Rock Berm Design For Pipeline Stability
Rock Berm Design For Pipeline Stability
Rock Berm Design For Pipeline Stability
OMAE2012
July 1-6, 2012, Rio de Janeiro, Brazil
OMAE2012- 83551
ABSTRACT INTRODUCTION
Stabilizing large diameter natural gas pipelines on the Pipelines are typically the most effective method for
seabed against extreme hydrodynamic loading conditions has transporting hydrocarbons from subsea wells to shore for
proven to be challenging in the northwest of Australia. Tropical processing. Extreme storm conditions and interference from
storms, which affect the area annually between November and shipping have resulted in numerous pipeline failures over the
April, can generate wave heights exceeding 30 m and storm past few decades and must be carefully designed for.
steady state currents of 2 m/s or more. Consequently, in shallow
It is common practice in the offshore industry to apply a
water depths, typically less than 40 60 m, subsea pipelines
concrete weight coating (CWC) to the pipeline to increase its
can be subjected to very high hydrodynamic loads, potentially
submerged weight for on-bottom stability. The concrete
causing significant lateral movement. To mitigate the risk of the
coating, which is typically a few inches thick, also provides
pipeline suffering mechanical damage due to excessive lateral
some degree of mechanical protection to the pipeline. However,
movement, quarried and graded rock is often dumped over the
there is a practical limit to how much weight coating can be
pipeline as a secondary stabilization solution.
applied to a pipeline, due to either the tension or handling
In order to satisfy functional requirements, the rock berm capacity of the pipeline installation vessel or the handling
must comprise of a sufficiently large rock grading size and capacity at the coating plant. In cases where the maximum
berm volume to withstand the design hydrodynamic loading coating thickness cannot provide the pipeline with a sufficient
such that the pipeline cannot break out of the berm. The design level of safety, a secondary stabilization method may have to be
of rock berms for pipeline secondary stabilization has adopted.
traditionally followed a deterministic approach that uses
One method for achieving pipeline secondary stabilization
empirical equations for preliminary rock sizing, followed by
and/or accidental external impact protection is by dumping
small-scale physical modeling for design verification and
quarried rock over the pipeline. Depending on the water depth
optimization. Whilst the traditional approach can be effective in
and armour rock grading size, a Side Dump Vessel (SDV) or
producing a robust rock berm design, opportunities for further
Fall Pipe Vessel (FPV) is typically used to install a rubble
optimization are inhibited by a lack of available data and an
mound near-bed structure that is commonly referred to as a
imperfect understanding of the failure mechanisms.
rock berm.
This paper presents an overview of an improved approach
This paper presents an overview of the rock berm design
for rock berm design optimization. A general overview of rock
concept, the analytical design methods, comparison of
berms, the design principles, benefits and risks are also
analytical method with physical model test results, and
presented.
recommendations for design practice
URE 2 ROCK B
FIGU BERM DESIGN
N FOR DYNAM
MIC STABILITY
Y
W
Where,
S 2.5
0.8
log(( N ) ((5)
Wheere,
a is a model cconstant The m most likely vaalue for the model
m hysical mod
Ph del testing
consttant is a = 0.0048, the upper bound is a = 0.12, the loower Given the limitations of o the variouus analytical design
bounnd is a = 0.02. meethods as weell as the highh consequences of failure, small-
hc1% is the dimensionless m mobility param
meter based onn the scale physical model testingg is almost aalways perform med to
peakk velocity at thhe berm crest aassociated withh H1% and Tp. veerify and optim
mize the rock bberm design.
m0 is the berm
m side slope. In additionn assessing the t response of the rockk berm
strructure to the design hydrodynamic loadds, physical modeling
m
S
S* is the dimeensionless erossion area per uunit of crest w
width, is a valuable toool for assessinng the likelihoood of lateral ppipeline
Bc, aand is given byy Eq. 7: displacement. Given
G that thee purpose of the rock berm m is to
prrovide pipelinee stability, it iis equally if not more impoortant to
unnderstand the rresponse of the pipeline.
Ae (7)
S* When asseessing the rresponse of the design to the
Bc Dn 50 chharacteristic hhydrodynamic loading conddition, the alllowable
beerm damage iss usually limitted such that it can be assum med the
pippeline is not aable to break-oout of the berm
m. For more eextreme
A common feeature of the vvarious damagged based metthods coonditions that are unlikely tto occur durinng the designn life of
is thhat they do noot include thee influence oof steady currrents. thee pipeline, thee performancee of the rock bberm may be judged
Van G Gent and Wallast [7] states that the influeence of the cuurrent onn whether it caan prevent pipeeline lateral diisplacement
can bbe neglected within
w the folloowing range: U/ uo < 2.2, w
where As is the case
c with the analytical meethods for rocck berm
U is the depth averraged current velocity (m/s)), for the followwing deesign, small-sccale physical modeling is not without its i own
rangee of the mobillity parameter:: 0.15 < < 3.5. lim
mitations and inaccuracies. This should bbe taken into account
a
IIt has been proposed eaarlier in thiss paper that the byy the pipeline designer whenn specifying thhe design acceeptance
accepptable level of damage for a dynamicallyy stable rock berm
b criiteria. The designer
d shouuld also aimm to minimiize the
be specified in teerms of an aallowable creest level dropp z. lim
mitations of mmodel testingg by selectingg an appropriaate test
A wave and current flume has traditionally been the most 100 year RP event the crest level may not drop below
commonly used facility for this work [10]. It allows for quasi- the crown of the pipeline. For the no-cover rock berm design,
2D modeling of structures exposed to long-crested waves and a any crest level drop is unacceptable.
co-linear steady current. The orientation of the model rock 1,000 year RP event some crest level drop is acceptable.
berm is typically perpendicular to the direction of waves and This may result in the entire crown of the pipeline being
currents. Some key advantages of using this type of facility are visible. Sufficient embedment and sheltering should be
availability and ease of model set-up and testing. Limitations provided by the rock berm such that pipeline instability does
are scaling effects for all but the largest flumes as well as end not occur.
effects due boundary conditions created by the walls of the test
section. Preliminary Berm Designs
A wave basin has been utilized on several past projects for Two rock berm design options were selected based on the
3D model testing of secondary stabilization designs [9]. Both results of empirical design methods and previous project
complex local bathymetry and directional waves can be experience.
modeled to provide a more realistic representation of the A no-cover rock berm design, comprising a 300 mm D50
prototype conditions. It is also possible to assess multiple rock grading, a berm crest height and width equal to the
designs in a single test run. Disadvantages of using this type of pipeline outer diameter, and side slopes of 1v:3h (Figure 1) was
facility include scaling effects, increased model set-up time and chosen as the base case design. The incipient motion approach
difficult to model steady currents. was used to calculate the required rock grading for a statically
structure under the 100 year return period tropical cyclonic
DESIGN CASE STUDY conditions.
The design outcomes from a recent project are presented in A full-cover rock berm profile, with a significantly smaller
this section of the paper to provide an example of how pipeline armour rock grading size that could be installed using a fall
designers may select a rock berm design for secondary pipe vessel, was selected as an alternative design. The design
stabilization. comprised a 175 mm D50 rock grading, a berm height of 2.1 m,
The preliminary berm designs were selected based on the crest width of 2.0 m and side slopes of 1v:2.5h (Figure 2).
empirical methods that have been discussed earlier in the paper. Results from damage based methods indicated that design
Physical modeling was performed to verify the preliminary would be dynamically stable, with any damage to the berm
designs and select a final design. likely to be within acceptable limits.
The paper will also provide some discussion of the test Physical Model Set-up
results, which will be compared against the predictions from The two preliminary rock berm designs were modelled in a
analytical design methods. wave/current flume at a length scale of 1:35. The flume is 30 m
long, 1.0 m wide and 1.5 m deep. At one end is a wave
Design Conditions generator capable of generating regular and irregular waves. At
To provide a summary of the extreme hydrodynamic the opposite end is a parabolic beach to absorb wave energy
loading conditions, the design values of the most relevant and create as little wave reflections as possible in the flume.
metocean parameters are listed in Table 1. Three wave gauges were positioned in the flume to measure the
surface elevation at three points.
TABLE 1: SUMMARY OF METOCEAN DESIGN VALUES A 50 cm diameter return pipe, a flow impeller, and the
Return Period (years) various connections at either end created circulation flow in the
Parameter Units flume/pipe system. With a flume water depth of 0.5 m, this
100 1,000 10,000
Still Water level m 14.2 15.0 15.9 system is capable of producing a current up to 60 cm/s.
Significant wave height m 6.5 6.9 7.3 Currents were measured by an Acoustic Doppler Velocity
Testt Results
F
For both the bbase case andd alternative roock berm dessigns,
the oobserved levell of berm deggradation was within acceptable
limitts for all three loading condiitions that werre tested.
F
FIGURE 4: BE
ERM PROFILE AFTER 100 YE
EAR RP TEST