CRP & Sas
CRP & Sas
1. General
The manufacturer of Relay panels and SAS equipments offered by the bidder is
subject to approval of TANTRANSCO.
All necessary material and works towards field interface of Control & Relay
panels to the switchgears, CTs, PTs, power supply equipment, communication
equipment, SAS (As applicable) etc. are in the scope of the bidder.
All the testing and commissioning of the Control & Relay panels and SAS
Equipments shall be carried out by engineers authorized /certified by the original
equipment manufacturer of SAS with the witness of the concerned TANTRANSCO
P&C engineer and the completion of all the works should be to the satisfaction of
TANTRANSCO.
All the relevant files such as ICD, SCD,SSD,CID etc shall be updated in the
relevant devices and provided in soft copy in CD and in a Spare HDD (Spare HDD
to be supplied in the spares for SAS) to the concerned Protection & Communication
engineer of TANTRANSCO.
a) Construction:
Free standing simplex type, Metal enclosed with swing frame to house the devices
and an outer glass door. The gland and plate assembly shall be vermin proof. The
panel shall be designed for wiring access from front of the C&R panel
Cable entries to the panel shall be from the bottom. The design of the interior of
the panel shall allow sufficient access to the terminals of all devices for removal
551
and repair. The design shall ensure that the heat generated by various apparatus
mounted in the panel shall not affect the performance of any of the devices.
Dimension : Depth x width x height : 800 x 800 x 2312 (or more
including base frame) in mm
Degree of protection : IP-41 as per IEC 60529 / IS 12063
Tests : All type tests and routine tests prescribed in IS/IEC
60947 Low- voltage Switchgear and Control gear
standards shall be performed on the complete panel
assembly.
Thickness of metal : Minimum 3mm for planes housing the devices and for
bottom plates. Minimum 2mm for all other sides.
Swing frame :
Play of Swing frame :120 degree or above capable of opening in the
opposite direction to glass door.
No of hinges : 3nos (minimum)
Door stopper : 1 No.
Protective Glass door : Splinter proof and transparent tempered glass of
minimum thickness 3mm.
Bottom plates : Knock slots shall be provided in the bottom plates
for facilitating cable entry at site.
b) Painting :
i) All sheet steel work shall be phosphated in accordance with IS-6005
ii) Oil, grease, dirt, swart, rust and scale shall be removed by adopting proper
cleansing procedure.
iii) After phosphating and thorough rinsing, the phosphate coating shall be
sealed with application of two coats of ready mixed stoved type zinc
chromate primer. The first coat shall be flash dried while the second coat
shall be stoved.
iv) After application of primer, two coats of finishing synthetic enamel paint
shall be applied, each coat followed by stoving
v) The colour of the panel shall match with the existing panel colour of
subject station and normally of following choice for new station.
Exterior - stoved enamel grey
552
553
554
555
556
iv) All metal case of the relays, instruments and other panel mounted devices
shall be connected to the earth bus by independent copper wires of size not
less than 2.5 sq.mm. The colour code of the earthing wire shall be green.
Earthing wire shall be connected on the terminals with suitable clamp
connectors and soldering shall not be permitted.
3.TRIVECTOR METER:
The tri-vector meter shall be AC static micro-processor based ABT type tri-vector
energy meters, DLMS (Category-B) compliant, suitable for availability based tariff
application. The meter should be capable to record and display Active, Reactive
and apparent energy and maximum demand for 3 phase 4 wire as well as 3 phase
3 wire AC balanced/ unbalanced loads without effecting the accuracy for a power
factor range of zero (lagging), unity and zero (leading) for export and import as per
the requirement given in this specification. The meter shall be capable to measure
in all the four quadrants. The meters measurement of metering values such as
Volatge,current,frequency,energy etc shall be based on true rms measurements.
3.1STANDARDS APPLICABLE
557
The energy meter shall be indoor type connected with the secondary side of
outdoor current and voltage transformers.
Supply system:
Actual primary values wherever applicable shall be programmable in the meter as per the
CT and PT value of the installed CTs and PTs.
3.3.1 The meter should be micro processor based 3 phase 4 wire type suitable
for connection to 3 phase 4 wire as well as 3 phase 3 wire system.
3.3.2 The meter shall compute the active energy and load import; active energy
and load export from the substation bus bars during each successive 15 minute
integration period block and store it in its non volatile memory.
558
3.3.3 The metering system shall normally operate with the power drawn through
the PT secondary voltage.
3.3.4 The meter shall be capable of withstanding surges and voltage spikes as
per IS that occur in the PT & CT circuits of EHV switch yards by providing
necessary isolation and/or suppression system built in the meter.
3.3.4 The active energy measurement shall be carried out on 3 phase 4 wire
principle with accuracy as per class 0.2S of IEC 62053-22. The meter shall
compute the active energy import and export and average frequency during each
successive 15 minute block and store in its memory along with its sign. It shall
also display on demand the active import and active export during the previous 15
minutes block. The values may be displayed directly in secondary quantities.
3.3.5 Further the meter shall continuously integrate and display on demand the
cumulative active energy import and export from the substation up to date and
time of meter reading. The cumulative active energy import and export reading
at each midnight shall be stored in the meter memory for last forty-five (45) days
and shall be reported at Base Computer Software (BCS) end. Separate registers
shall be maintained for active energy import and export.
3.3.6 The average frequency (Hz) of previous 15 minute block shall be displayed
on demand in the metering system.
3.3.7 The meter shall continuously compute the average of the RMS values
(fundamental only) of the 3 lines to neutral PT secondary voltage as the
percentage of 63.51 V and then display the same on demand.
3.3.8 The meter shall compute the reactive power (VAR) on 3 phase 4 wire
principle with accuracy as per IEC 60687-2000 and integrate the reactive
energy algebraically in two separate registers, one for the period for which
RMS voltage is higher than 103%(Reactive High), and the other for the
period for which the RMS voltage is below 97%.(Reactive Low). When
lagging reactive power is being sent out from the substation bus bars,
reactive registers shall move forward. When reactive power flow is in the
reverse direction, reactive registers shall move backwards. The Nett KVARH
559
for voltage high (103%) & Nett KVARH for low voltage (97%) both shall be
displayed.
3.3.9 Further, the reactive energy shall also be available as four different energy
registers for viewing at BCS and on meter display:
3.3.11Each meter shall have a unique identification code (serial number), which
shall be marked permanently on the front as well as in its memory.
3.3.12 Each meter shall have a non volatile memory in which the parameters as specified
in this specification shall be stored. The non volatile memory shall retain the data
for a period not less than 10 years under un-powered condition; battery backup
memory shall not be treated as NVM.
3.3.13 All meters shall be totally identical in all respects except for their unique
identification codes. They shall be totally sealed with no possibility of any
adjustment at site except for clock correction.
560
3.3.14 The meters shall safely withstand the usual fluctuation arising during faults
in particular, VT secondary voltage 115% of rated voltage applied continuously
and 190% voltage of rated for 3 seconds and CT secondary current 120% of rated
current applied continuously and 20 times of maximum current applied for 0.5
seconds, shall not cause any damage to or the mal-operation of the meters.
3.3.15 The meter should be user configurable for all the parameters at site using
the toolsprovided for the meter.
3.3.16 Power factor Range:
The meter shall be suitable for full power factor range from zero (lagging) through
unity to zero (leading). The meter shall work as an active energy import and
export and reactive (lag and lead) energy meter. The energy measurement should
be true four quadrant type.
The meter shall be suitable for working with following supply variation
Frequency - 50 Hz 5%.
3.3.18 Accuracy:
Class of accuracy of the meter shall confirm to 0.2S as per the relevant standard.
The accuracy should not drift with time.
Each of the meter supplied should be tested and certified for accuracy from a NABL
recognised laboratory in India.
i)Voltage circuit: The active and apparent power consumption in each voltage
circuit including the power supply of meter at reference voltage, reference
temperature and reference frequency shall not exceed 1.5 Watt per phase and 8
VA per phase respectively.
561
ii)Current Circuit: The apparent power taken by each current circuit at basic
current, reference frequency and reference temperature shall not exceed 1 VA per
phase.
The meter should start registering the energy at 0.1% ln at unity power factor.
Maximum Current:
The rated maximum current of meter shall be 120% of basic current (Ib).
3.4 GENERAL AND CONSTRUCTIONAL REQUIREMENTS
3.4.2 All the material and electronic power components used in the manufacture
of the meter shall be of highest quality and reputed make to ensure higher
reliability, longer life and sustained accuracy.
3.4.3 The meter shall be designed with application specific integrated circuits. The
electronic components shall be mounted on the printed circuit board using latest
Surface Mount Technology (SMT).
3.4.5 The meter shall be suitable for being connected through test terminal blocks
to the voltage transformer having a rated secondary line to neutral voltage of
110/3 V and to current transformers having a rated secondary current of 1A as
562
per requirement. Necessary isolation and suppression shall also be built-in, for
protecting the meters from surges and voltage spikes that occur in the VT and CT
circuits of extra high voltage switchyards.
3.4.6 Each meter shall have test output devices (visual) for checking the accuracy
of active energy (Wh), reactive energy (VARh) or apparent energy (VAh)
measurement using a suitable test equipment. This device shall be suitable for use
with sensing probe used with test benches or reference standards. The test output
device shall have constant pulse rate ie pulse/unit (KWh, KVARh) and its value
(Meter constant) should be indelibly printed/ appropriately mentioned on the rating
plate.
3.4.7 The metering system shall conform to the degree of protection IP 53 in the
normal working condition of IS12063/1EC529 for protection against ingress of dust,
moisture and vermin.
3.4.8 The meter base, meter cover, terminal block (as applicable) shall be made of
unbreakable, high grade, fire resistant, non-inflammable and good quality suitable
material to ensure safety. The manufacturer shall clearly indicate the material used.
3.4.9 The terminal block and the meter case shall be designed such that it ensures
reasonable safety against the spread of fire and shall not be ignited by thermic
overload of live parts in contact with them.
3.4.10 All terminals for CT and VT connections shall be arranged at the lower/
back side of the meters. Terminal shall have a suitable construction with barriers
and cover to provide a safe and secure connection of CT & VT wires.
3.4.11 The metering system shall be compact in design. Entire design and
construction shall be capable of withstanding stresses likely to occur in actual
service and rough handling during transportation. The meter shall be convenient to
transport and immune to shock and vibrations during transportation and handling
as per the relevant standard. Meter shall have the capability and facility to
compensate for errors of external measurement transformers i.e. CT and VT
563
The connection diagram of the meter shall be clearly shown for 3 phase 4 wire
system as well as 3 phase 3 wire system, on inside portion of the terminal cover
564
and shall be of permanent nature or suitably pasted in meter. The meter terminals
shall also be marked and this marking should appear in the above diagram. In
case of any special precautions need to be taken at the time of testing the meter,
the same may be indicated along with the circuit diagram.
3.9.1 The measured value(s) shall be displayed through Liquid Crystal Display
(Alpha numeric LCD backlit) section of metering system.
3.9.3 The register shall be able to record and display starting from zero, for a
minimum of 1500 hours, the energy corresponding to rated maximum current at
reference voltage and unity power factor. The register shall not roll over in
between this duration.
565
3.9.4 Any interrogation/ read operation shall not delete or alter any stored meter
data.
9. Exp MD KW
10. AVG Volt Ph A
11. AVG Volt Ph B
12. AVG Volt Ph C
13. AVG Current Ph A
14. AVG Current Ph B
15. AVG Current Ph C
16. AVG Frequency
17. Net VARh High
18. Net VARh Low
15-minute average of the above parameters shall be available for last forty five
(45) days. It shall be possible to select either demand or energy view at the BCS
end. The load survey data shall be made available in the form of bar charts as well
as in spread sheets at the metering PC end. The Base computer software shall
have the facility to give the complete load survey data both in numeric and graphic
form. All the 96 blocks shall be recorded for data indication on block day and no
supply period also shall be recorded .
The meter shall store following end day parameters for last forty five (45)
days at 00:00 hrs.
The meter shall have TOD registers for active energy import and export, apparent
energy import and export and apparent MD import and export. Maximum eight
time of day registers for each energy and MD can be defined. It shall be possible to
program number of TOD registers and TOD timings through software/CMRI with
multilevel password security system and authenticated transaction.
568
569
3.18.4 The clock of the trivector meter should be synchronised with the GPS clock
of the SAS.
3.19 Self Diagnostic Feature:
The meter shall be capable of performing complete self diagnostic check to monitor
the circuits for any malfunctioning to ensure integrity of data in memory location all
the time. The meter shall have indications/ display for
unsatisfactory/nonfunctioning/malfunctioning of the following:
a) Time and date and
b) Non volatile memory failure indication
c) Low Battery indication at BCS
Above indicationshould be made available at BCS end also.
While installing the meter, it should be possible to check the correctness of CT/VT
connection to the meter and their polarity from the functioning of the meter for
different voltage injections with the help of vector phasor diagrams. For this
purpose suitable software for field diagnosis of meter connections with the help of
MRI should be supplied.
The details of malfunctioning of time and date shall be recorded in the meter
memory.
3.20 Anomaly detection features:
The meter shall have features to detect the occurrence and restoration of, at least,
the following common ways of anomaly:
a) Missing potential: The meter shall be capable of detecting and recording
occurrences and restoration of missing potential (1 phase or 2 phases)
which can happen due to intentional/ accidental disconnection of
potential leads.
b) CT polarity reversal: The meter shall be capable of detecting and
recording occurrences and restoration of CT polarity reversal of one or
more phases.
c) Current and voltage unbalance: The meter shall be capable of detecting
and recording occurrences and restoration of unbalance of current and
voltage. Snap shots (numerical values) of phase wise voltages, phase
wise active currents, phase wise power factors and energy (active
energy) readings shall be provided with the above specified events.
570
Once one or more compartments have become full, the last anomaly event
pertaining to the same compartment shall be entered and the earliest (First one)
anomaly event should disappear. Thus, this manner each succeeding anomaly
event shall replace the earliest recorded event, compartment wise. Events of one
compartment/category should overwrite the events of their own
compartment/category only.
4. ANNUNCIATORS:
ii) The display in the announciator unit shall be High density LED type or
cluster LED type.
iii) Trip and non-trip discrimination shall be made in the fascia. For example
all trip fascia shall have red colour and non trip fascia white colour.
571
iv) A test, accept and reset push button facilities shall be provided for testing
the annunciation unit.
v) The annunciator unit should conform to the applicable parts of the IEC
60255/ Equivalent for type tests and routine tests.
ii) Equipped with Event recorder. Events storage shall be sufficient for the
application. minimum 200 events of storage is preferable and with a time stamp
resolution of 1ms.
vi) Equipped with Two optical Ethernet ports at the rear of the numerical
relayforparallel redundancy (in compliance to IEC-62439-3) in networking on
IEC 61850 Protocol.The above referred 2nos Ethernet ports shall also be used
for time synchronization using SNTP protocol with guaranteed resolution of
1ms.
572
IEC 61850 protocol with type test certification/report for compliance with relevant
parts of IEC 61850. The compliance shall include :
- Model implementation conformance statement (MICS)
- Protocol implementation conformance statement (PICS)
vii) Equipped with communication port (USB or RS232 or Ethernet port) for relay
configuration, Data and records retrieval. It shall be possible to carry out firmware
updates of the numeric relay through internet connectivity free of cost.
viii) Equipped with self monitoring feature during start up and always while in
service. A relay fail alarm should be available in dry contact type alarm output. A
relay healthy indication shall be provided. The numeric relay shall be provided with
diagnostic tools with which it shall be possible to identify and display all the
defective modules of the relay.
ix) Provided with the necessary software tools for complete configuration of the
protection relay, record retrieval, data retrieval. All firmware updates to the
numeric relays shall be feasible to be effected with download of files from
the manufacturers website free of cost.
x) Suitable to operate with the auxiliary DC supply voltage available in the sub-
Station (Nominal aux supply Voltage is 110V DC or 220V DC as per station DC
supply voltage.)
xi) Provision for display of alarms with LED/ LCD/Graphic display. The LEDs shall
be user programmable to any of the hardwired inputs and outputs as well as
virtual inputs and outputs.
xii) Support multiple relay settings for protection. The numeric relay should be
provided with a facility for settings file comparison. Facility should be provided to
view the abstract of adopted settings features of the relay.
xiii) All configuration files, data and records of the protection relay shall be stored
in a non- volatile memory and shall not be lost on absence of dc supply.
xiv) The relays should be suitable for testing with universally acceptable testing kit.
xv) The relay should be equipped with user configurable opto isolated Binary
inputs and potential free binary outputs as required for the specific
application. Numeric relays with non-programmble binary Inputs,
non-programmable binary outputs, non-programmable are not
acceptable.
573
xvi) Where ever the numerical relay is connected to the 3phase VTs, the relay
574
a. Power Input:
i. Auxiliary Voltage
iv. Indications
b. Accuracy Tests:
ii. Currents
iii. Voltages
c. Insulation Tests:
i. Dielectric Tests
d. Influencing Quantities
i. Limits of operation
f. Function Tests:
i. Indication
ii. Commands
g. Environmental tests:
i. Cold Temperature
v. Vibration
vi. Bump
576
vii. Shock
6. Electro-mechanical Relays:
ii) Unless otherwise specified all auxiliary relays and timers shall be
supplied in non-draw out cases / plug in type modular cases.
577
IEC 61850 All applicable parts of this standard certified by KEMA/ reputed
laboratory. Including type test certification/report for :
- Model implementation conformance statement (MICS)
- Protocol implementation conformance statement (PICS)
Note : For standards other than IS mentioned above, the equivalent or better IS
standards may be complied.
8. PROTECTION FOR 765 kV / 400 kV LINES/FEEDERS:
MAIN-I & MAIN II DISTANCE PROTECTION:
The numeric distance protection relays shall comply with the following
requirements.
1. The numerical distance protection relays shall comply with the specification for
general requirements for numerical protection relay as furnished in this
document.
2. The numeric relays shall be equipped with sufficient binary output contacts for
trip outputs, alarms, spare and for the protection scheme implementation.
3. The numeric relay shall be suitable for operating with Nominal PT input of
110V~ phase to phase, 63.5V ~ phase to ground, CT input of 1A.
4. Main-1 and Main-2 distance protection relay should be of different
manufacturer.
5. Equipped with the following built in protection functions:
21 : Distance protection
a. The distance protection relay shall have following maximum operating time
(including trip relay time, if any) under given set of conditions and with CVT
being used on line (with all filters included)
For Source to Impedance 4 15
ratio:
Relay setting 10 2
(Ohms)
Fault Locations (as % of 60 60
relay setting)
Fault resistance (Ohms) 0 0
Maximum operating time 40 for all faults 45 for 3 ph. Faults & 60
(Milliseconds ) for all other faults
b. There shall be a minimum of 3 forward and 1 reverse selectable distance
protection zones.
578
50/27 : SOTF
579
79: Built in auto reclose function with single shot, single phase (3phase for
110kV) reclose with adjustable dead time setting of 0.1sec to 1sec, and with
adjustable reclaim time of 1 to 250sec.
27/59 : Under voltage/ over voltage protection element. This protection element
should have two independent stages.
50N/51N IDMT directional earth fault relay with adjustable setting range of 10 to
80% with characteristic curve for normal inverse, very inverse and extremely
inverse of both IEC and IEEE curves.
DR : Disturbance recorder with minimum 8 analog and 12 digital inputs and with
minimum memory capacity to store at least 8 disturbance records with each record
of minimum 10 cycles.
Event recorder
Stub protection.
The power swing shall be detected by rate of change of impedance with suitable
characteristics. The blocking shall have continuously adjustable time delay with
setting range of not less than 2sec or shall have feature to block the tripping as
long as it exists. The relay shall have feature to unblock during fault. It shall be
explained how blocking is effected during power swing for phase to earth fault,
phase to phase faults and three phase faults. In each case the relay shall have
feature to unblock in the event of actual fault and with facility to block each
distance zone independently.
1. The numerical distance protection relays shall comply with the specification for
general requirements for numerical protection relay as furnished in this
document.
2. The numeric relays shall be equipped with sufficient digital output potential free
contacts for trip outputs, alarms and for the protection scheme implementation.
3. The numeric relay shall be suitable for operating with Nominal PT input of
110V~ phase to phase, 63.5V ~ phase to ground, CT input of 1A.
4. Features and characteristics.
Current settings :
O/C Phase fault setting : 20 to 200 % of rated current in at least 1% steps
E/F setting : 10% to 80 % of rated current in at least 1% steps.
Time multiplier : 0.05 to 1.0 in steps of 0.01 for phase fault and earth fault
settings.
Definite Time Delay : 0.05 to 20 Sec. in steps of 0.01 sec.
Drop out to pick up ratio : > 95%.
581
Inverse Characteristic : Normal Inverse (3 Sec, 1.3 Sec), Very Inverse &Extremely
Inverse of IEC curves. ( Curves should be Selectable at site)
Characteristic curves and settings shall be separately selectable for phase fault and
earth fault.
High set Instantaneous Unit :
O/C : 50 % to 2500 % of rated current in steps of 50% or lesser step size.
E/F : 50 % to 500 % of rated current in steps of 50% or lesser step size.
Current settings o/c 50 to 200% & E/F 10 to 80% in convenient steps
Redundant (1+1) numerical Bus Bar protection scheme for each bus
582
system for 400kV as well as 765kV shall be provided. The scheme shall be
engineered so as to ensure that operation of any one out of two schemes
connected to main faultybus shall result in tripping of the same. Each of the
redundant numerical bus bar protection scheme shall comply to the
following requirements.
1. The numerical bus bar protection relays shall comply with the specification
for general requirements for numerical protection relay as furnished in this
document.
2. Bus bar protection relay shall be of numerical low impedance type,
distributed architechture and shall have operate and restraint
characteristics. The distributed Numerical based bus bar protection scheme
shall comprise a central unit and peripheral units all of which communicate
in real time through a high speed fiber optic communication link.
3. Each Bus Bar protection scheme shall comply to the following requirements.
(a) have maximum operating time up to trip impulse to trip relay for all types
of faults of 25 milli seconds at 5 times setting value.
(b) Operate selectively for each zone of bus bars for all types of faults i.e Phase
to phase , Phase to ground faults including high resistive faults.
(c) Give hundred percent security up to 63 KA fault level for 400KV. be
stable for through fault condition up to 50KA fault level.
(d) incorporate continuous supervision of CT secondarys against any possible
open circuit and if it occurs, shall render the relevant zone of protection
inoperative after a time delay and initiate an alarm. However facility to
unblock CT supervision in case of actual fault occurring in the bus shall be
provided.
(e) be phase segregated triple pole type and provide independent zone of
protection. If bus section is provided, then each side of the bus section shall
have separate set of bus bar protection scheme. The bus section breaker
and bus coupler breakers shall be covered by overlapping bus bar protection
scheme of respective buses.
(f) shall include one overall check zone protection in addition to single/multiple
zones specified.Incorporate check zone feature for each phase and clear
zone indication. The check zone shall be without any switching. Also check
583
zone shall not over stabilize during internal fault due to unequal source &
load distribution.
(i) include provision for protection IN/OUT for each zone and check zone.
(j) be transient free in operation.
(k) includes continuous DC supply supervision.
4. The numeric relay shall be suitable for operating with CT inputs of 1A
(nominal). The secondary of the CT shall be directly connected to the Bus
bar relay without the aid of external auxiliary CTs. Ratio correction shall be
possible with through the relay configuration tools itself.
5. the relay must have harmonic rejection and shall not operate on second and
third harmonics. Second harmonic rejection ratio 2:1 minimum, third
harmonic rejection ratio 40 :1 minimum.
6. the high speed electrically reset high speed tripping relays (96) for tripping
each bay breakers on actuation of bus bar protection shall be on respective
bay protection relay panels and necessary provision for running the tripping
bus wires to actuate these relays shall be made. However, in case of
distributed Bus bar protection, individual trip relay shall not be required if
bay unit is having trip duty contacts for breaker tripping.The protection
scheme shall be wired in such a way that both check zone and bus
sectionalizing zone schemes shall operate to isolate the respective faulty bus
bar for internal fault condition.
7. The relay should be equipped completely for supporting six numbers spare
circuits in addition to all the circuits for feeders/ bays depicted in the single
line diagram for the sub-station. In case of distributed Bus bar Protection,
the bay units for future bays may be installed in a separate panel and the
same shall be located in switchyard panel room where bus bar protection
panel shall be installed.
8. The bus bar protection relay should support various bus architectures
selectable by means of the relay configuration (Single bus bar, Double bus
bar, Breaker and a half bus bar, two section bus bar with a bus tie, Double
bus bar with transfer bus and tie breaker) for its bus bar protection.
9. The relay shall incorporate dynamic bus replica and provide necessary end
584
zone fault protection depending on the bus bar protection CTs location.
The status of isolators shall be ascertained by hardwired double indication
method i.e Both N/C and N/O contact to be used.
10. The relay shall facilitate through relay configuration tools as well as through
user interface keypad/controls the following requirements:
- Adopting multiple CT ratios of different bays
- CT polarity selection
- Bay IN/OUT selection
- Bus differential enable or disable etc
- IN/OUT selection for each zone and check zone.
11. Facility to monitor the individual bay currents, bus differential currents and
bus restraint current for each zones shall be supported in the relay display
as well as through configuration tools.
12. The bus bar protection of respective bus sections shall trip respective set of
bus bar lockout relays and shall initiate BF of respective CB. The bus
bar protection scheme of each bus section shall be developed such
that one lockout relay shall be provided with each circuit breaker.
13. The bus bar protection relay shall be provided with built in breaker fail
(50BF) / LBB protection implemented in the respective Peripheral bay unit
for all the connected circuits. For LBB protection
Operating time : 15 ms
Resetting time : 15 ms
LBB protection scheme shall be implemented to get individual initiation from
the corresponding phase of main protections of line for each over current
element. However common three phase initiation is acceptable for other
protections and transformer/reactor equipment protections.
Have setting range of 20% to 80% of rated current.
Have timer with continuously adjustable setting range of 0.1 to 1 second.
14. The relay shall be equipped with VT modules to measure the bus voltages so
that reference load flow can be taken from bus voltage as well as for
providing secure operation in case of inadvertent shorting of CT.
585
Note: In case separate LBB relay is stipulated for EHT breakers, then LBB relay
shall be provided accordingly even though Bus bar relay is equipped with built in
LBB protection.
11. TRANSFORMER PROTECTION (APPLICABLE FOR 765 kV/ 400 kV ICT:
a) BIAS DIFFFRENTIAL PROTECTION RELAY FOR THREE WINDING
TRANSFORMER PROTECTION:
The numerical differential protection relays shall be comply with the following
requirements.
1. The numerical differential protection relays shall comply with the specification for
general requirements for numerical protection relay as furnished in this
document.
2. The numeric relay shall be suitable for operating with CT inputs of 1A.
3. Differential protection features and characteristics:
i. Based on low impedance differential principle for protection of three winding
transformer. Three phase with faulty phase identification.
ii. Shall have three instantaneous high set over current units with facility to
adjust 5 to 20 times normal current.
iii. Shall have second and fifth harmonic restraint feature with second harmonic
content in the range of 15 to 35% .Transformer inrush restraint functionality
shall be provided. Inrush and CT saturation shall not influence the differential
function.
iv. Facility to set transformer vector group and CT ratio selection/ correction
through relay configuration software tools.
v. Basic bias setting 20 to 40% in steps 1%.
vi. Operating current setting range 15% to 30%.
vii. have operating time not greater than 35ms at 3 times normal current.
viii. Maximum operating time for instantaneous operation: 25ms +/-4% of set
value.
ix. The differential protection shall have adjustable characteristics with adaptive
differential feature to maintain stability in case of through faults.
x. The protection relay shall be equipped with unrestrained differential protection
element for fast tripping on heavy internal faults.
586
xi. Facility to view the transformer differential current and bias current directly
from the Relay display as well as through configuration software.
4. Shall have inbuilt restricted earth fault protection and inbuilt over fluxing
protection.
i) Over Fluxing Protection shall be provided for HV side and shall comply with the
following requirements:
(a) operate on the principle of Voltage to frequency ratio and shall be phase to phase
connected
(b) have inverse time characteristics, matching with transformer over fluxing
withstand capability curve
(c) provide an independent 'alarm' with the time delay continuously adjustable
between 0.1 to 6.0 seconds at values of 'v/f' between 100% to 130% of rated
values
(d) tripping time shall be governed by 'v/f' Vs. time characteristics of the relay
(e) have a set of characteristics for Various time multiplier settings. The maximum
operating time of the relay shall not exceed 3 seconds and 1.5 seconds at
'v/f' values of 1.4 and 1.5 times, the rated values, respectively.
(f) have an accuracy of operating time, better than +/-10%
(g) have a resetting ratio of 95 % or better
(h) Over flux protection shall be provided in the HV
ii) Restricted Earth Fault Protection shall
(a) be single pole type
(b) be of current/voltage operated type
(c) have a current setting range of 10-40% of 1 Amp./ have a suitable voltage setting
range
(d) be tuned to the system frequency.
5. The protection relay shall be equipped with built in thermal overload protection.
6. The disturbance recording functions should be integrated in the relay module.
The disturbance recorder shall have facility to record at least 4 numbers of
digital signals apart from digital signal from the relay and currents in HV&LV
winding. Recording memory capacity: 5secs.
7. Equipped with sufficient numbers (minimum is 16 nos ) of programmable of
587
1
No of Stages 4 independent Stages
2
Frequency range 45 Hertz to 55 Hertz
3
Frequency steps In 0.01 HZ
4
Timers One timer for each stage independently programmable
588
settings
5
Timer setting Programmable between 0 to 5 sec in step of 0.01 sec
6
Operating time Within 100ms
7
No of phases 3
1
No of Stages 3 independent Stages
2
Settings range 0.1 HZ/Sec to 1 HZ/Sec in steps of 0.1HZ/Sec
Operational
accuracy 5 milli Hz./sec
3
Measuring cycles Programmable between 2 to 10 cycles
4
Operating time Within 100ms
5
No of phases 3
* The relay shall be equipped with built in VT supervision function and 2 protection
elements for under voltage blocking function selectable between IDMT/DT to block
all the frequency based protection elements. The under voltage measurement shall
be possible on phase to phase as well as phase to neutral basis.
* The relay shall have negative sequence overvoltage function. zero sequence
voltage detection for VT fuse fail detection shall be used so that the relay does not
maloperate on system ground faults
* Operating Voltage : 50 to 100% of nominal voltage with provision for selection.
Nominal voltage is 110V AC (Phase to phase).
Facility for under voltage blocking shall be provided with programmable range for
voltage setting.
* The relay functionality shall include measurement of phase/ line voltages (True
rms) , sequence voltages , system frequency and phase angles.
* Relay should have the capability to build the logic with which one should be able
to adapt to the load shedding requirement of the substation.
589
*Blocking of each of the protection elements shall be possible with user interface
through keypad/ buttons as well as through configuration port and Engineering
work station.
* The relay shall be highly reliable and immune to transient and surges. In case of
any component failure in the relay, the relay should not cause undesired trip.
Relay outputs:
* It shall be possible to assign each of the trip outputs reserved for feeders to any
of the three stages of under frequency protection function as well as f+df/dt
protection.
Indications
* The relay shall be equipped with indication lamps that is programmable to any of
the protection elements, inputs, outputs and logic outputs.
*Programmable LED indications shall be provided in the relay for each stage of
protection elements operated and for faulted phase indication.
Relay Inputs:
* The relay shall be highly reliable and immune to transient and surges.
* The relay shall be equipped with sufficient quantity of opto-isolated digital inputs
for facilitating external blocking of under frequency as well df/dt protection
elements for each feeder. Necessary isolation links should be provided to facilitate
manual isolation of under 81U and 81RF protection feeder wise.
* The relay shall be equipped with sufficient opto-isolated digital inputs and
potential free digital outputs to accommodate feeders all the feeders plus 3 spare
feeders for future use.
13.0 MISCELLANEOUS PROTECTION
13.1 D.C. Supply Supervision Relay.
The relay shall monitor continuously D.C. Supply to Protection System. The
de-energization of this relay will indicate the DC Supply failure. Auxiliary
supply for the relay is 220V DC. The relay shall have a time delay on drop
off of not less than 100 milli second. The relay shall be provided with
operation indicators (Reverse flag) self reset. Sufficient number of contacts
potential free may be provided. Separate relays for dual source are to be
provided.
13.2 Trip Circuit Supervision Relays.
590
The trip circuits shall be supervised by means of relays. The scheme shall
continuously monitor the trip circuit before closing and after closing of the
breaker. The schemes shall detect (I) failure of the trip supply (ii) open
circuit of trip circuit wiring and (iii) failure of mechanism to complete
operation. The relays shall supervise the healthiness of trip circuit
continuously (Both pre-closing and post-closing conditions of the circuit
breakers). The relay shall be capable of monitoring the healthiness of each
phase trip coil and associated circuits of the circuit breaker during ON and
OFF conditions. The relay shall work on 220V dc with allowable margin as
the case may be. The relay shall have adequate contacts for providing
connection to alarm and event logger, self reset. The relay shall have a
time delay on drop off of not less than 200 milli seconds and provided
with Operation indicators. The short circuiting of any series resistance
provided in this relay or short circuiting the coil of the relay should not
energize the trip coil of the breaker.
The relays shall have necessary contacts to be connected to
protection scheme and annunciation to SAS.
13.3 Tripping (Master) Relay :
- For tripping of feeder / transformer breakers in a station on operation
of protective relays and for interlock purposes. The relay shall be voltage
rated for station DC supply with allowable margin of variation, be
instantaneous (Operating time not exceed 10 milli seconds).
- Reset within 20 milli seconds.
- Hand and electrical reset type
- Have adequate contacts to meet the requirement of scheme, other
functions like auto reclose relay, LBB relay as well as to cater to associated
equipments like SER, DR etc., to be provided with operation element/ coil.
13.5 Check Synchronizing relay:-
Synchro check function should be part of the main relay.
The synchronism and energizing check functions shall feature:
Settable voltage, phase angle, and frequency difference.
Energizing for dead line - live bus, live line - dead bus or
dead line dead bus with no synchro-check function.
591
592
b. For each Kiosk pertaining to one diameter of EHV the following shall be
provided:
i. DCDB of suitable rating for 220V DC Source -1 with feeder MCBs for DC supply to
relay panels for one diameter of EHV. Typically 5 feeder MCBs dedicated to five
relay panels in one diameter plus feeder MCBs for other panels and 3 spare MCBs.
ii. DCDB of suitable rating for 220V DC Source -2: Similar to DCDB-1
iii. ACDB of suitable rating for 230V AC Source with feeder MCBs for AC supply to
relay panels for one diameter of EHV. Typically 5 feeder MCBs dedicated to five
relay panels in one diameter plus feeder MCBs for other panels, utility and auxiliary
items and 3 spare MCBs.
593
1) GENERAL :
This specification provides for complete Design & Engineering, Manufacture, FAT
(Factory acceptance test), packing, shipment, insurance, transport and delivery to
site, installation, testing and commissioning with SAT (Site acceptance test) of the
substation automation system completely as described in the following sections to
control and monitor the 765 kV bays, 400 kV bays, ICTs, Reactors and associated
equipments at the substation and all the station auxiliary equipments of the
substation. The scope of SAS commissioning is inclusive of the system integration
with the SAS of the following items: Control & Relay panels for EHT bays, Online
diagnostic monitoring system for transformers, Online diagnostic monitoring system
for transformers bushing in this context all necessary materials and works are
included in the SAS scope of supply and commissioning. Communication interface
between field device of online diagnostic monitoring system for
transformers,bushings and the associated Work station should be using fibre optic
cable only as the this media is necessary to protect from Electro magnetic
interference and the high voltage surges experience in the switch yard.
The details of Electrical bays in the substation are given in the single line diagram
of the substation.
The substation automation system (SAS) shall be installed to control and
monitor all the substation equipments from Local Control room as well as from the
remote load dispatch centre/ Master. The SAS shall be designed such that it
enables the user for control & monitoring of the substation at the HMI level
(through Operator work stations), at the Bay level ( through BCU) and at the
switchgear level/Manually (facilitated by TNC switch, Energy meters etc).
The SAS shall be based on a decentralized architecture and on a concept of
bay-oriented, distributed intelligence. Functions shall be decentralised, object-
oriented and located as close as possible to the process. The main process
information of the station shall be stored in distributed databases. The typical SAS
architecture shall be structured in two levels i.e. station and bay level. The
database sizing shall be sufficient to accommodate for current Single line diagram
and future expansions. The distributed architecture for the complete SAS is to be
implemented with all the control and relay panels for one complete diameter to be
594
located in a kiosk located in the switch yard close to the corresponding diameter.
The kiosk is of pucca building that ensures the room temperature even without the
air conditioner is well within the operating temperature of all the Control & relay
panels housed in the kiosk. All the communication link between the Control & relay
panels in the kiosk and the Control room is by fiber optic cables only. All the
communication link between the online diagnostic monitoring system for
transformers and its bushings, reactors etc and the Control room is by fiber optic
cables only.
At bay level, the IEDs shall provide all bay level functions regarding control,
monitoring and protection, inputs for status indication and outputs for commands.
The IEDs should be directly connected to the switchgear without any need for
additional interposition of transducers.
The data exchange between the electronic devices on bay and station level shall
take place via the communication infrastructure. This shall be realized using fiber
optic cables, thereby guaranteeing disturbance free communication. The fiber
optic cables shall be run in suitable conduit pipes. Data exchange is to be
realized using IEC 61850 standards with a external managed switched Ethernet
communication infrastructure in decentralized ring configuration.
o All the numerical IEDs must be fully IEC 61850 compliant and must
have the following features.
o Peer-to-peer communication using GOOSE messages (IEC 61850) for
interlocking.
o Interoperability with third party IEC 61850 compliant devices
o Generate XML file for integration/engineering with vendor
independent SCADA systems.
o Should be directly connected to the inter bay bus on IEC 61850
without the use of any gateways. Connections of bay protection IEDs
to the IEC 61850 bus through the bay control units are not
acceptable.
The sub-station configuration language shall be based on XML format shall be
defined for system configuration and the same shall be furnished for system
integration and end user.
Failure of one set of fiber shall not affect the normal operation of the SAS.
595
However, it shall be alarmed in SAS. Each fiber optic cable shall have adequate
spare fibers.
At station level, the entire station shall be controlled and supervised from
the stationHMI. It shall also be possible to control and monitor the bay from
the bay level equipment at all times, accordingly a graphic user interface
(GUI) display shall be provided in each baycontrol unit. The GUI display in
the BCU shall display the status of the bay devices (breakers, isolators,
switches etc) in real time along with the related measurands. All alarms
related to the respective bay shall be displayed in the BCU through its LEDs
or in its GUI display as an alarm list/scroll. A TNC switch shall be provided
for each breaker in the respective C&R panel of the bay for facilitating
manual operation for facilitating operation in emergency condition. The
BCUs shall be located in the respective relay panel itself and Multiple BCUs
shall not be housed in a single panel. Clear control priorities shall
preventoperation of a single switch at the same time from more than one of
the various control levels, i.e. station HMI, bay level or apparatus level. The
priority shall always be on the lowest enabled control level. The station level
contains the station-oriented functions, which cannot be realized at bay
level, e.g. alarm list or event list related to the entire substation etc. All the
data cabling & other interconnections shall be through fibre optic cables
wherever possible except for power supply.
Communication with the remote control centers State Sub-load Dispatch Centre
through Gateway on IEC 60870 5 101/104 of SCADA/EMS system through PLCC
Modems/Fibre optic interface equipment as applicable. This interface shall support
communication to the remote control centre on IEC 60870 5 101/104 through
redundant communication ports. TAN TRANSCO Engineers shall be co-coordinated
for integration. The data should be made available for the polling schedule of the
SCADA/EMS system at State Sub-load Dispatch control centre. Any support
required for completing the task shall be in bidders scope.
FUNCTIONAL REQUIREMENTS :
c) Data Exchange
d) Report Generation and Printing.
e) The updating times on the operator station under normal and calm
conditions in the substation shall be as follows:
Function Typical values
3) CONTROL:
Basic Functions :
597
g) Storage of data.
h) Collection of disturbance record files from various relays and analysis of the
same from Engg/DR works station with suitable software.
i) Auto re closure selection and monitoring.
j) Bus PT change-over.
k) Carrier IN/OUT selection.
l) Synchro check provision.
m) Reset facility from HMI for reset of all numerical relays, master trip relays.
n) Monitoring of control room temperature, kiosk room temperature etc.
5) INTERLOCKING:
The interlocking function provision through logic gates prevents unsafe
operation of equipments such as breakers ,isolators and earthing switches
for all switching operation within a bay or station . An override function at
Bay level shall be provided, which can be enabled to by-pass the interlocking
function via a key/password, in cases of maintenance or emergency
situations. This over ride function should be accessed with higher level
pass word security. All critical interlocks such as close operation of breakers
and isolators etc shall be implemented in hardwired method also. In order to
provide additional security for safe operation of the primary equipments, the
hard wired interlock shall also be implemented preferably at the yard control
cubicle.
- Polling on request
1) Numerical relays Electronic Energy meters (to be made available in all the
feeders, transformers both HV & LV sides).
2) OLTC, Battery charger etc., Data for the system shall be acquired as hard
wired input for all station equipments stated in the single line diagram.
KW, KVA, V,I, PF, kWh, kVah and kVarh from electronic energy meters (four
quadrant type) , bus voltage and frequency for the relevant EHV system
(765 kV and 400 Kv) shall be measured and communicated on MODBUS /
IEC 61850/ Standard Open protocol to SAS and values shall be obtained
and displayed in both HMIs.
599
Provision shall also be available for extracting these measurements from the
relays and BCUs in addition to following protection function data (not
exhaustive).
a. For each 765kV Bays .
All relevant Status, alarms pertaining to 400 KV Bays.
b. 400KV Bays:
All relevant Status, alarms pertaining to 400 KV Bays.
c. For each transformer separately
Differential relay tripping
Over current relay for HV tripping
Over current relay for LV tripping
Master relays(1 & 2 separately)
LBB relay actuation
DC fail for source 1 & 2
Buchholz relay alarm
Buchholz relay trip indication
Oil/winding temperature alarm
PRD acted
Fault I& V
d. For each breaker
Status ON/OFF
Air/gas pressure low
Air/gas pressure lockout
Pole discrepancy actuation
TSR (common for all trip coil per circuit breaker)
e. Isolator ON/OFF
f. earth switch On/Off
g. Others
Bus bar protection actuation for various voltage level buses. CT circuit
supervision for above bus bar protection(common for each voltage). In case
the bus bar protection relays provided with communication port the zone
operation and CT supervision function shall be acquired on the
communication interface or DI.
600
601
602
603
Wherever there is a redundant LAN architecture is specified for SAS, each BCU shall
be preferably equipped with two separate Ethernet ports for connection to
redundant LANs preferably with separate IP addresses.
Synchronism and energizing check
The BCU shall conform to the specification stipulated under General requirements
for Numeric type protection relays in this tender specification.The BCU should be
compatible to interoperate and integrate with the IEC 61850 based SAS in
TANTRASNCO sub-stations.
11) TIME SYNCHRONISATION
i) The Time synchronization equipment shall receive the co-ordinate Universal Time
(UTC) transmitted through Geo Positioning Satellite System (GPS) and synchronize
equipments to the Indian Standard Time in a substation. The system shall be able
to track the satellites to ensure no interruption of synchronization signal.
ii) Time synchronization equipment shall include antenna, all necessary accessories
and all special cables and processing equipment etc.
604
iii) The GPS antenna shall have adequate protection from wind, lightning etc. and
shall be mounted anywhere in the Substation roof at a place preferable by the
TANTRANSCO
iv) The synchronization equipment shall have 2 micro second accuracy. Equipment
shall give real time corresponding to IST (taking into consideration all factors like
voltage and temperature variations, propagation and processing delays etc.)
v) Equipment shall meet the requirement of IEC 60255 for storage and operation.
vi) The output signal from each port shall be programmable at site for either one
hour, half hour, minute or second pulse, as per requirement. The equipment shall
have a periodic time correction facility of one-second periodicity.
vi) Equipment shall have real time digital display in hour, minute, second (24 hour
mode)
vii) A separate time display unit (100 mm display high) at a suitable height in the
control room should also be provided.
vi) It shall be compatible for synchronization of all the SAS equipments, all
numerical devices and IEDs in the relay panels, Event Loggers, Disturbance
recorders, PMUs and SCADA at a substation etc.
vii) The equipments should be equipped and ready to provide time synchronization
signals with the following ports:
a)Ethernet ports -2nos for SNTP time signaling through the two separate Ethernet
LANs.
b) PPS Fibre optic ports of sufficient numbers to time synchronise the devices
requiring accurate time signals like Digital fault recorder, PMUs etc.
c) IRIG-B (Modulated) ports BNC type and FO serial ports of sufficient numbers
to signal the relevant devices for the new diameters of 765KV and 400KV level as
well as for 3 spare diameters each for 765KV and for 400KV level.
d) Potential free contact (Minimum pulse duration of 50 milli Seconds.)
e) PTP port for time synchronization of necessary devices.
The time synchronization of all the relevant SAS equipments shall be realized using
the SNTP protocol through the SAS LAN. A time accuracy of 1ms shall be achieved
for all the devices within SAS.
12) HMI FUNCTIONS:
PRESENTATION AND DIALOGUES GENERAL
605
The Local HMI for Operation & Engineers console shall provide basic functions
for supervision and control of the substation. The operator shall give commands
to the switchgear on the screen via mouse clicks or soft-keys through keyboard.
The HMI shall provide the operator with access to alarm and events displayed on
the screen. Besides these lists on the screen, there shall be a print out of hard
copies of alarm or events.
Following standard display shall be available from the HMI:
* Single line diagram showing the switchgear status and measured vales.
* Control dialogues.
* Measured values
* Alarms list.
* Events list.
* System status.
* A/R selection
* PT selection/ CT selection (one and half breaker scheme)
* Carrier status
* Tripping selection
13) SYSTEM SUPERVISION DISPLAY:
The SA system shall be comprehensively self-monitored and faults will be
immediately indicated to the operator before they develop into serious
situation. Such faults are recorded as faults in a system supervision display.
The display shall cover the status of the entire substation including all
switchgear, Numerical relays and communication links. Dynamic colouring
of single line diagram with load, power factor voltage. Bay view to zoom all
the parameter.
All interlock status information for control circuits pertaining to the CB,
Isolator, earth switch should be displayed in the SAS. Where ever interlock is
not satisfied that should be highlighted in separate colour for operator alert.
14) EVENT LIST
The event list shall contain events with time tag (universal time
synchronization with GPS) , which are important for the control and
monitoring of the substation. The date and time has to be displayed for
events. The events shall be registered in a chronological events list in which
606
the type of event and its time of occurrence are indicated. It shall be
possible to store all event in the HMI. The information shall be obtainable
also from printed event log.
15) ALARM LIST:
Fault and error occurring in the substation shall be listed in an alarm list and
shall be immediately transmitted to the control centre. The alarm list shall
substitute a conventional alarm table, and shall constitute an evaluation of
all station alarm however alarm and visual must be provided on receiving
alarm. It shall contain unacknowledged alarms and persisting faults. Date
and time of occurrence shall be indicated. Historical data sizing for storing
Data for 35 days shall be available in the SA system. The capacity of the
server is to be designed accordingly. Also necessary hardware and software
to copy and store data from server should be provided. The data collected
shall not be lost due to overflow. Whenever overflow is likely to occur, the
date shall be archived into storage media like CD so that there is no change
of losing historical data.
16) RIGHTS:
local HMI: shall be able to get data from all the equipments for monitoring
and control.
Engineering/DR work station: shall have the facility for relay setting and
analysis of faults by acquiring disturbance recorder data from Numerical
relays.
The alarm list consists of a summary display of the present alarm
situation. Each alarm shall be reported on one line that contain.
The alarm date and time.
The name of device in alarming state.
A descriptive text.
The acknowledgement state.
The operator shall be able to acknowledge alarms, which shall be
either audible or only displayed on the monitor. Acknowledged alarms
shall be marked at the list. Filters for selection of a certain type or group of
alarm shall be available as for events.
607
The SAS servers and the Engineering workstations, gateway devices shall be
equipped with all necessary hardware and original softwares to
accommodate the future electrical bays without additional cost to
TANTRANSCO and without the need for additional licenses from original
equipment manufacturer.
The SA system shall be designed to satisfy the very high demands for
reliability and availability concerning.
20) Documentation:
The following documentation to be provided for the system in the course
of the project shall be consistent, CAD supported, and of similar look/feel:
e. List of Drawings.
f. Substation automation system architecture.
g. Block Diagram.
h. Guaranteed technical parameters,
i. List of Signal-Analogue/Digital.
j. Schematic diagrams.
k. List of Apparatus.
l. List of Labels.
m. Logic Diagram.
n. Test schedule and reports of FAT/SAT
o. Product Manuals
p. Operators Manual.
m. Listing of software and loadable in CD ROM as well as in the
spare HDD.
609
- IED capability description file (ICD) that describes the available functions
logical nodes and services available from IED.
- Configured IED description file (CID) that is final file to download into IED
to enable its configuration
610
611
612
Each workstation shall be equipped with at least one (1) CD/DVD RW drive to
allow transfer of data and other software from the Hard Disk(s) to removable
CD/DVD media.
23) Metering PC
Type Industrial grade substation-hardened computer hardware
equipment
Cabinet for IP41 compliant standalone cabinet with outer protective glass door.
Server Equipped with all necessary accessories.
613
HDD 2 nos HDD 500 GB SATA. (In case 500 GB is not sufficient for
application including data then higher capacity shall be provided for
each HDD. )
All relevant original software and tools for viewing in real time and generating
reports relevant to metering data.
The metering data from the meters shall also be integrated in to the station
HMI servers in real time through the SAS LAN. The metering PC should be
provided with comprehensive anti-virus protection and cyber protection as
appropriate.
614
ii. Redundancy boxes for interface of each of the computers without of PRP
(PARALLEL REDUNDANCY PROTOCOL) support for compatibility with
redundant communication architecture using to parallel redundancy
protocol should be provided. However all numerical relays, BCUs and SAS
servers,Gateway should be inherently equipped with two ports using PRP
(PARALLEL REDUNDANCY PROTOCOL).
Inter-bay LANs:
615
* Support SNMP preferably the latest version to provide secure and full
network management. Port Security through disabling of
packets from unauthorized MAC addresses. RMON for
monitoring of network status & statistics.
* IGMP Snooping enabling reductions in multicast
traffic
* SNTP for synchronizing the internal clock of all the devices
connected to the LAN.
* RSTP (IEEE 802.1w) industry standard method
for providing recovery of redundant networks
* RMON for monitoring of network status & statistics
* Port Mirroring assisting network troubleshooting
* Event Logs creating a historical record of events
occurring on the network
* Port Security through disabling of packets
from unauthorized MAC addresses
* SSL Web encryption preventing eavesdropping,
tampering or message forgery
* The backbone link for each ring network
25) CAPACITY:
The system should be capable of handling up to 150 IEDs and 10,000 data
points. In case the application considering with future bays necessitates to support
higher number of devices and data points then the system shall be equipped
accordingly.
26) SEQUENCY OF EVENTS (SOE) FEATURE:
To analyze the chronology or sequence of events occurring in the power
system, time tagging of data is required which should be achieved through SOE
feature of SA. The server should have an internal clock with adequate stability.
The Server time should be set from time synchronization messages received from
GPS equipment to be supplied by bidder. The Server should maintain a clock and
should time-stamp the digital status data. Any digital status input data point in the
Server should be assignable as an SOE point. Each time a SOE status indication
point changes the state, the Server should time-tag the change and store in SOE
616
buffer within it. SOE shall be transferable to the Remote Control Centre through
the IEC 60870-5-101 gateway. The time resolution for SOE should be 1 ms at
point of acquisition.
27) ETHERNET SWITCHES:
The Ethernet switches used for creating the LAN network should meet the
specification as laid down in the IEC 61850 standard and should be of managed
type SNMP based. The Ethernet switches should comply to IEC 61850-3
standard/equivalent for EMI Immunity and environmental compliance pertaining
with Electrical utility substations applications.
* The Ethernet switches shall be equipped with 50% spare ports.
* Dedicated Separate set of Ethernet switches shall be provided for each dia.
*Ethernet switches shall support the features stipulated under general specification
for the LAN.
* Should be Compliant to parallel redundancy Protocol (PRP) in networking on
IEC 61850.
* Digital Diagnostic Monitoring (DDM) for Fiber :
Ethernet switches shall be equipped with the functionality to monitor ST/SC (as
well as SFP) connectors, and NMS via SNMP trap when abnormalities are detected,
allowing
operators to initiate maintenance procedures, Further the complete LAN system
shall allow system operators to monitor things like transmission and reception
power, temperature, and voltage/current along optical fiber connections in real
time.
28) GATEWAY EQUIPMENT
The Gateway equipment shall conform to the following technical
requirements:
- The gateway equipment shall be based on embedded technology without moving
parts.
- The gateway equipment shall comply to IEC 60255 standards / Equivalent
IS for EMC and Environmental compliances.
- Support IEC 61850 protocol, IEC 60870-5-101/104 protocol.
617
- Perform the data concentration by directly collecting data from the bay level
devices and provide the same to the remote LDC/Master with out the aid of the
SAS HMI servers.
- The gateway device should be equipped with sufficient memories for firmware,
Configuration data, Process data, records.
- Equipped with redundant communication ports for SAS interfaces as well as for
remote LDC/Master interfaces.
- Equipped to run high speed programmable logic control function that includes
provision for implementing station level interlocks and automation logic as
necessary.
- Necessary software with original license for Anti-virus protection with Relevant
firewall should be provided for operating system based on MS windows.
- The gateway equipment shall be rack mount housed in a IP31 compliant cabinet
with protective glass door. Cabinet design shall ensure to be equipped with the
standard accessories specified for relay cabinets.
- Gateway shall be equipped with redundant power supply modules and
communication modules.
Redundant Gateways i.e 2 nos Gateways operating in redundant
configuration shall be provided. One of which operating in online and the other
operating in hot standby by shall be provided. The switchover between gateway
devicesshall beAutomatic, quick enough for the application, bump less
without loss of SAS data during switchover, the databases of the
online and hot stand by shall be synchronized in real time. It shall be
possible to operate with one gateway device in case of outage or failure of
one gateway device.
Each of the gateway unit shall be equipped with two Ethernet ports for parallel
redundancy (in compliance to IEC-62439-3) in networking on IEC 61850
Protocol.The above referred 2nos Ethernet ports shall also be used for time
synchronization using SNTP protocol with guaranteed resolution of 1ms.
618
STATION LAN-A
Protocol GPS
converter SYSTEM
IEC101/104
TOREMOTE Communication Redundant Device
LDC terminal Gateway
Equipment Devices Meter
Meter
ToStation
Ethernetswitchfor1No
765kVdiameter
Ethernetswitchfor1No
Ethernetswitchfor1No InterbayLANAFOLINK
400kVdiameter
765kVdiameter
Ethernetswitchfor1No
400kVdiameter
ToStation Ethernetswitchfor1No
765kVdiameter
Ethernetswitchfor1No
Ethernetswitchfor1No InterbayLANBFOLINK
400kVdiameter
765kVdiameter
Ethernetswitchfor1No
400kVdiameter
619
Ethernetswitchfor1No765kVdiameter Ethernetswitchfor1No765kVdiameter
765kVFRP
ToLANA
Main1 PRPPorts ToLANB
ToLANA
BCU PRPPorts ToLANB
RS485FOlinktoMeteringPC(DLMS)
ABTMeter
ToLANA (IEC61850)
PU ToLANA
PRPPorts
(BBPMain) ToLANB 765KVTIERP
ToCUBBP(Main) ToLANA
PRPPorts Main
ToLANB
PU ToLANA
PRPPorts
(BBPMain) ToLANB
ToCUBBP(Backup)
ToLANA
PRPPorts BCU
765kVTRF(HV)RP ToLANB
ToLANA
Main1 PRPPorts ToLANB
ToLANA
Main2 PRPPorts ToLANB
ToLANA
BCU PRPPorts ToLANB
CSD ToLANA
Redundancy
Box PRPPorts ToLANB
RS485FOlinktoMeteringPC(DLMS)
ABTMeter
ToLANA (IEC61850)
PU ToLANA
PRPPorts
(BBPMain) ToLANB
ToCUBBP(Main)
PU ToLANA
PRPPorts
(BBPMain) ToLANB
ToCUBBP(Backup)
620
Note :
621
30. INVERTER :
1.The inverters shall comply with the following specification and characteristics:
Nominal frequency 50 Hz
Power factor range Rated 0.8 (0.6 to Unity, within KVA & KW)
Note: A worksheet depicting the total calculation of the assigned load should be
furnished in assessing the rating of the inverter.
2.The inverters shall comply with the following characteristics:
i) The inverters shall normally operate in synchronism with the mains AC power
source. Upon loss of the mains AC power source or its frequency deviating beyond
a preset range, the inverters shall revert to their own internal frequency standard.
When the mains AC source returns to normal, the inverters shall return to
synchronized operation with the mains AC source. Such reversal of operation of
622
inverters from synchronous to free running mode and vice-versa shall not introduce
any distortion or interruption to the connected loads. A suitable dead band for
frequency may be provided to avoid unnecessary frequent reversal of inverter
operation between free running mode and synchronized mode under fluctuating
frequency conditions.
ii). For safe operation in the event of Power failure or input source voltage
dropping below preset value, necessary safeguard software shall be built in for
proper shutdown and restart.
iii) The inverters shall be synchronized to the main AC source unless that
source deviates from 50 Hz by more than 1% (adjustable to "1/2/3/4/5%).
iv). The inverters shall provide interrupter switch to isolate the unit from the load
on failure of the unit. The interrupter switch shall be rated to carry full continuous
load and to interrupt the inverter under full fault load.
v).The inverters shall be capable of supporting a start-up surge or
overload of 150 % of rated output for up to 60 seconds.
vi).The transient voltage response shall not exceed "4% for the first half-
cycle recovering to 1% within ten cycles for a 100 percent step load
application or removal.
3. Control panel for auto/manual switch over of the redundant inverters shall
be provided with the inverter.
4.The scope of supply, installation, testing and commissioning of inverter also
includes All the necessary AC Distribtuion boards, DC Distribution boards, Control
panel to facilitate manual change over, auto change over and bypass mode with
meters for monitoring the voltages. Tender scope includes all the necessary power
cables and control cables for this equipment.
5. Type tests for inverter:
The inverter shall comply to IS 13314 / Equivalent standards as applicable for the
KVA required for the project
This includes the following tests.
1. Visual inspection test
2. High voltage test
3. Insulation resistance test
4. No-load test
623
5. Output test
6. Climatic tests
7. Harmonic contents test
8. Radio frequency interference test for conducted emission in the AC output
circuit.
31. Laptop computer for SAS tool
Keyboard & Full size Spill resistant keyboard with 10key numeric keypad,
MOUSE Optical mouse.
Connectivity Wifi, Bluetooth, USB port-3nos, RJ45 10/100Mbs Ethernet port.
624
Note :
1.The bill of materials for relay panels in this section is for conceptual information,
however any additional component and devices required in the relay panels to fulfill
the protection, control and metering scheme shall be included without additional
cost.
2. The Bus bar protection panel shall be equipped completely to accommodate all
the Bays including future Bays depicted in the single line diagram of the
substations plus 6 spare circuits.
3.The under frequency scheme for feeders shall be shall be equipped completely to
accommodate all the feeders including future feeders depicted in the single line
diagram of the substations plus 3 spare feeders.
4. DC supervision relay should be provided for each of DC sources and at the DC
output of the DC selection relay. The DC fail alarm should be made available to the
SAS.
5. If Functions of supervision relays, trip relays,selector switches,auxiliary relays
are incorporated in a multifunction IED then it is subject to design approval from
TAN TRANSCO. Such scheme should be designed such that a single point of failure
in the multifunction IED should not cause failure of simultaneous failures of Main-
I/Main and main-II/Backup protection scheme
6.VT selection for control & Relay panes:
VT selector switch for selection between Line VT/ Bus VT-1/ Bus VT2 shall be
provided. However the scheme shall be provided with logic to ascertain the correct
Bus VT. Separate core shall be wired for Main-1 protection, Main-2 protection and
metering devices.
7. Redundancy boxes for interface of each of the IEDs with single Ethernet port for
compatibility with redundant communication architecture using to parallel
redundancy protocol should be provided. However all numerical relays,
BCUs,Gateway and SAS servers should be inherently equipped with two ports using
PRP (PARALLEL REDUNDANCY PROTOCOL).
625
9. Control switch (TNC) spring return type with pistol grip handle for Breaker 1 No.
12. Three phase Master Trip relay (H&ER reset contacts, Hand reset flags) 2 Nos.
13. Three phase master Trip relay for UF (81U,81R) scheme 1 No.
14. Supervision relays for all the master tripping and lockout relays As required
21. Standard relay panel accessories as stipulated in this specification -As required
626
II. BOM: ISLANDING PANEL for 765 kV Feeders as well as for 400 kV
Feeders
4. Supervision relays for all the tripping and lockout relays As required
8. 3-phase Master Trip relay for UF (for 81U,81RF) scheme for future feeders: 6 nos
Note :
1. Master Trip relay for UF (81U,81RF) scheme is to be provided in the respective feeder
relay panels.
2.As the SAS is in distributed architecture and in order to reduce the cabling, the stage
wise trip output commands for respective feeders shall be communicated through GOOSE
messaging to the numerical main-1 and main-2 protection relays of respective feeder bays.
III.BOM: Relay panel for 765 kV Tie breaker as well as for 400 kV Tie
breaker :
3. Three phase Master Trip relay (H&ER reset contacts, Hand reset flags) 2 Nos.
627
6. Trip Circuit Supervision relay (Pre close and Post close) 6 Nos
9. TNC Control switch spring return type with pistol grip handle for Breaker 1 No 10. Relay
for Automatic DC source selection As required.
11. High speed trip relay (96) for busbar protection As required.
12.Supervision relays for all the tripping and lockout relays As required
1) Set of low impedance bus bar protection scheme of Numerical type for 1 Set
single/double zone with check zone for bus. 1 Set is inclusive of:
ii) Peripheral units As required for all Main breakers of each diameter plus six spare
peripheral units.
3) Bus bar cut IN/OUT switch Main and check zones. As required
Note :
1.The Bus bar protection is a redundant (1+1) scheme i.e The above BOM will be
duplicated in second set of Bus bar protection panel. One set of busbar
protection should be of different make from the other set.
2.Spare Peripheral units shall be installed in a separate panel and the same shall be
located in switchyard panel room where bus bar protection panel shall be installed.
3.Peripheral units with all necessary associated materials shall be installed in the
respective bay protection relay panels.
4. For dedicated FO link for redundant Busbar protection scheme consider LIUs as required
apart from the LIUs for the SAS LANs.
6. Numerical non-direction over current protection relay with LBB and high set 1 No.
for LV side
7. TNC Control switch spring return type with pistol grip handle for Breaker 2 Nos
8. Three phase Master Trip relay (H&ER reset contacts, Hand reset flags)As required
629
10. Trip circuit supervision relay for HV and LV trip coils As required
(pre close and post close)
13. Supervision relays for all the tripping and lockout relays As required
(Typically : Buchholz alarm-3 Element, Oil flow alarm-3, WTI-3 Element, OTI-3
Element, Oil level alarm-3 Element, PRV Trip-3 Element, Buchholz trip-3 Element,
OLTC Low oil Level- 3Element )
17. P.T. selection scheme with bistable relays ( for HV and LV ) 2 Sets.
18. High Speed tripping relay (96) for B/B protection 2 Nos
Note :
2. CSD in the scope of supply of breaker for each transformer shall be installed
in the transformer relay and integrated with SAS.
(Low Z based For Neutral and neutral grounding reactor side as applicable)
12. Three phase Master Trip relay (H&ER reset contacts, Hand reset flags) 2 Nos.
13. Supervision relays for all the tripping and lockout relays As required
14. TNC Control switch spring return type with pistol grip handle for Breaker 1 No
Note :
1.The protection scheme for Bus reactor may be grouped in to Grouped in to two
numerical multifunction protection relays wherein the differential protection and backup
impedance shall not be implemented in the same relay. In this context the protection
scheme shall be such that all type of faults within the reactor shall be detected by both the
group 1 & group2 relays. However separate numerical relay for LBB protection is
applicable.
631
3. CSD in the scope of supply of breaker for reactor shall be installed in the reactor relay
and integrated with SAS.
VI.BILL OF MATERIALS FOR RELAY PANEL FOR 765 KV BUS REACTOR AS WELL
AS FOR 400 KV BUS REACTOR:
(Low Z based For Neutral and neutral grounding reactor side as applicable)
12. Three phase Master Trip relay (H&ER reset contacts, Hand reset flags) 2 Nos.
13. Supervision relays for all the tripping and lockout relays As required
14. TNC Control switch spring return type with pistol grip handle for Breaker 1 No
632
Note :
1.The protection scheme for Bus reactor may be grouped in to Grouped in to two
numerical multifunction protection relays wherein the differential protection and backup
impedance shall not be implemented in the same relay. In this context the protection
scheme shall be such that all type of faults within the reactor shall be detected by both the
group 1 & group2 relays. However separate numerical relay for LBB protection is
applicable in case the LBB for the breaker(s) are not covered in any other scheme.
2. CT supervision, VT supervision shall be provided in the relays.
3. CSD in the scope of supply of breaker for reactor shall be installed in the reactor relay
and integrated with SAS.
VII. Standard relay panel accessories:
All the Control & Relay panels shall have the following
4. Test terminal block for testing metering & protection devices - As required
633
( Free standing, self supported, with swing frame for devices and outer glass door.)
14. MCBs (with auxiliary contact) for DC Supply and AC supply distribution As required
circuits
15. DC fail test/accept button - 2 Each
18. Push button for manual resetting of master trip relays (86,96) As required
20. Dedicated Line interface unit for interbay fiber optic LAN interface As required
(Typically 4 nos; i.e 2 Units for each LAN. For dedicated FO link for redundant
Busbar protection scheme consider LIUs as required)
General: The following items are included under the scope of supply for relay
panels and for SAS equipments
634
10 All LAN cables with associated cable ducts and all Lot 1
accessories, media converters etc running within a KIOSK
for each diameter as well as in control room building).
635
panels- 1 set
Note:
1. The price of the relay panel shall be inclusive of the BCU mentioned in the BOM for the
respective relay panel. The BCU/IED for common alarms shall be considered under supply
of SAS.
2.IED(s)/ BCU(s) with graphic display of sufficient I/O capacity shall be offered for covering
all the sub-station auxiliary items, RMU,Fire alarm system, complete Power supply
(Charger, Batteryand distribution system (DCDB,ACDB),common alarms in the sub-station.
636
3. Media type (PLCC or Fibre optic media or leased line ) for gateway interface to the
remote load dispatch centre would be known during project execution.
4. Furniture shall be industrial grade, reputed brand with design life for 20 years.
5. Outdoor type armoured Fibre optic cables for the SAS LANs for linking the Relay panels
in each diameter housed in each kiosk to the SAS LANs (at level-1,2) and for implementing
communication link for any other control, protection and metering scheme should be
provided in the SAS scope if a separate price item for these cables are not in the price
schedule.
XV. Spares:
637
Nos. As stipulated for relay panel
17 D.C. supply supervision relay 2
Nos. As stipulated for relay panel
18 Trip circuit supervision relay 4
Nos. As stipulated for relay panel
Single phase trip relay (with self-
19 reset contacts) 2
Nos. As stipulated for relay panel
20 Selector switch for L/R selection 2
Nos. As stipulated for relay panel
21 Selector switch (A/R IN/OUT) 2
Nos. As stipulated for relay panel
22 Selector switch (Carrier IN/OUT) 2
No. As stipulated for SAS
23 Hard disk for HMI server 1
Each type of Hardware Modules
24 for GPS equipment Set 1
Includes all necessary spares for maintenance of
Inverter for 5 years. IGBT should also be included.
25 Spares for Inverter for SAS Set 1
Complete with FO patch cable.
Line interface unit for SAS FO LAN
26 for one diameter Set 1
Spares for relay panels and SAS in the scope of supply shall be the same make,model/type
as in the actual supply. The numerical relays,IEDs,BCUs under the spares shall be
equipped for maximum I/O configuration.
XVI. TRAINING SCOPE:
Training shall be imparted at works and at site as described below.
a) Training at suppliers works :
Minimum one week training for two batches of Boards engineers at the
manufacturers works with lectures and hands on training on complete SAS &
protection relays. This training shall be imparted prior to commissioning of SAS &
protection system. Training shall be organized in batche(s) wherein each batch
shall comprise at least 5 trainees. All relevant training material, tools and
equipments shall be provided for each trainee towards this training. The training
shall cover the technology, principle of operation, functions etc of the protection
relays and SAS devices. Training content should be furnished to TANTRANSCO for
obtaining concurrence prior to training schedule.
All expenses for trainees towards boarding, lodging, travel , travel insurance etc to
attend the training program is in the bidders scope. In this context charges of any
kind shall not be levied to TANTRANSCO.
b) Training at site (Applicable for each sub-station):
Comprehensive hands on training of TAN TRANSCO engineers at site should be
imparted for two batches as follows:
i. For 1 batch of at least 5 engineers oriented for operations of SAS &
protection system. This training shall be imparted after commissioning of
SAS.
ii. For 1 batch of at least 5 engineers oriented for Testing, commissioning
& maintenance of complete SAS & protection relays. This training shall
be imparted after installation of SAS & protection system. This training
638
639
software shall also be supplied for on line transfer of data from all acquisition units
to Evaluation unit.
The acquisition unit shall have the following features:
1. The acquisition unit shall have a 16 bit analog to digital convertor with a
minimum of 8 analog inputs, 32 digital inputs.
2. The resolution for digital inputs shall be better than 80 ns.
3. The frequency response shall be DC on lower side and 3.0kHz or better on
upper side.
4. It shall also have indication for data transfer, normal operation and powered up
stage and shall communicate with evaluation units on fiber optic
communication.
5. The acquisition unit shall be capable of acquiring current or voltage or milli
Amp.
6. It shall supervise healthiness of Acquisition units, failure of acquisition must be
indicated in acquisition unit as well as central unit
7. It shall supervise communication path between acquisition and central unit
8. It must have provision for mounting acquisition units at each bay to reduce
panel wiring
9. It should have sampling rate of up to 256 samples per cycle for each input
(CT,VT, Transducer and Binary input)
10. It must support LAN based triggering of all recorder connected in network
11. The drift in internal clock must not be greater than 0.1 sec, if GPS signal is lost
(Not available) for 24 hours.
12. Shall support a maximum distance of up to 2 km between acquisition unit and
central unit, and it shall also support compensation for communication delay
between acquisition and central unit
13. The CT and VT input shall be selectable at site, if required same input of
acquisition unit need to be used for either CT or VT
14. The recorder system shall be capable to directly acquire IEC 61850-9-2 sampled
values ; it shall also be possible to acquire inputs on IEC 61850-8-1.
640
Transient Recorder:
These records shall be very short in duration and typically include faults that are
cleared immediately by circuit breaker operation. These events shall be analyzed to
determine correct protection operation, faultlocation, or verification of system
model parameters.
641
Sampling Rate:
The trigger and continuous recorder sampling rate is 1 point-per-cycle of the
nominal frequency of the inputsignal.
Steady State Record
There records are steady state disturbances where system operation is not
threatened, but power quality is affected.This may include harmonics or sub-
harmonics produced by the load and/or the interaction between powersystems
components.Steady-state records are created daily. Measurements are continuously
recorded and averaged over 1 or 10min (user selectable). A new record is created
at the rollover of each day.
Sampling Rate:
The daily steady-state recorder sampling rate is 256 points-per-cycle, aggregated
in 1 point-per-minute or 1point-per-10-minutes as selected by the user.
Sequence-of-Events Recorder (SER)
Recorder shall gather and time tag operational data from substation equipment and
control schemes as they react to asystem event. This data allows the chain of
events to be studied for the cause (or causes) of any maloperationand the linkages
between individual actions and effects.SOE records are created daily recording on a
tabular format all the changes in digital and GOOSE inputs aremonitored.
Sampling Rate:
The SOE sampling rate is 256 points-per-cycle of the nominal frequency of the
input signal. Therefore, theresolution of the signal is better than 80 s.
Phasor Measurement Unit:
The acquisition units shall be either standalone for each line or composite unit
with thecapability to cater to four lines emanating from the substations. Incase
more than onelines are to be accommodated in one acquisition unit, then
suitable coupler unit shallbe provided in individual line bay C&R panels and only
secondary wiring shall bebrought to common acquisition unit. While offering this
option, bidders are advised totake care of maximum distance between
acquisition unit & line bays C&R panels, whichshall be placed in different Kiosks.
643