FCCNHT Manual
FCCNHT Manual
Draft
OPERATING MANUAL FOR
FCC NAPHTHA HYDRO TREATER UNIT, Rev. A
VRCFP, HPCL VISAKH Page 1 of 195
OPERATING MANUAL
FOR
PREFACE
This operating manual for FCC Naphtha HydroTreater Unit (Unit No.-75) of
Visakh Refinery Clean Fuel Project for HPCL Visakh Refinery has been prepared
by M/s Engineers India Limited for M/s Hindustan Petroleum Corporation Limited.
The objective of FCC Naphtha Hydrotreating Unit is to process FCC
Gasoline to obtain product streams (Light gasoline and Heavy Hydrotreated
gasoline) with targeted qualities of octane number, sulphur content, benzene
content and olefins content. This manual contains process description and
operating guidelines for the unit and is based on documents supplied by the
Process Licensor (Axens). Hence the manual must be reviewed /approved
by the licensor before the start-up /operation of the unit. Operating
procedures & conditions given in this manual are indicative. These should be
treated as general guide only for routine start-up and operation of the unit. The
actual operating parameters and procedures may require minor
modifications/changes from those contained in this manual as more experience is
gained in operation of the Plant.
For detailed specifications and operating procedures of specific equipment,
corresponding Vendor's operating manuals/instructions need to be referred in
addition to Process Package and Design Basis.
TABLE OF CONTENTS
5.1 GENERAL............................................................................................................................................................. 65
5.2 PRE-COMMISSIONING ACTIVITIES .............................................................................................................. 65
5.2.1 Inspection / Checking .................................................................................................................................. 65
5.2.2 Inspection of equipments ............................................................................................................................. 66
5.2.3 Piping and Accessories ................................................................................................................................ 66
5.2.4 Instruments ................................................................................................................................................... 66
5.2.5 Relief Valves................................................................................................................................................. 67
5.2.6 Rotary Equipment ........................................................................................................................................ 67
5.2.7 Drainage System .......................................................................................................................................... 67
5.3 PREPARATION FOR PRE-COMMISSIONING .............................................................................................................. 67
5.4 PRE-COMMISSIONING ............................................................................................................................................. 68
5.4.1 Commissioning of Utilities .......................................................................................................................... 68
5.4.2 Final Inspection of Vessels .......................................................................................................................... 70
5.4.3 Pressure Test Equipment ............................................................................................................................. 71
5.4.4 Wash Out Lines and Equipment .................................................................................................................. 72
5.4.5 Functional Test of Rotating Equipment ...................................................................................................... 74
5.5 INSTRUMENTS CHECKING ....................................................................................................................................... 77
5.6 SAFETY DEVICES CHECK ........................................................................................................................................ 78
5.7 HEATER REFRACTORY DRY-OUT AND REACTION SECTION DRY-OUT .................................................................... 79
5.8 PURGING AND GAS BLANKETING ........................................................................................................................... 79
5.9 TIGHTNESS TEST .................................................................................................................................................... 80
5.10 CATALYST LOADING PROCEDURE ...................................................................................................................... 83
SECTION- 1 INTRODUCTION
1.1 INTRODUCTION
Hindustan Petroleum Corporation Limited (HPCL), Visakh is in the process of
augmenting the capacity of the existing refinery by revamping the existing
primary units and installing additional facilities required to meet the product
specifications.
The objective of this Unit is to process FCC gasoline to produce a blend of two
streams (LCN+HCN), Maximise the octane number while meeting pool
specifications in term of sulphur content, benzene content and olefins content.
Three different feeds considered for the design of the FCC Naphtha Hydrotreater
unit: are NITCASE, AM (Arab Mix) CASE, BH (Bombay High) CASE
AM BH NIT
Characteristics
CASE CASE CASE
Max Available Rate, t/hr 111 666 111 666 111 666
St m3/hr 152.3 156.0 152.8
Density at 15C, g/cc 0.7334 0.716 0.731
Total Sulfur, wppm / RSH 2400/720 180/90 1133/229
AM BH NIT
Characteristics
CASE CASE CASE
RON 93 93 91.4
MON 80.6 81.6 81.2
PONA (vol %)
Paraffins, vol % 29.5 29.2 24.35
Olefins, vol % 35.5 38.5 54.47
(Diolefins wt %) (2.0) (2.0) (2.0)
Naphthenes, vol % 10.7 10.3 7.01
Aromatics, vol % 24.3 22.0 14.17
(Benzene, vol%) (1.8) (1.9) (0.38)
Distillation (ASTM-D86), C
IBP 46.1 46.1 40
10 % vol 56.1 56.1 57.6
30 % vol 75.5 75.5 70.6
50 % vol 95.5 95.5 92
70 % vol 124.4 124.4 123.2
90 % vol 155 155 156.4
95 % vol 167.7 167.7 168.2
FBP 180 180 187
C5 mercaptan 263 33 12
C6+ mercaptan 97 12 5
Carbonyle disulfide 0.5 0.1 0.5
Dimethyl sulfide 2 0.2 1
NIT AM BH
Characteristics
CASE CASE CASE
Max Available Rate, t/hr NA 16000 15000
St m3/hr NA 23.1 22.4
Density at 15C, g/cc NA 691.6 671.0
MW, kg/kmol NA 85.4 85.4
Sulfur, wppm NA 1116 64
PONA (vol %)
Paraffins, vol % NA 36.5 33.0
Olefins, vol % NA 46.5 51.7
(Diene Value) (0.0) (0.0)
HR 845
Relevant to Selective Hydrogenation Reactor, 75-R-01
Trade mark HR 845, manufactured by :
Axens Procatalyse Catalysts & Adsorbents
Presentation Spheres, diameter 3mm (2 to 4mm)
Estimated cycle length Refer (1)
Estimated life time Refer (1)
Loaded catalyst volume 38.2 m3, Refer (2), (3)
(1) Catalyst cycle length and estimated life time is different for each case:
NIT CASE : Estimated cycle life = 3 years, Estimated life time = 5 years
AM CASE : Estimated cycle life = 1.5 years, Estimated life time = 2.5 years
BH CASE : Estimated cycle life = 3 years, Estimated life time = 5 years
These cycle length and life duration are defined at iso-capacity (111 666 kg/hr)
(2) The 75-R-01 is designed to have some provision in the reactor for a future
loading. Additional catalyst amount will 49.7 m3 allow to increase catalyst cycle life
and life time for AM CASE feed.
AM CASE : Estimated cycle life = 3 years, Estimated life time = 5 years
HR 806
(1) Catalyst cycle length and estimated life time is different for each case:
NIT CASE : Estimated cycle life = 3 years, Estimated life time = 5 years
AM CASE : Estimated cycle life = 1.5 years, Estimated life time = 2.5 years
These cycle length and life duration were defined at iso-capacity (111 666 kg/hr)
(2) The 75-R-02 was designed to have some provision in the reactor for a future
loading. Additional catalyst amount will be 38.2 m3 allowing to increase catalyst
cycle life and life time for AM CASE feed.
AM CASE : Estimated cycle life = 3 years, Estimated life time = 5 years
(3) Sock loading catalyst method
(1)
The volume specified for inert balls does not include inert balls volume
occupied by unloading catalyst nozzles.
(1)
This amount of inert balls is defined for catalyst future loading provision.
1.10.4 CHEMICALS
o 75-R-01 : 6012 kg
o 75-R-02 : 2061 kg
Pressure Temperature
Stream Steam and condensate
(kg/cm2g) (deg.C)
Very High Pressure Minimum (for thermal 33 340
(From CCR unit) design):
Normal 35 360
Maximum 38 380
Mechanical design: 40 400
Medium pressure Minimum (for thermal 9 Saturated.
design):
Normal: 10 250
Maximum: 11 280
Mechanical design: 12.5 300
Low pressure Minimum (for thermal 2.5 saturated
design):
Normal: 3.0 150
Maximum: 4.0 170
Mechanical design: 5.5 190
Steam condensate (HP Normal: 5.5 100
and HP steam) Mechanical design: 10 185
Pressure Temperature
Stream Steam and condensate
(kg/cm2g) (deg.C)
Boiler feed water Minimum: 47/17.5 120/120
(VHP/HP) Normal: 50/20.5 120/120
Maximum: - -
Mechanical Design: 71/29 155/155
Demineralised water Minimum: - -
Normal: 3.0 Ambient
Maximum: - -
Mechanical Design: 9.0 65
Plant air (oil-free and Minimum: 3.0
water for catalyst Normal: 4.0 Ambient
regeneration) Maximum: 5.0
Mechanical Design: 9.0 65
Instrument air Minimum: 4.0
Normal: 5.0 Ambient
Maximum: 6.0
Mechanical Design: 9.0 65
Nitrogen Minimum: 5.0
Normal: 6.0 Ambient
Maximum: 7.0
Mechanical Design: 10.5 65
Fuel gas Minimum: 2.5 30
Normal: 3.0 40-50
Maximum: 3.5 60
Mechanical design: 9.0 100
Fuel oil Minimum: 7.0 100
Normal: 8.0 130
Maximum: 11 170
Mechanical design: 17 200
pH 8.5-9.5
Cation conductivity @ 25 0C (micromho/cm) - <5
Hardness (CaCo3) (mg/l) Nil
Dissolved Oxygen (mg/l) 0.007
Copper (mg/l) Nil
Total Fe (mg/l) 0.03
Total SiO2 (mg/l) - <0.05
KMnO4 Value @ 100 0C mg/l) - <5
4. DM WATER
pH 6.7-7.3
Cation conductivity @ 25 0C (micromho/cm) 1-2
Hardness (CaCo3) (mg/l) Nil
Turbidity (NTU) Nil
Copper (mg/l) Nil
Total Fe (mg/l) <0.03
Total SiO2 (mg/l) - <0.05
KMnO4 Value @ 100 0C mg/l) - <5
pH 7.5-8.0
Hardness (CaCo3) (mg/l) 140-210
Turbidity (NTU) 20-30 (max 50)
Total dissolved solids (mg/l) 875-1300
M. Alkalinity (mg/l) 100-120
Chlorides as Cl (mg/l) 225-335
Sulphates as SO4 (mg/l) 205-466
Organophospahtes as PO4 (mg/l) 8-10
Total Fe (mg/l) 1 (max)
KMnO4 Value @ 100 0C mg/l) 30-40 (Max 50)
Oil content (mg/l) 10 (max)
Zinc Sulphate as Zn (mg/l) 1-2
b) Start-up nitrogen
Nitrogen gas is required for start-up and shutdown periods in order to free the
unit of any oxygen or hydrocarbons.
Unit pressurization: 8V
Unit purge: 3V
Unit purge: 10 V
Total: 30 V
d) Start-up steam
LP Steam: LP Steam will also be used during start-up to inertise other equipments by
steam out.
b) MP steam
MP steam is used for catalyst in-situ regeneration:
through the SHU Feed / Effluent Exchanger 75-E-02 and into the Splitter 75-C-
01, under pressure control.
stream is cooled by light gasoline air cooler 75-A-02 and pumped by 75-P-05 A/B
to storage after final cooling in 75-E-06 A/B under flow control reset by 31st tray
temperature control.
As the selective hydrogenation reactor is operated mainly in liquid phase, a
sufficient liquid velocity shall be maintained at its inlet. Therefore, the
hydrocarbon flow rate to the reactor shall be at least of 75% of the normal flow
rate. In case of turndown (50% of feed), part of the splitter bottom shall be
recycled to the SHU feed surge drum under flow control.
The HDS effluent is further heated in HDS heater, 75-F-01. The heater operates in
vapor phase and the feed HDS reactor inlet temperature is controlled via fuel gas
control. The effluent from the heater is then cooled by the HDS feed / effluent
exchangers 75-E-08 A/B/C and by exchanger with the SHU reactor feed/HDS
effluent exchanger 75-E-01. Final cooling is achieved in the HDS effluent air
cooler 75-A-03 and the reactor effluent trim coolers 75-E-09 A/B.
An intermittent washing water injection point upstream the HDS effluent air
condenser 75-E-03 enables to flush these equipment from salt deposit that may
have been formed at low temperature.
The hydrocarbon liquid is partially pumped back to the HDS section through 75-P-
06 A/B quench pumps. The remaining part of the liquid is routed to the stabilizer
section under flow control reset by 75-V-03 level control.
The PrimeG+ unit is equipped with catalyst in-situ facilities that involve:
An air injection line to Reactor heater 75-F-01 for burning operation
A steam injection to Reactor heater 75-F-01 for stripping and burning
operations,
A nitrogen injection to Rector heater 75-F-01 for heating operation
The regeneration steps described below are equivalent for each reactor 75-R-
01 and 75-R-02 except the duration which may vary depending on the amount of
catalyst and steam and air flow rate.
The reaction section is hydrocarbon free and put under nitrogen atmosphere.
Then feed surge drum, feed pumps, splitter and stripper sections are isolated
from the reaction section.
The regeneration procedure includes:
1. A heating phase by nitrogen with 200C catalytic bed reactor temperature.
2. A stripping phase by steam with 400C catalytic bed reactor temperature for 8
hours.
3. A coke burning phase by steam and air with 0.3 up to 3.0 vol % oxygen in the
reactor inlet gas with 460C catalytic bed reactor temperature
4. A catalyst polish burning phase by steam and air with 3.0 up to 8.0 vol %
oxygen and 480C reactor inlet temperature. (These conditions are kept
during 4 hours).
5. A first cooling down of the reactor temperature to 200C by steam.
6. A second cooling down of the reactor temperature to 65C. Steam is replaced
by nitrogen.
The reaction is carried out in one down flow reactor operating mainly in liquid
phase with dissolved hydrogen at low temperature.
The reactor effluent is separated into three fractions in the splitter: light gasoline,
heart cut (intermittent mode for high benzene content in the feed) and heavy
gasoline. The light stream has a very low sulfur content and does not require an
extractive sweetening to further lower the sulfur content.
The light gasoline is a final product and is blended with the stabilizer bottom
before being routed to storage tanks, while heavy gasoline is fed to the HDS
reactor for further hydrodesulfurization.
octane losses in the HDS Reaction Section. Alternatively, a higher light FCC
gasoline withdrawal rate from the Splitter will produce an heavy FCC gasoline
with lower olefin concentrations which is initially favorable for octane losses in the
HDS Reaction Section but with increased sulfur levels in the light FCC gasoline.
As the light FCC gasoline rate in the Splitter is increased, the severity of the HDS
Reaction Section has to be increased to offset the amount of sulfur that has left
with the light FCC gasoline.
A) Cyclodiolefins
A typical example is cyclohexadiene which is hydrogenated into cyclohexene
with no further hydrogenation with the catalyst and at the operating conditions
of the first stage.
+ H2
Cyclohexadiene Cyclohexen
B) Normal or isodiolefins
Normal diolefins:
Their hydrogenation produce several isomers, for example:
CH3 - CH2 - CH2 - CH2 - CH2 - CH = CH2
Iso-diolefins
Isodiolefins hydrogenation produces also various isomers. Moreover double bond
migration can also occur within the newly generated isomer.
Diolefins are very unstable compounds, which polymerize easily into gums.
Therefore conversion of diolefins into olefins improves the product quality: these
reactions are highly exothermic. The difference between the diene value (DV) or
the maleic anhydride value (MAV) of the feed and the DV or MAV of product
measures the yield of these reactions and could be related to the hydrogen
consumption. Refer to chapter "Operation of the unit".
temperature and high pressure. The typical heats of reaction (per mole of
reactant) are respectively:
Diolefins to olefins : 26 Kcal/mole
Olefins to paraffins : 30 Kcal/mole
From a kinetic viewpoint, with a proper catalyst, at temperature in the range of
160C, the rate of the diolefins hydrogenation is high enough for almost complete
hydrogenation.
The reactor operating pressure is fixed at the design stage, operator will maintain
this maximum operating pressure during all normal operation.
nitrogen compounds that are present in the feed occur simultaneously with
desulfurization.
The reaction taking place in the reactor can be grouped as follows:
Hydrorefining (i.e. desulfurization, denitrification).
Hydrogenation of olefins (which are undesirable reactions).
3.8.2 HYDROREFINING
A) Desulfurization
The typical sulfur compounds in cracked gasoline are of the thiophenic and
benzothiophenic types.
The desulfurization occurs in several phases.
CH CH
+ 4H 2 C H + NH 3
5 12
CH C - CH 3
NH
+ 5 H2 C5 H12 + NH3
n- pentane ammonia
N
pyridine
The heat released by the denitrification reactions is also negligible owing to the
small amount of nitrogen compound involved.
n - olefins > n internal olefins > branched olefins > cyclic olefins > internal branched
olefins
CH3 - CH2 - CH2 -CH2 -CH2 - CH = CH2 CH3 - CH2 - CH2 - CH2 - CH2
-CH2 -CH3
1-heptene (n - olefins) n-heptane
+ H2
CH3 - CH - CH = CH CH3 CH3 - CH - CH2 - CH2 - CH3
3.9.2 TEMPERATURE
Thermodynamically, as the hydrodesulfurization and olefin hydrogenation
reactions are exothermic, these reactions are favored by low temperature.
C) H2 / HC ratio
As the operating pressure is selected during the design stage, the most important
operating variable is the H2/HC ratio. An increase of the H2/HC ratio enhances
4.1 INTRODUCTION
The utility system consists of Nitrogen, Instrument Air (IA). Plant Air (AP), Sea
Cooling Water (WC), Service Water (SW), Boiler Feed Water (BFW), HP/MP/LP
Steam, LP Condensate, Bearing Cooling water (BCW) and Fuel Gas (FG).
Closed Blow down (CBD), Amine Blow down (ABD) Flare is also provided within
the unit.
Description related to various utility systems for Prime G+unit is given below.
A 2" Instrument Air header supplies IA to Prime G+ Unit. The header is provided
with isolation valve and a spectacle blind. Various Instrument air tapping are
taken from this header. In DCS FI-4502 with FQ and FAH/FAL, PI-4505 with
PAH/PAL and TI-4502with TAH/TAL and local TI, PI is provided on the 3 header
at B/L.
A 6" Plant Air header supplies PA to Prime G+ Unit. The header is provided with
isolation valve and a spectacle blind. Various Instrument air tapping are taken from
this header. Plant air is also used during in-situ regeneration. In DCS FI-4501 with
FQ, and local TI, PI is provided on the 6 header at B/L.
Cooling water from the supply header is taken to the following equipment in Prime
G+ Unit.
Recycle Compressor (75-K-01A/B)
FCC Heart cut cooler (75-E-06A/B)
Light Gasoline cooler (75-E-05A/B)
Splitter post condenser (75-E-04A/B)
Reactor effluent trim cooler (75-E-09A/B)
Heavy Gasoline cooler (75-E-12A/B)
The return water is collected in a 16 return header and sent to B/L. Individual return
line from cooler is provided with a Local temperature Indicator (TI) and Thermal
safety valve. The return header is provided with isolation valve and a spectacle
blind for positive isolation at the battery limit. The return header is also provided with
TI-4603, with TAH/TAL, PI-4603 with PAH/PAL and FI-4602 with FAL/FAH in DCS
and local PI & TI at B/L. A 6 Jump over between supply and return header is also
provided at B/L.
FAL/FAH in DCS and local PI & TI at B/L. A 4 Jump over between supply and
return header is also provided at B/L.
4.1.6 NITROGEN
A 8 header supplies N2 to Prime G+ Unit. N2 is used for various purposes
in equipment, line etc. for inertisation, blanketing, purging, in-situ regeneration
etc. The supply header is provided with DCS FI/FQ-4101 with FAH/FAL, PI-4102
with PAL/PAH along with local PI & TI at B/L.
Fuel Gas is received in Fuel gas Knock-out drum (75-V-16) and from KOD
FG is distributed to various users. The FG receiving header is of 3 size and it is
provided with double block valve and spectacle blind at B/L. FI/FQ-2201 with
FAH/FAL is provided in DCS to indicate FG consumption.
Fuel Gas is used in the following points of the unit:
HDS Reactor Feed Heater (75-F-01)
In Amine Blow-down Drum (75-D-18)
Continuous sevice for light ends and H2S removal: about 428 to 855 kg/hr, 400C
at operating temperature.
5.1 GENERAL
As the new unit nears completion, there is a large amount of preparatory
work, which should be performed by the operating crew. A planned check of the
unit will not only set the foundation of a smooth start-up, but will also provide a
firm basis for acquainting operators with the equipment. Start-up is a critical
period and the operator must know exactly the operation of each equipment.
Some of the pre-commissioning works can be carried out simultaneously
along with construction. But, care in the organisation of this work is necessary so
that it does not interfere in the construction activities. It is most important to plan
schedule and record with checklists and test schedules all the preliminary
operation and to co-ordinate the constructions programme.
5.2.4 INSTRUMENTS
All instrument tapings for pressure, level and flow should be clear and
Thermowells should not foul with the internals. These should be checked prior to
box up of the equipment.
Instruments will be checked, starting from the controller and proceeding
logically through the control loop. Cascade control system will be checked from
the impulse point of primary loop. Operating crew should check proper mounting
of control valves. Control valves responses should be checked for controller
outputs. The shutdown systems of the equipment and machinery will be checked
by simulating the various conditions in the control circuits.
5.4 PRE-COMMISSIONING
Prior to the commissioning of the plant there are several pre-commissioning
operations that must be conducted to prepare the plant for the actual start-up
these are:
1. Commissioning of utilities
2. Final inspection of vessels
3. Pressure test equipment
4. Wash out lines and equipment
5. Functional test of rotating equipment
6. Instruments checking
7. Safety device checking
8. Heater Refractory dry-out
9. Purge and gas blanketing
10. Tightness test
11. Catalyst loading procedure
12. Charging of chemicals
a) Steam Network
Network is blown through completely from battery limit with a strong steam
flow in order to clean the lines. The following steps are recommended:
Network shall be cleaned from battery limit with a strong water flow. All
equipment will be disconnected at the inlet and reconnected when lines are
cleaned. Control valves and orifice plates will be removed and re-installed, after
the lines become clean. When system has been flushed, charge the lines to the
operating pressure.
Network shall be blown through completely from battery limit with strong flow
of air in order to clean and dry the lines. All joints and connections shall be
checked for tightness with soap solution. Header and branch lines will be blown
through with a high flow rate of air. During all tests, the instruments and control
valve shall be carefully isolated from the system.
It will not be practical to test all of the equipment together. Thus, the unit will
be divided into sections as governed by the location of the various items of
equipment and the test pressures to which each item will be subjected. Suitable
blanks must be made up for insertion on nozzles and between flanges to isolate
the various sections of equipment as required. Normally, the exchangers,
receivers, etc., for the various towers will be tested together with the main
vessels. Test pressures will be determined from the pressure vessel summary
for the unit. During pressure testing, all safety valves must be blinded off since
their normal relieving pressure will be exceeded.
It may be convenient to test the heaters and reactors in one group. A field
hydrostatic test on the gas compressor after installation could result in damage to
the internals, so the compressors must be isolated from the reactor system. As
the heaters are normally tested at a higher pressure than the reactors, it would be
simplest to blind off the heaters and test them first and then test the entire system
at the reactor test pressure. Blanks can be provided with connections for
introduction of water for testing and for venting of air as the system is filled with
water. It may be necessary to use Thermowells connections and pressure taps
for additional vents in the reactor system. At the completion of the hydrostatic
test, all water should be removed from the equipment. Where necessary, flanges
may be broken to drain low points and the equipment air blown to remove as
much water as possible before flanging up.
After hydrostatic pressure testing, a tightness test must be conducted to
check all flanges and fittings, especially the ones opened during hydro testing.
This final tightness test must be witnessed by Licenser representatives and is
normally done just prior to start-up.
All possible lines and pumps should be used during the washing procedure for
complete clearout of the system. Of course, no water circulation should be
carried out in the gas sections of the unit. Temporary water connections should be
provided at convenient locations in the system for carrying out water flushing. The
following points should be remembered during water flushing.
Low point drains and high point vents should be purged.
All instrument connection should be isolated, orifice plates removed, control
valves isolated and by-passed. In case there is no bypass, remove control
valve and flush the line. The valve will be installed after clean water starts
coming out and further flushing may be continued.
If there is any heat exchanger in the line, flushing should be done up to and
around the exchanger using by-pass line. It should be ensured that dirty water
from initial flushing does not get into the exchanger. Wherever bypasses are
not available, the flanged joints at the inlet of heat exchanger should be first
opened and the line flushed till clear water starts coming out. Then reconnect
flange and flush through the exchanger.
At each opening of the flanged joints, a thin metallic sheet should be inserted
to prevent dirty water from entering the equipment or piping.
The flow of water should preferably be from top to bottom for flushing of heat
exchanger coolers. The bottom flange of the equipment should be opened to
permit proper flushing.
The flushing should be carried out with maximum possible flow of water till
clear water starts coming out.
Vertical lines, which are long and rather big (say over 100-mm dia) should
preferably be flushed from top to bottom. This will ensure better flushing.
Filling the lines and releasing from bottom is also helpful. The rundown lines
can also be flushed conveniently from the unit to the respective tanks.
It should be ensured in all flushing operation that design pressure of lines and
equipment is never exceeded. After flushing of lines and equipment, water
should be thoroughly drained from all low points. Lines and equipment
containing pockets of water should not be left idle for a long time; it is
preferable to dry these lines and equipment with air after water flushing.
b) Pumps
Prior to unit start up, all centrifugal pumps should be thoroughly checked and
run in properly (after pressure testing and water flushing) as indicated in the
following outline: The pumps will be started and operated according to the
manufacturers instructions.
CAUTION: Many high head pumps are not designed to pump water. To do
so can result in damage to the pump internals. Check the vendors
specifications before attempting to run in pumps with water.
Check to see that all necessary water piping has been made to stuffing boxes,
bearing jackets, pedestals and quench glands. Make sure that all necessary
lube oil piping is installed, and that this piping is not mistakenly connected to
the water system.
Check arrangements to vent the pump for priming if the pump is not self-
venting. See that special connections such as bleeds and drains are properly
installed.
Check strainers in pump suction lines. Strainers must be installed before
aligning pumps. A 4-mm (three to five mesh) strainer is provided for each
pump suction line during start-up. To avoid pump damage during flushing
with water, the strainers should temporarily be lined with 1-mm (20-mesh)
screen.
Remove this screen after water flushing is completed. All strainers should be
flagged, and a list similar to the blind list should be kept, so as to prevent a
lost screen from plugging and upsetting unit operation later on.
Check that power is available for running in the pump. Check that pressure
gauges and any special instrumentation are in working order.
Water circulation on motor driven hydrocarbon pumps can result in motor
overloading if the full pumping capacity is used. In this type of equipment, the
capacity must be reduced by throttling the discharge during such periods. An
ammeter can be used to determine the required throttling.
Before lubricating oil-lubricated bearings, check bearing chamber in pumps to
see that no flushing compounds or shipping grease is left in the chamber.
Mechanical-type pumps should be flushed with water prior to pump operation
so no dirt gets into the seal and scores the seal faces.
It is extremely important that the proper type and viscosity oil and proper
grade of grease is used to lubricate the equipment. Refer to manufacturers
instructions and lubricating schedule for this information.
Motor should be checked and started to ensure that it has the correct direction
of rotation. The motor speed should be checked with tachometer to ensure
that RPM is correct. The manufacturer's lubrication schedule should be used
to ensure that all lubrication points have been serviced. After a short run each
bearing should be felt to ensure that it is free and not overheated.
See that the driver rotates the pump in the direction indicated by the arrow on
the pump casing. Rotate the pump by hand to see that it is clear before
starting.
Couple up and align the pumps, then check for cooling water availability and
start flow of cooling water to the pumps requiring external cooling, before they
are run in.
Open pump suction valve and close discharge valve (crack discharge valve
for high capacity, high head pumps). Make sure the pump is full of liquid.
Start the pump. As the pump is motor driven, the pump will come up to
speed. Immediately check discharge pressure gauge. If no pressure is
shown, stop the pump and find the cause. If the discharge pressure is
satisfactory, slowly open the discharge valve and give the desired flow rate.
Check the amperage of the motor. Do not run the pump with the discharge
block valve closed except for a very short time. Note any unusual vibration or
operation condition.
Check bearings of pumps and drivers for signs of heating. Recheck all oil
levels.
Run the pump for approximately one hour, then shut off to make any
adjustment necessary and check parts for tightness. Since it is not possible
to run the pump at operating temperature, a final check of alignment must be
made during normal operation by switching to the spare pump.
Start the pump and run it for at least four hours.
Shut the pump down and pull the strainer. Clean the strainer and replace it in
the suction line. Remove the temporary fine mesh liner from the strainer after
water flushing is complete.
On a new unit, the screens are sometimes left in service for the first run on all
locations where spare pumps have been provided.
When water is used for pressure testing and washing, it is sometimes better
to have packing in the pumps for a seal to prevent dirt from ruining the
mechanical seal.
After the lines and equipment are judged to be clean and all the pumps have
been run in, the water should be drained from the various systems. Lines
containing low spots should be broken at the low spot if no drain is provided.
Underground lines, without drains, should be blown free of water. Before
draining any vessel, a vent must be opened on that vessel so that a vacuum will
not be created on draining. If the towers are to be left standing for a long period
of time before steam drying or before operation, an inert gas, such as nitrogen or
sweet fuel gas, must be introduced to the vessels to prevent rusting of the
internals from oxygen in the air.
B) The following guidelines may be adopted for checking and calibration of all
instruments.
a) Orifice Plates
Before each orifice plate is installed the orifice taps should be blown clear.
The plate should be callipered to check if the correct size orifice plate is installed.
The plate should then be installed after checking for the correct direction.
b) Differential pressure Transmitters and Receivers
Ordinarily these should be calibrated locally against a manometer. The
calibration should be checked at the receiver, which may be board or locally
mounted recorder or indicator.
c) Pressure Transmitters and Receivers
These should be checked in place. The calibration of the receiver should be
checked at the same time.
d) Alarms checking
All alarms, auto start and cut off systems should be checked by simulating the
conditions. Make sure that the field instruments actuate the corresponding light or
audible alarm in the control room or DCS printer.
e) Valves
The control valves are removed during washing operations. They should be
checked for cleanness of the seats and free movement of the plug or ball.
Check the valves motion and their response to the controller signal.
When all the single instruments have been individually checked, when all
their addresses have been verified in the DCS, then the loop checking can take
place for each loop or group of control loops.
For the purpose of leak tests the unit will be divided into sections of
approximately the same design pressure. Air or nitrogen will be injected at
different locations depending on check valves locations.
C) Splitter section
Gasoline Splitter 75-C-01
Splitter reboiler exchanger 75-E-07
Splitter overhead air condenser 75-A-01
Splitter post condenser 75-E-04
Splitter reflux drum 75-V-02
Light FCC gasoline trim cooler 75-E-05
FCC heart cut cooler 75-E-06
SHU recycle air cooler 75-A-04
D) HDS section
HDS Feed/Effluent exchangers 75-E-08 A/B/C (shell and tube sides).
HDS reactor 75-R-02
HDS reactor feed heater 75-F-01
SHU feed/HDS effluent exchanger 75-E-01 (shell side).
HDS effluent air condenser 75-A-03
HDS effluent trim condenser 75-E-09 A/B(shell side)
Separator drum 75-V-03
Amine K.O. drum 75-V-06
Amine absorber 75-C-02
Lean amine preheater 75-E-10 (shell side)
Recycle compressor K.O. drum 75-V-04
The HDS section shall be isolated from other sections by blinds or valves.
E) Stabilization section
Stabilizer feed/bottom exchanger 75-E-11 A/B (tube and shell sides)
Stabilizer column 75-C-03
Stabilizer overhead condenser 75-A-05
6.1 INTRODUCTION
Start up and Operating Procedure are described in this section. Start up
and shutdown are the most critical periods in operation. It is then that the
hazardous possibilities for fire and explosion are greatest.
The hazards encountered most frequently in start up and shut down of units
are accidental mixing of air and hydrocarbons / hydrogen and contacting of water
with hot oil. Other hazards primarily associated with start up are pressure, vacuum
and thermal and mechanical shocks. These can result in fires, explosions,
destructive pressure surges and other damages to unit as well as injury to
personnel.
Fires occur when oxygen and fuel vapour or mists are mixed in flammable
proportions and come in contact with an ignition. They may run out of control or
touch off devastating explosion. Pressure surge from unplanned mixing of water
and hot oil may cause damage of equipment and or loss of valuable production.
Extensive, costly down time on process unit may result. Fires usually follow if the
explosion bursts lines or vessels.
Preparation for start-up begins with a complete review of the start up
procedure by the operating crew. Activities of Prime G+ unit should be co-
ordinated with control room, other units, and utility section.
All instruments have been checked, calibrated and ready for service. Control
should be on manual.
All safety valves are in position after setting and testing. Isolating valves will be
left in lock open position. Spare valves should be kept isolated.
Necessary utility headers (cooling water, steam, air, fuel gas, fuel oil, water etc)
are charged.
Flare, closed blow down and sewer systems are in operable condition.
All related units are informed of the start-up plan.
All other pre-commissioning activities such as flushing, cleaning, purging,
tightness testing etc are completed.
Fire and safety related equipment are checked.
All safety devices and emergency sequences have been tested.
General Service system such as lighting, PA, telephone etc is in working
condition.
The proper quantity and quality of nitrogen is available.
The unit is under a slight nitrogen pressure.
The reaction section has been dried out.
The feed, splitter and stabilizer sections have been thoroughly drained of free
water.
Catalysts have been loaded into the reactors.
On the sewer lines and utilities except cooling water and nitrogen,
catalyst. The vacuum ejector installed in this section is used for decreasing
the number of purging and nitrogen refilling cycles.
b) By steam out and subsequent refilling the equipment with fuel gas. This
method will be used for all equipment where humidity and steam can not
deteriorate the equipment or catalyst.
Note: During steam out operation, Reaction section and Compressor
section are isolated with blinds and filled with nitrogen. It is recommended
to start filling with nitrogen on reaction section, SHU preheating section
including.
The ejector (75-J-01) is connected to the vapor outlet line from the separator
drum. Isolate Reaction section with valves and blinds from remaining sections
of the Unit.
This section is isolated from the SHU and HDS reaction section by valves
and/or blinds. Isolate Pumps from the section by the valves at suction and
discharge and purged separately by nitrogen pressurizing/ depressurizing.
Stabilizer section
This section involves the following equipment and interconnecting piping:
75-C-03 Stabilizer
75-E-13 Stabilizer Reboiler
75-A-05 Stabilizer overhead air condenser
75-E-14 Stabilizer overhead trim cooler
75-V-05 Stabilizer reflux drum
75-E-11 A/B Stabilizer feed/bottom exchangers
75-A-07 Heavy gasoline air cooler
75-E-12 Heavy gasoline trim cooler
Isolated this section from the HDS reaction section by valves and/or blinds
Isolate Pumps from the section by the valves at their suction and discharge
and purged separately by nitrogen pressurizing/ depressurizing.
Eliminate air In the splitter and stabilizer sections by steam out and
subsequent filling with sweet fuel gas.
The start-up steam hoses for LP steam should be connected to the maximum
points, usually on suction-discharge of pumps, vessel bottoms. All vents on
columns reflux drums and other high points of lines should be opened. The air
coolers should be shut-down and cooling water circulation through coolers
and condensers stopped.
Introduced steam slowly to heat up slowly all parts of equipment/lines. Drain
the condensate at low points of piping and drums. The steam out operation
can be used for tightness test. This can be done by pressurizing the system
with steam and observing the flange connections to determine possible leaks.
Note: Do not allow any part of the system to develop vacuum. This will
result in introduction of air and danger of explosion.
Start pumping inert naphtha from storage or from the upstream units and
establish a level in the feed drum (75-V-01).
Put in operation the level control of the feed drum LIC-1102.
When the level in the feed drum reaches 40%, start the feed pumps (75-P-01
A/B) and through the start-up lines that by pass the reactors, establish a level
in the splitter bottoms (75-C-01).
When the level in the splitter reaches 40%, start the HDS feed pump 75-P-02
A/B and open the FV-1103 to recirculate the naphtha back to the feed surge
drum via SHU recycle line.
Drain lines on low points to eliminate water and remove foreign materials from
lines and equipment.
Provide cleaning of pumps strainers.
During the circulation it is good practice to switch to the standby's to check out
both pumps.
Note:
1. During the circulation it is good practice to switch to the standby's to
check out both pumps.
2. During the circulation minimum flow line of pumps must be kept in line.
Start-up
X-01 A V-01 a P-01A/B b V-02 c P-03A/B
Naphtha
d C-01
f
h
m P-02A/B
V-05
n
i
E-11A/B l k J P-09A/B
P-07A/B C-03
E-12A/B
As soon as the level in the reflux drum is established, start the reflux pumps
(75-P-03 A/B) and commission level and flow instruments on the reflux line,
(LIC-1601 and FIC-1601 respectively). The light FCC gasoline draw off and
the FCC heart cut draw off are closed.
The splitter is left operating at total reflux for several hours as necessary to
commission all involved equipments and instruments.
The pressure in the reflux drum must be kept at constant value by injecting N2
at the reflux drum if necessary.
Shutdown the splitter Reboiler heater while keeping circulation until the
temperature decreases in the splitter column bottom to 50C. Splitter should
be kept under pressure with nitrogen.
The stabilizer (now isolated from the splitter) is left operating at total reflux for
several hours as necessary to commission all involved equipments and
instruments.
Shutdown the stabilizer heater while keeping circulation until the temperature
decreases in the stabilizer column bottom to 50C. Stabilizer should be kept
under pressure with nitrogen.
The sulfiding flow scheme for the first HDS reactor catalyst is:
Recycle compressor 75-K-01 A&B HDS feed / effluent exchangers
shell side Heater 75-F-01 First HDS reactor 75-R-02 HDS feed /
effluent exchangers tube side HDS effluent air condenser 75-A-03
HDS effluent trim cooler Separator drum 75-V-03 Recycle compressor
K.O. drum 75-V-04 Recycle compressor 75-K-01 A&B.
From the actual recycle gas flow and the sulfiding agent injection, one can
calculate the H2S percent volume at reactor inlet which should be within 0.5%
to 1%. If required, adjust the sulfiding agent injection to match this range.
The sulfurization reactions produce water and the amount of water recovered
in the separator confirms the progress of the sulfurization. Drain the separator
when necessary.
Note: Proceed with caution, since the water is saturated with H2S.
Stop the sulfiding agent injection when the required amount is reached.
However proceed to intermittent injections if the H2S content in the recycle
gas was to fall below 0.5% volume.
Then:
Check that the H2S contents inlet and outlet of the reactor are equal.
Check that an injection of sulfiding agent results instantaneously in an
increase of the H2S content in the recycle gas.
The catalyst sulfurization is then considered as completed. Decrease the
reactor inlet temperature down to 100C at a rate of 30C/h.
At 100C, stop the HDS heater 75-F-01.
Remark: During sulfiding operation, the recycle gas is highly toxic and
flammable owing to its H2S content. It must not be vented to atmosphere.
The operators must be equipped with H2S protective masks when checking
the H2S content. Access to the unit must be forbidden to non-operating
personnel.
the same time reduce the recirculation rate from the 75-V-01 by the same
amount.
Adjust the make-up hydrogen gas as necessary to keep the pressure in the
Splitter and SHU Reactor at the normal operating values.
Ensure that the pressure difference between the reactor and the Splitter is
maintained through pressure control loop (PIC-1501).
Gradually increase the flow of raw FCC light gasoline to the feed surge drum
75-V-01, by increments of 10% of the normal flow rate. In the same
proportion, decrease the recirculation of naphtha from cooler 75-E-12 to the
feed surge drum (75-V-01). Excess naphtha is sent to off-spec storage tank.
Stabilize operating conditions after each increase of FCC light gasoline in the
feed.
Watch carefully the temperature gradient on the reactors. Decrease the inlet
temperature to the reactors if the temperature rise is too fast.
If there is no temperature rise in the reactors, increase the reactor inlet
temperature in steps of 2C maximum.
Monitor the temperature rise on each catalyst bed.
Adjust the operating conditions according to the analysis of the product
(MAV).
The Gasoline Splitter (75-C-01), light FCC gasoline draw-off, is put into
operation when the column top temperature reaches the design value and
reflux drum (75-V-02) liquid level is stabilized.
The FCC heart cut gasoline draw-off is put into operation if required (high
benzene content in FCC feed) when TIC-1502 reaches the operating value.
Gasoline should be sent to slop if it is not on-specification.
Once draw-off has started, start to add FCC gasoline to the SHU feed surge
drum (75-V-01).
The Stabilizer is operated with vapor distillate product only. The condensate is
returned to the column as reflux. The RVP of Hy. Gasoline and the H2S
stripping required to be monitored to define the proper operating pressure and
Reboiler temperature in the column.
Send off-spec Hydrotreated gasoline to slop until it is on-specification.
When the product is on-specification slowly increase unit feed flow rates in
steps of 5% up to 100%.
7.2 INTRODUCTION
Normal operation implies that the unit is lined out at the desired capacity
and the products meet the required specifications. However it is possible, to
optimize the unit so that utility consumption is reduced. This is accomplished by
adjusting the parameter while maintaining the desired product qualities. The
reflux flow rate and the heat input to the column are directly related as discussed
in process description section.
S.
Description Tag no. Unit Value
No.
Gasoline mixed with H2 to SHU FEED/HDS o
13. TI-1203 C 66
Effluent Exchanger
14. H2 to SHU section FIC-1203 Nm3/hr 1513
H2 from Isomerisation Make-up Compressor o
15. TI-2701 C 40
Discharge
Gasoline & H2 stream from SHU FEED PUMPS
16. PI-1206 Kg/cm2g 66
to SHU FEED/HDS Effluent Exchanger
Gasoline bypass before SHU Feed/HDS Effluent
17. FIC-1204 M3/hr 31.3
Exchanger
Gasoline & H2 stream from SHU FEED PUMPS to
18. PI-1206 Kg/cm2g 33.4
SHU FEED/HDS Effluent Exchanger
Gasoline & H2 after SHU Feed/HDS Effluent
19. PI-1207 Kg/cm2g 32.9
Exchanger
Gasoline & H2 stream before & after 1ST SHU
20. PDI-1208 Kg/cm2g 0.4
Feed/HDS Effluent Exchanger
Gasoline & H2 at the inlet of SHU o
21. TI-1301 C 65-162
FEED/EFFLUENT EXCHANGER
22. VHP condensate from SHU Preheater FIC-1301 M3/hr 15.4
Reactor Effluent (Gasoline & H2) after passing o
23. TI-1302 C 162-189
through SHU FEED/EFFLUENT EXCHANGER
Gasoline & H2 stream before & after SHU
24. PDI-1302 Kg/cm2g 0.4
Feed/Effluent Exchanger
25. Gasoline & H2 stream before SHU Preheater PI-1303 Kg/cm2g 32.4
Reactor feed from SHU FEED/Effluent Exchanger o
26. TI-1304 C 86-189
to SHU Preheater
Reactor feed from SHU Preheater to SHU o
27. TI-1305 C 160-200
Reactor
28. VHP steam inlet to SHU Preheater PI-1306 Kg/cm2g 31.9-37.6
Reactor feed from SHU FEED/Effluent Exchanger o
29. TI-1303 C 189
to SHU Preheater
30. Gasoline & H2 stream after SHU Preheater PI-1307 Kg/cm2g 32
Gasoline & H2 stream before & after SHU
31. PDI-1308 Kg/cm2g 0.4
Preheater
o
32. Reactor feed stream before & after the Preheater TDIC-1306 C 5-74
Reactor feed stream from SHU Preheater to SHU o
33. TIC-1401 C 160-200
Reactor
S.
Description Tag no. Unit Value
No.
34. Gasoline & H2 stream by pass to SHU Reactor PDIC-1401 Kg/cm2g 0.8
A Bypass line of reactor feed stream to SHU o
35. TIC-1402 C 160-200
reactor
Gasoline & H2 stream Inside SHU Reactor on the o
36. TI-1403 C 160-219
first bed of catalyst
Gasoline & H2 stream before entering SHU
37. PI-1403 Kg/cm2g 30
Reactor
Gasoline & H2 stream Inside SHU Reactor on the o
38. TI-1404 C 160-219
first bed of catalyst
39. Gasoline & H2 stream by pass PI-1404 Kg/cm2g 30
Gasoline & H2 stream Inside SHU Reactor on the o
40. TI-1405 C 160-219
first bed of catalyst
41. Gasoline & H2 stream by pass PI-1405 29
Gasoline & H2 stream after passing through the
42. PI-1407 Kg/cm2g 30
1st bed of catalyst in SHU Reactor
Gasoline & H2 stream before entering SHU
43. Reactor & after passing through the 1st bed of PDI-1408 Kg/cm2g 0.5
catalyst in SHU Reactor
44. SHU Reactor Effluent PI-1409 Kg/cm2g 28
Gasoline & H2 stream after 1st bed of catalyst in
45. PDI-1410 Kg/cm2g 0.5
SHU Reactor & Effluent from SHU reactor
46. SHU Reactor Effluent PI-1411 Kg/cm2g 28
Gasoline & H2 stream Inside SHU Reactor on the o
47. TI-1407 C 160-219
second bed of catalyst
Gasoline & H2 stream Inside SHU Reactor on the o
48. TI-1410 C 160-219
second bed of catalyst
Gasoline & H2 stream Inside SHU Reactor on the o
49. TI-1414 C 160-219
second bed of catalyst
o
50. Effluent from the SHU Reactor TI-1415 C 160-219
o
51. Effluent from the SHU Reactor TI-1416 C 160-219
o
52. Effluent from the SHU Reactor TI-1417 C 160-219
o
53. Gasoline & H2 stream inside the Splitter TIC-1501 C 107-117
2
54. SHU Reactor Effluent to Gasoline Splitter PKIC-1501 Kg/cm g 6.3
3
55. VHP Steam to Reboiler Splitter FIC-1501 M /hr 26.7
o
56. Gasoline & H2 stream inside the Splitter TIC-1502 C 139-142
S.
Description Tag no. Unit Value
No.
57. SHU Reactor Effluent to Gasoline Splitter PI-1502 Kg/cm2g 6.3
58. Heavy Naphtha at the bottom of Gasoline Splitter LIC-1502 Mm *
Inert Naphtha in Start-up filling line from SHU
59. FI-1502A/B M3/hr *
Feed pump to Splitter inlet
Heavy naphtha from the splitter bottom to HDS o
60. TI-1504 C 174-181
section
61. Splitter overhead i.e. Gasoline vapour PI-1505 Kg/cm2g 6
Inside the Splitter column above the heart cut
62. PI-1507 Kg/cm2g 6.2
naphtha plate at 37th tray
o
63. Reboiler outlet to Splitter bottom TI-1507 C 218-221
Inside the Splitter column above the feed plate at
64. PI-1508 Kg/cm2g 6.5
20th tray
o
65. Splitter outlet to Reboiler inlet TI-1508 C 214-217
2
66. Inside the Splitter column below 1st tray PI-1511 Kg/cm g 6.5
Gasoline & H2 stream on the 19th tray inside the o
67. TI-1505 C 181-199
Splitter column
68. Splitter overhead & splitter underflow PDI-1506 Kg/cm2g 0.5
o
69. Gasoline & H2 stream to the Splitter Feed TI-1504 C 122-160
2
70. Light gasoline vapor in splitter reflux drum PIC-1601 Kg/cm g 5.5
o
71. Splitter overhead (vapor gasoline) TI-1602 C 93-97
Splitter overhead to Splitter Reflux drum after o
72. TI-1603 C 55
Splitter overhead air condenser
Fuel gas from Splitter Reflux Drum to Fuel gas o
73. TI-1605 C 40
header
74. Fuel gas to FCC inlet PI-1610 Kg/cm2g 4.5
75. Splitter overhead to splitter reflux drum PI-1603 Kg/cm2g 5.5
o
76. Light FCC Gasoline to MS POOL TI-1706 C 40
Light Gasoline from Accumulator tray no.48 of
77. PI-1703 Kg/cm2g 7.6
Splitter
Light Gasoline after light gasoline cooler to light
78. PI-1704 Kg/cm2g 7.7
gasoline MS POOL
o
79. FCC HEART CUT GASOLINE TI-1702 C 65
FCC Heart cut gasoline from accumulator tray
80. PI-1707 Kg/cm2g 7.6
no.36
S.
Description Tag no. Unit Value
No.
FCC Heart cut gasoline after FCC Heart cut
81. PI-1714 Kg/cm2g 7
cooler to storage
FCC Heart cut gasoline after FCC Heart cut o
82. TI-1713 C 40
cooler to storage
Light Gasoline to storage after light gasoline
83. PI-1710 Kg/cm2g 7
cooler
Gasoline & H2 at the inlet of First HDS Feed /
84. PI-1901 Kg/cm2g 23.5-30
Effluent Exchanger
HDS feed & HDS recycle to HDS feed / effluent o
85. TI-1901 C 148-176
exchanger.
86. Vapor gasoline to HDS feed PI-1904 Kg/cm2g 22-28.5
Gasoline & H2 at the inlet of 1st HDS
87. Feed/Effluent Exchanger & at the outlet of 3rd PDI-1905 Kg/cm2g 1.2
HDS Feed/Effluent Exchanger
HDS feed from First HDS Feed/Effluent
o
88. Exchanger to second HDS Feed/Effluent TI-1902 C 210-240
Exchanger
HDS feed from second HDS Feed/Effluent o
89. TI-1903 C 242-271
Exchanger to third HDS Feed/Effluent Exchanger
Gasoline & H2 at the outlet of 2nd HDS
90. PI-1903 Kg/cm2g 22.5-29
FEED/EFFLUENT Exchanger
HDS Reactor Effluent after 3rd HDS Feed/Effluent
91. PI-1904 Kg/cm2g 22-28.5
Exchanger
HDS rector effluent from HDS feed/effluent o
92. TI-1906 C 207-227
exchanger tube side outlet.
HDS rector effluent from HDS feed/effluent
93. PI-1908 Kg/cm2g 16.3-22.8
exchanger tube side outlet.
Heavy FCC Gasoline after 3rd HDS Feed/Effluent o
94. TIC-2001 C 275-312
Exchanger to first HDS Reactor
Heavy FCC Gasoline before entering first HDS
95. PI-2001 Kg/cm2g 22.9
Reactor
Heavy FCC Gasoline after third HDS o
96. TI-2002 C 275-312
Feed/Effluent Exchanger to first HDS Reactor
Heavy FCC Gasoline before entering first HDS
97. PI-2002 Kg/cm2g 22.9
Reactor
S.
Description Tag no. Unit Value
No.
On the First bed of catalyst inside first HDS o
98. TI-2003 C 275-355
Reactor
Liq. Gasoline on 2nd bed of catalyst in 1st HDS
99. PDI-2006 Kg/cm2g 0.5
Reactor
On the First bed of catalyst inside first HDS o
100. TI-2004 C 275-355
Reactor
Liq. Gasoline on 1st bed of catalyst in 1st HDS
101. PDI-2004 Kg/cm2g 0.5
Reactor
Gasoline after passing through first bed of catalyst
102. PI-2003 Kg/cm2g 28.4
in first HDS Reactor
103. First HDS Reactor Effluent PI-2007 Kg/cm2g 28.4
On the 2nd bed of catalyst inside first HDS o
104. TI-2010 C 275-355
Reactor
o
105. First HDS Reactor Effluent TI-2019 C 275-355
o
106. First HDS Reactor Effluent to HDS Fired Heater TI-2102A/B C 301-355
2
107. First HDS Reactor Effluent to HDS fired heater PI-2102A/B Kg/cm g 19.8-26.3
o
108. Effluent of HDS Fired Heater TI-2104A/B C 336-373
2
109. HDS fired heater outlet to second HDS Reactor PI-2103A/B Kg/cm g 17.8-24.3
HDS Reactor Effluent from SHU feed/HDS o
110. TI-2301 C 144-157
Effluent Exchanger to HDS Effluent Air Condenser
Gasoline from SHU Feed/HDS Effluent Exchanger
111. PI-2301 Kg/cm2g 16-22.5
to HDS Effluent air condenser
HDS Reactor Effluent after HDS Effluent Air o
112. TI-2303 C 65
Condenser
Gasoline after passing through HDS Effluent air
113. PI-2303 Kg/cm2g 15.6-22.0
condenser
114. Separator drum outlet PI-2409 Kg/cm2g 15-21.5
3
115. Stabilizer feed from separator drum FIC-2402 M /hr 82.3
2
116. Off gas from Separator Drum PIC-2403 Kg/cm g 15
117. separator drum boot drain LIC-2401 M3/hr *
Lean Ammine from ARU after being pre-heated in o
118. TI-2501 C 50
the lean amine pre-heater
o
119. Lean Ammine from ARU TI-2504 C 40
OFF GAS from Amine K.O. Drum to Amine o
120. TI-2502 C 40
Absorber
S.
Description Tag no. Unit Value
No.
o
121. LP Steam to Lean Amine Preheater TDIC-2503 C 10
2
122. Off gas to Amine Absorber PI-2601 Kg/cm g 14.8
2
123. Amine & Fuel gas in Amine Absorber PDI-2602 Kg/cm g 0.3
2
124. Fuel gas from Amine Absorber PI-2603 Kg/cm g 14.7-21.5
3
125. Rich amine from amine absorber LIC-2601 M /hr *
2
126. Amine & Fuel gas inside Amine Absorber PI-2608 Kg/cm g 14.7
2
127. Rich Amine from Amine Absorber PI-2609 Kg/cm g 6
o
128. Make-up H2 to Recycle Compressor K.O. Drum TI-2701 C 40
2
129. Make up H2 to Recycle Compressor K.O. Drum PI-2701 Kg/cm g 38.9
130. make up H2 to Recycle Compressor K.O. Drum FIC-2701 Nm3/hr 6944
Recycle gas from Recycle Compressor K.O. drum
131. PI-2705 Kg/cm2g 14.4-21.4
to Recycle compressor
132. H2 from Recycle Compressor to HDS Section FI-2803 Nm3/hr 35145
133. H2 to HDS section FI-2804 Nm3/hr 35145
Gasoline from Separator to Stabilizer o
134. TI-2901 C 41
Feed/Bottom Exchangers
135. Stabilizer Feed from Separator Drum PI-2901 Kg/cm2g 9
Heavy Gasoline from Heavy Gasoline Trim Cooler
136. FI-2901 M3/hr *
to MS POOL
Gasoline after Stabilizer Feed/Bottom Exchangers
137. PI-2903 Kg/cm2g 7
to stabilizer
Heavy Gasoline from Stabilizer Bottom to o
138. TI-2903 C 225-226
Stabilizer Feed/Bottom Exchangers
o
139. Heavy Gasoline after Heavy Gasoline Trim Cooler TI-2903 C 40
Heavy Gasoline from Stabilizer Feed/Bottom o
140. TI-2905 C 106-107
Exchanger to Heavy Gasoline Trim Cooler
o
141. Heavy Gasoline to MS POOL via Storage TI-2909 C 40
142. Heavy Gasoline from Stabilizer Bottom Pumps PI-2909 Kg/cm2g 9.5
Heavy Gasoline at the bottom of Stabilizer
143. LIC-3001 mm *
Column
144. Stabiliser reflux from, stabiliser Reflux Pumps FIC-3001 M3/hr 15
o
145. Stabilizer Feed TI-3002 C 168-169
3
146. VHP Steam to Stabilizer Reboiler FIC-3002 M /hr 9.7
2
147. Vap. Gasoline from Stabilizer overhead PI-3003 Kg/cm g 6.8
S.
Description Tag no. Unit Value
No.
From Stabilizer bottom to Stabilizer Feed/Bottom
148. FIC-3003 M3/hr 106
Exchangers
Stabilizer overhead to Stabilizer overhead o
149. TI-3004 C 134-140
Condenser
150. Vap. Gasoline below 1st tray in Stabilizer PI-3004 Kg/cm2g 7
151. VHP Condensate Pot for Stabilizer column LIC-3004 MM *
o
152. Top of Stabilizer column TI-3005 C 160-200
153. Gasoline vapour at the top of Stabilizer column PI-3005 Kg/cm2g 6.9
o
154. Inside Stabilizer column below the feed plate TI-3006 C 203-217
Treated Heavy Gasoline from the bottom of o
155. TI-3013 C 225-226
Stabilizer
Heavy Gasoline from the bottom of Stabilizer to o
156. TI-3009 C 221
VHP steam reboiler
Heavy Gasoline from VHP steam reboiler to o
157. TI-3010 C 225
Stabilizer
7.4 ALARMS:
S. No. Descriptions Tag no. Unit Value
o
1. Mixed stream of FCC Gasoline from TAHH-1105 C 77
FCC unit & Storage to SHU FEED
DRUM
o
2. Gasoline & H2 at the inlet of SHU TAL-1301 C 60
FEED/EFFLUENT EXCHANGER
o
3. Reactor feed from SHU FEED/Effluent TAL-1304 C 80
Exchanger to SHU Preheater
o
4. Reactor feed stream from SHU TAH-1401 C TAH-210
Preheater to SHU Reactor
o
5. Reactor feed stream from SHU TAL-1401 C TAL-150
Preheater to SHU Reactor
o
6. A Bypass line of reactor feed stream to TAH-1402 C TAH-210
SHU reactor
o
7. Gasoline & H2 stream Inside SHU TAH-1403 C TAH-225
Reactor on the first bed of catalyst
o
8. Gasoline & H2 stream Inside SHU TAHH-1403 C TAHH-230
Reactor on the first bed of catalyst
o
48. Stabilizer Feed TAL-3002 C TAL-163
th o
49. Above the 17 plate of Stabilizer TAH-3006 C 227
column
50. Above the 12th plate of Stabilizer TAH-3007 o
C 227
column
51. Feed Surge Drum pressure control PAH-1101 Kg/cm2g 3.5
2
52. FCC Gasoline from FCC unit to SHU PDAH-1106 Kg/cm g 0.5
Feed Surge Drum
53. Gasoline & H2 stream before & after PDAH-1208 Kg/cm2g 0.7
1ST SHU Feed/HDS Effluent
Exchanger
54. Gasoline & H2 stream before & after PDAH-1302 Kg/cm2g 0.6
SHU Feed/Effluent Exchanger
55. Gasoline & H2 stream before & after PDAH-1308 Kg/cm2g 0.6
SHU Preheater
56. Gasoline & H2 stream before entering PAL-1403 Kg/cm2g 29.2
SHU Reactor
57. Gasoline & H2 stream after passing PAL-1407 Kg/cm2g 28
through the 1st bed of catalyst in SHU
Reactor
58. Gasoline & H2 stream before entering PDAH-1408 Kg/cm2g 1.75
SHU Reactor & after passing through
the 1st bed of catalyst in SHU Reactor
59. SHU Reactor Effluent PAL-1409 Kg/cm2g 27
2
60. Gasoline & H2 stream after 1st bed of PDAH-1410 Kg/cm g 1.75
catalyst in SHU Reactor & Effluent from
SHU reactor
61. Splitter overhead & splitter underflow PDAH-1506 Kg/cm2g 1
2
62. Light gasoline vapour in splitter reflux PAH-1601 Kg/cm g PAH-6.5
drum
63. Light gasoline vapour in splitter reflux PAL-1601 Kg/cm2g PAL-5.2
drum
64. Gasoline from splitter reflux pumps to PALL-1604 Kg/cm2g 4.2
top of splitter column
65. Vapour gasoline to HDS feed PAL-1904 Kg/cm2g 21
2
76. Vap. Gasoline from Stabilizer overhead PAL-3003 Kg/cm g PAL-6.5
2
77. Vap. Gasoline below 1st tray in PAH-3004 Kg/cm g 7.8
Stabiliser
3
78. FCC Gasoline Feed to SHU Feed FAL-1102 M /hr 117.6
Surge Drum
79. Gasoline SHU Feed FAL-1202 M3/hr *
3
80. Gasoline SHU Feed FALL-1205 M /hr 111.7
3
81. H2 to SHU section FAL-1203 Nm /hr 1000
3
82. VHP Steam to Reboiler Splitter FAH-1501 M /hr 30.7
3
83. Separator drum boot drain FAH-2403 M /hr 5.6
3
84. Make up H2 to Recycle Compressor FAL-2701 Nm /hr 1284
K.O. Drum
85. H2 from Recycle Compressor to HDS FALL-2802 Nm3/hr 20832
FEED/EFFLUENT Exchanger
86. H2 from Recycle Compressor to HDS FAL-2803 Nm3/hr 20832
Section
87. H2 to HDS section FALL-2801 Nm3/hr 13020
7.6.1 PUMPS
75-P-05
FCC HEART CUT PUMPS 24.7 27.2 10.1 38.6 >8
A/B
75-P-06
QUENCH PUMPS 44.3 53.1 36.2 187.4 3.7
A/B
7.6.2 VESSELS:
7.6.3 COLUMNS:
7.6.4 REACTORS:
Tag No. Item Description Internal TL-TL Oper. Temp Oper Press
Dia (mm) (mm) C Kg/cmg
75-R-01 SHU REACTOR 1800 23420 200 30
75-R-02 HDS REACTOR 2500 12950 355 28.4
Sr. Tag Service Shell side Tube side Shell side Tube side
No. No. fluid fluid temp (C) temp (c)
IN OUT IN OUT
1 75-E-01 SHU Feed / HDS HDS Effluent SHU Feed 211 156 66 155
Effluent exchanger
2 75-E-02 SHU Feed / Effluent SHU Effluent SHU Feed 219 188 155 188
exchanger
3 75-E-03 SHU preheater VHP Steam SHU Feed 238 238 128 200
4 75-E-04 Splitter post condensor HC+H2 Cooling water 55 40 33 40
5 75-E-05 Light Gasoline cooler Light Gasoline Cooling water 65 40 33 40
6 75-E-06 FCC Heartcut cooler Gasoline Cooling water 65 40 33 40
7 75-E-07 Splitter reboiler VHP Steam HC 238 238 216 221
8 75-E-08 HDS Feed / Effluent HDS Feed HDS Effluent 174 312 370 207
A/B/C Exchanger
9 75-E-09 Reactor effluent trim HC Cooling water 65 40 33 40
cooler
10 75-E-10 Lean Amine preheater Lean Amine LP steam 40 50 128 128
11 75-E-11 Stabilizer Feed/Bottom Stabilizer Feed Stabilizer 225 107 41 169
A/B exchanger Bottom
12 75-E-12 Heavy gasoline trim Heavy Cooling water 65 40 33 40
A/B cooler gasoline
13 75-E-13 Stabilizer reboiler VHP steam Stabilizer 238 238 221 225
bottom
14 75-E-14 Stabilizer overhead trim Stabilizer Cooling water 65 40 33 40
cooler overhead
List of safety valves is already given in the previous section. Detail of relive
load summary such as relieve valve tag, location, set pressure, capacity, failure
scenarios considered are given in Flare Load Summary.
Sr.
CAUSE EFFECT
No.
ACTUATOR DESCRIPTION DEVICE ACTION DESCRIPTION
1 75-LAHH-1103 Very high level in 75-UV- Close FCC gasoline feed
SHU feed surge 1101
drum 75-UV- Close Hydrogenated
1102 gasoline recycle
2 75-PALL-1604 Very low pressure 75-P-03 stop Pump 75-P-03 A/B
at 75-P-03A/B operating protection
discharge 75-P-03 Start Spare pump auto
spare start
3 75-LALL-1701 Low level 75-P- Stop Light gasoline
04A/B pump stops
4 75-LALL-1505 C-01 chimney 75-P-05 Stop FCC heart cut
tray level low A/B pump stop
5 75-AT-2101 High O2 content 75-UV- close Air make up during
75-TAHH- Very High temp in 2101 regeneration
1403-1415 75-R-01
6 75-HS-1102A Case of fire 75-UV- Close Close SHU feed
1104 surge drum bottom
inventory valve
75-HS-1102A 75-P- Stops Stop 75-P-01 A/B
01A/B
7 75-LALL-1106 Very low level in 75-UV- Close Boot drain to OWS
SHU feed surge 1103
drum boot
8 75-PAHH-1510 Very high 75-UV- Close VHP steam to 75-
pressure at 1503 E-07 stop
splitter overhead
Operator action on these parameter enables the unit to match different feed
and product qualities provided they are within the basis of design of the unit.
theoretically in liquid phase. This may lead to problems with liquid distribution and
pressure drop.
The temperature increase in the selective hydrogenation reactor is a function
of the diolefin content and H2/HC ratio.
Moreover, reactions of oligomerisation can take place if the temperature is too
high, leading to gum formation. In practice, the operating temperature will be set
so that the exothermicity starts to be perceptible. The hydrogen make-up will be
adjusted so that the heavy FCC gasoline MAV is decreased below 2.(Diene value
< 0.5)
separator drum 75-V-03 is recycled and mixed with the HDS feed for olefin
dilution.
In AM case; selective mode, the exotherm in the HDS rector is controlled at
200C by the liquid quench of the HDS reactor.
Catalytic coke
During the catalyst cycle, coke may build-up on the catalyst surface within
the pores, reducing the reaction surface and consequently the activity. An
adjustment will be required on the Reactor inlet temperature to compensate for
this activity loss. This change is very gradual over the catalyst cycle and depends
upon the feed quality.
Coke formation due to coke precursors in the feed
This coke formation is due to a combined action of dissolved oxygen, rust
and temperature. Therefore, it is very important to be careful with the quality of
the feed especially to limit content of compounds containing the carbonyl bound
(C=O) and the rust content.
This formation of coke leads to a higher P in reactors and decreases the
catalyst cycle. The coke formation due to coke precursors in feed is more
important than catalytic coke.
The end of a catalyst cycle is reached when the following takes place:
The catalyst deactivation is such that it is no longer possible to meet the product
specifications.
The maximum allowable temperatures have been reached.
The pressure drop in the reactor is too high.
In this case, the catalyst must be regenerated ex-situ.
The hydrogen rate is set to decrease the MAV in the heavy FCC gasoline
product below 2.
reductions however, the operator may lower the reactor inlet temperature to
preserve the cycle length. It is recommended that, if an adjustment to a new
temperature level is considered, the reduction must be in increments no greater
than 2C until the new stable performance level is reached.
In general the following rules are valid:
In case of feed is to be increased: first increase the temperature, then
increase the feed rate.
In case of feed is to be decreased: first decrease the feed rate, then
decrease the temperature.
These measures are required to keep the safe side of the gasoline quality.
7.10.6 FEED QUALITY
1. Contaminant content
Feed quality is an indirect variable, a variable that the operator reacts to
rather than adjusts for performance control. The unit is designed for a particular
feedstock with a maximum design level of sulfur, Nitrogen, Mercury, Arsenic and
with other contaminant levels defined within the normal range of most crudes. As
the feed quality changes during processing of different crudes i.e. higher levels of
nitrogen and sulfur, the operator must raise the reactor inlet temperature to
maintain unit performances.
Prior to a crude change, the operator must be made aware of potential higher
contaminant levels than the previous crude by reviewing the crude essays. For
new crude, the raw gasoline feed to the unit must be thoroughly analyzed for all
contaminants including metals. If possible, this must be done prior to feeding the
unit but if not, as early as possible. This will avoid a higher rate of catalyst
saturation due to higher metals content. Moreover, it is important to be careful
with the content of compounds with carbonyl bound (C = O) and of rust. Indeed, a
combined action of dissolved oxygen, rust and temperature leads to a coke
formation, which increases P in reactors and decreases the catalyst cycle.
2. Di-olefin content
Di-olefin content higher than the design means an increased exothermicity for
the Di-olefin reactor. As there is no quench or diluent on them, an increase of
diolefin content in the feed induces a higher T across the catalyst bed. This
results in a shorter cycle length. If all the di-olefins are not hydrogenated in the
Diolefin reactor, they will reduce the second reactor cycle length.
3. Olefin content
Olefin content higher than the design in the heavy FCC gasoline fraction of
the feed means an increased exothermicity for the HDS reactor. This can be
compensated, in order to keep the same WABT, either by decreasing the inlet
temperature or by higher quench and diluent flow rates.
If these conditions are not sufficient, then the feed flow rate has to be
reduced, while maximizing the diluent rate and quench.
For a planned shutdown some work can be done in advance, such as:
Prepare blind lists and blind list accounting procedures for required isolations.
Have test equipment onsite for:
Explosive Gas and Hydrogen Analyzers
Reduce unit capacity to 60% of normal feed rate. It should not be necessary
to adjust the reactor inlet temperatures immediately before the shutdown.
Maintain hydrogen gas flow rate and make-up hydrogen through selective
hydrogenation reactor.
Disconnect the level cascaded controllers on the separator drum 75-V-03, and
on the Stabilizer bottom while keeping normal flow rates.
Switch the products to off-spec storage. (light cut, heart cut and heavy FCC
gasoline)
Shut down steam flow to the SHU feed steam heater 75-E-03 to decrease
inlet temperature to selective hydrogenation reactor at least down to 10C
below the normal temperature.
The make-up H2 supply to the selective hydrogenation reactor is also
stopped.
Reduce the temperature at the inlet to the first HDS reactor 75-R-02 by
decreasing firing in 75-F-01 at a rate of 40C per hour down to 180C.
Close block valves on liquid flow outlet from the separator drum 75-V-03 when
level decreases below 30%.
Shutdown DEA solution circulation through the Amine absorber and open the
bypass line of absorber.
When the selective hydrogenation reactor temperature is at least 10C below
the normal temperature, and levels in splitter and stabilizer have decreased,
shut-off level control valves. The evacuation of stabilizer column 75-C-03
depends on pressure in the column. In order to avoid sudden decrease of
pressure, the reflux flow rate must be reduced and fuel gas flow rate to
reboiler heater is controlled consequently. The splitter and stabilizer shall
operate at total reflux.
Stop the fresh feed to the selective hydrogenation reactor 75-R-01.
Close the block valves on the Splitter bottom. The SHU and HDS sections are
now isolated.
The circulation of hydrogen through the HDS reaction section is continued for
a period of two hours to strip out hydrocarbons from the catalyst.
Important notes
1. Entry of personnel to vessels needs particular safety precautions. Vessels
operating in presence of H2S may contain sulfides adhered to the surface of
metal. These sulfides are pyrophoric and may release H2S. The forced
ventilation and permanent supervision is required on vessels subject to work
of personnel inside these vessels.
2. The nitrogen purge does not mean that vessel is ready for entering of
personnel. Nitrogen is suffocating gas leading to death. The vessels must be
fully vented and tested for oxygen content before admission of personnel
entry. The "dead" spaces in vessels such as down comers, separation weirs,
etc. must be considered.
This unit is equipped with certain emergency shutdown controls which will
automatically place the unit in a non-hazardous status should a major failure
occur. The actions of the emergency shutdowns are aimed at protecting (a) the
personnel and (b) the catalyst and equipment from heavy coking or serious
damage.
Personnel and equipment protection also results from the following:
Personnel having a satisfactory knowledge of the safe operating and
shutdown procedures.
A compliance with the safety rules in plant construction i.e. safety distances,
adequate orientation etc.
The installation of adequate fire and gas detection devices and fire fighting
equipment.
Adequate operator safety awareness and procedures training.
An excessive catalyst temperature gain which can change the structure of the
alumina (> 700C). To avoid damaging the catalyst structure, bulk
temperature must never exceed 500C. Note that the design temperature of
the reactor (under design pressure) is much lower.
The presence of hydrocarbons without a sufficient hydrogen quantity which
would result in a rapid coke deposit and the possible agglomeration of catalyst
particles.
The following sections cover most situations operators may have to face
according to Axens' operating experience. All operating personnel must study
and fully understand the steps to be taken in such situations prior to the unit start-
up.
Many of these situations are handled by automatic shutdown trips. These trips
must always be operational, by-passing must be kept to a minimum e.g. during
start-up, transient periods only.
The following procedures include all the actions to be taken by the operator
assuming no action by the automatic devices. Some of the following situations
may end up in an emergency shutdown. If the right and prompt action is taken,
an orderly normal shutdown is possible.
HDS section:
In case of short period loss of feed to the HDS section,
Maintain H2 circulation.
Allow the stabilizer to operate on total reflux.
When the level in the stabilizer starts to fall, close the valves on the stabilizer
bottom and heavy FCC gasoline line to storage.
Maintain these conditions until feed is available again. Maintain pressure in
the HDS reaction section by hydrogen make-up.
Start-up again from former current reactor operating temperature if the feed is
recovered shortly. If not proceed with the normal shutdown as previously
explained (Refer to section Shutdown of the unit/ Normal shutdown/ Short
duration shutdowns). Do not leave catalyst under a hot hydrogen circulation for
more than 12 hours, unless the H2S content in the recycle is maintained between
100-200 ppm vol. Note also that an increased H2S content while circulating hot
hydrogen would be the sign of a catalyst desulfiding and would require the
cooling down of the catalyst bed.
The following is only an overview of the steps to be taken during the discovery
of a leak resulting in a fire. This section will be defined in detail by the Unit Owner
and the Engineering Contractor according to the refinery safety philosophies and
will include any safety devices (hardware or software) which may be added
during detailed engineering. The following steps are described from a process
point of view, mainly aimed at avoiding runaway reactions and protecting the
equipment and catalyst.
Shut-off fuel to heater by activating the fuel gas emergency shutdown system
from the control room.
Shutdown the raw gasoline feed pump, close the splitter and stabilizer feed
and block-in.
Shut-off steam to the reboiler of the splitter and stabilizer, and to the SHU
feed steam 75-E-03.
Isolate the unit: Block the feed, product and hydrogen make-up gas lines.
Isolate the reaction section from the feed, splitter and stabilizer sections.
Depending on the severity of the leak and its location, shutdown the hydrogen
recycle compressor immediately, block-in and depressurize the HDS reaction
section to the flare.
Depressurize the splitter and stabilizer sections to the flare.
Drain all the vessels to the hydrocarbon blowdown.
As the depressurized hot vessels cool down, watch the pressure and inject N2
as necessary to avoid a vacuum.
Nitrogen purging and steam out should be considered for the splitter and
stabilizer circuits.
If a fire has occurred, then all the steps above will be taken while the fire
fighting is taking place. Note, however, that the depressurizing step may be
needed sooner than described above depending upon the gravity of the situation.
If a small leak occurs in the heater, the hydrocarbons will ignite immediately in
this confined area. Open the snuffing steam and the damper (if possible) and
maximize the draft to keep the fire under control within the heater box.
In case of extreme emergency, the reaction section can be depressurized to
the flare, using the quick depressurization valve by actuating HS-2401
emergency shut down push button.
Process vessels, heater, compressors are fitted with switches which actuate
the corresponding devices to avoid damage of equipment in case that operating
variable exceeds the threshold limits. Hereafter are summarized the causes and
effects for the unit shutdown interlocks. Causes and effects for the equipment
safety interlocks are summarized in the Process Book. Other interlocks have to
be specified by Engineering Contractor or Manufacturer of equipment (heater,
compressor, etc).
In several cases, a number of actions are carried out by the emergency safety
sequences. But operators must always check the satisfactory completion of the
sequence and complement it as described. In addition they must be able to
perform the safety sequence in manual mode, if needed.
A few actions through hand-switches are left to operators judgement, who can
anticipate the automatic action such as reactors depressurization.
saturation or higher diolefins content in the feed. Monitoring of the MAV at the
splitter bottom should be used to adjust the make-up H2 rate.
11.1 GENERAL
Control tests provide the information to the operating staff for making
necessary adjustments to get the maximum output and on-spec quality
products. The control tests are to be made at all steps to monitor the intermediate
and final products whether or not they are at the desired specification. Samples
are taken and analysed at regular intervals such that the operation of the plant
are monitored and any deviation (from specification will indicate some mal
operation / malfunction of the plant which can be spotted and rectified in time
without undue loss of time and product. Sometimes, samples are taken to find out
the effect of certain changes brought about in the operating conditions. The
samples are to be taken with great care so that the samples are representative
samples. The frequency of sampling, the type of analysis and points where
samples are to be taken are attached as annexure. During guarantee tests some
additional samples can be taken at higher frequencies that is also specified in the
technical procedures prior to test run. The following guidelines should be followed
while collecting samples.
uncontrolled rate. Never tap the line to release the plugging. Call the
maintenance gang to properly unplug the line. In case of congealing type
samples, sample point should be equipped with copper coil type steam tracer.
It should be ensured that steam tracing line is functioning normally.
4. The operator taking the sample should be careful to stand in a position such
that the liquid does not splash on him and he has unobstructed way out from
the sample point in case of accident.
5. While taking dangerous toxic material for sampling, it will act as an observer
for safety. Proper gas mask is to be used. It is advisable to stand opposite to
wind direction in case of volatile toxic liquid.
6. Sample should be collected in clean, dry and stoppered bottle. In case of
congealing samples use clean dry ladle.
7. Rinsing of the bottle should be thorough before actual collection.
8. Before collecting, ensure that the line content has been drained and fresh
sample is coming.
9. Gradually warm up the sample bottle / metallic can by repeated rinsing before
collecting the sample.
10. Stopper the bottle immediately after collection of sample.
11. Attach a tag to the bottle indicating date, time, and name of the product and
tests to be carried out.
12. A few products suffer deterioration with time.
For example, the colour of the heavier distillates slowly deteriorates with time.
So these sampls should be sent to laboratory at the earliest after collection.
1. The samples after collection should be kept away from any source of ignition
to minimise fire hazard.
2. Volatile samples (e.g. naphtha) should be collected in bottles and kept in ice
particularly for some critical test like RVP.
The person who is taking sample should use personal protection appliances
like apron, gas mask and hand gloves to protect himself.
8. Send sample bomb to laboratory for analysis. Protect the bomb from heat
exposure.
c) Gas Sample
For collection of gas sample that are not under high pressure and
temperature, rubber bladders are used. For the operations under vacuum or low
pressure, aspirator is used. For representative sample, purge the bladder 3 to 4
times with the gas and then take t he final sample. Use of 3 ways valve with
bladder / aspirator will facilitate purging and sampling.
Sample bombs are to be used for taking gas samples from high pressure and
high temperature source. Procedure mentioned under high pressure liquid
sampling (flashing type) is to be used.
12.1 INTRODUCTION
Safety of personnel and equipment is very important. Ignorance of the
details of the unit or the techniques of safe and efficient operation reduces the
margin of safety of personnel and subjects the equipment to more hazardous
conditions. All the operating and maintenance crew therefore must be fully
familiar with the equipment and materials being handled in the unit, and
recognise the hazards involved in handling them and the measures taken to
ensure safe operations.
Since the unit handles with one of the most potential source of fire and
explosion like LPG; therefore adherence of safety rules should be given uphill
importance.
Operators must continually inspect each equipment and flanges for leaks.
All leaks require immediate action. The pressure reduction results in heating of
hydrogen contrary to hydrocarbons, or other gases which are cooled down
(Joule-Thomson effect). When heated above its ignition temperature by pressure
release from high pressure the hydrogen gas starts to burn in presence of air.
a) Physical properties
Physical state : gas
Color: : colorless
Boiling point : -79.2F (-61.8C)
Melting point : -117.2F (-82.9C)
Molecular weight : 34.08
Specific gravity/air : 1.189
d) Personal protection
Gas mask of appropriate type or positive air mask should be used.
e) First aid
A person unconscious in an atmosphere which may be contaminated with
hydrogen sulfide should be assumed to have hydrogen sulfide poisoning. This is
a serious medical emergency and requires immediate attention. The affected
individual should be immediately removed to a clean atmosphere, so that
rescuers are not also exposed to hydrogen sulfide. Artificial respiration should be
resorted immediately, if necessary, and the victim should be kept warm and at
rest.
DMDS
The material safety data sheet must be obtained from the
manufacturer/supplier.
Catalysts
The material safety data sheets for HR 845, HR 806, HR 841, ACT 065, ACT 077
and ceramic balls are attached in Attachment
c) Entry permits
Entry permits are required for entering enclosed spaces such as vessels,
sewer, pits, trenches, etc.
The use of any tool or machinery, which could provide a source of ignition, is
forbidden. Also, prior to entry it should be ensured that area is well ventilated and
the oxygen content in air is about 21% by volume. A fresh airflow to be ensured
in the enclosed space through out the duration of work. A gas test for H2S and
flammable gases should also be performed before entry. A person should also be
on alert outside the enclosed space for rescue in case of emergency. Procedure
for carrying out work and rescue plan shall be formulated before commencement
of work.
No one shall be allowed to enter the vessel or other enclosed spaces without
suitable protective clothing until the vessels or the enclosed spaces become
safe for entry by means of proper isolation, proper ventilation and suitable
check of the atmosphere inside and availability of rescue person outside the
enclosed equipment.
If welding or hot work is to be done ensure that
Fire fighting system is ready
Close the neighbouring surface drains with wet gunny bags
Keep water flowing in the neighbouring area to cool down any spark.
Responsible operation supervisor should be present at the place of hot work
till the first torch is lighted.
Note:Open a vent on the upper part of the vessel to allow gases to escape during
filling and to allow air inside the vessel during draining. Ensure proper ventilation
inside the vessel by opening all manholes. For hydrocarbon or other gases,
pressurise the vessel with N2 or gas and fill in the liquid and drain under pressure.
This is to avoid hydrocarbon going to atmosphere.
After the above operations have been made, a safety permit should be
issued for carrying out the work. A responsible operating supervisor should be
personally present at the place of hot work till the first torch is lighted. Hot work
should be immediately suspended if instructed by the supervisor or on detecting
any unsafe condition.
When people have to enter a vessel for inspection or other work, one
person should stand outside near the manhole of the vessel for any help needed
by the persons working inside. The person entering the vessel should have tied
on his waist a rope to enable pulling him out in case of urgency. Detail procedure
for preparation for vessel entry is given in next sub-section.
drain connections in the same or adjoining units. Any hazards found in the
survey should be isolated or removed.
Vessel Access
Safe access must be provided both to the exterior and interior of the vessel
to be entered. The exterior access should be a solid, permanent ladder and
platform or scaffolding strong enough to support the people and equipment that
will be involved in the work to be performed.
Access to the interior should also the strong and solid. Scaffolding is
preferred when the vessel is large enough to permit it to be sued. The
scaffolding base should rest firmly on the bottom of the vessel and be solidly
encored. If the scaffolding is tall, the scaffolding should be supported in several
places to prevent sway. The platform boards should be sturdy and capable of
supporting several people and equipment at the same time and also be firmly
fastened down. Rungs should be provided on the scaffolding spaced at a
comfortable distance for climbing on the structure.
If scaffolding will not fit in the vessel a ladder can be used. A rigid ladder is
always preferred over a rope ladder and is essential to avoid fatigue during
lengthy periods of work inside a vessel. The bottom and top of the ladder should
be solidly anchored. If additional support is available, then the ladder should also
be anchored at intermediate locations. When possible, a solid support should
pass through the ladder under a rung, thereby providing support for the entire
weight should the bottom support fail. Only one person at a time should be
allowed on the ladder.
When a rope ladder is used, the ropes should be thoroughly inspected prior
to each new job. All rungs should be tested for strength, whether they are made
of metal or wood. Each rope must be individually secured to an immovable
support. If possible, a solid support should pass through the ladder so that a
rung can help support the weight and the bottom of the ladder should be fastened
to a support to prevent the ladder from swinging. As with the rigid ladder, only
one person should climb the ladder at a time.
procedure. Each point of entry and any dead areas inside of the vessel, such as
receiver boots or areas behind internal baffles, where there is little air circulation
should be checked.
Fresh air can be circulated through the vessel suing an air mover, a fan, or,
for the cases where moisture is ca concern, the vessel can be purged using dry
certified instrument air from a hose or hard piped connection. When an air mover
is used, make certain that the gas driver uses plant air, not nitrogen, and direct
the exhaust of the driver out of the vessel to guarantee that this gas does not
enter the vessel. When instrument air is used, the Licenser technical adviser
must confirm the checking of the supply header to ensure that it is properly lined
up. It should be confirmed that there are no connections where nitrogen can enter
the system (Sometimes nitrogen improperly used as a backup for instrument air
by some refiners). The fresh air purge should be continued throughout the time
that people are inside of the vessel. The responsible control room should be
informed that instrument air is being used for breathing so that if a change to
nitrogen is required the people are removed from the affected vessel.
A minimum of one fresh air mask for each person entering the vessel and at
least one spare mask for the Manway watcher should be provided at the vessel
entry. These masks should completely cover the face, including the eyes, and
have a second seal around the mouth and nose. When use of the mask is
required, it must first be donned outside of the vessel where it is easy to render
assistance in order to confirm that the air supply is safe. Each mask must have a
backup air supply that is completely independent of the main supply. It must also
be independent of electrical power. This supply is typically a small, certified
cylinder fastened to the safety harness and connected to the main supply line via
a special regulator that activates when the air pressure to the mask drops below
normal. The auxiliary supply should have an alarm, which alerts the user that he
is on backup supply and it should be sufficiently large to give the user 5 minutes
to escape from danger.
plant, the entire unit can be isolated by installing blinds at the battery limits rather
than by individually isolating every vessel nozzle.
The operating personnel should be fully conversant with Fire fighting system
provided in the unit. All of them should have adequate fire fighting training and
will serve as an auxiliary Fire Squad in the event of a fire breakout. It will be the
primary responsibility of unit personnel to fight the fire at the very initial stage
and, at the least, localise it.
Major Fire fighting facilities provided in the unit comprising the following:
b) Foam System
For containing large Hydrocarbon fires, foam systems are useful. They
have inherent blanketing ability, heat resistance and security against burn back.
Low expansion foam is used for hydrocarbon oil fire.
Foam can be applied over burning oil pool with the help of foam tenders/foam
delivery system.
d) Fire Signal
Break Glasses have been provided at strategic locations of unit to see fire
alarm in fire station. If a fire is sighted, glass of window should be smashed,
causing fire alarm switch to actuate. This is an emergency call & should be
periodically tested for proper functioning.
e) Steam Smothering
LP Steam hose connections have been provided at every convenient point
inside unit. Steam lances of standard 15M length can be fitted with these hose
stations. Wherever hydrocarbon leakage is detected which is likely to catch fire,
Steam blanketing may be done. Apart from diluting combustible Hydrocarbons,
steam prevents atmospheric oxygen from taking part in combustion & thus help in
extinguishing fire. However, steam should never be applied on large pool of
hydrocarbon fire. Direct application of steam on burning oil may result in spillage
of burning hydrocarbon & spread of fire. Similarly use of firewater on hot oil
surfaces may cause sputtering & spread of fire.
Foot protection
Safety shoes are to be worn for foot protection.
Ear protection
Whenever persons are required to be work in noisy areas proper ear protection
device such as earplug etc, is to be used.
Breathing apparatus
Whenever persons are required to work or enter an area of high
toxic/aromatic/hydrocarbon vapour concentration, wear appropriate respiratory
protection, such as self-contained breathing apparatus or an air mask with an
external air supply.
13.1 GENERAL
This section covers the general procedure for operation and trouble
shooting of commonly used equipment like pumps, heat exchangers and furnace
etc. For specific information and more detail refer to vendor's manuals.
Start-up
Inspect and see if all the mechanical jobs are completed.
Establish cooling water flow where there is such provision. Also open steam
for seal quenching in pumps having such facilities.
Check oil level in the bearing housing, flushing may be necessary if oil is dirty
or contains some foreign material.
Rotate the shaft by hand to ensure that it is free and coupling is secure.
Coupling guard should be in position and secured properly.
Open suction valve. Ensure that the casing is full of liquid. Bleed, if necessary,
from the bleeder valve.
Energise the motor. Start the pump and check the direction of rotation. Rectify
the direction of rotation if it is not right.
Check the discharge pressure. Bleed if necessary to avoid vapour locking.
Open the discharge valve slowly. Keep watch on the current drawn by the
motor, if ammeter is provided. In other cases check at motor control centre.
In some pumps a by-pass has been provided across the check valve and
discharge valve to keep the idle pump hot. In such pumps, the by-pass valve
should be closed before starting the pump. It should be ensured that casing of
these pumps are heated up sufficiently prior to starting of the pump to guard
against damage of the equipment and associated piping due to thermal shock.
Shutdown
Close discharge valve fully.
Stop the pump
a) If pump is going to remain as standby and has provision for keeping the pump
hot, proceed as follows:
Open the valve in the by-pass line across the discharge valve and check
valve.
The circulation rate should not be so high to cause reverse rotation of idle
pump and also overloading of the running pump.
b) If pump is to be prepared for maintenance, proceed as follows:
Close suction and discharge valves.
Close valve on check valve by-pass line, if provided.
Close cooling water to bearing, if provided. Also shut off steam for seal
quenching, if provided.
Slowly open pump bleeder and drain liquid from pump if the liquid is very hot
allow sufficient time before draining is started. Ensure that there is no
pressure in the pump. Also drain pump casing.
Blind suction and discharge and check valve by-pass line and flare connection
if any.
Cut-off electrical supply to pump motor prior to handling over for maintenance.
Trouble Shooting
a) Pump not developing pressure
Bleed to expel vapour/air
Check the lining up in the suction side.
Check the suction strainer.
Check the liquid level from where the pump is taking the suction the suction.
Check pump coupling and rotation.
Get the pump checked by a technician.
b) Unusual Noise
Check the coupling guard if it is touching.
Check for proper fixing of fan and fan cover.
Check for pump cavitations.
Get the pump checked by a technician.
d) Hot Gland
Adjust cooling water if facility exists.
Slightly loosen the gland nut, if possible.
Stop the pump and hand over to maintenance.
Arrange external cooling if pump has to be run for sometime.
e) Unusual Vibration
Check the foundation bolts.
Check the fan cover for looseness.
Stop the pump and hand over to maintenance.
f) Leaky Gland
Check the pump discharge pressure.
Tighten the gland nut slowly, if possible.
Prepare the pump for gland packing or adjustment/replacement of mechanical
seal as the case may be.
13.3.1 GENERAL
The unit has a number of heat exchangers, air coolers. Suitable valves for
bypassing and isolation were provided wherever necessary to offer the required
operational flexibility.
The exchangers have been provided with draining and flushing connections.
The coolers and condensers have been provided with TSV's on the cooling
waterside to guard against possible rise of pressure due to faulty operations with
the safety release to atmosphere. Temperature gauges or Thermowells have
been provided at the inlet and outlet of exchangers. Where water is the cooling
medium, no temperature measurement is provided for water inlet temperature,
which is the same as cooling water supply header temperature.
13.3.3 EXCHANGERS
Shell and Tube type heat exchangers can be broadly classified into following types:
Water Coolers/condensers
Steam heaters (Reboiler)
Exchangers
Start-up/shut down procedures for each unit shall vary slightly from case to case.
However, general start-up/shut-down procedures are discussed in the following
paragraphs.
START-UP
After the heat exchanger has been pressure tested and all blinds removed,
proceed as follows:
Open cooling medium vent valve to displace non-condensable (air, fuel gas,
inert gas etc.) from the system. Ensure the drain valves are capped. For high-
pressure system, drain valves should be flanged. This activity is not required if
gas is the medium.
Open cooling medium inlet valve. Close vent valve when liquid starts coming
out through it, then open cold medium outlet valve and fully open the inlet
valve also. Where cold medium is also hot, warming up of cold medium side
gradually is also essential.
Open hot medium side vent valve to displace non-condensable (air, fuel inert
gas etc.). Check that the drain is closed and capped. This activity is not
required if gas is the medium.
Crack open hot medium inlet valve. When liquid starts coming out from the
vent valve, close it. Open hot medium inlet valve and then open the outlet
valve fully. In case of steam heaters, initially the condensate shall be drained
to sewer till pressure in the system builds up to a level where it can be lined
up to the return condensate header.
In case by passes are provided across shells and tube side, gradually close
the bypass on the cold medium side and then the bypass across the hot
medium side.
Check for normal inlet and outlet temperatures. Check that TSVs are not
popping.
The operation of inlet and outlet valves should be done carefully ensuring that
the exchangers are not subjected to thermal shock.
In case of coolers/condensers, adjust the water flow to maintain the required
temperature at the outlet.
For avoiding fouling, velocity of water should be at least 1 m/sec in a
cooler/condenser.
Shutdown
Shut down of an exchanger, coolers, condenser is considered when the equipment
is to be isolated for handling over to maintenance while the main plant is in
operation. The following is the suggested procedure for isolation of the piece of
equipment
Isolate the hot medium first. In case both hot and cold medium are from
process streams, exchanger shall remain in service till the hot stream has
cooled down enough.
In case of a cooler, adjust cooling water flow to the cooler, which is in line so that
product temperature is within allowable unit.
Isolate the cold medium next.
Drain out the shell and tube sides to OWS/Sewer/Closed blow down system as
applicable. In case flushing oil connection is given flush the exchanger to CBD.
Ensure that the CBD drum has sufficient usage to receive the flushing of the
exchanger
Depressurise the system to atmosphere/flare/blow down system as applicable.
Purge/flush if required. This is particularly important in congealing services.
Blind inlet and outlet lines before handing over the equipment for maintenance.