Minutes of Meeting WK282 - After Meeting

Download as docx, pdf, or txt
Download as docx, pdf, or txt
You are on page 1of 4

MINUTES OF MEETING (Three O Clock Meeting)

PT ADIMITRA BARATAMA NUSANTARA


Project:
SANGASANGA, EAST KALIMANTAN Project No 3874C
Purpose: Mine planning meeting PTP/ABN Week 282
Location: ABN Meeting Room Reviewed Period 26th January - 1st February 2015
Date / Time: Progress Plan
2nd February, 2015 2nd February - 8th February 2015
Period

Attendees: PTP ABN


Ahjab A Karim - Deputy Project Manager Juvenry S - Engineering Manager
Andreas Junico - Engineering Superintendent Andi Victor - Manager Production
Eka B - HSE Manager Saut M - Engineer Superintendent
Katimin - Operation Manager Hery H - Engineering Coordinator
Lambok LR - Sr. Mine Engineer Rochim - HSE Superintendent
Ridwan - HSE Coordinator

Apologies: Riaan Basson - Project Manager Sudharmono Saragih - Operational Director

Recorded by: Lambok LR Signature:

Once printed this document becomes uncontrolled, Refer to Petrosea Intranet for controlled copy.
FORM No.: PTP-ADM-FO-G-0006 REV No.: 0 Page 1 of 4
MINUTES OF MEETING (Three O Clock Meeting)

RESPONSIBLE FOR
ITEM NO. POINTS RAISED STATUS DESCRIPTION
ACTION
1 SAFETY & ENVIROMENT
1.1. Traffic Management - No Issue

1.2 Training - No Issue

1.3 Safety ABN Info - ABN asks all contractors to take participation on activities during bulan K3
on ABN area.-->continue.
PTP Action - ABN remind PTP to construct ditch on each bench wastedump that have
been spreaded soil refer to SOP.

1.4 Access - No Issue

1.5 Environment ABN,PTP Action - ABN info will remaintain SP05 and total cost will be shared proporsionally
ABN and contractors.
1.6 Inspection ABN Info - ABN will do re- commissioning for all units contractors start on January
2015 continue
2 MINE PLANNING & MINE OPERATIONAL
2.1 Status 3 Month Plan, 12 Months PTP,ABN Action - PTP will submit draft mine plan Three month and Monthly at 25 every
Plan, LOM Plan month, continue to be reviewed by ABN and PTP until final mine plan on 28
every month.

2.2 Coal quality issues reported PTP Action - Coal getting for weekly achievement based on weekly plan -> Focus seam 4,
ABN Info dan group 5600 LS.(priority)
- ABN info will use label seam again on each DT coal to control coal quality.
-->3 feb 15.
- ABN will give guideline to PTP about coal handling and seam labeling on field
to avoid misunderstanding operationally.
2.3 Coal and OB production PTP Action - ABN asks PTP to maintain coal recovery all Pit. ( 96% as contract) continue
2.4 Haul distance PTP Info - Actual distance PIT 1:1,872 m Per 06th February 2015 A BN
- Actual distance PIT SARI: 2,246 m Per 06th February 2015 ABN
- Plan Monthly Feb : P1=1,967 m, PS=2,439 m.
PTP/ABN Action - ABN and PTP must be consistent for reconcile overhaul distance every 3
Once printed this document becomes uncontrolled, Refer to Petrosea Intranet for controlled copy.
FORM No.: PTP-ADM-FO-G-0006 REV No.: 0 Page 2 of 4
MINUTES OF MEETING (Three O Clock Meeting)

dayscontinue.
2.5 Survey PTP info - Focus control stake out at area final LOM Disposal WD 4 (update progress)
- Volume control weekly: P1= 0.75 % ; PS=0.24 %
2.6 Dewatering PTP Action - ABN ask PTP to maintain pumps performance pump (Debit Ratio 1.5)
- PTP info have been ordered for rent 1 x MF420 EX as replace 2 x MF385 (end
PTP Action of February).
- PTP info continue constructs channel on toe WD Pit 1 and Pit Sari.
2.7 Dump Area PTP/ABN Action - ABN asks PTP to balance WD 4 refer to Monthly plan January 2015
2.8 Top Soil - No Issue
2.9 Mobilization & demobilization - No Issue
2.10 Equipment PTP Action - No issue
2.11 Mine Plan & Design PTP Action - ABN ask PTP to keep 1 pumping Psari SP05
2.12 Hauling Road PTP/ABN Info - ABN asks PTP keep maintain road on underpass 1 area.
2.13 Mud excavation - No issue
2.14 Geotechnical Issue ABN Action - PTP asks ABN to send geotech assessment for South Waste dump Sari area.
- ABN asks PTP to dump at west area WD Sari as priority until geotech
assessment published and progress construct catch bench at south finished
by ARKA.
2.15 Model ABN Info - Last model ABN January 2015.
2.16 Other ABN/ PTP info - PTP already send formal letter about increase comsumption fuel caused by
increase bio disel at solar
- PTP info, already replace fuel filter based from recommendation due to fuel
quality issue (bio diesel) update per 25 january 15 ( excavator 91%, dozer
100%, truck 90%, grader 100% and units support 19%).
- ABN suggests PTP to invite PTP,ABN, and Solaris to solve case increasing fuel
consumption by bio disel solar.

Once printed this document becomes uncontrolled, Refer to Petrosea Intranet for controlled copy.
FORM No.: PTP-ADM-FO-G-0006 REV No.: 0 Page 3 of 4
MINUTES OF MEETING (Three O Clock Meeting)

3 PRESENTATION OF WEEKLY MINE PLAN & WORK AREA STATUS, DOCUMENT TABLE & SLIDE PRESENTANTION
3.1 Liebherr K0133 PTP Info - 09 th February 2015; standby; Pit 01
3.2 Liebherr K0134 PTP Info - 09 th February 2015; elevation -124.32; Pit 01
3.3 Liebherr K0135 PTP Info - 09 th February 2015; elevation -119 Pit 01
3.4 Liebherr K0143 PTP Info - 09 th February 2015; standby; Pit 01
3.5 Liebherr K0144 PTP Info - 09 th February 2015; standby; Pit 01
3.6 Hitachi K0154 PTP Info - 09 th February 2015; elevation -98.5; Pit 01
3.7 Hitachi K0131 PTP Info - 09 th February 2015; standby; Pit 01
3.8 Komatsu K0172 PTP Info - 09 th February 2015; off hire; out
3.9 Komatsu K0173 PTP Info - 09 th February 2015; elevation -119; Pit 01
3.10 Liebherr K0159 PTP Info - 09 th February 2015; elevation 24.44; Pit 01
3.11 Liebherr K0160 PTP Info - 09 th February 2015; elevation -28.2; Pit 01
3.12 Liebherr K0161 PTP Info - 09 th February 2015; elevation -128.5; Pit 01
3.13 Liebherr K0167 PTP Info - 09 th February 2015; standby; Pit 01
3.14 Liebherr K0136 PTP Info - 09 th February 2015; elevation 17.26; Pit Sari
3.15 Komatsu K0177 PTP Info - 09 th February 2015; standby; Pit 01
3.16 Liebherr K0140 PTP Info - 09 th February 2015; elevation 13.22; Pit Sari
3.17 Liebherr K0139 PTP Info - 09 th February 2015; elevation 3.14; Pit Sari
3.18 Liebherr K0141 PTP Info - 09 th February 2015; standby; Pit Sari
3.19 Liebherr K0145 PTP Info - 09 th February 2015; elevation 17.97; Pit Sari
3.20 Liebherr K0142 PTP Info - 09 th February 2015; standby; Pit Sari

Representative: Riaan Basson Project Manager Duraisamy Rajaram Project Manager


Date:
Signature:

Once printed this document becomes uncontrolled, Refer to Petrosea Intranet for controlled copy.
FORM No.: PTP-ADM-FO-G-0006 REV No.: 0 Page 4 of 4

You might also like