Standard Operating Procedure (Sop) : Transfer Bus Couler
Standard Operating Procedure (Sop) : Transfer Bus Couler
Standard Operating Procedure (Sop) : Transfer Bus Couler
2. Ensure Proper Permission (Permit) from Authorized Personal for Opening Isolators.
3. Open Bus Isolator 89A (Bus-1) or 89B (Bus-2) whichever is Closed.
4. Open isolator 89L of respective bay which is transferred/89L2 in case of SEZ line
feeders.
5. Check voltage , current of TBC panel, it should show total load of feeder.
6. Provide Do Not Operate Tag/Board.
7. Note down complete report in shift logbook.
* STATION TRANSFORMER *
Common Check Points:
1. Ensure Proper Permission (Permit) from Authorized Personal.
2. Ensure no any personals are working on system in respective bay.
3. Ensure all Earth switches are in Open condition.
4. Ensure Power & control supply is ON in CRP, Breaker & Isolators Panels.
5. Ensure LBB Link in CRP & 96 Link in Bus Differential panel are connected.
6. Ensure all relays are in RESET condition.
7. Ensure annunciation window are in normal condition.
8. Ensure physical status of all equipments is OK & match with CRP indications.
9. Ensure selector switch of Breaker & Isolators of that particular bay are in Remote.
10. Select MODE of operation i.e. CP (Through Discrepancy switch) or BCU (Through
F650 relay mimic, relay should be in LOCAL mode) or SCADA (Through control room
PC, F650 relay should be in REMOTE mode)
Operations for Close:
1. Remove Do Not Operate Tag / Board.
2. Ensure MPP side Bus on which Transformer is to be synchronised is charged.
3. Inform to MSETCL & BTG control room for Isolator operations.
4. Close Bus Isolator 89A (Bus-1) or 89B (Bus-2) as per planning.
5. Close Line isolator 89L (Line isolator)
6. Ensure physical status of Isolators is in close condition.
7. Take Clearance from BTG Electrical shift in charge for Breaker close.
8. Close Breaker & ensure physical status of breaker that it is closed.
9. After closing Circuit Breaker, ensure all relays & annunciations are in normal
condition.
10. Compare Electrical parameters (Power, Voltage & Current) with 6.6 KV Incomer.
11. Confirm to MSETCL for Generator taken in Grid (Line)
12. Note down complete report in shift logbook.
ABHIJEET MADC NAGPUR ENERGY PRIVATE LIMITED
220 KV SUBSTATION - ELECTRICAL DEPARTMENT
STANDARD OPERATING PROCEDURE (SOP)
Operations for Open:
1. After Breaker open from BTG control room, ensure physical status of breaker that all
three poles are Open.
2. Ensure Proper Permission (Permit) from Authorized Personal for Opening Isolators.
3. Open Line isolator 89L (Line isolator).
4. Open Bus Isolator 89A (Bus-1) or 89B (Bus-2) which is Closed.
5. Provide Do Not Operate Tag/Board.
6. Note down complete report in shift logbook.
* START-UP TRANSFORMER *
Common Check Points:
1. Ensure Proper Permission (Permit) from Authorized Personal
4. Ensure Power & control supply is ON in CRP, Breaker & Isolators Panels.
5. Ensure LBB Link in CRP & 96 Link in MSETCL Bus-bar panel are connected.
8. Ensure physical status of all equipments is OK & matched with CRP indications.
9. Ensure selector switch of Circuit Breaker & Isolators of that particular bay are in
Remote mode.
10. Select MODE of operation i.e. CP (Through Discrepancy switch) or BCU (Through
F650 relay mimic, relay should be in LOCAL mode) or SCADA (Through control room PC,
F650 relay should be in REMOTE mode).
11. Ensure personals are not working on Start-up Transformer.
Operations for Closing:
13. Remove Do Not Operate Tag / Board.
14. Inform to MSETCL & BTG control room for Isolator operations.
15. Close Bus Isolator 89A (Bus-1) or 89B (Bus-2) as per planning.
16. Close Line isolator 89L (Line isolator).
17. Ensure physical statuses of Isolators are in close condition.
ABHIJEET MADC NAGPUR ENERGY PRIVATE LIMITED
220 KV SUBSTATION - ELECTRICAL DEPARTMENT
STANDARD OPERATING PROCEDURE (SOP)
18. Take Clearance from BTG Electrical shift In-charge as well as from MSETCL Shift In-
charge for Breaker close.
19. Close Breaker & ensure physical status of breaker is closed.
20. After Breaker closing, ensure all relays & annunciations are in normal condition.
21. Compare Electrical parameters (Power, Voltage & Current) with 6.6 KV Incomer.
22. Convey to MSETCL that Start-up Transformer is taken in service.
23. Note down complete report in shift logbook.
Operations for Opening:
1. After opening Circuit Breaker from MPP control room, ensure physical status that
Breaker is Open.
2. Ensure Proper Permission (Permit) from Authorized Personal for Opening Isolators.
* BUS SECTIONALISER - 1 *
Common Check Points:
12. Ensure Proper Permission (Permit) from Authorized Personal.
13. Ensure no any personals are working on system in respective bus.
14. Ensure all Earth switches and all bus isolators are in Open condition.
15. Ensure Power & control supply is ON in CRP, Breaker & Isolators Panels.
16. Ensure LBB Link in CRP & 96 Link in MPP Bus Differential panel or MSETCL Bus Bar
panel are connected.
17. Ensure all relays are in RESET condition.
18. Ensure annunciation window are in normal condition.
19. Ensure physical status of all equipments is OK & match with CRP indications.
20. Ensure selector switch of Breaker & Isolators of that particular bay are in Remote.
21. Select MODE of operation i.e. CP (Through Discrepancy switch) or BCU (Through
F650 relay mimic, relay should be in LOCAL mode) or SCADA (Through control room
PC, F650 relay should be in REMOTE mode)
Operations for Close:
ABHIJEET MADC NAGPUR ENERGY PRIVATE LIMITED
220 KV SUBSTATION - ELECTRICAL DEPARTMENT
STANDARD OPERATING PROCEDURE (SOP)
* BUS SECTIONALISER - 2 *
Common Check Points:
22. Ensure Proper Permission (Permit) from Authorized Personal.
23. Ensure no any personals are working on system in respective bus.
24. Ensure all Earth switches and all bus isolators are in Open condition.
25. Ensure Power & control supply is ON in CRP, Breaker & Isolators Panels.
26. Ensure LBB Link in CRP & 96 Link in MPP Bus Differential panel or MSETCL Bus Bar
panel are connected.
27. Ensure all relays are in RESET condition.
28. Ensure annunciation window are in normal condition.
29. Ensure physical status of all equipments is OK & match with CRP indications.
30. Ensure selector switch of Breaker & Isolators of that particular bay are in Remote.
ABHIJEET MADC NAGPUR ENERGY PRIVATE LIMITED
220 KV SUBSTATION - ELECTRICAL DEPARTMENT
STANDARD OPERATING PROCEDURE (SOP)
31. Select MODE of operation i.e. CP (Through Discrepancy switch) or BCU (Through
F650 relay mimic, relay should be in LOCAL mode) or SCADA (Through control room
PC, F650 relay should be in REMOTE mode)
Operations for Close:
34. Remove Do Not Operate Tag / Board.
35. Inform to MSETCL & BTG control room for Isolator operations.
36. Close Bus Isolator 89AE then 89BE as per planning.
37. Ensure physical status of Isolators is in close condition.
38. Take Clearance from MSETCL shift in charge for Breaker close.
39. Close Breaker & ensure physical status of breaker that it is closed.
40. After closing Circuit Breaker, ensure all relays & annunciations are in normal
condition.
41. Compare Electrical parameters (Power, Voltage & Current) with 6.6 KV Incomer.
42. Confirm to MSETCL for Generator taken in Grid (Line)
43. Note down complete report in shift logbook.
Operations for Open:
12. After Breaker open from BTG control room, ensure physical status of breaker that all
three poles are Open.
13. Ensure Proper Permission (Permit) from Authorized Personal for Opening Isolators.
14. Open Bus Isolator 89AE or 89BE which is Closed.
15. Provide Do Not Operate Tag/Board.
16. Note down complete report in shift logbook.