
bay protection relay panels and necessary provision for running the tripping
bus wires to actuate these relays shall be made. However, in case of
distributed Bus bar protection, individual trip relay shall not be required if
bay unit is having trip duty contacts for breaker tripping.The protection
scheme shall be wired in such a way that both check zone and bus
sectionalizing zone schemes shall operate to isolate the respective faulty bus
bar for internal fault condition.
7. The relay should be equipped completely for supporting six numbers spare
circuits in addition to all the circuits for feeders/ bays depicted in the single
line diagram for the sub-station. In case of distributed Bus bar Protection,
the bay units for future bays may be installed in a separate panel and the
same shall be located in switchyard panel room where bus bar protection
panel shall be installed.

8. The bus bar protection relay should support various bus architectures
selectable by means of the relay configuration (Single bus bar, Double bus
bar, Breaker and a half bus bar, two section bus bar with a bus tie, Double
bus bar with transfer bus and tie breaker) for its bus bar protection.
9. The relay shall incorporate dynamic bus replica and provide necessary end

584

zone fault protection depending on the bus bar protection CTs location.
The status of isolators shall be ascertained by hardwired double indication
method i.e Both N/C and N/O contact to be used.
10. The relay shall facilitate through relay configuration tools as well as through
user interface keypad/controls the following requirements:
- Adopting multiple CT ratios of different bays
- CT polarity selection
- Bay IN/OUT selection
- Bus differential enable or disable etc
- IN/OUT selection for each zone and check zone.
11. Facility to monitor the individual bay currents, bus differential currents and
bus restraint current for each zones shall be supported in the relay display
as well as through configuration tools.
12. The bus bar protection of respective bus sections shall trip respective set of
bus bar lockout relays and shall initiate BF of respective CB. The bus
bar protection scheme of each bus section shall be developed such
that one lockout relay shall be provided with each circuit breaker.
13. The bus bar protection relay shall be provided with built in breaker fail
(50BF) / LBB protection implemented in the respective Peripheral bay unit
for all the connected circuits. For LBB protection
Operating time : 15 ms
Resetting time : 15 ms
LBB protection scheme shall be implemented to get individual initiation from
the corresponding phase of main protections of line for each over current
element. However common three phase initiation is acceptable for other
protections and transformer/reactor equipment protections.
Have setting range of 20% to 80% of rated current.
Have timer with continuously adjustable setting range of 0.1 to 1 second.
14. The relay shall be equipped with VT modules to measure the bus voltages so
that reference load flow can be taken from bus voltage as well as for
providing secure operation in case of inadvertent shorting of CT.

585

Note: In case separate LBB relay is stipulated for EHT breakers, then LBB relay
shall be provided accordingly even though Bus bar relay is equipped with built in
LBB protection.
11. TRANSFORMER PROTECTION (APPLICABLE FOR 765 kV/ 400 kV ICT:
a) BIAS DIFFFRENTIAL PROTECTION RELAY FOR THREE WINDING
TRANSFORMER PROTECTION:
The numerical differential protection relays shall be comply with the following
requirements.
1. The numerical differential protection relays shall comply with the specification for
general requirements for numerical protection relay as furnished in this
document.
2. The numeric relay shall be suitable for operating with CT inputs of 1A.
3. Differential protection features and characteristics:
i. Based on low impedance differential principle for protection of three winding
transformer. Three phase with faulty phase identification.
ii. Shall have three instantaneous high set over current units with facility to
adjust 5 to 20 times normal current.
iii. Shall have second and fifth harmonic restraint feature with second harmonic
content in the range of 15 to 35% .Transformer inrush restraint functionality
shall be provided. Inrush and CT saturation shall not influence the differential
function.
iv. Facility to set transformer vector group and CT ratio selection/ correction
through relay configuration software tools.
v. Basic bias setting 20 to 40% in steps 1%.
vi. Operating current setting range 15% to 30%.
vii. have operating time not greater than 35ms at 3 times normal current.
viii. Maximum operating time for instantaneous operation: 25ms +/-4% of set
value.
ix. The differential protection shall have adjustable characteristics with adaptive
differential feature to maintain stability in case of through faults.
x. The protection relay shall be equipped with unrestrained differential protection
element for fast tripping on heavy internal faults.

586

xi. Facility to view the transformer differential current and bias current directly
from the Relay display as well as through configuration software.
4. Shall have inbuilt restricted earth fault protection and inbuilt over fluxing
protection.
i) Over Fluxing Protection shall be provided for HV side and shall comply with the
following requirements:
(a) operate on the principle of Voltage to frequency ratio and shall be phase to phase
connected
(b) have inverse time characteristics, matching with transformer over fluxing
withstand capability curve
(c) provide an independent 'alarm' with the time delay continuously adjustable
between 0.1 to 6.0 seconds at values of 'v/f' between 100% to 130% of rated
values
(d) tripping time shall be governed by 'v/f' Vs. time characteristics of the relay
(e) have a set of characteristics for Various time multiplier settings. The maximum
operating time of the relay shall not exceed 3 seconds and 1.5 seconds at
'v/f' values of 1.4 and 1.5 times, the rated values, respectively.
(f) have an accuracy of operating time, better than +/-10%
(g) have a resetting ratio of 95 % or better
(h) Over flux protection shall be provided in the HV
ii) Restricted Earth Fault Protection shall
(a) be single pole type
(b) be of current/voltage operated type
(c) have a current setting range of 10-40% of 1 Amp./ have a suitable voltage setting
range
(d) be tuned to the system frequency.
5. The protection relay shall be equipped with built in thermal overload protection.
6. The disturbance recording functions should be integrated in the relay module.
The disturbance recorder shall have facility to record at least 4 numbers of
digital signals apart from digital signal from the relay and currents in HV&LV
winding. Recording memory capacity: 5secs.
7. Equipped with sufficient numbers (minimum is 16 nos ) of programmable of

587

opto isolated Binary inputs and sufficient numbers (minimum is 20 nos) of


programmable potential free binary outputs with wetting voltage for digital inputs
to be field programmable to 48V / 110V / 220V DC.
8. The minimum number of LEDs shall be 14 nos, In case Graphic display is provided
then atleast 4 nos LEDs shall be provided for important alarms.
b) BACKUP NON-DIRECTIONAL OVER CURRENT PROTECTION WITH HIGH SET
INSTANTANEOUS FOR HV:
Specification same as that required for numerical DIRECTIONAL O/C &E/F RELAY
but without directional feature. However the phase and ground Over current
functions shall incorporate a harmonic restraint feature.
c) BACKUP NON-DIRECTIONAL OVER CURRENT RELAY FOR LV:
Specification same as that required for numerical DIRECTIONAL O/C &E/F RELAY
but without directional feature.
12. Under Frequency Relay :
* Comply with the general requirements for numeric type relay furnished in this
technical specification document.
* The relay support programmable scheme logic. The PSL shall support Boolean
logic and shall be possible to configure using preferably IEC 61131-3 standard
compliant tools.
* The relay shall be equipped with separate protection elements for 4 independent
stages for under frequency protection, 3 independent stages for (81RF) Frequency
supervised rate of change of frequency protection.
* The relay shall have a discrete (digital) selection unit with built in timer and
associated tripping relays to activate tripping.
*UF Relay should have both phasor estimation & frequency averaging methods to
correctly determine UF condition during voltage dip condition also.
Under frequency protection function (81U)

1
No of Stages 4 independent Stages
2
Frequency range 45 Hertz to 55 Hertz
3
Frequency steps In 0.01 HZ
4
Timers One timer for each stage independently programmable

588

settings

5
Timer setting Programmable between 0 to 5 sec in step of 0.01 sec
6
Operating time Within 100ms
7
No of phases 3

Frequency supervised df/dt protection (81RF)

1
No of Stages 3 independent Stages
2
Settings range 0.1 HZ/Sec to 1 HZ/Sec in steps of 0.1HZ/Sec
Operational
accuracy 5 milli Hz./sec
3
Measuring cycles Programmable between 2 to 10 cycles
4
Operating time Within 100ms
5
No of phases 3
* The relay shall be equipped with built in VT supervision function and 2 protection
elements for under voltage blocking function selectable between IDMT/DT to block
all the frequency based protection elements. The under voltage measurement shall
be possible on phase to phase as well as phase to neutral basis.
* The relay shall have negative sequence overvoltage function. zero sequence
voltage detection for VT fuse fail detection shall be used so that the relay does not
maloperate on system ground faults
* Operating Voltage : 50 to 100% of nominal voltage with provision for selection.
Nominal voltage is 110V AC (Phase to phase).
Facility for under voltage blocking shall be provided with programmable range for
voltage setting.
* The relay functionality shall include measurement of phase/ line voltages (True
rms) , sequence voltages , system frequency and phase angles.
* Relay should have the capability to build the logic with which one should be able
to adapt to the load shedding requirement of the substation.

589

*Blocking of each of the protection elements shall be possible with user interface
through keypad/ buttons as well as through configuration port and Engineering
work station.
* The relay shall be highly reliable and immune to transient and surges. In case of
any component failure in the relay, the relay should not cause undesired trip.
Relay outputs:
* It shall be possible to assign each of the trip outputs reserved for feeders to any
of the three stages of under frequency protection function as well as f+df/dt
protection.
Indications
* The relay shall be equipped with indication lamps that is programmable to any of
the protection elements, inputs, outputs and logic outputs.
*Programmable LED indications shall be provided in the relay for each stage of
protection elements operated and for faulted phase indication.
Relay Inputs:
* The relay shall be highly reliable and immune to transient and surges.
* The relay shall be equipped with sufficient quantity of opto-isolated digital inputs
for facilitating external blocking of under frequency as well df/dt protection
elements for each feeder. Necessary isolation links should be provided to facilitate
manual isolation of under 81U and 81RF protection feeder wise.
* The relay shall be equipped with sufficient opto-isolated digital inputs and
potential free digital outputs to accommodate feeders all the feeders plus 3 spare
feeders for future use.
13.0 MISCELLANEOUS PROTECTION
13.1 D.C. Supply Supervision Relay.
The relay shall monitor continuously D.C. Supply to Protection System. The
de-energization of this relay will indicate the DC Supply failure. Auxiliary
supply for the relay is 220V DC. The relay shall have a time delay on drop
off of not less than 100 milli second. The relay shall be provided with
operation indicators (Reverse flag) self reset. Sufficient number of contacts
potential free may be provided. Separate relays for dual source are to be
provided.
13.2 Trip Circuit Supervision Relays.

590

The trip circuits shall be supervised by means of relays. The scheme shall
continuously monitor the trip circuit before closing and after closing of the
breaker. The schemes shall detect (I) failure of the trip supply (ii) open
circuit of trip circuit wiring and (iii) failure of mechanism to complete
operation. The relays shall supervise the healthiness of trip circuit
continuously (Both pre-closing and post-closing conditions of the circuit
breakers). The relay shall be capable of monitoring the healthiness of each
phase trip coil and associated circuits of the circuit breaker during ON and
OFF conditions. The relay shall work on 220V dc with allowable margin as
the case may be. The relay shall have adequate contacts for providing
connection to alarm and event logger, self reset. The relay shall have a
time delay on drop off of not less than 200 milli seconds and provided
with Operation indicators. The short circuiting of any series resistance
provided in this relay or short circuiting the coil of the relay should not
energize the trip coil of the breaker.
The relays shall have necessary contacts to be connected to
protection scheme and annunciation to SAS.
13.3 Tripping (Master) Relay :
- For tripping of feeder / transformer breakers in a station on operation
of protective relays and for interlock purposes. The relay shall be voltage
rated for station DC supply with allowable margin of variation, be
instantaneous (Operating time not exceed 10 milli seconds).
- Reset within 20 milli seconds.
- Hand and electrical reset type
- Have adequate contacts to meet the requirement of scheme, other
functions like auto reclose relay, LBB relay as well as to cater to associated
equipments like SER, DR etc., to be provided with operation element/ coil.
13.5 Check Synchronizing relay:-
Synchro check function should be part of the main relay.
The synchronism and energizing check functions shall feature:
Settable voltage, phase angle, and frequency difference.
Energizing for dead line - live bus, live line - dead bus or
dead line dead bus with no synchro-check function.

591

Synchronising between live line and live bus with synchro-check


function.
The relays equipped with synchronism and energizing check shall comply with the
requirements as mentioned above.
13.6 Relay for Automatic DC selection
Relay for automatic DC selection shall comply with the relevant parts of IEC 60255
/ IS standards. The performance of the relay shall be satisfactory so as to facilitate
minimum interruption of DC during DC change over and the DC interruption during
change over shall not cause the numeric relays to reboot / switch off, also all the
numeric relays shall be type tested for DC supply interruption and suitable to
function without reboot/power off during the DC change over.
In case diode oring based DC selection scheme is proposed, then the scheme
should ensure that any kind of component failure will not cause shorting of the
input DC sources, the dielectric isolation between the two input DC sources should
be sufficient for safe operation. Spare diodes 2sets should be provided for the
substation.
14. Numerical relay for LBB protection
Comply with the general requirements for numeric type relay furnished in this
technical specification document. Built in timer and necessary I/Os. Relay shall be
of triple pole type and equipped with auto reclose protection with check
Synchronising function. The operating time as well as a resetting time of the relay
shall be preferably less than 15 ms.
15. Test terminal blocks
The test terminal blocks (TTB) to be provided shall be fully enclosed with
removable covers and made of moulded, non-inflammable plastic material
with boxes and barriers moulded integrally. All terminals shall be clearly
marked with identification numbers or letters to facilitate connection to
external wiring. Terminal block shall have shorting, disconnecting and testing
facilities for CT circuits, Testing facilities for VT circuits.
16. Guideline for Distribution of auxiliary power supply for Kiosk:
a. All ACDBs and DCDBs of suitable rating shall be provided with auxiliary contacts
wired in
to terminal block for alarm indication of each MCB tripping.

592

b. For each Kiosk pertaining to one diameter of EHV the following shall be
provided:
i. DCDB of suitable rating for 220V DC Source -1 with feeder MCBs for DC supply to
relay panels for one diameter of EHV. Typically 5 feeder MCBs dedicated to five
relay panels in one diameter plus feeder MCBs for other panels and 3 spare MCBs.
ii. DCDB of suitable rating for 220V DC Source -2: Similar to DCDB-1
iii. ACDB of suitable rating for 230V AC Source with feeder MCBs for AC supply to
relay panels for one diameter of EHV. Typically 5 feeder MCBs dedicated to five
relay panels in one diameter plus feeder MCBs for other panels, utility and auxiliary
items and 3 spare MCBs.

593

TECHNICAL SPECIFICATION FOR SUB-STATION AUTOMATION SYSTEM (SAS)

1) GENERAL :
This specification provides for complete Design & Engineering, Manufacture, FAT
(Factory acceptance test), packing, shipment, insurance, transport and delivery to
site, installation, testing and commissioning with SAT (Site acceptance test) of the
substation automation system completely as described in the following sections to
control and monitor the 765 kV bays, 400 kV bays, ICTs, Reactors and associated
equipments at the substation and all the station auxiliary equipments of the
substation. The scope of SAS commissioning is inclusive of the system integration
with the SAS of the following items: Control & Relay panels for EHT bays, Online
diagnostic monitoring system for transformers, Online diagnostic monitoring system
for transformers bushing in this context all necessary materials and works are
included in the SAS scope of supply and commissioning. Communication interface
between field device of online diagnostic monitoring system for
transformers,bushings and the associated Work station should be using fibre optic
cable only as the this media is necessary to protect from Electro magnetic
interference and the high voltage surges experience in the switch yard.
The details of Electrical bays in the substation are given in the single line diagram
of the substation.
The substation automation system (SAS) shall be installed to control and
monitor all the substation equipments from Local Control room as well as from the
remote load dispatch centre/ Master. The SAS shall be designed such that it
enables the user for control & monitoring of the substation at the HMI level
(through Operator work stations), at the Bay level ( through BCU) and at the
switchgear level/Manually (facilitated by TNC switch, Energy meters etc).
The SAS shall be based on a decentralized architecture and on a concept of
bay-oriented, distributed intelligence. Functions shall be decentralised, object-
oriented and located as close as possible to the process. The main process
information of the station shall be stored in distributed databases. The typical SAS
architecture shall be structured in two levels i.e. station and bay level. The
database sizing shall be sufficient to accommodate for current Single line diagram
and future expansions. The distributed architecture for the complete SAS is to be
implemented with all the control and relay panels for one complete diameter to be
594

located in a kiosk located in the switch yard close to the corresponding diameter.
The kiosk is of pucca building that ensures the room temperature even without the
air conditioner is well within the operating temperature of all the Control & relay
panels housed in the kiosk. All the communication link between the Control & relay
panels in the kiosk and the Control room is by fiber optic cables only. All the
communication link between the online diagnostic monitoring system for
transformers and its bushings, reactors etc and the Control room is by fiber optic
cables only.
At bay level, the IEDs shall provide all bay level functions regarding control,
monitoring and protection, inputs for status indication and outputs for commands.
The IEDs should be directly connected to the switchgear without any need for
additional interposition of transducers.
The data exchange between the electronic devices on bay and station level shall
take place via the communication infrastructure. This shall be realized using fiber
optic cables, thereby guaranteeing disturbance free communication. The fiber
optic cables shall be run in suitable conduit pipes. Data exchange is to be
realized using IEC 61850 standards with a external managed switched Ethernet
communication infrastructure in decentralized ring configuration.
o All the numerical IEDs must be fully IEC 61850 compliant and must
have the following features.
o Peer-to-peer communication using GOOSE messages (IEC 61850) for
interlocking.
o Interoperability with third party IEC 61850 compliant devices
o Generate XML file for integration/engineering with vendor
independent SCADA systems.
o Should be directly connected to the inter bay bus on IEC 61850
without the use of any gateways. Connections of bay protection IEDs
to the IEC 61850 bus through the bay control units are not
acceptable.
The sub-station configuration language shall be based on XML format shall be
defined for system configuration and the same shall be furnished for system
integration and end user.
Failure of one set of fiber shall not affect the normal operation of the SAS.

595

However, it shall be alarmed in SAS. Each fiber optic cable shall have adequate
spare fibers.
At station level, the entire station shall be controlled and supervised from
the stationHMI. It shall also be possible to control and monitor the bay from
the bay level equipment at all times, accordingly a graphic user interface
(GUI) display shall be provided in each baycontrol unit. The GUI display in
the BCU shall display the status of the bay devices (breakers, isolators,
switches etc) in real time along with the related measurands. All alarms
related to the respective bay shall be displayed in the BCU through its LEDs
or in its GUI display as an alarm list/scroll. A TNC switch shall be provided
for each breaker in the respective C&R panel of the bay for facilitating
manual operation for facilitating operation in emergency condition. The
BCUs shall be located in the respective relay panel itself and Multiple BCUs
shall not be housed in a single panel. Clear control priorities shall
preventoperation of a single switch at the same time from more than one of
the various control levels, i.e. station HMI, bay level or apparatus level. The
priority shall always be on the lowest enabled control level. The station level
contains the station-oriented functions, which cannot be realized at bay
level, e.g. alarm list or event list related to the entire substation etc. All the
data cabling & other interconnections shall be through fibre optic cables
wherever possible except for power supply.
Communication with the remote control centers State Sub-load Dispatch Centre
through Gateway on IEC 60870 5 101/104 of SCADA/EMS system through PLCC
Modems/Fibre optic interface equipment as applicable. This interface shall support
communication to the remote control centre on IEC 60870 5 101/104 through
redundant communication ports. TAN TRANSCO Engineers shall be co-coordinated
for integration. The data should be made available for the polling schedule of the
SCADA/EMS system at State Sub-load Dispatch control centre. Any support
required for completing the task shall be in bidders scope.
FUNCTIONAL REQUIREMENTS :

a) Control of all equipments mentioned in the Single Line diagram.


b) Supervisory function (i.e.) Data Acquisition, Processing, Monitoring,
Analysis and Diagnostic,
596

c) Data Exchange
d) Report Generation and Printing.
e) The updating times on the operator station under normal and calm
conditions in the substation shall be as follows:
Function Typical values

Exchange of display (first reaction) <1s


Presentation of a binary change in the process display < 0.5 s
Presentation of an analogue change in the process display <1s
From order to process output < 0.5 s
From order to updating the display < 1.5 s

3) CONTROL:
Basic Functions :

a) To execute commands from both operator work stations HMI.


b) Select before execute commands.
c) Operation of all 230 kV and 110 kV Circuit breakers and all the associated
motorized Isolators through output contacts of corresponding BCUs.
d) Operation of On load Tap Changer: Manual Operation from HMIs through
BCU is envisaged.
e) Provide interlocking of different switchgear/isolators for their correct and
safe operation.
f) Monitoring of Circuit breakers, Isolators and Earth Switch contacts (status)
4) OTHER FUNCTIONS:
a) Switching sequences.
b) Time synchronizing through GPS.
c) Monitoring of complete DC system, input & output supply Voltages of
chargers,load currents, Battery voltages etc.
d) Monitoring of fire-protection system.
e) Monitoring of DG operation.
f) Changing relay settings of all numerical relays from Engg./DR works
station with suitable software.

597

g) Storage of data.
h) Collection of disturbance record files from various relays and analysis of the
same from Engg/DR works station with suitable software.
i) Auto re closure selection and monitoring.
j) Bus PT change-over.
k) Carrier IN/OUT selection.
l) Synchro check provision.
m) Reset facility from HMI for reset of all numerical relays, master trip relays.
n) Monitoring of control room temperature, kiosk room temperature etc.
5) INTERLOCKING:
The interlocking function provision through logic gates prevents unsafe
operation of equipments such as breakers ,isolators and earthing switches
for all switching operation within a bay or station . An override function at
Bay level shall be provided, which can be enabled to by-pass the interlocking
function via a key/password, in cases of maintenance or emergency
situations. This over ride function should be accessed with higher level
pass word security. All critical interlocks such as close operation of breakers
and isolators etc shall be implemented in hardwired method also. In order to
provide additional security for safe operation of the primary equipments, the
hard wired interlock shall also be implemented preferably at the yard control
cubicle.

6) SUPERVISORY FUNCTION: DATA ACQUISITION, PROCESSING


MONITORING, ANALYSIS AND DIAGNOSTICS.
The status of each switchgear, e.g., circuit breaker, isolator, transformer tap
changer etc., shall be continuously acquired through polling sequences. ie.,

- Polling on request

- Automatic Polling (Every 5sec, 10sec,.)

- Polling by exception (change of digital status)

Every detected change of position shall be immediately visible on the screen


in the single-line diagram, recorded in the event list, Alarms shall be initiated
in cases when spontaneous position changes have taken place.
598

Each position of an apparatus shall be indicated by two binary auxiliary


switches which are opposite each other in normally closed (NC) and
normally opened (NO) position. An alarm shall be initiated if these position
indication indicate an excessive running time of the operating mechanism to
change position through watchdog timers.

7) DATA ACQUISITION, PROCESSING AND MONITORING:


Conventional interlock through hardware wiring is to be provided in
addition to the software interlock. The BCU shall be located in the relay
panel itself. The main and redundant station HMI should be located in the
operator table. The distance between the BCU and the HMI will vary
according to site conditions during execution. Bay control shall be provided
to each bay and the number of bays to be provided in each substation as
per SLD is furnished in the bill of materials.
The SA system shall acquire data (analog and digital inputs) from

1) Numerical relays Electronic Energy meters (to be made available in all the
feeders, transformers both HV & LV sides).

2) OLTC, Battery charger etc., Data for the system shall be acquired as hard
wired input for all station equipments stated in the single line diagram.

Automatic Disturbance File Transfer

All recorded disturbance files from the IEDs with integrated


disturbance recorder systems shall be automatically uploaded to a station
HMI database. All the analog values shall in the disturbance records shall
be displayed in primary values. A dedicated computer as relay engineers
console (EWS) shall be offered for analysis of records additionally.
DATA REQUIRED:

KW, KVA, V,I, PF, kWh, kVah and kVarh from electronic energy meters (four
quadrant type) , bus voltage and frequency for the relevant EHV system
(765 kV and 400 Kv) shall be measured and communicated on MODBUS /
IEC 61850/ Standard Open protocol to SAS and values shall be obtained
and displayed in both HMIs.

599

Provision shall also be available for extracting these measurements from the
relays and BCUs in addition to following protection function data (not
exhaustive).
a. For each 765kV Bays .
All relevant Status, alarms pertaining to 400 KV Bays.
b. 400KV Bays:
All relevant Status, alarms pertaining to 400 KV Bays.
c. For each transformer separately
Differential relay tripping
Over current relay for HV tripping
Over current relay for LV tripping
Master relays(1 & 2 separately)
LBB relay actuation
DC fail for source 1 & 2
Buchholz relay alarm
Buchholz relay trip indication
Oil/winding temperature alarm
PRD acted
Fault I& V
d. For each breaker
Status ON/OFF
Air/gas pressure low
Air/gas pressure lockout
Pole discrepancy actuation
TSR (common for all trip coil per circuit breaker)
e. Isolator ON/OFF
f. earth switch On/Off
g. Others
Bus bar protection actuation for various voltage level buses. CT circuit
supervision for above bus bar protection(common for each voltage). In case
the bus bar protection relays provided with communication port the zone
operation and CT supervision function shall be acquired on the
communication interface or DI.

600

The measured values shall be displayed locally, on the HMI,


Threshold limit values shall be selectable for alarm actuation.
Basic monitoring functions are:
Switchgear status indication
Measurements (U, P, Q, F)
Event list
Alarm list
Status and display of DC system
Status of display of fire protection system
Acquisition of alarm and fault record from protection relays
Disturbance records
Trend curves
All necessary Indication, alarms, analog values etc apart from the above
mentioned items for the complete substation shall be provided.
8) DATA EXCHANGE TO REMOTE CONTROL CENTRE
All data, records etc as available from all the SAS devices including protection
relays and meters shall be exchanged with Remote control centre through the
gateway equipment with out the aid of Station HMI servers. The gate way
equipment shall be equipped with sufficient memory for data, records etc and
shall support IEC 61850 protocol towards the SAS and IEC 60870 5
101/104 towards the remote control centre.
9) REPORT GENERATION:
Substation Automation System shall record all activities, switching, changes
etc., made in a substation.
Following shall be Automatically monitored:
-Status
-Events, alarms
-Limit values.
Following printouts shall be available from the printer and shall be printed
on demand:
i. Hourly voltage,current and frequency curves.
ii. Trend curves for MW & MVAR.
iii. Printouts of the maximum and minimum.

601

iv. Printout on demand for MW, MVAR, Current, Voltage on


each feeder and transformer tap position, status of pumps
and fans for transformer.
v. Printout on demand system frequency and average
frequency.
vi. Daily, weekly and monthly reports are required. The SA
system shall be capable of delivering the same.
10) BAY CONTROL UNIT
Communication Port :
Equipped with Two optical Ethernet ports at the rear of BCU for parallel
redundancy (in compliance to IEC-62439-3) in networking on IEC 61850 Protocol.
The
above referred 2nos Ethernet ports shall also be used for time synchronization
using SNTP
protocol with guaranteed resolution of 1ms.
Binary Inputs : Sufficient for application plus spare opto-isolated inputs
(Spare binary inputs shall be minimum 4 nos or 20% of application quantity
whichever is higher).
Binary Outputs : Sufficient for application plus spare potential free outputs
(Spare binary outputs shall be minimum 4 nos or 20% of application quantity
whichever is higher).
For BCU used for common alarms for the substaion : The BCU shall be equipped
with I/O modules sufficient for the application plus spare I/O points that are spare
Binary input : 16 Nos, spare Binary Output : 8 Nos, Spare DC Analog input : 8
Nos.All necessary station alarms including but not limited to GIS alarms,Fire alarm
system, Inverter, online diagnostic monitoring system for transformer,bushings etc
shall be wired to SAS and made available in the SAS HMI.
All binary inputs, binary outputs and LEDs of BCU must be user programmable,
BCU without this facility will not be acceptable. The IEDs should be directly
connected to the switchgear without any need for additional interposition of
transducers. The bay control units shall be equipped with I/O modules inherently in
the unit without external I/O modules for interfacing with the process inputs and
outputs, However, all the commands extending for control of switchgears

602

(Breakers, isolators) shall be routed through suitable interposing relays with a


scheme to automatically check the healthiness of these interposing relays. The Bay
control IED should be provided with sufficient number of programmable LEDs.
Each bay control IED shall be independent from each other and its functioning shall
not be affected by any fault occurring in any of the other bay control units of the
station. The bay control unit shall be fed from redundant DC power supplies, this
may implemented with redundant power supply modules in the BCU or with
automatic DC source selection with a suitable auxiliary relay.
Functions for BCU:
Control mode selection
Select-before-execute principle
Command supervision:
Interlocking and blocking
Double command
Synchro check, voltage selection
Run Time Command cancellation
Operation counters for circuit breakers and pumps
Hydraulic pump/ Air compressor runtime supervision
Operating pressure supervision through digital contacts only
Breaker position indication per phase
Alarm annunciation
Measurement and display of Vrms, Irms ,HZ ,W, Var for each phase and for
3phase
Local HMI (local guided, emergency mode) with Graphic display for real
time display of the bay status, measurands etc. The single line diagram in
the display of the BCU shall be user configurable at site.
Interface to the station HMI.
Data storage for at least 200 events
Capability to implement bay level interlocks
The update rate for measurement and display of digital inputs , analog inputs and
the control command execution scheme shall be of satisfactory performance as
applied for sub-station applications.

603

Wherever there is a redundant LAN architecture is specified for SAS, each BCU shall
be preferably equipped with two separate Ethernet ports for connection to
redundant LANs preferably with separate IP addresses.
Synchronism and energizing check

The synchronism and energizing check functions shall feature:


Settable voltage, phase angle, and frequency difference.
Energizing for dead line - live bus, live line - dead bus or
dead line dead bus with no synchro-check function.
Synchronising between live line and live bus with synchro-check
function.
Each bay control IED shall be independent from each other and its functioning shall
not be affected by any fault occurring in any of the other bay control units of the
station. The bay control unit shall be fed from redundant DC power supplies which
may implemented with redundant power supply modules in the BCU or with
automatic DC source selection with a suitable auxiliary relay. The GUI display in
the BCU shall display the status of the bay devices (breakers, isolators, switches
etc) in real time along with the related measurands. All alarms related to the
respective bay shall be displayed in the BCU through its LEDs or in its GUI display
as an alarm list/scroll.

The BCU shall conform to the specification stipulated under General requirements
for Numeric type protection relays in this tender specification.The BCU should be
compatible to interoperate and integrate with the IEC 61850 based SAS in
TANTRASNCO sub-stations.
11) TIME SYNCHRONISATION
i) The Time synchronization equipment shall receive the co-ordinate Universal Time
(UTC) transmitted through Geo Positioning Satellite System (GPS) and synchronize
equipments to the Indian Standard Time in a substation. The system shall be able
to track the satellites to ensure no interruption of synchronization signal.
ii) Time synchronization equipment shall include antenna, all necessary accessories
and all special cables and processing equipment etc.

604

iii) The GPS antenna shall have adequate protection from wind, lightning etc. and
shall be mounted anywhere in the Substation roof at a place preferable by the
TANTRANSCO
iv) The synchronization equipment shall have 2 micro second accuracy. Equipment
shall give real time corresponding to IST (taking into consideration all factors like
voltage and temperature variations, propagation and processing delays etc.)
v) Equipment shall meet the requirement of IEC 60255 for storage and operation.
vi) The output signal from each port shall be programmable at site for either one
hour, half hour, minute or second pulse, as per requirement. The equipment shall
have a periodic time correction facility of one-second periodicity.
vi) Equipment shall have real time digital display in hour, minute, second (24 hour
mode)
vii) A separate time display unit (100 mm display high) at a suitable height in the
control room should also be provided.
vi) It shall be compatible for synchronization of all the SAS equipments, all
numerical devices and IEDs in the relay panels, Event Loggers, Disturbance
recorders, PMUs and SCADA at a substation etc.
vii) The equipments should be equipped and ready to provide time synchronization
signals with the following ports:
a)Ethernet ports -2nos for SNTP time signaling through the two separate Ethernet
LANs.
b) PPS Fibre optic ports of sufficient numbers to time synchronise the devices
requiring accurate time signals like Digital fault recorder, PMUs etc.
c) IRIG-B (Modulated) ports BNC type and FO serial ports of sufficient numbers
to signal the relevant devices for the new diameters of 765KV and 400KV level as
well as for 3 spare diameters each for 765KV and for 400KV level.
d) Potential free contact (Minimum pulse duration of 50 milli Seconds.)
e) PTP port for time synchronization of necessary devices.
The time synchronization of all the relevant SAS equipments shall be realized using
the SNTP protocol through the SAS LAN. A time accuracy of 1ms shall be achieved
for all the devices within SAS.
12) HMI FUNCTIONS:
PRESENTATION AND DIALOGUES GENERAL

605

The Local HMI for Operation & Engineers console shall provide basic functions
for supervision and control of the substation. The operator shall give commands
to the switchgear on the screen via mouse clicks or soft-keys through keyboard.
The HMI shall provide the operator with access to alarm and events displayed on
the screen. Besides these lists on the screen, there shall be a print out of hard
copies of alarm or events.
Following standard display shall be available from the HMI:
* Single line diagram showing the switchgear status and measured vales.
* Control dialogues.
* Measured values
* Alarms list.
* Events list.
* System status.
* A/R selection
* PT selection/ CT selection (one and half breaker scheme)
* Carrier status
* Tripping selection
13) SYSTEM SUPERVISION DISPLAY:
The SA system shall be comprehensively self-monitored and faults will be
immediately indicated to the operator before they develop into serious
situation. Such faults are recorded as faults in a system supervision display.
The display shall cover the status of the entire substation including all
switchgear, Numerical relays and communication links. Dynamic colouring
of single line diagram with load, power factor voltage. Bay view to zoom all
the parameter.
All interlock status information for control circuits pertaining to the CB,
Isolator, earth switch should be displayed in the SAS. Where ever interlock is
not satisfied that should be highlighted in separate colour for operator alert.
14) EVENT LIST
The event list shall contain events with time tag (universal time
synchronization with GPS) , which are important for the control and
monitoring of the substation. The date and time has to be displayed for
events. The events shall be registered in a chronological events list in which

606

the type of event and its time of occurrence are indicated. It shall be
possible to store all event in the HMI. The information shall be obtainable
also from printed event log.
15) ALARM LIST:
Fault and error occurring in the substation shall be listed in an alarm list and
shall be immediately transmitted to the control centre. The alarm list shall
substitute a conventional alarm table, and shall constitute an evaluation of
all station alarm however alarm and visual must be provided on receiving
alarm. It shall contain unacknowledged alarms and persisting faults. Date
and time of occurrence shall be indicated. Historical data sizing for storing
Data for 35 days shall be available in the SA system. The capacity of the
server is to be designed accordingly. Also necessary hardware and software
to copy and store data from server should be provided. The data collected
shall not be lost due to overflow. Whenever overflow is likely to occur, the
date shall be archived into storage media like CD so that there is no change
of losing historical data.
16) RIGHTS:
local HMI: shall be able to get data from all the equipments for monitoring
and control.
Engineering/DR work station: shall have the facility for relay setting and
analysis of faults by acquiring disturbance recorder data from Numerical
relays.
The alarm list consists of a summary display of the present alarm
situation. Each alarm shall be reported on one line that contain.
The alarm date and time.
The name of device in alarming state.
A descriptive text.
The acknowledgement state.
The operator shall be able to acknowledge alarms, which shall be
either audible or only displayed on the monitor. Acknowledged alarms
shall be marked at the list. Filters for selection of a certain type or group of
alarm shall be available as for events.

607

17) SYSTEM TESTING:


The supplier shall submit a test specification for factory acceptance test
(FAT) and commissioning tests of the station automation system for
approval. If the complete system consists of parts from various suppliers or
some parts are already installed on the site, the FAT shall be sub-system
tests. In such a case, the complete system test shall be performed on site
together with the site acceptance test (SAT).

18) EXTENDABILITY IN FUTURE:


Offered substation automation system shall be suitable for extension in
future for additional bays. During such requirement, all the drawings and
configurations, alarm/event list etc. displayed shall be designed in the such
a manner that its extension shall be easily performed by the Engineers
authorized. During such event, normal operation of the existing substation
shall be unaffected and system shall not require a complete shutdown.

The SAS servers and the Engineering workstations, gateway devices shall be
equipped with all necessary hardware and original softwares to
accommodate the future electrical bays without additional cost to
TANTRANSCO and without the need for additional licenses from original
equipment manufacturer.

19) RELIABLITY AND AVAILABLITY:


The bidder shall select & design & supply the SAS for the overall availability
of 99.98% with the following understanding.

The SA system shall be designed to satisfy the very high demands for
reliability and availability concerning.

a. Solidmechanical and electrical design


b. Security against electrical interference (EMI).
c. High quality components and TAN TRANSCOs.
d. Modular, well-tested hardware.
e. Thoroughly developed and tested modular software.
f. Easy-to-understand programming language for application
programming.
608

g. Detailed graphical documentation and application software.


h. Built-in supervision and diagnostic function.
i. Panel design appropriate to the harsh electrical environment
and ambient conditions.
j. Panel grounding immune against transient ground potential
rise.
The entire SAS shall be provided with comprehensive cyber security including
intrusion protection and protection against virus attacks preferably integrated in the
Ethernet switches, routers, IEDs etc. The cyber security shall provide protection
against unauthorized access to the equipment and unauthorized transfer,
modification or destruction of data whether deliberate or accidental. The SAS
vendor shall propose how the SAS solution provides the cyber security. In this
context all the necessary hardware and softwares is included in the scope of the
SAS.

20) Documentation:
The following documentation to be provided for the system in the course
of the project shall be consistent, CAD supported, and of similar look/feel:

e. List of Drawings.
f. Substation automation system architecture.
g. Block Diagram.
h. Guaranteed technical parameters,
i. List of Signal-Analogue/Digital.
j. Schematic diagrams.
k. List of Apparatus.
l. List of Labels.
m. Logic Diagram.
n. Test schedule and reports of FAT/SAT
o. Product Manuals
p. Operators Manual.
m. Listing of software and loadable in CD ROM as well as in the

spare HDD.

609

3 sets of CD ROM containing all the as built documents/drawing shall be


provided.

Also the final documentation shall provide:

- The System specification description (SSD) file that outlines this

substation automation project.

- IED capability description file (ICD) that describes the available functions
logical nodes and services available from IED.

- Substation capability description file (SCD) that describes the relationship


among the IEDs in the substation automation system and their information
exchange structure.

- Configured IED description file (CID) that is final file to download into IED
to enable its configuration

21) HMI SERVERs:


The HMI server functionality and operator work station facilities may be
integrated in the station HMI (Main) as well as in the redundant station HMI.
* Each server shall be equipped with at least one (1) CD/DVD RW drive to
allow transfer of data and other software from the Hard Disk(s) to removable
CD/DVD media.
All computers including HMI servers, Work stations etc shall be provided with
comprehensive anti-virus protection and cyber protection as appropriate.
Type Industrial grade substation-hardened computer hardware
equipment suitable to be rack mount in a IP 41 compliant cabinet
housing 19 rack frames.
Includes all necessary software and hardware for the application.
KVM extender with Full size Keyboard with 10key numeric
keypad,Mouse ,Monitor. DVD +/- RW read write facility.
Communication ports : 3XUSB, Dual 1000Mbps LAN ports, Plus
ports for other user interface.
Cabinet for IP41 compliant standalone cabinet with outer protective glass door.
Server Equipped with all necessary accessories.

610

Processor Latest generation intel processor ,3 GHz or Higher

Bus side speed 1000MHZ or higher

Softwares Windows 8.1 professional or advanced version. 32 bit or higher.


With antivirus software package. All necessary softwares for the
application.
HDD 2 nos HDD 500 GB in redundant RAID-2 configuration
(In case 500 GB is not sufficient for application including data then
higher capacity shall be provided for each HDD. The HDDs should
be configured such that mirror image of the data is available in the
other HDD.
RAM Expandable RAM equipped for 4GB or 200% application
requirement whichever is higher.
DISPLAY 29 LED monitor Flicker free, high resolution of reputed make.
MONITOR Flicker free (TUV Certified), Anti glare, IPS Panel, Full HD
Resolution (1920x1080) with HDMI port and conventional port
interface for computer interface. Min height : 15.5.
Note : The above configuration is minimum requirement, however a higher
configuration is required for the application then the server shall be provided
accordingly.
The redundant station HMI server shall operate in hot standby mode and vice
versa in case of a switch over. The real time data base of the main and
redundant HMI servers shall be synchronized at all times without loss of real
time data in case of a switchover. Also one remote client facility for Station
HMI access with relevant original licenses and software shall be provided.
Each of the server shall be equipped with two Ethernet ports for parallel
redundancy (in compliance to IEC-62439-3) in networking on IEC 61850
Protocol. The above referred 2nos Ethernet ports shall also be used for time
synchronization using SNTP protocol with guaranteed resolution of 1ms.
22) Engineering Work station
Type Industrial grade substation-hardened computer hardware equipment.

Includes all necessary software and hardware for the application.


Full size Keyboard with 10key numeric keypad,Mouse ,Monitor. DVD
+/- RW read write facility.

611

Communication ports : 3xUSB, Dual 1000Mbps LAN ports, Plus ports


for other user interface.
Processor Latest generation intel processor ,3 GHz or Higher

Bus side speed 1000MHZ or higher

Software Windows 8.1 professional or advanced version. 32 bit or


higher. With antivirus software package.
All necessary softwares for the application.
HMI Client access software. All softwares for configuration of
numerical relays, IEDs,BCUs etc.
DR Software for View and analysis of COMTRADE files.
HDD 2 nos HDD 500 GB in redundant RAID-2 configuration
(In case 500 GB is not sufficient for application including data
then higher capacity shall be provided for each HDD. The HDDs
should be configured such that mirror image of the data is
available in the other HDD.
RAM Expandable RAM equipped for 4GB or 200% application
requirement whichever is higher.

DISPLAY 29 LED monitor Flicker free, high resolution of reputed make.


MONITOR Flicker free (TUV Certified), Anti glare, IPS Panel, Full HD
Resolution (1920x1080) with HDMI port and conventional port
interface for computer interface. Min height : 15.5.

Note : The above configuration is minimum requirement, however a higher


configuration is required for the application then the server shall be provided
accordingly.

The engineering work station should be equipped for :


- Data retrieval and analysis of recorded data from SAS devices including
disturbance records, fault records, event records etc
- Remote configuration of SAS IEDs, Numerical protection relays, Digital
Energy meters etc. All relevant software tools is to be provided for this
purpose.
- Client access facility to station HMI with all the relevant softwares.

612

The engineering works station shall be provided with a simple Network


Management System (NMS) software for following management functions of
Ethernet switches, SAS devices supporting SNMP.
a. Configuration Management
b. Fault Management
c. Performance Monitoring
This system shall be used for management of communication devices
and other IEDs in the system. This NMS shall be easy to use, user friendly
and menu based.

The Engineering work station shall be provided with comprehensive anti-virus


protection and cyber protection as appropriate.

Each workstation shall be equipped with at least one (1) CD/DVD RW drive to
allow transfer of data and other software from the Hard Disk(s) to removable
CD/DVD media.

23) Metering PC
Type Industrial grade substation-hardened computer hardware
equipment

Includes all necessary software and hardware for the


application. Full size Keyboard with 10key numeric keypad, Mouse
,Monitor. DVD +/- RW read write facility.

Communication ports : 3xUSB, Dual 1000Mbps LAN ports, Plus


ports for other user interface.

Cabinet for IP41 compliant standalone cabinet with outer protective glass door.
Server Equipped with all necessary accessories.

Processor Latest generation intel processor ,3 GHz or Higher

Bus side speed 1000MHZ or higher

Software Windows 8.1 professional or advanced version. 32 bit or higher.


With antivirus software package.

Base communication software for ABT meter configuration and

613

automated data retrieval from ABT meters using DLMS protocol.

HDD 2 nos HDD 500 GB SATA. (In case 500 GB is not sufficient for
application including data then higher capacity shall be provided for
each HDD. )

RAM Expandable RAM equipped for 4GB or 200% application


requirement whichever is higher.

DISPLAY 27 LED monitor Flicker free, high resolution of reputed make.


MONITOR Flicker free (TUV Certified), Anti glare, IPS Panel, Full HD
Resolution (1920x1080) with HDMI port and conventional port
interface for computer interface. Min height : 15.5.

Note : The above configuration is minimum requirement, however a higher


configuration is required for the application then the server shall be provided
accordingly.

All relevant original software and tools for viewing in real time and generating
reports relevant to metering data.

Metering reports should be customized as per TANTRANSCOs requirements.

The metering data from the meters shall also be integrated in to the station
HMI servers in real time through the SAS LAN. The metering PC should be
provided with comprehensive anti-virus protection and cyber protection as
appropriate.

24) COMMUNICATION NETWORK:


All the SAS equipments that are to be integrated with the SAS should be
provided with suitable communication ports to connect to the LAN and
support IEC 61850 protocol. Digital energy meter may be integrated with
the IEC 61850 inter bay bus suitably through data concentrators / media
converters.
Station LANs:
i. Communication network at Station level (i.e at Level-2) : Dual LANs
preferably Bus topologies.

614

ii. Redundancy boxes for interface of each of the computers without of PRP
(PARALLEL REDUNDANCY PROTOCOL) support for compatibility with
redundant communication architecture using to parallel redundancy
protocol should be provided. However all numerical relays, BCUs and SAS
servers,Gateway should be inherently equipped with two ports using PRP
(PARALLEL REDUNDANCY PROTOCOL).

Inter-bay LANs:

i. Communication network at inter-bay level (i.e at Level-1) : LAN


implemented with double Redundant Rings. This implies that the Ethernet
switches shall support double ring connectivity.
ii. Self healing ring architecture shall be provided. The ring LAN architecture
shall have the latest IEEE Standard version of RSTP with acceptable
recovery time satisfactory for the application. Alternatively Redundant LANs
based on PRP (parallel redundancy protocol ) that facilitates vendor
interoperable communications according to IEC 62439-3 is also acceptable.
iii. Separate line interface unit for one full 400kv dia towards fiber optic cable
interface for inter bay LANs shall be provided.
General:
The station LANs shall be separate from the bay level LANs.
All the LANs (Level-1, level-2 stipulated in IEC 61850 standard) for SAS shall
support the following features:
* The entire SAS shall be provided with comprehensive cyber security
including intrusion protection and protection against virus attacks preferably
integrated in the Ethernet switches, routers, IEDs etc. The cyber security
shall provide protection against unauthorized access to the equipment and
unauthorized transfer, modification or destruction of data whether deliberate
or accidental. The SAS vendor shall propose how the SAS solution provides
the cyber security.
* IEEE 802.1Q VLAN facility.
* Traffic segregation and prioritization control via IEEE 802.1p and IEEE
802.1Q

615

* Support SNMP preferably the latest version to provide secure and full
network management. Port Security through disabling of
packets from unauthorized MAC addresses. RMON for
monitoring of network status & statistics.
* IGMP Snooping enabling reductions in multicast
traffic
* SNTP for synchronizing the internal clock of all the devices
connected to the LAN.
* RSTP (IEEE 802.1w) industry standard method
for providing recovery of redundant networks
* RMON for monitoring of network status & statistics
* Port Mirroring assisting network troubleshooting
* Event Logs creating a historical record of events
occurring on the network
* Port Security through disabling of packets
from unauthorized MAC addresses
* SSL Web encryption preventing eavesdropping,
tampering or message forgery
* The backbone link for each ring network
25) CAPACITY:
The system should be capable of handling up to 150 IEDs and 10,000 data
points. In case the application considering with future bays necessitates to support
higher number of devices and data points then the system shall be equipped
accordingly.
26) SEQUENCY OF EVENTS (SOE) FEATURE:
To analyze the chronology or sequence of events occurring in the power
system, time tagging of data is required which should be achieved through SOE
feature of SA. The server should have an internal clock with adequate stability.
The Server time should be set from time synchronization messages received from
GPS equipment to be supplied by bidder. The Server should maintain a clock and
should time-stamp the digital status data. Any digital status input data point in the
Server should be assignable as an SOE point. Each time a SOE status indication
point changes the state, the Server should time-tag the change and store in SOE

616

buffer within it. SOE shall be transferable to the Remote Control Centre through
the IEC 60870-5-101 gateway. The time resolution for SOE should be 1 ms at
point of acquisition.
27) ETHERNET SWITCHES:
The Ethernet switches used for creating the LAN network should meet the
specification as laid down in the IEC 61850 standard and should be of managed
type SNMP based. The Ethernet switches should comply to IEC 61850-3
standard/equivalent for EMI Immunity and environmental compliance pertaining
with Electrical utility substations applications.
* The Ethernet switches shall be equipped with 50% spare ports.
* Dedicated Separate set of Ethernet switches shall be provided for each dia.
*Ethernet switches shall support the features stipulated under general specification
for the LAN.
* Should be Compliant to parallel redundancy Protocol (PRP) in networking on
IEC 61850.
* Digital Diagnostic Monitoring (DDM) for Fiber :
Ethernet switches shall be equipped with the functionality to monitor ST/SC (as
well as SFP) connectors, and NMS via SNMP trap when abnormalities are detected,
allowing
operators to initiate maintenance procedures, Further the complete LAN system
shall allow system operators to monitor things like transmission and reception
power, temperature, and voltage/current along optical fiber connections in real
time.
28) GATEWAY EQUIPMENT
The Gateway equipment shall conform to the following technical
requirements:
- The gateway equipment shall be based on embedded technology without moving
parts.
- The gateway equipment shall comply to IEC 60255 standards / Equivalent
IS for EMC and Environmental compliances.
- Support IEC 61850 protocol, IEC 60870-5-101/104 protocol.

617

- Perform the data concentration by directly collecting data from the bay level
devices and provide the same to the remote LDC/Master with out the aid of the
SAS HMI servers.
- The gateway device should be equipped with sufficient memories for firmware,
Configuration data, Process data, records.
- Equipped with redundant communication ports for SAS interfaces as well as for
remote LDC/Master interfaces.
- Equipped to run high speed programmable logic control function that includes
provision for implementing station level interlocks and automation logic as
necessary.
- Necessary software with original license for Anti-virus protection with Relevant
firewall should be provided for operating system based on MS windows.
- The gateway equipment shall be rack mount housed in a IP31 compliant cabinet
with protective glass door. Cabinet design shall ensure to be equipped with the
standard accessories specified for relay cabinets.
- Gateway shall be equipped with redundant power supply modules and
communication modules.
Redundant Gateways i.e 2 nos Gateways operating in redundant
configuration shall be provided. One of which operating in online and the other
operating in hot standby by shall be provided. The switchover between gateway
devicesshall beAutomatic, quick enough for the application, bump less
without loss of SAS data during switchover, the databases of the
online and hot stand by shall be synchronized in real time. It shall be
possible to operate with one gateway device in case of outage or failure of
one gateway device.
Each of the gateway unit shall be equipped with two Ethernet ports for parallel
redundancy (in compliance to IEC-62439-3) in networking on IEC 61850
Protocol.The above referred 2nos Ethernet ports shall also be used for time
synchronization using SNTP protocol with guaranteed resolution of 1ms.

618

29)CONCEPTUAL SCHEME FOR SAS

EventPrinter StationHMI Redundant Engg.WS MeteringPC


Report
StationHMI
Printer

STATION LAN-A

STATION LAN-B STATION LAN (IEC 61850 LEVEL-2)

Protocol GPS
converter SYSTEM
IEC101/104
TOREMOTE Communication Redundant Device
LDC terminal Gateway
Equipment Devices Meter

Meter

INTERBAY LAN (IEC 61850 LEVEL-1)

ToStation
Ethernetswitchfor1No
765kVdiameter
Ethernetswitchfor1No
Ethernetswitchfor1No InterbayLANAFOLINK
400kVdiameter
765kVdiameter

Ethernetswitchfor1No
400kVdiameter

ToStation Ethernetswitchfor1No
765kVdiameter
Ethernetswitchfor1No
Ethernetswitchfor1No InterbayLANBFOLINK
400kVdiameter
765kVdiameter

Ethernetswitchfor1No
400kVdiameter

619

SAS ARCHITECHTURE : INTERBAY LAN (IEC 61850 LEVEL-1)

Ethernetswitchfor1No765kVdiameter Ethernetswitchfor1No765kVdiameter

765kVFRP
ToLANA
Main1 PRPPorts ToLANB

Main2 PRPPorts ToLANB

ToLANA
BCU PRPPorts ToLANB

RS485FOlinktoMeteringPC(DLMS)
ABTMeter
ToLANA (IEC61850)

PU ToLANA
PRPPorts
(BBPMain) ToLANB 765KVTIERP
ToCUBBP(Main) ToLANA
PRPPorts Main
ToLANB
PU ToLANA
PRPPorts
(BBPMain) ToLANB
ToCUBBP(Backup)
ToLANA
PRPPorts BCU
765kVTRF(HV)RP ToLANB
ToLANA
Main1 PRPPorts ToLANB

ToLANA
Main2 PRPPorts ToLANB

ToLANA
BCU PRPPorts ToLANB

CSD ToLANA
Redundancy
Box PRPPorts ToLANB

RS485FOlinktoMeteringPC(DLMS)
ABTMeter
ToLANA (IEC61850)

PU ToLANA
PRPPorts
(BBPMain) ToLANB
ToCUBBP(Main)

PU ToLANA
PRPPorts
(BBPMain) ToLANB

ToCUBBP(Backup)
620

Note :

1. Link between Ethernet switches in each diameter is of ring architecture with


RSTP protocol the ring recovery time should be small enough to avoid disruption to
sub-station automation system. This is applicable for LAN-A as well as LAN-B
Ethernet switches. Ethernet switches should also be compliant to PRP.
2. All Devices connected to Both LAN-A and LAN-B should be compliant to parallel
redundancy protocol.
3. Ethernet switch for one diameter should be equipped with tributary ports for
connecting all devices in the relay panels for one EHV diameter plus 50% spare
ports.
4. Devices shown in the drawings above is for conceptual information. Any other
devices and relay panels in each diameter will be applicable as required.

621

30. INVERTER :

1.The inverters shall comply with the following specification and characteristics:

Type of inverter On Line P controlled IGBT


TYPE based Static inverter

120% of assigned load or 3 KVA whichever


Rating @ 50 c of each inverter is higher.

Type of power switching Pulse width modulation

2 nos to operate in redundant


configuration with automatic switch over in
No. of inverters case of failure of one unit.

220V DC +/- 10% taken from station battery


Input Voltage banks

Output voltage Single phase 230V AC + /-1%

Nominal frequency 50 Hz

Frequency regulation i) Free running 0.01 HZ

Less than 2.5% for linear load &


Total harmonic distortion of output voltage Less than 5% for non-linear load

Single harmonic of output voltage Less than 3%

Power factor range Rated 0.8 (0.6 to Unity, within KVA & KW)

Method of cooling Forced air cooling

SAS Servers, Engineering Workstation,


Metering PC, LAN Equipments pertaining
Assigned Load to Level-2, Printers Etc.

Alarm Dry contact for minor and major alarm

Note: A worksheet depicting the total calculation of the assigned load should be
furnished in assessing the rating of the inverter.
2.The inverters shall comply with the following characteristics:
i) The inverters shall normally operate in synchronism with the mains AC power
source. Upon loss of the mains AC power source or its frequency deviating beyond
a preset range, the inverters shall revert to their own internal frequency standard.
When the mains AC source returns to normal, the inverters shall return to
synchronized operation with the mains AC source. Such reversal of operation of
622

inverters from synchronous to free running mode and vice-versa shall not introduce
any distortion or interruption to the connected loads. A suitable dead band for
frequency may be provided to avoid unnecessary frequent reversal of inverter
operation between free running mode and synchronized mode under fluctuating
frequency conditions.
ii). For safe operation in the event of Power failure or input source voltage
dropping below preset value, necessary safeguard software shall be built in for
proper shutdown and restart.
iii) The inverters shall be synchronized to the main AC source unless that
source deviates from 50 Hz by more than 1% (adjustable to "1/2/3/4/5%).
iv). The inverters shall provide interrupter switch to isolate the unit from the load
on failure of the unit. The interrupter switch shall be rated to carry full continuous
load and to interrupt the inverter under full fault load.
v).The inverters shall be capable of supporting a start-up surge or
overload of 150 % of rated output for up to 60 seconds.
vi).The transient voltage response shall not exceed "4% for the first half-
cycle recovering to 1% within ten cycles for a 100 percent step load
application or removal.
3. Control panel for auto/manual switch over of the redundant inverters shall
be provided with the inverter.
4.The scope of supply, installation, testing and commissioning of inverter also
includes All the necessary AC Distribtuion boards, DC Distribution boards, Control
panel to facilitate manual change over, auto change over and bypass mode with
meters for monitoring the voltages. Tender scope includes all the necessary power
cables and control cables for this equipment.
5. Type tests for inverter:
The inverter shall comply to IS 13314 / Equivalent standards as applicable for the
KVA required for the project
This includes the following tests.
1. Visual inspection test
2. High voltage test
3. Insulation resistance test
4. No-load test

623

5. Output test
6. Climatic tests
7. Harmonic contents test
8. Radio frequency interference test for conducted emission in the AC output
circuit.
31. Laptop computer for SAS tool

Type Reputed make laptop computer

Processor Latest generation intel processor ,3 GHz or Higher

Software 1.Windows 8.1 professional or advanced version. 32 bit or higher.


2. Antivirus software package validity for entire project guarantee
period.

3. HMI software for client access to SAS HMI.

4. MS office suite latest version.

5.All other necessary software for configuration of SAS devices,


Relay panels devices.

HDD 2 nos HDD 500 GB

(In case 500 GB is not sufficient for application including data


then higher capacity shall be provided for each HDD. )

RAM Expandable RAM equipped for 4GB or 200% application


requirement whichever is higher.

DISPLAY 15 LED monitor HD resolution, Anti glare.

Optical drive DVD +/-RW

Keyboard & Full size Spill resistant keyboard with 10key numeric keypad,
MOUSE Optical mouse.
Connectivity Wifi, Bluetooth, USB port-3nos, RJ45 10/100Mbs Ethernet port.

624

BILL OF MATERIALS FOR CONTROL & PROTECTION RELAY PANELS

Note :
1.The bill of materials for relay panels in this section is for conceptual information,
however any additional component and devices required in the relay panels to fulfill
the protection, control and metering scheme shall be included without additional
cost.
2. The Bus bar protection panel shall be equipped completely to accommodate all
the Bays including future Bays depicted in the single line diagram of the
substations plus 6 spare circuits.
3.The under frequency scheme for feeders shall be shall be equipped completely to
accommodate all the feeders including future feeders depicted in the single line
diagram of the substations plus 3 spare feeders.
4. DC supervision relay should be provided for each of DC sources and at the DC
output of the DC selection relay. The DC fail alarm should be made available to the
SAS.
5. If Functions of supervision relays, trip relays,selector switches,auxiliary relays
are incorporated in a multifunction IED then it is subject to design approval from
TAN TRANSCO. Such scheme should be designed such that a single point of failure
in the multifunction IED should not cause failure of simultaneous failures of Main-
I/Main and main-II/Backup protection scheme
6.VT selection for control & Relay panes:
VT selector switch for selection between Line VT/ Bus VT-1/ Bus VT2 shall be
provided. However the scheme shall be provided with logic to ascertain the correct
Bus VT. Separate core shall be wired for Main-1 protection, Main-2 protection and
metering devices.
7. Redundancy boxes for interface of each of the IEDs with single Ethernet port for
compatibility with redundant communication architecture using to parallel
redundancy protocol should be provided. However all numerical relays,
BCUs,Gateway and SAS servers should be inherently equipped with two ports using
PRP (PARALLEL REDUNDANCY PROTOCOL).

625

I. BOM : Relay panel for 765 kV Feeder/Lines as well as for 400 kV


Feeder/Lines

1. Numerical distance protection relay for Main-1 protection as per 1 No


Specification.
2. Numerical distance protection relay for Main-2 protection as per 1 No
Specification. Make should be different from Main-1.

3. Bay control unit 1 No

4. Auxiliary relay for Automatic DC source selection As required.

5. Electronic ABT Trivector meter(As per specification) 1No.

6. Single phase trip relay (with self-reset contacts) 6 Nos.

7. Trip circuit supervision relay 6 Nos.

8. DC supply supervision relay As required.

9. Control switch (TNC) spring return type with pistol grip handle for Breaker 1 No.

10. P.T. selection scheme with bistable relays 1 Set

11. Bus bar Tripping relay (96) 1 No

12. Three phase Master Trip relay (H&ER reset contacts, Hand reset flags) 2 Nos.

13. Three phase master Trip relay for UF (81U,81R) scheme 1 No.

(Self reset contacts, HR flags)

14. Supervision relays for all the master tripping and lockout relays As required

15. Selector switch (A/R IN/OUT; 2Position stayput ) 2 Nos.

16. Selector switch (Carrier IN/OUT, 2Position, 4 Ways,Stay put) 2 Nos.

17. Auxiliary relay for Automatic DC source selection 1 Set

18. Auxiliary relay for circuit breaker alarms/trip As required

(Typically :Loss of SF6, PD Trip, General Lockout, SF6 Lockout, 81X)

19. Synchronising socket 12 Pin / Bus wiring As required

20. Auxiliary relays and timers to fullfill protection scheme As required

21. Standard relay panel accessories as stipulated in this specification -As required
626

II. BOM: ISLANDING PANEL for 765 kV Feeders as well as for 400 kV
Feeders

1. Numerical under frequency relay 1 Set

(As per specification includes 81U,81RF,27,59 etc)

2. DC supply supervision relay As required.

3. P.T. selection scheme with bistable relays 1 Set

4. Supervision relays for all the tripping and lockout relays As required

5. Selector switch for IN/OUT selection of UV,UF,f+df/dt, As required

6. Auxiliary relays and timers to full fill protection scheme As required

7. Auxiliary relay for Automatic DC source selection As required.

8. 3-phase Master Trip relay for UF (for 81U,81RF) scheme for future feeders: 6 nos

9. Supervision relays for all the 86UF relays 6 nos

10.Standard relay panel accessories as stipulated in this specification As required

Note :

1. Master Trip relay for UF (81U,81RF) scheme is to be provided in the respective feeder
relay panels.

2.As the SAS is in distributed architecture and in order to reduce the cabling, the stage
wise trip output commands for respective feeders shall be communicated through GOOSE
messaging to the numerical main-1 and main-2 protection relays of respective feeder bays.

III.BOM: Relay panel for 765 kV Tie breaker as well as for 400 kV Tie
breaker :

1. Bay Control unit 1 No

2. Numerical relay for LBB and O/C,E/F protection 1 No

3. Three phase Master Trip relay (H&ER reset contacts, Hand reset flags) 2 Nos.

4. Three phase Trip relay for UF (81U,81R) scheme 1 No.

(Self reset contacts, HR flags)

627

5. Single phase trip relay with self reset contact 6 Nos

6. Trip Circuit Supervision relay (Pre close and Post close) 6 Nos

7. DC supervision relay As required.

8. Ethernet switch as per specification As required

(Atleast 1 no for one full 400KV dia)

9. TNC Control switch spring return type with pistol grip handle for Breaker 1 No 10. Relay
for Automatic DC source selection As required.

11. High speed trip relay (96) for busbar protection As required.

12.Supervision relays for all the tripping and lockout relays As required

13. Auxiliary relays and timers As required

14. Auxiliary relay for circuit breaker alarms/trip As required

(Typically :Loss of SF6, PD Trip, General Lockout, SF6 Lockout, 81X)

15. .Standard relay panel accessories as described in this technical specification


document.
IV. BILL OF MATERIALS FOR BUS BAR PROTECTION RELAY PANEL 765
KV as well as for 400 KV:

1) Set of low impedance bus bar protection scheme of Numerical type for 1 Set

single/double zone with check zone for bus. 1 Set is inclusive of:

i) Central unit -1 No.

ii) Peripheral units As required for all Main breakers of each diameter plus six spare

peripheral units.

2) DC supervision relays As required.

3) Bus bar cut IN/OUT switch Main and check zones. As required

4) Auxiliary relays for automatic DC source selection As required

5) Auxiliary relays and timers to fulfill scheme As required

6) 3 Phase trip relay (96) As required


628

(shall be be a part of relay panel of the respective panels)

7) Supervision relay for B/B protection As required

trip relays (shall be a part of relay panel of the respective panels)

8) Standard relay panel accessories as stipulated in this specification As required

Note :

1.The Bus bar protection is a redundant (1+1) scheme i.e The above BOM will be
duplicated in second set of Bus bar protection panel. One set of busbar
protection should be of different make from the other set.

2.Spare Peripheral units shall be installed in a separate panel and the same shall be
located in switchyard panel room where bus bar protection panel shall be installed.

3.Peripheral units with all necessary associated materials shall be installed in the
respective bay protection relay panels.

4. For dedicated FO link for redundant Busbar protection scheme consider LIUs as required
apart from the LIUs for the SAS LANs.

V.BOM : RELAY PANEL FOR 765 kV / 400 kV ICT (AUTO TRANSFORMER)

3. Electronic Trivector meter 2 Nos.


4. Numerical relay for Main-1 protection
(As per specification for biased differential protection for three winding 1 No.
Transformer plus non-directional over current protection with LBB and
high set for HV side )

5. Numerical relay for Main-2 protection


(As per specification for biased differential protection for three winding 1 No.
Transformer plus non-directional over current protection with LBB and
high set for HV side )

6. Numerical non-direction over current protection relay with LBB and high set 1 No.
for LV side

5. Relay for Automatic DC selection As required.

6. Bay control units for HV and LV 2 Nos

7. TNC Control switch spring return type with pistol grip handle for Breaker 2 Nos

8. Three phase Master Trip relay (H&ER reset contacts, Hand reset flags)As required

9. Trip transfer switch 1 Set

629

(3 Postion (Normal-BCU Auto-Transfer selector switch), stay put, Lockable type


with removable key, sufficient way)(This item applicable if transfer breaker is
available)

10. Trip circuit supervision relay for HV and LV trip coils As required
(pre close and post close)

11. D.C. supply supervision relay As required.

12. Transducer for Tap position indication 1 no.

(30-250VDC auxiliary supply, IEC 60688 compliant, Output 4-20mA)

13. Supervision relays for all the tripping and lockout relays As required

14. Auxiliary relay for transformer alarms and trip As required

(Typically : Buchholz alarm-3 Element, Oil flow alarm-3, WTI-3 Element, OTI-3
Element, Oil level alarm-3 Element, PRV Trip-3 Element, Buchholz trip-3 Element,
OLTC Low oil Level- 3Element )

15. Auxiliary relay for circuit breaker alarms/trip As required

(Typically :Loss of SF6, PD Trip, General Lockout, SF6 Lockout, 81X)

16. Auxiliary relays and timers to fulfill scheme As required

17. P.T. selection scheme with bistable relays ( for HV and LV ) 2 Sets.

18. High Speed tripping relay (96) for B/B protection 2 Nos

19. Standard relay panel accessories as stipulated in this specification As required


21. Selector switch for L/R selection 2 Nos

Note :

1.Main-1 and main-2 numerical relays should be of different make.

2. CSD in the scope of supply of breaker for each transformer shall be installed
in the transformer relay and integrated with SAS.

VI.BILL OF MATERIALS FOR RELAY PANEL FOR 765 KV LINE REACTOR AS


WELL AS FOR 400 KV LINE REACTOR:

1. Numerical Reactor differential protection relay (87R) - 1 Each

2. Numerical Restricted earth fault protection relay (64R) -As required

(Low Z based For Neutral and neutral grounding reactor side as applicable)

3. Numerical Local breaker back up protection (LBB) (50Z) - 1 Each


630

4. Numerical under impedance protection relay ( 21R) - 1 Each

5. Numerical protection relay for (50/51, 50N/51N,64R,50Z,59) As required

6. Numerical neutral displacement protection relay As requierd

7. Flag relays for thermal imaging, MOG,WTI,OTI, As required.

Bucholz,PRV and staus indication.

8. Bay control unit 1 No

9. DC supervision relays As required.

10. Auxiliary relays and timers,trip relays etc. to fulfill - As required.

protection & automation scheme.

11. High speed trip relay (96) for busbar protection 1 No

12. Three phase Master Trip relay (H&ER reset contacts, Hand reset flags) 2 Nos.

13. Supervision relays for all the tripping and lockout relays As required

14. TNC Control switch spring return type with pistol grip handle for Breaker 1 No

15. Auxiliary relay for circuit breaker alarms/trip As required

(Typically :Loss of SF6, PD Trip, General Lockout, SF6 Lockout, 81X)

16. LBB isolation link 1 No.

17. Relay for Automatic DC source selection 1 no.

18. Standard relay panel accessories as described in this technical specification


document.

Note :

1.The protection scheme for Bus reactor may be grouped in to Grouped in to two
numerical multifunction protection relays wherein the differential protection and backup
impedance shall not be implemented in the same relay. In this context the protection
scheme shall be such that all type of faults within the reactor shall be detected by both the
group 1 & group2 relays. However separate numerical relay for LBB protection is
applicable.

631

2. CT supervision, VT supervision shall be provided in the relays.

3. CSD in the scope of supply of breaker for reactor shall be installed in the reactor relay
and integrated with SAS.

VI.BILL OF MATERIALS FOR RELAY PANEL FOR 765 KV BUS REACTOR AS WELL
AS FOR 400 KV BUS REACTOR:

1. Numerical Reactor differential protection relay (87R) - 1 Each

2. Numerical Restricted earth fault protection relay (64R) -As required

(Low Z based For Neutral and neutral grounding reactor side as applicable)

3. Numerical Local breaker back up protection (LBB) (50Z) - As required

4. Numerical under impedance protection relay ( 21R) - 1 Each

5. Numerical protection relay for (50/51, 50N/51N,64R,50Z,) As required

6. Numerical neutral displacement protection relay As requierd

7. Flag relays for thermal imaging, MOG,WTI,OTI, As required.

Bucholz,PRV and staus indication.

8. Bay control unit 1 No

9. DC supervision relays As required.

10. Auxiliary relays and timers,trip relays etc. to fulfill - As required.

protection & automation scheme.

11. High speed trip relay (96) for busbar protection 1 No

12. Three phase Master Trip relay (H&ER reset contacts, Hand reset flags) 2 Nos.

13. Supervision relays for all the tripping and lockout relays As required

14. TNC Control switch spring return type with pistol grip handle for Breaker 1 No

15. Auxiliary relay for circuit breaker alarms/trip As required

(Typically :Loss of SF6, PD Trip, General Lockout, SF6 Lockout, 81X)

16. LBB isolation link 1 No.

632

17. Relay for Automatic DC source selection As required.

18. Standard relay panel accessories as described in this technical specification


document.

Note :
1.The protection scheme for Bus reactor may be grouped in to Grouped in to two
numerical multifunction protection relays wherein the differential protection and backup
impedance shall not be implemented in the same relay. In this context the protection
scheme shall be such that all type of faults within the reactor shall be detected by both the
group 1 & group2 relays. However separate numerical relay for LBB protection is
applicable in case the LBB for the breaker(s) are not covered in any other scheme.
2. CT supervision, VT supervision shall be provided in the relays.
3. CSD in the scope of supply of breaker for reactor shall be installed in the reactor relay
and integrated with SAS.
VII. Standard relay panel accessories:

All the Control & Relay panels shall have the following

1. Cubicle illumination Lamp (CFL/LED ) with door switch 1 Set.

2. Space heater with thermostat and ON/OFF switch - 1 Set.

3. 5A&15A, 3-Pin socket with pin and ON/OFF switch - 1 Set.

4. Test terminal block for testing metering & protection devices - As required

5. Test block - As required

6. Cable glands As required

7. Terminal blocks As required+20% Spares

8. Wires for CT, Earthing As required

(2.5 Sq.mm, Multi strand, 1100V Grade, PVC Insulated, FRLS )

9. Wires for VT, Alarms, status, Control As required

(1.5 Sq.mm, Multi strand, 600v/1100V Grade, PVC Insulated, FRLS)

633

10. 25*6mm Tinned copper bar As required

11. Cabinet 1 Each

( Free standing, self supported, with swing frame for devices and outer glass door.)

12. Labels for devices 2 Sets

(Inside and outside the panel)

13. Label for panel designation - 2 Nos

14. MCBs (with auxiliary contact) for DC Supply and AC supply distribution As required

circuits
15. DC fail test/accept button - 2 Each

16. AC bell for DC fail alarm - 1 no

17. Synchronising socket (12 Pin) - 1 No.

(Applicable for interface with synchronising trolley) 1 No.

18. Push button for manual resetting of master trip relays (86,96) As required

19. Fuses (VT circuits) and links As required

20. Dedicated Line interface unit for interbay fiber optic LAN interface As required

(Typically 4 nos; i.e 2 Units for each LAN. For dedicated FO link for redundant
Busbar protection scheme consider LIUs as required)

21. Isolation links for isolation of LBB, trip outputs etc. As


required

22. Cable glands As required.

General: The following items are included under the scope of supply for relay
panels and for SAS equipments

1. Manuals (hard copy & soft copy) 3 Sets.

2. As built drawings (hard copy & soft copy) 5 Sets.

634

VIII. BOM FOR SAS (Applicable for each SAS)

Sl. Description Unit


No Qty

1 Industrial grade computer for station HMI (As per Nos.


technical specification) 2

2 Engineering work station (As per technical specification) No. 1

3 Metering PC (As per technical specification) No. 1

4 Gateway Panel (Complete with panel, Gateway Devices- No.


2nos in redundant configuration, Hooter-2nos for
substation urgent & non-urgent alarms) 1

5 Communication equipment (Complete with MODEMs, sets


Lightning arrestors for MODEM, Communication ports 2 (i.e 1 set at SS
and Media interface device etc for gateway redundant and 1 set at
interface to LDC) Remote LDC)

6 Bay Control Unit Nos. As required.


(Refer note
below.)

7 Ethernet Switches ( 50 % spare ports in each switch) to Nos. As required.


implement Redundant LANs at Station level and inter bay
level

8 General printer (A3 Colour LASER Jet Printer) No. 1

9 Report printer (A4 Colour LASER Jet Printer) No. 1

10 All LAN cables with associated cable ducts and all Lot 1
accessories, media converters etc running within a KIOSK
for each diameter as well as in control room building).

All communication cables with associated cable ducts and


all accessories, media converters etc for control,
protection, metering scheme running within a KIOSK for
each diameter as well as in control room building)

Line interface units : As required.

FO Patch panel 2sets (in control room for termination


and interface of FO cables from the switchyard)

11 Time synchronization system (GPS with all accessories, Set


Antenna, cables, software, Lightning arrestors for GPS,
Separate time display unit display size of approx. 100
mm height. etc) 1

635

12 Configuration tools for SAS and Relay panels. Set

1.SAS HMI software for Client access.

2.Laptop computer with all necessary software-1 set.

3. CMRI Instrument (DLMS compatible for ABT meter)


1No.

4. Software for configuration of all devices in relay

panels- 1 set

5. Software for configuration of all SAS devices-1 set.

6. Special Crimping tools 1 set

7. Test plug 3nos

8. Fibre optic Splicing kit-1 set.

9.Any other necessary tools for SAS & relay panels. 1

13 Inverter (As per technical specification) Sets 2

14 Relevant manuals as per SA specification. Lot 1

15 Furniture : Chair (industrial grade revolving type with Nos.


cushion, neck rest and adjustable height and wheels for
mobility.) 5

16 Furniture : Curved type Tables for SAS operator 2Nos; Lot


Table for Engg WS & Metering PC : 2nos. Each table
shall be provided with lockable daweres-2nos. 1

17 Furniture : Tables with drawers-4nos suitable for housing Lot


all the drawings & manuals of the SAS and protection
system. 1

18 Digital temperature sensor with backlit LCD display and


transducer for SAS interface for room temperature
measurement in each Kiosk. Sets As required

Note:

1. The price of the relay panel shall be inclusive of the BCU mentioned in the BOM for the
respective relay panel. The BCU/IED for common alarms shall be considered under supply
of SAS.
2.IED(s)/ BCU(s) with graphic display of sufficient I/O capacity shall be offered for covering
all the sub-station auxiliary items, RMU,Fire alarm system, complete Power supply
(Charger, Batteryand distribution system (DCDB,ACDB),common alarms in the sub-station.

636

3. Media type (PLCC or Fibre optic media or leased line ) for gateway interface to the
remote load dispatch centre would be known during project execution.
4. Furniture shall be industrial grade, reputed brand with design life for 20 years.

5. Outdoor type armoured Fibre optic cables for the SAS LANs for linking the Relay panels
in each diameter housed in each kiosk to the SAS LANs (at level-1,2) and for implementing
communication link for any other control, protection and metering scheme should be
provided in the SAS scope if a separate price item for these cables are not in the price
schedule.

XV. Spares:

Sl.no Description Unit Qty Remark

BCU shall be equipped with maximum configuration


1 Bay control Unit for 765 KV No. 1 stipulated among 765 kV Bays application.
BCU shall be equipped with maximum configuration
2 Bay control Unit for 400 KV No. 1 stipulated among 400 kV Bays application.
Numerical Main-1 Distance
protection relay suitable for 765
2 kV feeder No. 1 Main-1 as stipulated for 765 kV relay panel.
Numerical Main-2 Distance
protection relay suitable for 765
3 kV feeder No. 1 Main-2 as stipulated for 765 KV relay panel.
Numerical Main-1 Distance
protection relay suitable for 400
2 kV feeder No. 1 Main-1 as stipulated for 400 kV relay panel.
Numerical Main-2 Distance
protection relay suitable for
3 400KV feeder No. 1 Main-2 as stipulated for 400KV relay panel.
Numerical Main-1 protection relay
4 for 765 kV/400 kV ICT. No. 1 Main-1 relay as stipulated for relay panel for ICTs.
Numerical Main-2 protection relay
5 for 765 kV/400 kV ICT. No. 1 Main-1 relay as stipulated for relay panel for ICTs.
Numeric relay for bus bar Each set should be of different make corresponding
7 protection- Central Unit Sets 2 to the bus bar relay panel.
Numeric relay for bus bar Each set should be of different make corresponding
8 protection- Peripheral Unit Sets 2 to the bus bar relay panel.
Ethernet switch for one diameter Nos. 4
9 plus 50% spare ports
No. 1
Ethernet switch for Control room
10 plus 50% spare ports
No. 1 As stipulated for relay panel
11 Electronic Trivector meter (ABT)
Nos. 4 As stipulated for relay panel.
12 Automatic DC selection relay
13 Master tripping relay (86) No. 4 As stipulated for relay panel.
No. 4 As stipulated for relay panel.
Master tripping relay for bus bar
14 application (96)
15 TNC Switch Nos. 2 As stipulated for relay panel
16 PT selection relay / Switch No. 2 As stipulated for relay panel.

637


Nos. As stipulated for relay panel
17 D.C. supply supervision relay 2
Nos. As stipulated for relay panel
18 Trip circuit supervision relay 4
Nos. As stipulated for relay panel
Single phase trip relay (with self-
19 reset contacts) 2
Nos. As stipulated for relay panel
20 Selector switch for L/R selection 2
Nos. As stipulated for relay panel
21 Selector switch (A/R IN/OUT) 2
Nos. As stipulated for relay panel
22 Selector switch (Carrier IN/OUT) 2
No. As stipulated for SAS
23 Hard disk for HMI server 1
Each type of Hardware Modules
24 for GPS equipment Set 1
Includes all necessary spares for maintenance of
Inverter for 5 years. IGBT should also be included.
25 Spares for Inverter for SAS Set 1
Complete with FO patch cable.
Line interface unit for SAS FO LAN
26 for one diameter Set 1
Spares for relay panels and SAS in the scope of supply shall be the same make,model/type
as in the actual supply. The numerical relays,IEDs,BCUs under the spares shall be
equipped for maximum I/O configuration.
XVI. TRAINING SCOPE:
Training shall be imparted at works and at site as described below.
a) Training at suppliers works :
Minimum one week training for two batches of Boards engineers at the
manufacturers works with lectures and hands on training on complete SAS &
protection relays. This training shall be imparted prior to commissioning of SAS &
protection system. Training shall be organized in batche(s) wherein each batch
shall comprise at least 5 trainees. All relevant training material, tools and
equipments shall be provided for each trainee towards this training. The training
shall cover the technology, principle of operation, functions etc of the protection
relays and SAS devices. Training content should be furnished to TANTRANSCO for
obtaining concurrence prior to training schedule.
All expenses for trainees towards boarding, lodging, travel , travel insurance etc to
attend the training program is in the bidders scope. In this context charges of any
kind shall not be levied to TANTRANSCO.
b) Training at site (Applicable for each sub-station):
Comprehensive hands on training of TAN TRANSCO engineers at site should be
imparted for two batches as follows:
i. For 1 batch of at least 5 engineers oriented for operations of SAS &
protection system. This training shall be imparted after commissioning of
SAS.
ii. For 1 batch of at least 5 engineers oriented for Testing, commissioning
& maintenance of complete SAS & protection relays. This training shall
be imparted after installation of SAS & protection system. This training
638

should be implemented to enable the trainees to configure, trouble


shoot all the SAS devices including numeric relays, BCU etc for
rectification of faults and prepare the trainees to use all the
configuration tools for all of the SAS devices. The training should
enable the trainees to carry out the necessary modifications in SAS for
bay extensions / deletion/modifications etc.
All expenses of the training instructor for executing the training at site is in the
bidders scope.
Delivery receipt signed by the trainees deputed should be furnished towards
completion of training at works and at site. Training scope is included under the
commissioning of SAS.
XVI. Fiber optic cables for complete SAS,Control,protection,metering,
DFR System :
Specification to be provided later.
XVII. DIGITAL FAULT RECORDER CUM PMU CUM FL
Technical Specification for Comprehensive Digital fault Recorder (DFR) System
The DFR Recorder shall be multi-time frame recording system used to monitor
electrical power systems. It shall record analogue channels and digital (status)
channels and store as max recordings as possible. The recorder shall record data
simultaneously in three time domains: highspeed fault recording with a minimum
sampling rate of 256 samples per cycle (continuously or triggered), low speed
dynamic swing (continuously or triggered) at a sample rate of one point per cycle,
and per day steady state trend recording with settable time frame between 1 point
per minute or 1 point per 10 minutes.
Recording shall initiate when a single or Boolean equation combination of
thresholds is violated, by a cross trigger signal from another recorder or by a
manual trigger using the web interface. The recording lengths should be user
selectable up to 60 seconds for high speed recording, up to 20 minutes for dynamic
swing recording. Each record shall contain data of all the connected bays.
If there is any need foradditional items such as hardware and software which are
not specifically mentioned in this specification,but is required for the complete
recorder system design, the vendor shall supply all such items that meet allof the
purchasers functional requirements defined in this specification.
The recorder shall consist of individual acquisition units, one for each feeder and an
Evaluation unit which is common for the entire Substation. Whenever, more than
one acquisition units are connected to an Evaluation unit, necessary hardware and

639

software shall also be supplied for on line transfer of data from all acquisition units
to Evaluation unit.
The acquisition unit shall have the following features:

1. The acquisition unit shall have a 16 bit analog to digital convertor with a
minimum of 8 analog inputs, 32 digital inputs.
2. The resolution for digital inputs shall be better than 80 ns.
3. The frequency response shall be DC on lower side and 3.0kHz or better on
upper side.
4. It shall also have indication for data transfer, normal operation and powered up
stage and shall communicate with evaluation units on fiber optic
communication.
5. The acquisition unit shall be capable of acquiring current or voltage or milli
Amp.
6. It shall supervise healthiness of Acquisition units, failure of acquisition must be
indicated in acquisition unit as well as central unit
7. It shall supervise communication path between acquisition and central unit
8. It must have provision for mounting acquisition units at each bay to reduce
panel wiring
9. It should have sampling rate of up to 256 samples per cycle for each input
(CT,VT, Transducer and Binary input)
10. It must support LAN based triggering of all recorder connected in network
11. The drift in internal clock must not be greater than 0.1 sec, if GPS signal is lost
(Not available) for 24 hours.
12. Shall support a maximum distance of up to 2 km between acquisition unit and
central unit, and it shall also support compensation for communication delay
between acquisition and central unit
13. The CT and VT input shall be selectable at site, if required same input of
acquisition unit need to be used for either CT or VT
14. The recorder system shall be capable to directly acquire IEC 61850-9-2 sampled
values ; it shall also be possible to acquire inputs on IEC 61850-8-1.

The recorder shall be capable of recording in COMTRADE format.

640

The disturbance recorder shall have an optional feature of Phasor Measurement


Unit and travelling wave fault location (TWFL).
The disturbance recorder system offered shall have following functionality:
1. Transient Recorder
2. Short Term Recorder
3. Long Term Recorder
4. Continuous Recorder
5. Sequence of Events Recorder

Transient Recorder:

These records shall be very short in duration and typically include faults that are
cleared immediately by circuit breaker operation. These events shall be analyzed to
determine correct protection operation, faultlocation, or verification of system
model parameters.

Short Term Record:


These records shall include all other time-delayed fault clearing and reclosing
events where the system operation(stability) is not affected. These events shall be
analyzed to determine correctprotection operation, fault location or verification of
system model parameters.
These records shall be possible to create by following ways:
Continuously: measurements are continuously recorded. A new record shall be
available each 10 minutes.
Triggered: The fault recorder is triggered when a single or Boolean equation
combination of thresholds isviolated, by a cross-trigger signal from another
recorder or by a manual trigger using the Web Interface.
Sampling Rate:
The triggered recorder sampling rate be user-selectable among 256, 128, or 64
points-per-cycle of the nominalfrequency of the input signal.
Long Term Record:
These records include those events that affect system stability such as power
swings, frequency variations andabnormal voltage problems. These events are
usually analyzed to determine causes of incorrect systemoperations.

641

Sampling Rate:
The trigger and continuous recorder sampling rate is 1 point-per-cycle of the
nominal frequency of the inputsignal.
Steady State Record
There records are steady state disturbances where system operation is not
threatened, but power quality is affected.This may include harmonics or sub-
harmonics produced by the load and/or the interaction between powersystems
components.Steady-state records are created daily. Measurements are continuously
recorded and averaged over 1 or 10min (user selectable). A new record is created
at the rollover of each day.
Sampling Rate:
The daily steady-state recorder sampling rate is 256 points-per-cycle, aggregated
in 1 point-per-minute or 1point-per-10-minutes as selected by the user.
Sequence-of-Events Recorder (SER)
Recorder shall gather and time tag operational data from substation equipment and
control schemes as they react to asystem event. This data allows the chain of
events to be studied for the cause (or causes) of any maloperationand the linkages
between individual actions and effects.SOE records are created daily recording on a
tabular format all the changes in digital and GOOSE inputs aremonitored.
Sampling Rate:
The SOE sampling rate is 256 points-per-cycle of the nominal frequency of the
input signal. Therefore, theresolution of the signal is better than 80 s.
Phasor Measurement Unit:

The equipment must be able to construct accurate synchrophasor data based on


the incoming measurements from the units. The solution must be scalable in terms
the number of analogue channels and phasors available. The synchrophasor
measurement must be carried our according ot IEEE C37.118.1a-2014 phasor
measurement unit with M Class compliance.
Travelling wave fault locators:
Travelling wave fault location is particularly efficient way to define fault in the
transmission line with in vicinity of a particular tower. Such accuracy within few
hundred of meter is not achievable through traditional impedance based fault
location.
642

Distance to fault locator:

Be microprocessor online type

Be suitable for breaker operating time of minimum 2 cycle

Should provide fault location in directly in km without requiring any additional


computations.

Have fault location accuracy of +/- 150 meter or better

The accuracy should not be affected by following parameters,

Presence of remote end infeed


Series compensation
Non uniform line length
Mutual coupling
Transposition of line
Fault resistance
Severe CVT transient

The acquisition units shall be either standalone for each line or composite unit
with thecapability to cater to four lines emanating from the substations. Incase
more than onelines are to be accommodated in one acquisition unit, then
suitable coupler unit shallbe provided in individual line bay C&R panels and only
secondary wiring shall bebrought to common acquisition unit. While offering this
option, bidders are advised totake care of maximum distance between
acquisition unit & line bays C&R panels, whichshall be placed in different Kiosks.

643

You might also like