Activity On Node

The document provides examples and solutions for network analysis problems involving calculating earliest and latest start times of activities to determine minimum project duration and critical activities. It includes a problem with options for activity completion times to be formulated as an integer program to minimize total cost while completing within 17 weeks. A second example involves calculating the effect of delays to activities E and F on the project completion time.

Uploaded by

Zain uddin
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
227 views11 pages

Activity On Node

The document provides examples and solutions for network analysis problems involving calculating earliest and latest start times of activities to determine minimum project duration and critical activities. It includes a problem with options for activity completion times to be formulated as an integer program to minimize total cost while completing within 17 weeks. A second example involves calculating the effect of delays to activities E and F on the project completion time.

Uploaded by

Zain uddin
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
You are on page 1/ 11

OR-Notes

J E Beasley
OR-Notes are a series of introductory notes on topics that fall under the broad heading
of the field of operations research (OR). They were originally used by me in an
introductory OR course I give at Imperial College. They are now available for use by
any students and teachers interested in OR subject to the following conditions.

A full list of the topics available in OR-Notes can be found here.

Network analysis - activity on node examples

Network analysis example 1997 UG exam

The table below defines the activities within a small project.


Activity Completion time Immediate predecessor
(weeks) activities
A 2 -
B 3 -
C 4 A
D 3 B,A
E 8 D,C
F 3 C
G 2 E
H 3 F,G

Draw the network diagram.


Calculate the minimum overall project completion time and identify which
activities are critical.
What is the slack (float) time associated with each of the non-critical activities.

In the above network there are a number of options for the completion time for
activities C, D and E as shown below:
Activity Completion time Cost ('000)
C 4 3
3 7
2 10
1 15
D 3 12
2 16
1 25
E 8 5
7 9
6 14

For example choosing a completion time for activity E of 6 weeks costs 14,000.

Formulate the problem of deciding the completion time for C, D and E so as to ensure
that the project is completed within 17 weeks as an integer program.

Solution

The network diagram is shown below. Note the introduction of a dummy activity I
with a duration of zero to represent the end of the project.

Let Ei represent the earliest start time for activity i such that all its preceding activities
have been finished. We calculate the values of the Ei (i=A,B,...,I) by going forward,
from left to right, in the network diagram.

To ease the notation let Ti be the activity completion time associated with activity i
(e.g. TB = 3). Then the Ei are given by:

EA = 0 (assuming we start at time zero)


EB = 0 (assuming we start at time zero)
EC = EA + TA = 0 + 2 =2
ED = max[EA + TA, EB + TB] = max[0 + 2, 0 + 3] = 3
EE = max[EC + TC, ED + TD] = max[2 + 4, 3 + 3] = 6
EF = EC + TC = 2 + 4 = 6
EG = EE + TE = 6 + 8 = 14
EH = max[EF + TF, EG + TG] =max[6 + 3, 14 + 2] = 16
EI = EH + TH = 16 + 3 = 19

Hence the minimum possible completion time for the entire project is 19 weeks i.e. 19
(weeks) is the minimum time needed to complete all the activities.

We now need to calculate the latest times for each activity.

Let Li represent the latest start time we can start activity i and still complete the
project in the minimum overall completion time. We calculate the values of the
Li (i=A,B,...,I) by going backward, from right to left, in the network diagram. Hence:

LI = 19
LH= LI - TH = 19 - 3 = 16
LG = LH - TG = 16 - 2 = 14
LF = LH - TF = 16 - 3 = 13
LE = LG - TE = 14 - 8 = 6
LD = LE - TD = 6 - 3 = 3
LC = min[LE - TC, LF - TC] = min[6 - 4, 13 - 4] = 2
LB = LD - TB = 3 - 3 = 0
LA = min[LC - TA, LD - TA] = min[2 - 2, 3 - 2] = 0

Note that as a check all latest times are >=0 at least one activity has a latest start time
value of zero.

As we know the earliest start time Ei, and latest start time Li, for each activity i it is
clear that the amount of slack or float time Fi available is given by Fi = Li - Ei which is
the amount by which we can increase the time taken to complete activity i without
changing (increasing) the overall project completion time. Hence we can form the
table below:
Activity Li Ei Float Fi
A 0 0 0
B 0 0 0
C 2 2 0
D 3 3 0
E 6 6 0
F 13 6 7
G 14 14 0
H 16 16 0

Any activity with a float of zero is critical. Note here that, as a check, all float values
should be >= 0.
Hence the critical activities are A,B,C,D, E,G and H and the float for the only non-
critical activity F is 7 weeks.

In order to formulate the problem of deciding the completion time for C, D and E so
as to ensure that the project is completed within 17 weeks we make use of integer
programming.

Let the x variables (suitably subscripted) represent feasible start times for each
activity (>=0 and integer). Note here that we deal with feasible start times in
formulating this program rather than (as above) with earliest start times.

Introduce zero-one variables:


Ci = 1 if a completion time of i (i=4,3,2,1) chosen for activity C, 0 otherwise
Di = 1 if a completion time of i (i=3,2,1) chosen for activity D, 0 otherwise
Ei = 1 if a completion time of i (i=8,7,6) chosen for activity E, 0 otherwise

then the constraints relating to the choice of completion time are:

C4 + C3 + C2 + C1 =1
D3 + D2 + D1 = 1
E8 + E7 + E6 = 1

i.e. exactly one completion time must be chosen for C, D and E respectively.

The constraints relating to the network logic are:

xA= xB = 0

xC >= xA + 2

xD >= xB + 3
xD > = xA + 2

xE >= xC + 4C4 + 3C3 + 2C2 +1C1

where 4C4 + 3C3 + 2C2 +1C1 is the completion time for activity C (remember C4, C3,
C2 and C1 are zero-one variables).

xE >= xD + 3D3 + 2D2 +1D1

xF >= xC + 4C4 + 3C3 + 2C2 +1C1

xG >= xE + 8E8 + 7E7 + 6E6


xH >= xF + 3
xH >= xG + 2

xH <= 17 - 3 (to complete in 17 weeks)

and the objective is:

minimise 3C4 + 7C3 + 10C2 +15C1 + 12D3 + 16D2 +25D1 + 5E8 +9E7 +14E6

Network analysis example 1996 MBA exam

A project consists of 8 activities. The activity completion times and the precedence
relationships are as follows:
Activity Completion time Immediate predecessor
(days) activities
A 5 -
B 7 -
C 6 -
D 3 A
E 4 B,C
F 2 C
G 6 A,D
H 5 E,F

Draw the network diagram.


Calculate the minimum overall project completion time and identify which
activities are critical.
If activity E is delayed by 3 days how is the project completion time affected?
If activity F is delayed by 3 days how is the project completion time affected?

Solution

The network diagram is shown below. Note the introduction of a dummy activity I
with a duration of zero to represent the end of the project.
Let Ei represent the earliest start time for activity i such that all its preceding activities
have been finished. We calculate the values of the Ei (i=A,B,...,I) by going forward,
from left to right, in the network diagram.

To ease the notation let Ti be the activity completion time associated with activity i
(e.g. TB = 7). Then the Ei are given by:

EA = 0 (assuming we start at time zero)


EB = 0 (assuming we start at time zero)
EC = 0 (assuming we start at time zero)
ED = EA + TA = 0 + 5 = 5
EG = max[EA + TA, ED + TD] = max[0 + 5, 5 + 3] = 8
EE = max[EB + TB, EC + TC] = max[0 + 7, 0 + 6] = 7
EF = EC + TC = 0 + 6 = 6
EH = max[EE + TE, EF + TF] = max[7 + 4, 6 + 2] = 11
EI = max[EG + TG, EH + TH] = max[8 + 6, 11 + 5] = 16

Hence the minimum possible completion time for the entire project is 16 days, i.e. 16
days is the minimum time needed to complete all the activities.

We now need to calculate the latest times for each activity.


Let Li represent the latest start time we can start activity i and still complete the
project in the minimum overall completion time. We calculate the values of the
Li (i=A,B,...,I) by going backward, from right to left, in the network diagram. Hence:

LI = 16
LG = LI - TG = 16 - 6 = 10
LH = LI - TH = 16 - 5 = 11
LD = LG - TD = 10 - 3 = 7
LA = min[LD - TA, LG - TA] = min[7 - 5, 10 - 5] = 2
LE = LH - TE = 11 - 4 = 7
LF = LH - TF = 11 - 2 = 9
LC = min[LE - TC, LF - TC] = min[7 - 6, 9 - 6] = 1
LB = LE - TB = 7 - 7 = 0

Note that as a check all latest times are >=0 at least one activity has a latest start time
value of zero.

As we know the earliest start time Ei, and latest start time Li, for each activity i it is
clear that the amount of slack or float time Fi available is given by Fi = Li - Ei which is
the amount by which we can increase the time taken to complete activity i without
changing (increasing) the overall project completion time. Hence we can form the
table below:
Activity Li Ei Float Fi
A 2 0 2
B 0 0 0
C 1 0 1
D 7 5 2
E 7 7 0
F 9 6 3
G 10 8 2
H 11 11 0

Any activity with a float of zero is critical. Note here that, as a check, all float values
should be >= 0.

Hence the critical activities are B, E and H and the floats for the non-critical activities
are given in the table above.

If activity E is delayed by 3 days then as E is critical the project completion time


increases by exactly 3 days.

If activity F is delayed by 3 days then as F has a float of 3 days the project completion
time is unaffected.
Network analysis example 1994 MBA exam

A project consists of 8 activities named A to H.

Construct a network so as to satisfy the scheduling requirements shown in the table


below.
Activity Completion time Immediate predecessor
(days) activities
A 3 -
B 6 A

C 7 A
D 5 A
E 13 B,C
F 8 C,D
G 11 D,F
H 6 G,E

Find the least time required to complete the whole project and identify the critical
activities.

How is the project completion time affected if:

activity F is delayed by 3 days


activity E is delayed by 7 days
activity G is finished 7 days early

Solution

The network diagram is shown below. Note the introduction of a dummy activity I
with a duration of zero to represent the end of the project.
Let Ei represent the earliest start time for activity i such that all its preceding activities
have been finished. We calculate the values of the Ei (i=A,B,...,I) by going forward,
from left to right, in the network diagram.

To ease the notation let Ti be the activity completion time associated with activity i
(e.g. TB = 7). Then the Ei are given by:

EA = 0 (assuming we start at time zero)


EB = EA + TA = 0 + 3 = 3
EC = EA + TA = 0 + 3 = 3
ED = EA + TA = 0 + 3 = 3
EE = max[EB + TB, EC + TC] = max[3 + 6, 3 + 7] = 10
EF = max[EC + TC, ED + TD] = max[3 + 7, 3 + 5] = 10
EG = max[EF + TF, ED + TD] = max[10 + 8, 3 + 5] = 18
EH = max[EE + TE, EG + TG] = max[10 + 13, 18 + 11] = 29
EI = EH + TH = 29 + 6 = 35

Hence the minimum possible completion time for the entire project is 35 days, i.e. 35
days is the minimum time needed to complete all the activities.

We now need to calculate the latest times for each activity.

Let Li represent the latest start time we can start activity i and still complete the
project in the minimum overall completion time. We calculate the values of the
Li (i=A,B,...,I) by going backward, from right to left, in the network diagram. Hence:
LI = 35
LH = LI - TH = 35 - 6 = 29
LG = LH - TG = 29 - 11 = 18
LE = LH - TE = 29 - 13 = 16
LF = LG - TF = 18 - 8 = 10
LB = LE - TB = 16 - 6 = 10
LC = min[LE - TC, LF - TC] = min[16 - 7, 10 - 7] = 3
LD = min[LF - TD, LG - TD] = min[10 - 5, 18 - 5] = 5
LA = min[LB - TA, LC - TA, LD - TA] = min[10 - 3, 3 - 3, 5 - 3] = 0

Note that as a check all latest times are >=0 at least one activity has a latest start time
value of zero.

As we know the earliest start time Ei, and latest start time Li, for each activity i it is
clear that the amount of slack or float time Fi available is given by Fi = Li - Ei which is
the amount by which we can increase the time taken to complete activity i without
changing (increasing) the overall project completion time. Hence we can form the
table below:
Activity Li Ei Float Fi
A 0 0 0
B 10 3 7
C 3 3 0
D 5 3 2
E 16 10 6
F 10 10 0
G 18 18 0
H 29 29 0

Any activity with a float of zero is critical. Note here that, as a check, all float values
should be >= 0.

Hence the critical activities are A, C, F, G and H and the floats for the non-critical
activities are given in the table above.

If activity F is delayed by 3 days then as F is critical the project completion time


increases by exactly 3 days.

If activity E is delayed by 7 days then as E has a float of 6 days the project completion
time is affected. The project completion time will increase by exactly (7-6) = 1 day to
36 days.

If activity G is finished 7 days early then as G is a critical activity the overall project
completion time will (potentially) be reduced. To see the effect of this change we
need to redo the calculation for the earliest times given above but with a completion
time for G of 4 days. The only change is in the calculation of EH and EI and these now
are:
EH = max[EE + TE, EG + TG] = max[10 + 13, 18 + 4] = 23
EI = EH + TH = 23 + 6 = 29
Hence the overall project completion time falls to 29 days (a decrease of 6 days).