Fundamentals of Piping Technology
Fundamentals of Piping Technology
We need some
branch
connections
Not Preferable
Preferable
While carrying out pipe routing we also need to consider the following
Valves, strainers, instruments on the pipe should be easily accessible.
If needed separate ACCESS PLATFORMS to be provided to facilitate these.
Desired location and orientation of valves / instruments and other pipe components
are to be checked and maintained, like some valves or strainers can only be installed
in horizontal position.
Specific requirements for instrument installation to be checked, like temperature
gauge can not be installed in pipe which is less than 4 inch in size.
Specific requirements of STRAIGHT LENGTH of pipe for some components to be
maintained, like for flow orifice we need to provide 15 times diameter straight pipe
length at upstream of orifice and 5 times diameter straight at down stream of orifice.
Let us look
into typical
Vent and
Drain
arrangement
in a pipeline
This is a 3D model
of Feed water line
along with pumps
and other
accessories
Find out type Find out Check Pipe Select suitable Check Mat. YES Pipe
of Fluid Fluid Temp. life Material per Listed in Material
flowing & Pressure Expectancy practice (Note-1) Design Code OK
NO
Note-1 : Material is selected per past experience with cost in
mind and per material listed in design code. If material is See Note-
not listed in code we may select next suitable material
listed.
1
Pipe Sizing Calculation - to select required pipe diameter based on velocity and pressure drop.
Find out Check Velocity Calc. flow area Calc. Press. Check Press. YES Pipe
Flow volume Allowable per required and Drop for that Drop meets Size
per second second Pipe size Pipe size Press. Budget OK
NO
Increase
Pipe Size
Pipe Thickness Selection - to select appropriate pipe thickness based on flowing fluid property.
Rigid Support
of load)
There are two types of spring Rigid Hanger
support
Variable load type, here support
load changes as the pipe moves.
Dynamic Support,
Constant load support, the load
Snubber
remains constant within some
range of movement. Rigid Support
Some Special Considerations for Piping
When pipes are routed UNDER GROUND (Buried) following points to be kept in mind:
Minimum pipe size to be routed under ground shall be not less than1 inch.
Avoid flange joint in U/G piping.
Keep in mind if pipe leaks U/G, it will be difficult to detect, so avoid U/G routing of pipe
carrying hazardous fluid.
Pipe to be laid below Frost Zone at areas where ambient temperature goes below freezing.
U/G, Buried piping should be properly protected from corrosion.
Pipe may be properly wrapped and coated to prevent corrosion.
Or U/G piping be protected by using Cathodic protection.