Commissioning Schedule1

The document outlines a commissioning schedule for the Indonesia Muara Jawa Project. It includes 29 systems that will be commissioned between August 2017 and November 2017. The systems include compressed air, boiler makeup water treatment, cooling water, fuel oil, coal handling, ash handling, soot blowing, and steam blowing systems. Each system lists the start and end dates for commissioning and references the relevant commissioning procedure.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
34 views1 page

Commissioning Schedule1

The document outlines a commissioning schedule for the Indonesia Muara Jawa Project. It includes 29 systems that will be commissioned between August 2017 and November 2017. The systems include compressed air, boiler makeup water treatment, cooling water, fuel oil, coal handling, ash handling, soot blowing, and steam blowing systems. Each system lists the start and end dates for commissioning and references the relevant commissioning procedure.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 1

Commissioning Schedule of Indonesia Muara Jawa Project

No Description Start time Completion time Remark


1 Compressed air system 12-Aug-17 15-Aug-17 Air Compressor System Commissioning Procedure
2 Raw water pretreat system 10-Aug-17 14-Aug-17 Boiler Make-up Water System Commissioning Procedure
3 Boiler Makeup water treating system 23-Aug-17 29-Aug-17 Boiler Make-up Water System Commissioning Procedure
4 CCCW Sysytem 29-Aug-17 4-Oct-17 Closed Cycle Cooling Water Commissioning Procedure
5 Circulating Water System 20-Oct-17 26-Oct-17 Circulating Water System Commissioning Procedure
6 OCCW System 27-Oct-17 29-Oct-17 Open Cycle Cooling Water System Commissioning Procedure
7 Condensate Water System 4-Oct-17 8-Oct-17 Condensate Water System Commissioning Procedure
8 Darin Pump System 1-Oct-17 3-Oct-17
9 Boiler feedwater System 4-Oct-17 8-Oct-17 Feed Water System Commissioning Procedure
10 Fuel Oil System 10-Oct-17 15-Oct-17 Fuel Oil System Commissioning Procedure
11 Boiler dryoff 3-Oct-17 2-Oct-17
12 High pressure fluidizing air fan system 14-Oct-17 17-Oct-17 Air and Flue Gas System Commissioning Procedure
13 Induced draft fan system 14-Oct-17 17-Oct-17 Air and Flue Gas System Commissioning Procedure
14 Secondary air fan 14-Oct-17 17-Oct-17 Air and Flue Gas System Commissioning Procedure
15 Primary air fan system 14-Oct-17 17-Oct-17 Air and Flue Gas System Commissioning Procedure
16 Dynamic field test 25-Oct-17 30-Oct-17
17 Boiler chemical cleaning 31-Oct-17 6-Nov-17
18 Fluidized test 7-Nov-17 12-Nov-17
19 coal handling system 25-Oct-17 15-Nov-17 Coal Handling System Commissioning Procedure
20 Coal feeder system 1-Nov-17 4-Nov-17 Coal Feeder System Commissioning Procedure
21 Slug handling system 30-Oct-17 3-Nov-17 Ash and Slag Handling System Commissioning Procedure
22 Ash handling system 30-Oct-17 3-Nov-17 Ash and Slag Handling System Commissioning Procedure
23 Shooting blowing system 30-Oct-17 3-Nov-17 Soot Blower System Commissioning Procedure
24 Clorination system 8-Oct-17 18-Oct-17 Producing Chlorine System Commissioning Procedure
25 lube oil system 10-Oct-17 30-Oct-17 Lubricating Oil and Turning Gear System Commissioning Procedure
26 Turning gear system 5-Nov-17 5-Nov-17 Lubricating Oil and Turning Gear System Commissioning Procedure
27 FSSS system 1-Nov-17 5-Nov-17 FSSS Commissioning Procedure
28 Industrial waste water system 5-Nov-17 10-Nov-17 Waste Water Treatment System Commissioning Procedure
29 Boiler ignition and steam blowing 17-Nov-17 22-Nov-17