00 C C 00 Co P Qa 00 002 - 00
00 C C 00 Co P Qa 00 002 - 00
00 C C 00 Co P Qa 00 002 - 00
INDEX
INDEX ..............................................................................................................................................2
1. SCOPE AND PURPOSE ........................................................................................................6
2. DEFINITIONS AND ACRONYMS ..........................................................................................6
2.1 PROJECT DEFINITIONS .......................................................................................................6
ACRONYMS.....................................................................................................................................8
3. RESPONSIBILITES AND OBLIGATIONS ........................................................................... 10
3.1 PROJECT PROCUREMENT MANAGER ............................................................................ 10
3.2 PROCUREMENT COORDINATOR / BUYER ...................................................................... 10
3.3 EXPEDITING & TRANSPORT COORDINATOR / EXPEDITOR .......................................... 11
3.3.1 Expediting Coordinator .......................................................................................... 11
3.3.2 Shipping Coordinator ............................................................................................. 11
3.4 PROCUREMENT QC SUPERVISOR (PQCS)...................................................................... 12
3.5 PROCUREMENT QC MANAGER (PQCM) .......................................................................... 12
3.6 ASSIGNED INSPECTORS ................................................................................................... 13
3.7 PROJECT ENGINEERING MANAGER ............................................................................... 13
3.8 PROJECT DIRECTOR ......................................................................................................... 13
3.9 PROJECT QUALITY MANAGER ......................................................................................... 13
4. REFERENCE DOCUMENTS................................................................................................ 14
4.1 CODES AND STANDARDS ................................................................................................. 14
4.2 COMPANY DOCUMENTS ................................................................................................... 15
4.3 CONTRACTOR DOCUMENTS ............................................................................................ 15
5. QC PERSONNEL QUALIFICATION AND TRAINING ......................................................... 15
5.1 PERSONNEL QUALIFICATION .......................................................................................... 15
5.2 COMPANY INTERVIEW AND TESTING ............................................................................. 16
5.3 INSPECTOR ASSIGNMENT ................................................................................................ 16
6. PROCUREMENT PROCEDURE .......................................................................................... 17
6.1 GENERAL ............................................................................................................................ 17
6.2 PO PLACED TO MATERIALS STOCKIST .......................................................................... 18
7. INSPECTION PLANNING .................................................................................................... 19
7.1 INSPECTION AND TEST PLAN (ITP) ................................................................................. 19
7.2 INSPECTION REPORTS ..................................................................................................... 19
7.3 INSPECTION DOCUMENTATION REVIEW ........................................................................ 20
7.4 INSPECTION ASSIGNMENT PACKAGE (IAP) ................................................................... 20
This document is CONFIDENTIAL and the sole property SAIPEM/ SNAMPROGETTI/STAR CONSORTIUM. It shall not be shown to Third Parties nor used for purposes other than those for which it was
prepared.
Long Term Agreement for Offshore
Facilities
This document is CONFIDENTIAL and the sole property SAIPEM/ SNAMPROGETTI/STAR CONSORTIUM. It shall not be shown to Third Parties nor used for purposes other than those for which it was
prepared.
Long Term Agreement for Offshore
Facilities
This document is CONFIDENTIAL and the sole property SAIPEM/ SNAMPROGETTI/STAR CONSORTIUM. It shall not be shown to Third Parties nor used for purposes other than those for which it was
prepared.
Long Term Agreement for Offshore
Facilities
Amendment CONTRACTOR
Date Page Description
and revision Rep.
Issued for Comments /
A 24.05.2016 All PB
Approval
Relevant sections as
B 08.06.2016 per COMPANY Re-issued for Comments / PB
Comments Approval
(A) Relevant Sections
(Section 3, 7.7.3, 9.5.1
& 9.5.2) as per
COMPANY Comments
This document is CONFIDENTIAL and the sole property SAIPEM/ SNAMPROGETTI/STAR CONSORTIUM. It shall not be shown to Third Parties nor used for purposes other than those for which it was
prepared.
Long Term Agreement for Offshore
Facilities
The scope issued under Schedule Q of the Contract Attachment III of this document is to address
Company quality requirements for Contractor material and equipment to be procured by Contractor and
to define the operating modalities to be followed in order to manage project quality control related
activities of the following CRPOs and any upcoming CRPOs under the LTA Contract.
The following sections define criteria and functional responsibilities for planning and implementation of
QC surveillance at Suppliers. In addition, this document outlines specific contractual obligations to be
complied with in order to ensure that pertinent information are made available to the Procurement QC
Manager (PQCM) and Procurement QC Supervisor (PQCS), to project involved functions and Company
Representative, and that the supplies required level of quality is achieved within project budget and
schedule.
PQM and PD shall respectively verify and approve this QA plan for procurement of materials and
equipment, and PPM along with PQCM has the responsibility of the preparation, distribution and the
updating of this document
This plan shall be available to all project personnel including third parties.
CERTIFYING AUTHORITY The authority entrusted by COMPANY for the certification fit for purpose
of the WORK.
DOCUMENTS All incoming and outgoing correspondence (letters, faxes, telexes, e-mail),
and Technical Documents.
DMS DMS is the system to share, harmonize and manage documents inside a
global repository and answer the following questions:
This document is CONFIDENTIAL and the sole property SAIPEM/ SNAMPROGETTI/STAR CONSORTIUM. It shall not be shown to Third Parties nor used for purposes other than those for which it was
prepared.
Long Term Agreement for Offshore
Facilities
NON CONFORMITY REPORT Document issued by the Inspector in order to trace a non-fulfillment of a
(NCR) requirement.
PROJECT Maintain Potential Facilities Offshore Long Term Agreement
PROJECT DOCUMENTS Created and issued by the Contractor, include the following documents:
Any document produced by a member of the Contractor team and needed
for the execution of the Contractors scope, or which is a formal document
required for submission to Company or any other third party in the frame
of the Project, under the terms of the Contract.
PURCHASE ORDER (PO) Document issued by the Procurement Department for the purchase of
materials and equipment. This document and relevant attachments,
defines the parties' mutual obligations of Contractor and Supplier.
PO REVISION Document issued by Procurement Department to exercise the right of
(Modification Of Order) option, and/or to modify the Scope and/or quantities of supply, and/or to
modify commercial and/or technical clauses of the basic order.
PUNCH LIST Document issued by the Inspector during inspections in order to track the
missing activities that need to be completed on the Material prior to
shipment or accepted by the Contractor to be completed at Site with open
NCR
QUALITY STATEMENT (FOR Document issued by Contractor Quality Control department, for material
INSPECTION LEVEL 0) with Inspection level 0 certifying the conformity of purchase materials to
standards, codes and technical specifications mentioned in the Order. It is
issued on the basis of Manufacturers tests results and certificates issued
by Supplier.
RELEASE NOTE Document issued by Contractor after partial or inspection at balance
certifying that, for released material, the required inspections, tests,
review of certification have been performed and the relevant results are in
conformity with requirements. The Release Note is sent to Supplier by
email and copy to AOC.
SUBCONTRACT Contract signed by SUBCONTRACTOR and CONTRACTOR for the
performance of the portion of the WORK within the Project
SUBCONTRACTOR All Subcontractors and Vendors
This document is CONFIDENTIAL and the sole property SAIPEM/ SNAMPROGETTI/STAR CONSORTIUM. It shall not be shown to Third Parties nor used for purposes other than those for which it was
prepared.
Long Term Agreement for Offshore
Facilities
SUPPLIER'S CERTIFICATES Documentation and certificates issued by the Supplier after intermediate
and final tests, as required in the ARAMCO FORM 175, approved ITP and
technical attachments to the PO.
TECHNICAL DOCUMENTS Drawings, calculations, specifications, procedures, technical reports, etc.
TECHNICAL AND Exchange of information and documents with the Supplier during the
COMMERCIAL supply. This may include technical clarifications or duly approved
CORRESPONDENCE WITH modifications to the technical specifications.
SUPPLIERS
ACRONYMS
DC Document Controller
IR Inspection Report
MR Material Requisition
NC Non Conformance
This document is CONFIDENTIAL and the sole property SAIPEM/ SNAMPROGETTI/STAR CONSORTIUM. It shall not be shown to Third Parties nor used for purposes other than those for which it was
prepared.
Long Term Agreement for Offshore
Facilities
PC Procurement Coordinator
PD Project Director
PO Purchase Order
PR Purchase Requisition
PS Project Secretary
QA Quality Assurance
QC Quality Control
This document is CONFIDENTIAL and the sole property SAIPEM/ SNAMPROGETTI/STAR CONSORTIUM. It shall not be shown to Third Parties nor used for purposes other than those for which it was
prepared.
Long Term Agreement for Offshore
Facilities
Project Procurement Manager is responsible to Review Purchase Orders (PO) and follow up
actions including technical reviews, transportation, customs clearance, material handling and
storage, and Coordinate with the Procurement QC Supervisor to ensure that all material and
equipments are properly inspected and accepted.
This document is CONFIDENTIAL and the sole property SAIPEM/ SNAMPROGETTI/STAR CONSORTIUM. It shall not be shown to Third Parties nor used for purposes other than those for which it was
prepared.
Long Term Agreement for Offshore
Facilities
ensure the proper selection of the assigned inspectors against the relevant purchase
orders/equipment;
ITPs review;
ensure the completeness of the Inspection documentation package to be transmitted to
Company and assigned Inspectors;
PIM Organization and management;
review all inspection reports;
ensure that any outstanding pending points, for the equipment and material ready for shipment,
have been clarified and a solution implemented;
review and management of the NCR;
release note review;
ensure the consistency of Inspection Disposition Report;
ensure the collection and proper filing by his Inspection Organization for future retrieval;
ensure the completion and the transmission of the Inspection Fabrication Status Report (IFSR)
and Two Weeks Look Ahead Report to Company.
Review the quality of submittals (eg. MR, IAP, Inspection reports, etc.)
This document is CONFIDENTIAL and the sole property SAIPEM/ SNAMPROGETTI/STAR CONSORTIUM. It shall not be shown to Third Parties nor used for purposes other than those for which it was
prepared.
Long Term Agreement for Offshore
Facilities
Approve the PR
Commitment to Quality policy
Objectives
Management review
Resources availability
This document is CONFIDENTIAL and the sole property SAIPEM/ SNAMPROGETTI/STAR CONSORTIUM. It shall not be shown to Third Parties nor used for purposes other than those for which it was
prepared.
Long Term Agreement for Offshore
Facilities
4. REFERENCE DOCUMENTS
This document is CONFIDENTIAL and the sole property SAIPEM/ SNAMPROGETTI/STAR CONSORTIUM. It shall not be shown to Third Parties nor used for purposes other than those for which it was
prepared.
Long Term Agreement for Offshore
Facilities
Contractors QC corporate organization shall prepare and maintain Inspector's resume and
qualifications records, which shall include:
- Education level
- Brief professional history
- Training (if any)
This document is CONFIDENTIAL and the sole property SAIPEM/ SNAMPROGETTI/STAR CONSORTIUM. It shall not be shown to Third Parties nor used for purposes other than those for which it was
prepared.
Long Term Agreement for Offshore
Facilities
- Examinations(if any)
- Experience (indicate duration of each work)
- Qualification/certification records
PQCS shall ensure that only personnel with acceptable qualifications, as per the above requirements,
are assigned to perform inspection activity.
PQCS is responsible for ensuring that only inspectors that fulfil schedule Q Attachment-I
requirements are proposed to Company for approval.
The inspection personnel will be Company approved Contractors personnel or from qualified
agencies. Inspectors approval shall be granted prior to their assignment.
Log of approved inspectors and their approval status is updated by Contractor (template log format is
attached, see Attachment No. 15).
Procurement Process shall be executed in accordance to the below mentioned project Work
Instructions:
Prior to start inspection activities at Vendors, Contractor shall submit to Company for concurrence all
QC Personnel CV and for Agencies not previously qualified by Company to conduct interviews and
tests to Contractor proposed QC candidates prior to their assignment.
This activity ensures that the selected inspector has adequate experiences and qualification to perform
the specific inspection or to witness tests of materials and equipments of various type and complexity.
PQCS, with the support of the Procurement Quality Control Manager, shall assign inspectors to
purchase orders. The selection shall take into consideration the criticality of materials and equipments
as well as the following:
The inspection level and the assigned inspector shall be recorded in the Inspection Assignment (see
Attachment N 1) duly compiled by PQCS. This document shall be transmitted to Company along with
the IAP as per paragraph 6.2.
This document is CONFIDENTIAL and the sole property SAIPEM/ SNAMPROGETTI/STAR CONSORTIUM. It shall not be shown to Third Parties nor used for purposes other than those for which it was
prepared.
Long Term Agreement for Offshore
Facilities
6. PROCUREMENT PROCEDURE
6.1 GENERAL
The Procurement Department will coordinate all procurement activities closely with SAUDI ARAMCO,
and other departments (especially the Engineering, Construction, Project Control & Planning and
Quality Control Departments). This is to ensure the following;
Materials and equipment purchased for this project are in full compliance with Contract
specifications
Quantities purchased are accurate
Delivery schedules for material and equipment meet the on-site need dates to support
construction schedule
All Project Procurement activities are under the overall responsibility and authority of Contractor
Procurement Manager.
All purchasing, expediting/inspection, shipping, receipt and delivery activities will be planned and
executed under close supervision of the PPM in coordination with the PQCS and / or PQCM & PEM.
Procurement Process shall be executed in accordance to the below mentioned project Work
Instructions:
Typically, MR contains:
Index, Amendments & Revisions, Permanent Material Requisition slip, Permanent Material
Requisition Technical Specification & Data sheets, Applicable NMRs & Form SA-175, Applicable
Saudi Aramco standard drawing, Applicable Saudi Aramco standards, Approved Manufacturers
list (RVL), Inspection Level, Inspection & test plan, Notes to vendor, Attachments
This document is CONFIDENTIAL and the sole property SAIPEM/ SNAMPROGETTI/STAR CONSORTIUM. It shall not be shown to Third Parties nor used for purposes other than those for which it was
prepared.
Long Term Agreement for Offshore
Facilities
Contractor will place PO stocked inspectable materials, to Saudi Aramco approved stockist
only.
Contractor PO placed to materials stockist shall be limited only to the scope of SAEP 347.
Contractor will ensure that the stockist review and accept the purchase requisition requirements
related to the material prior to place the order. Is preferable that stockist furnish the total PO
quantity. Partial quantity supplied from different stockist will be exceptionally acceptable in case
one stockist only will not have the full quantity required by PO.
Contractor will ensure that all applicable material specifications and requirements are defined.
The stockist has the ability to meet the defined requirements.
This document is CONFIDENTIAL and the sole property SAIPEM/ SNAMPROGETTI/STAR CONSORTIUM. It shall not be shown to Third Parties nor used for purposes other than those for which it was
prepared.
Long Term Agreement for Offshore
Facilities
The stockist shall disclose deviation from the purchase orders requirements in writing to the
Buyer Representative, approval of any deviation shall be obtained prior to stockist acceptance
of the purchase order.
The stockist shall specify the plant ID, name and location of the approved manufacturer and
confirm the compliance with all applicable Saudi Aramco Material System Procedures and
Inspection Requirements Form A-175 referenced within Saudi Aramco purchase requisition; in
case there is no applicable form, special 175 form will be prepared as per SCH.Q 3.4.
Contractor will ensure that the stockist comply with SAEP 347 requirement.
When Valves will be procured, the testing shall be done at Manufacturer facility or approved
facility by Aramco, according SAEP 347 par. 8.7.
IAP must clearly indicate names and plant numbers of the manufacturers even if PO is placed
to stockist
7. INSPECTION PLANNING
Requirements for inspection, examination and testing shall be defined by PSL function and shall be
indicated in specifications, drawings and other engineering documents, or else in referred design
codes and Standards in accordance with Companys contract and Contractors detailed engineering
requirements.
PSL shall be responsible to include in the requisition documentation, all the above requirements and
all others necessary instruction to Supplier related to the submittal of ITP(s) for material equipment,
special process procedures and personnel qualifications Submittal Schedule (welding, repair, welder
qualifications, hydro-testing, coating and non-destructive testing procedures), for Contractors and
Companys review and approval.
The supplier ITP shall comply with SA 175 form as well as PO requirements.
PQCS shall review all Suppliers ITP(s) to ensure that quality requirements, as called in all applicable
Company Standards and Procedures. Each ITP shall identify the inspection level and detail all witness,
hold and quality records reviews as specified in Company Form-175 (Inspection Requirements).
Contractor shall carry out Suppliers and Sub-Suppliers surveillance in conformance with the ARAMCO
SAEP 1151, Form 175s provisions and approved ITP.
All ITPs for inspection level 2 and above and above shall be submitted to Company for approval and
contents of the ITP shall comply Sch. Q, Att. III requirement.
The Company/Contractor participation to the inspection and testing work to be carried out by Suppliers
shall be defined on the relevant ITP or 175 form where applicable.
An Inspection Report will be issued after every inspection performed as per the requirements of
Schedule Q of Contract, with the following information:
This document is CONFIDENTIAL and the sole property SAIPEM/ SNAMPROGETTI/STAR CONSORTIUM. It shall not be shown to Third Parties nor used for purposes other than those for which it was
prepared.
Long Term Agreement for Offshore
Facilities
Vendor name
Inspection date
Report number
Line item
Description
Contractual quantity
Quantity inspected
Inspection results
The SA-175/ITP Inspection points covered during the inspection
Punch list / outstanding work list (when applicable)
Inspectors name & signature
Contractor shall review all requisition and purchase orders documentation package in accordance with
this Procurement Plan. PSL and PPM shall respectively ensure that Requisitions and Purchase
Orders include all quality related documentation and in particular the following requirements:
When vendor doesnt meet the specified performance requirements in the purchase order, or
Company has placed the vendor On Hold after the Company has issued a No Objection letter to
Contractor, Contractor shall increase the inspection level to the next highest level for the purchase
order without additional cost to Company, subject to Company approval
Sub-orders to be reviewed by Contractor and then passed to Company, also the sub-vendors approval
status to be reviewed by Contractor & Company prior to sub-order placement. No order or sub-order
can be placed with manufacturers wherein their current quality system is on hold or not approved by
Company. If the manufacturers quality system is on hold, the Purchase Order placed by
CONTRACTOR to this vendor shall be considered valid if the order was placed before the
manufacturer / vendor was put on hold by COMPANY.
No later than twenty-one (21) calendar days prior to the pre-inspection meeting and start of any
fabrication, either at the prime Supplier or major sub-Supplier, PQCS shall compile and forward to
This document is CONFIDENTIAL and the sole property SAIPEM/ SNAMPROGETTI/STAR CONSORTIUM. It shall not be shown to Third Parties nor used for purposes other than those for which it was
prepared.
Long Term Agreement for Offshore
Facilities
Company Representative one (1) hard copy and two (2) CD of the Contractor's Inspection Assignment
Package which shall include:
a complete copy of the Contractor's unpriced purchase order or subcontract, material
requisition, and attachments;
Inspection Assignment Package Checklist : reviewed by PQCM;
copies of sub-Supplier's unpriced purchase orders;
material requisition (to be provided by PSL);
inspection assignment sheet specifying the inspector(s) that will perform the inspections (to be
provided by PQCS);
inspection and test plan (to be provided by PSL);
the level of inspection (to be specified by the PSL);
agenda for each pre-inspection meeting where appropriate (to be provided by PQCS);
Aramco applicable documents (SAMSS and Form 175);
Resume of assigned Inspector;
Inspection Assignment Package checklist: should be prepared prior to submitted to Company
IAP shall be dedicated to each manufactures, material commodities and inspection levels;
Inspection Assignment Sheet shall clearly address the manufacture name and ID number that
start by 3*******, as well as the vendor name and number if available.
Note: Inspectable materials should not be categorized as bulk materials.
Inspection Assignment Packages shall be prepared for Inspection Level 1 and above materials as
well as equipment.
Inspection level shall be in accordance with tables provided in Appendices A & B. follow SAEP-
1151.In case of materials/ equipment not listed in these tables, the SAIR will determine the
appropriate inspection level as per clause 5.4.6 of SAEP-1151.
This section sets out requirements for conducting pre-inspection meetings in order to ensure proper
coordination between Company, Contractor and Suppliers.
A pre-inspection meeting will be held for all major equipment purchase orders classified as Company
level 2, 3, 4 (identified by complexity of equipment, metallurgy, fabrication, welding, testing and
assembly). The inspection level is assigned in accordance with SAEP-1151.
The pre-inspection meeting will take place at the Suppliers manufacturing location or a sub-Supplier
location when equipment on sub-orders falls into this category.
Pre-Inspection Meetings shall be conducted by the inspectors(s) approved for the subject material or
equipment being manufactured. Contractor shall ensure inspector continuity through fabrication.
Suppliers Inspection and Test Plan must be reviewed or accepted with comments by the Contractor
for inclusion in the Inspection Assignment Package to be prepared for the pre-inspection meeting and
prior of any start of fabrication.
This document is CONFIDENTIAL and the sole property SAIPEM/ SNAMPROGETTI/STAR CONSORTIUM. It shall not be shown to Third Parties nor used for purposes other than those for which it was
prepared.
Long Term Agreement for Offshore
Facilities
PQCS shall compile and forward to the Company Representative no later than twenty-one (21)
calendar days prior to the pre-inspection meeting one (1) hard copies and two (2) cd of the
Contractors Inspection Assignment Package.
PQCS will confirm the pre-inspection meeting agreed date with the Supplier, Company and Assigned
inspector. For this purpose PQCS shall formally notify the pre-inspection meeting to all parties
involved. Pre-inspection meeting notification form shall contain as a minimum the information as per
the attached form (see Attachment N 8).
The notification of PIM shall include the meeting agenda and the request to ensure that the appropriate
Suppliers personnel shall attend the meeting with the necessary schedules and documentation.
Agenda shall include different topics as applicable to the scope of the purchase order as per attached
form (see Attachment N 2). Sample of Minutes of Meeting hereto attached for reference (see
Attachment N 19).
Due to type of equipment/material ordered, PQCS may amend the attached agenda.
PQCS shall require Supplier to provide at the date of the Pre Inspection Meeting the following:
PQCS shall require Supplier to submit for each materials, equipment or part of it, the inspection
advance notification 15 calendar days in advance for all agreed ITPs hold/witness points, and
in case of need of postponing the inspection date or cancellation of notification, the request
shall be issued 7 calendar days (5 working days) prior to the inspection notified event.
The inspection notification shall be sent via e-mail to PQCS who in turn will notify the SAIR or
their assigned inspection representatives and inspection Agencies. The inspection notification
form shall contain as a minimum the following information as per Attachment N 10.
This activity (Inspection Advance Notice) is essential to facilitate the Assigned Inspector and
Company Inspector Representative to plan their availability to satisfy the terms and conditions
This document is CONFIDENTIAL and the sole property SAIPEM/ SNAMPROGETTI/STAR CONSORTIUM. It shall not be shown to Third Parties nor used for purposes other than those for which it was
prepared.
Long Term Agreement for Offshore
Facilities
of the purchase order. Therefore, PQCS shall clearly address all the above requirements, to be
enclosed in requisition package and purchase orders for all Suppliers.
Inspection waiver request shall be in accordance with paragraph 7.6 of Schedule Q of the
Contract.
When required by Company standards, and prior to start of the relevant fabrication work, PSL shall
submit to Company for review and approval all Supplier procedures for welding, welding repair
approved by Contractor, welding specialist and NDT and alloy verification , procedures approved by
the authorized Level III Inspector. PSL shall register, control the timely vendors submittal and the
approval status of the above documentation, and shall make the register available to Company upon
request.
Supplier and sub-Supplier personnel for NDT, Positive Material Identification, and welding shall be
qualified as specified by Companys Standards and Attachment I of the Schedule Q. Contractors
authorized inspector shall review and approve such qualifications prior to the start of manufacturing.
The qualification and certification of Out of Kingdom Non-destructive Testing (NDT) personnel shall
be in accordance with the nationally recognized program as listed in SAEP-1142. Contractors
designated Level III Inspector shall review and approve all Supplier and sub-Supplier NDT personnel
qualification and certification program as well as procedures prior to commencement of any NDT
operations.
Contractor shall make Supplier and sub-Supplier NDT personnel records and Welder Qualification
Records available to the Company Representative on request. Contractor shall create logs for all
special processes procedures approval status (See Attachment No. 15).
The welding procedure approval responsibilities are defined in Companys engineering procedures
SAEP-352, and applicable SAMSS.
9. REPORTING
9.1 GENERAL
PQCM is responsible for the preparation, distribution and the updating of QC reports of procurement
phase, and shall keep COMPANY informed and obtain consent for any revision/correction found
necessary for QC reporting method, format, etc.
This document is CONFIDENTIAL and the sole property SAIPEM/ SNAMPROGETTI/STAR CONSORTIUM. It shall not be shown to Third Parties nor used for purposes other than those for which it was
prepared.
Long Term Agreement for Offshore
Facilities
PQCS or his delegate shall be responsible for recording the pre-inspection minute of meeting (MOM).
The MOM shall be prepared and filled up as per Attachment N 19, and shall be circulated to all
attendees for confirmation and acceptance before official issuing. The MOM shall be sent to Company
within 10 days after the meeting.
If the meeting is conducted by the Assigned Inspector, the minute of meeting will be sent to PQCS
within 48 hours after completing the PIM. Follow up meetings as a result of issues raised at the PIM
will also be put in record. This record Log all outstanding PIM issues and their status (Template is
attached, see Attachment No.9).
On the basis of the inspection intervention plan agreed with Supplier and the inspection performed,
PQCS shall submit to Company Representative the Weekly Inspection/ Fabrication Status Report and
the Two-week Look Ahead Report.
Reports shall be sent electronically in a format acceptable to Company as per Attachment N 12.
Reports shall include, as a standard, the following information for each purchase order:
CONTRACTOR shall follow section 1.2 of Attachment III for suppliers & sub-suppliers selection
The Assigned Inspector shall send the Inspection Report to PQCS within 24 hours after completion of
This document is CONFIDENTIAL and the sole property SAIPEM/ SNAMPROGETTI/STAR CONSORTIUM. It shall not be shown to Third Parties nor used for purposes other than those for which it was
prepared.
Long Term Agreement for Offshore
Facilities
the visit at Supplier. The inspection report shall be prepared as per the form attached (see Attachment
No. 11).
The front sheet of the Inspection Report shall be always filled up with the following data and
information:
The other sheet(s) shall always be used to report the following information as applicable:
Suppliers certification will not be attached to the report but will be part of the MDR.
PQCS shall review and endorse all inspection reports to ensure correctness and completeness, as
well as follow up actions and relevant close out if and when applicable. PQCS after his review shall
distribute in PDF format all inspection reports to COMPANY, to the PSL and Supplier.
9.6 NCR
When Contractors Inspector identifies a Non Conformance (NC) on material, activity or lack of
documentation, a "Non Conformance Report" (NCR) shall be completed and issued by the Inspector
as per section 10. Copy of the NCR shall be attached to the Inspection Report. Within 48 hours of
issuance copy of the NCR shall be forwarded to COMPANY by PQCS.
The non-conformance report shall be prepared as per the form Attachment N 20.
The applicable procedure is NCR management Doc.No. 00-C0-C-CO-Q-P-006.
This document is CONFIDENTIAL and the sole property SAIPEM/ SNAMPROGETTI/STAR CONSORTIUM. It shall not be shown to Third Parties nor used for purposes other than those for which it was
prepared.
Long Term Agreement for Offshore
Facilities
complete repair, fully complying with the contractual standards and specifications, by
means of a qualified and/or approved procedure (when this is required);
replacement having no impact on the project schedule or costs;
"use-as-is" with no violation with Company standards requirements.
Any others rules to class an NCR shall be per relevant Aramco Documents (SAMSS,
SAES, etc.).
The Release Note shall be issued before shipment for each item or part of materials after verification
that the requirements for each Purchase Order have been meet.
In order to verify the conformance of each item or part of the whole Purchase Order, checks and
verifications shall be carried out by the Assigned Inspector on the QC activities performed during the
execution of the work and shall consider but not be limited to:
In case of successful results the Assigned Inspector shall issue the Release Note to be prepared as
per Attachment N 8.
If the material includes non-conformity at the final inspection as a minimum the following shall be
accomplished:
This document is CONFIDENTIAL and the sole property SAIPEM/ SNAMPROGETTI/STAR CONSORTIUM. It shall not be shown to Third Parties nor used for purposes other than those for which it was
prepared.
Long Term Agreement for Offshore
Facilities
The material or equipment may be released to Site if PQCM and Company Inspection Representatives
agree that the non-conformity can be corrected at Site.
Copies of the inspection release note shall be submitted to COMPANY within 48 hours of issue.
After having received the Manufacturer Data Record Book (MDR) from Supplier, PQCS, after
acceptance of material or equipment, shall prepare and issue to Company the Final Disposition Report
for critical items that are Inspection Level 2 and above. For items with Inspection Level 1, the Final
Inspection Report and Release Note shall be forwarded to the SAIR to close the Inspection Lot.
Disposition Report shall be as per schedule Q. Para 3.15. The Inspection Disposition Report (IDR)
shall include (where applicable) the Final Test Certificate (FTC) or Release Certificate from TPI, and
for material and equipment of inspection level 1 & 0 the "Quality Statement" (QS) will be issued, if
applicable. QS and FTC form samples shown respectively as Attachment 5 and Attachment 6.
PQCS shall ensure prompt transmission of the IDR required number of copies and CD-ROM to
Company and to construction Site.
Within two weeks of acceptance of the materials/ equipment, Contractor shall prepare & issue to the
COMPANY Representative an Inspection Disposition Report (IDR).
10. ATTACHMENTS
This document is CONFIDENTIAL and the sole property SAIPEM/ SNAMPROGETTI/STAR CONSORTIUM. It shall not be shown to Third Parties nor used for purposes other than those for which it was
prepared.
Long Term Agreement for Offshore
Facilities
Attachment 12: Inspection Fabrication Status Report & Two-week Look Ahead Inspection Schedule
(FORM-LTA-047)
Attachment 15: NDE Personnel & Welding Inspectors Qualification Log (FORM-LTA-050)
This document is CONFIDENTIAL and the sole property SAIPEM/ SNAMPROGETTI/STAR CONSORTIUM. It shall not be shown to Third Parties nor used for purposes other than those for which it was
prepared.
Long Term Agreement for Offshore
Facilities
Page 1 of 2
This document is CONFIDENTIAL and the sole property SAIPEM/ SNAMPROGETTI/STAR CONSORTIUM. It shall not be shown to Third Parties nor used for purposes other than those for which it was
prepared.
Long Term Agreement for Offshore
Facilities
Page 2 of 2
This document is CONFIDENTIAL and the sole property SAIPEM/ SNAMPROGETTI/STAR CONSORTIUM. It shall not be shown to Third Parties nor used for purposes other than those for which it was
prepared.
Long Term Agreement for Offshore
Facilities
This document is CONFIDENTIAL and the sole property SAIPEM/ SNAMPROGETTI/STAR CONSORTIUM. It shall not be shown to Third Parties nor used for purposes other than those for which it was
prepared.
Long Term Agreement for Offshore
Facilities
This document is CONFIDENTIAL and the sole property SAIPEM/ SNAMPROGETTI/STAR CONSORTIUM. It shall not be shown to Third Parties nor used for purposes other than those for which it was
prepared.
Long Term Agreement for Offshore
Facilities
This document is CONFIDENTIAL and the sole property SAIPEM/ SNAMPROGETTI/STAR CONSORTIUM. It shall not be shown to Third Parties nor used for purposes other than those for which it was
prepared.
Long Term Agreement for Offshore
Facilities
This document is CONFIDENTIAL and the sole property SAIPEM/ SNAMPROGETTI/STAR CONSORTIUM. It shall not be shown to Third Parties nor used for purposes other than those for which it was
prepared.
Long Term Agreement for Offshore
Facilities
This document is CONFIDENTIAL and the sole property SAIPEM/ SNAMPROGETTI/STAR CONSORTIUM. It shall not be shown to Third Parties nor used for purposes other than those for which it was
prepared.
Long Term Agreement for Offshore
Facilities
Page 1 of 2
This document is CONFIDENTIAL and the sole property SAIPEM/ SNAMPROGETTI/STAR CONSORTIUM. It shall not be shown to Third Parties nor used for purposes other than those for which it was
prepared.
Long Term Agreement for Offshore
Facilities
Page 2 of 2
This document is CONFIDENTIAL and the sole property SAIPEM/ SNAMPROGETTI/STAR CONSORTIUM. It shall not be shown to Third Parties nor used for purposes other than those for which it was
prepared.
Long Term Agreement for Offshore
Facilities
This document is CONFIDENTIAL and the sole property SAIPEM/ SNAMPROGETTI/STAR CONSORTIUM. It shall not be shown to Third Parties nor used for purposes other than those for which it was
prepared.
Long Term Agreement for Offshore
Facilities
This document is CONFIDENTIAL and the sole property SAIPEM/ SNAMPROGETTI/STAR CONSORTIUM. It shall not be shown to Third Parties nor used for purposes other than those for which it was
prepared.
Long Term Agreement for Offshore
Facilities
This document is CONFIDENTIAL and the sole property SAIPEM/ SNAMPROGETTI/STAR CONSORTIUM. It shall not be shown to Third Parties nor used for purposes other than those for which it was
prepared.
Long Term Agreement for Offshore
Facilities
This document is CONFIDENTIAL and the sole property SAIPEM/ SNAMPROGETTI/STAR CONSORTIUM. It shall not be shown to Third Parties nor used for purposes other than those for which it was
prepared.
Long Term Agreement for Offshore
Facilities
Page 1 of 2
This document is CONFIDENTIAL and the sole property SAIPEM/ SNAMPROGETTI/STAR CONSORTIUM. It shall not be shown to Third Parties nor used for purposes other than those for which it was
prepared.
Long Term Agreement for Offshore
Facilities
Page 2 of 2
This document is CONFIDENTIAL and the sole property SAIPEM/ SNAMPROGETTI/STAR CONSORTIUM. It shall not be shown to Third Parties nor used for purposes other than those for which it was
prepared.
Long Term Agreement for Offshore
Facilities
Page 1 of 3
This document is CONFIDENTIAL and the sole property SAIPEM/ SNAMPROGETTI/STAR CONSORTIUM. It shall not be shown to Third Parties nor used for purposes other than those for which it was
prepared.
Long Term Agreement for Offshore
Facilities
Page 2 of 3
This document is CONFIDENTIAL and the sole property SAIPEM/ SNAMPROGETTI/STAR CONSORTIUM. It shall not be shown to Third Parties nor used for purposes other than those for which it was
prepared.
Long Term Agreement for Offshore
Facilities
Page 3 of 3
This document is CONFIDENTIAL and the sole property SAIPEM/ SNAMPROGETTI/STAR CONSORTIUM. It shall not be shown to Third Parties nor used for purposes other than those for which it was
prepared.
Long Term Agreement for Offshore
Facilities
This document is CONFIDENTIAL and the sole property SAIPEM/ SNAMPROGETTI/STAR CONSORTIUM. It shall not be shown to Third Parties nor used for purposes other than those for which it was
prepared.
Long Term Agreement for Offshore
Facilities
Page 2 of 3
This document is CONFIDENTIAL and the sole property SAIPEM/ SNAMPROGETTI/STAR CONSORTIUM. It shall not be shown to Third Parties nor used for purposes other than those for which it was
prepared.
Long Term Agreement for Offshore
Facilities
Page 3 of 3
This document is CONFIDENTIAL and the sole property SAIPEM/ SNAMPROGETTI/STAR CONSORTIUM. It shall not be shown to Third Parties nor used for purposes other than those for which it was
prepared.
Long Term Agreement for Offshore
Facilities
This document is CONFIDENTIAL and the sole property SAIPEM/ SNAMPROGETTI/STAR CONSORTIUM. It shall not be shown to Third Parties nor used for purposes other than those for which it was
prepared.
Long Term Agreement for Offshore
Facilities
This document is CONFIDENTIAL and the sole property SAIPEM/ SNAMPROGETTI/STAR CONSORTIUM. It shall not be shown to Third Parties nor used for purposes other than those for which it was
prepared.
Long Term Agreement for Offshore
Facilities
This document is CONFIDENTIAL and the sole property SAIPEM/ SNAMPROGETTI/STAR CONSORTIUM. It shall not be shown to Third Parties nor used for purposes other than those for which it was
prepared.
Long Term Agreement for Offshore
Facilities
ATTACHMENT 15: NDE PERSONNEL AND WELDING INSPECTOR QUALIFICATION LOG (FORM-
LTA-050)
This document is CONFIDENTIAL and the sole property SAIPEM/ SNAMPROGETTI/STAR CONSORTIUM. It shall not be shown to Third Parties nor used for purposes other than those for which it was
prepared.
Long Term Agreement for Offshore
Facilities
This document is CONFIDENTIAL and the sole property SAIPEM/ SNAMPROGETTI/STAR CONSORTIUM. It shall not be shown to Third Parties nor used for purposes other than those for which it was
prepared.
Long Term Agreement for Offshore
Facilities
This document is CONFIDENTIAL and the sole property SAIPEM/ SNAMPROGETTI/STAR CONSORTIUM. It shall not be shown to Third Parties nor used for purposes other than those for which it was
prepared.
Long Term Agreement for Offshore
Facilities
This document is CONFIDENTIAL and the sole property SAIPEM/ SNAMPROGETTI/STAR CONSORTIUM. It shall not be shown to Third Parties nor used for purposes other than those for which it was
prepared.
Long Term Agreement for Offshore
Facilities
Page 3 of 3
This document is CONFIDENTIAL and the sole property SAIPEM/ SNAMPROGETTI/STAR CONSORTIUM. It shall not be shown to Third Parties nor used for purposes other than those for which it was
prepared.
Long Term Agreement for Offshore
Facilities
Page 1 of 4
This document is CONFIDENTIAL and the sole property SAIPEM/ SNAMPROGETTI/STAR CONSORTIUM. It shall not be shown to Third Parties nor used for purposes other than those for which it was
prepared.
Long Term Agreement for Offshore
Facilities
This document is CONFIDENTIAL and the sole property SAIPEM/ SNAMPROGETTI/STAR CONSORTIUM. It shall not be shown to Third Parties nor used for purposes other than those for which it was
prepared.
Long Term Agreement for Offshore
Facilities
Page 2 of 4
This document is CONFIDENTIAL and the sole property SAIPEM/ SNAMPROGETTI/STAR CONSORTIUM. It shall not be shown to Third Parties nor used for purposes other than those for which it was
prepared.
Long Term Agreement for Offshore
Facilities
Page 3 of 4
This document is CONFIDENTIAL and the sole property SAIPEM/ SNAMPROGETTI/STAR CONSORTIUM. It shall not be shown to Third Parties nor used for purposes other than those for which it was
prepared.
Long Term Agreement for Offshore
Facilities
Page 4 of 4
This document is CONFIDENTIAL and the sole property SAIPEM/ SNAMPROGETTI/STAR CONSORTIUM. It shall not be shown to Third Parties nor used for purposes other than those for which it was
prepared.
Long Term Agreement for Offshore
Facilities
MINUTES OF MEETING
(Mom) FORM-LTA-001
Rev. 01 14/02/08
Date: M. of M. No.:
LOCATION:
SUBJECT:
A
T
T
E
N
D
E
D
B
Y
C
O
P
I
E
S
T
O
This document is CONFIDENTIAL and the sole property SAIPEM/ SNAMPROGETTI/STAR CONSORTIUM. It shall not be shown to Third Parties nor used for purposes other than those for which it was
prepared.
Long Term Agreement for Offshore
Facilities
NOTE:
NOTES:
MINUTES OF MEETING
(Mom)
FORM-LTA-001
Rev. 01 14/02/08
M.M. No.:
REQUIRED
ITEM DESCRIPTION OF DISCUSSION
ACTION BY COMPLETION
DATE
1 Introduction
The present meeting is relevant to the inspection and Quality
requirements.
The Pre-Inspection Meeting (PIM) is held to review all the
requirements of the Purchase Order in detail, with
respect to manufacturing, fabrication, inspection, and
schedule and to highlight any problem areas requiring
immediate action to facilitate the progress of the order.
All Sections below shall be completed and all comments
and/or action requirements shall be detailed in each
section and reported in the last Section Outstanding
Points.
All attendees introduced them self to the meeting in their
respective rules
Register of attendees has been compiled and attached
(Attachment n1)
This document is CONFIDENTIAL and the sole property SAIPEM/ SNAMPROGETTI/STAR CONSORTIUM. It shall not be shown to Third Parties nor used for purposes other than those for which it was
prepared.
Long Term Agreement for Offshore
Facilities
Snamprogetti:
(name) QC Manager (PC) Tel + Fax + e-mail
3. Vendor Organization:
Vendor Project Engineer briefed the project organization.
An organization chart
(X) was given to illustrate the relationship between the
departments at Vendor facility.
( ) was not given.
Name of the QC inspector has been add to the chart.
Attachment n ___
__________________________________________________
___________
This document is CONFIDENTIAL and the sole property SAIPEM/ SNAMPROGETTI/STAR CONSORTIUM. It shall not be shown to Third Parties nor used for purposes other than those for which it was
prepared.
Long Term Agreement for Offshore
Facilities
_____________________________________________
____
( ) YES ( ) NO
_____________________________________________
____
( ) YES ( ) NO
_____________________________________________
____
The quality System Overview was judged to correctly address
to all the necessary issue.
This document is CONFIDENTIAL and the sole property SAIPEM/ SNAMPROGETTI/STAR CONSORTIUM. It shall not be shown to Third Parties nor used for purposes other than those for which it was
prepared.
Long Term Agreement for Offshore
Facilities
5 Shop Tour
( X ) YES ( ) NO
This document is CONFIDENTIAL and the sole property SAIPEM/ SNAMPROGETTI/STAR CONSORTIUM. It shall not be shown to Third Parties nor used for purposes other than those for which it was
prepared.
Long Term Agreement for Offshore
Facilities
Exceptions /Deviations
( ) YES ( ) NO
_____________________________________________
____
( ) YES ( ) NO
_____________________________________________
____
( ) YES ( ) NO
_____________________________________________
____
This document is CONFIDENTIAL and the sole property SAIPEM/ SNAMPROGETTI/STAR CONSORTIUM. It shall not be shown to Third Parties nor used for purposes other than those for which it was
prepared.
Long Term Agreement for Offshore
Facilities
Item Supplier
This document is CONFIDENTIAL and the sole property SAIPEM/ SNAMPROGETTI/STAR CONSORTIUM. It shall not be shown to Third Parties nor used for purposes other than those for which it was
prepared.
Long Term Agreement for Offshore
Facilities
Document Register
Drawings were initially issued for review as Rev A. Subsequent
review revision will follow the letter designation sequence. After
all comments have been incorporated and approved, the
drawings will be issued for construction as Rev.00, in
accordance with Saudi Aramco drafting requirements.
Document register has been provide some comments has been
marked up on the attached document Attachment n
Vendor is requested to implement the comments.
( ) NO ___________________________
Vendor will provide the required documents by ___________
- Drawings approval
This document is CONFIDENTIAL and the sole property SAIPEM/ SNAMPROGETTI/STAR CONSORTIUM. It shall not be shown to Third Parties nor used for purposes other than those for which it was
prepared.
Long Term Agreement for Offshore
Facilities
This document is CONFIDENTIAL and the sole property SAIPEM/ SNAMPROGETTI/STAR CONSORTIUM. It shall not be shown to Third Parties nor used for purposes other than those for which it was
prepared.
Long Term Agreement for Offshore
Facilities
Company Name
Delivery Address
ZIP code
Country
Local Contact
Person
Phone & Fax
DHL Receiver
Account
968829695
Number
_______________________________________________
___________
This document is CONFIDENTIAL and the sole property SAIPEM/ SNAMPROGETTI/STAR CONSORTIUM. It shall not be shown to Third Parties nor used for purposes other than those for which it was
prepared.
Long Term Agreement for Offshore
Facilities
This document is CONFIDENTIAL and the sole property SAIPEM/ SNAMPROGETTI/STAR CONSORTIUM. It shall not be shown to Third Parties nor used for purposes other than those for which it was
prepared.
Long Term Agreement for Offshore
Facilities
To:
Mr. QC Manager
[email protected]
Mr. QC Assistant
[email protected]
Mr QC Assistant
[email protected]
CC:
Agency
Mr
Agency
( Mr ..
This document is CONFIDENTIAL and the sole property SAIPEM/ SNAMPROGETTI/STAR CONSORTIUM. It shall not be shown to Third Parties nor used for purposes other than those for which it was
prepared.
Long Term Agreement for Offshore
Facilities
Saudi Aramco
Mr. SAIR [email protected]
Mr.
attached.
NCR will be enclosed in dedicated section of the
Manufacturers inspection data book
This document is CONFIDENTIAL and the sole property SAIPEM/ SNAMPROGETTI/STAR CONSORTIUM. It shall not be shown to Third Parties nor used for purposes other than those for which it was
prepared.
Long Term Agreement for Offshore
Facilities
This document is CONFIDENTIAL and the sole property SAIPEM/ SNAMPROGETTI/STAR CONSORTIUM. It shall not be shown to Third Parties nor used for purposes other than those for which it was
prepared.
Long Term Agreement for Offshore
Facilities
This document is CONFIDENTIAL and the sole property SAIPEM/ SNAMPROGETTI/STAR CONSORTIUM. It shall not be shown to Third Parties nor used for purposes other than those for which it was
prepared.
Long Term Agreement for Offshore
Facilities
This document is CONFIDENTIAL and the sole property SAIPEM/ SNAMPROGETTI/STAR CONSORTIUM. It shall not be shown to Third Parties nor used for purposes other than those for which it was
prepared.
Long Term Agreement for Offshore
Facilities
This document is CONFIDENTIAL and the sole property SAIPEM/ SNAMPROGETTI/STAR CONSORTIUM. It shall not be shown to Third Parties nor used for purposes other than those for which it was
prepared.