Prefix RANKING
Ward 14 Office 2017 List
14 W 33RD DENISON ARCHWOOD C/D Large divots/craters for duration of area
W 48TH HOUSE #3590 HOUSE #3609 Large sections in very bad shape, very poor cement job done after utility
work.
14 W 56TH DENISON STORER D Craters for duration
14 W 62ND DENISON STORER F Rough terrain for duration of street. Extensive impact of resurfacing due to
numerous homes on street
14 W 86TH WENTWORTH DENISON C/D Large sections in very bad shape, heavily overpatched.
14 MAPLEDALE W 33RD PEARL D Craters and poorly sealed utility cuts throughout. Confirm cost to W. 36th;
discusss strategy to complete in 2-3 years based on length and expense,
similar to what was done on Archwood.
2016 COMPLETIONS
14 CARLOS W. 47TH W. 52ND
14 W. 47TH DENISON CARLOS
14 CARLYLE W. 34TH FULTON
2015 COMPLETIONS
14 W 38TH ARCHWOOD DENISON D- 2015 Final. ONLY PATCH 20x30 section in F condition.
14 RIVERSIDE W 39TH PEARL C-/D 2015 Final (worst sections from Pearl-W. 39 & 35th-39th)
14 W 39TH PLACE POE DAISY F 2015 Final
14 W 52ND EICHORN STORER C-/D 2015 Final
14 W 58TH DENISON STORER D- 2015 Final
14 CARLOS W 49TH W 52ND D- 2015 Final
14 CARLYLE W 34TH FULTON D- 2015 Final
14 SCRANTON W 25TH EGLINDALE C/D 2015 Final High Priority Metrohealth/EMS route
2014COMPLETIONS
14 W 17TH BRAINARD VALENTINE
14 W 35TH RIVERSIDE MAPLEDALE
14 W 39TH ARCHWOOD MAPLEDALE
14 W 61ST DENISON BARBERTON
14 W 67TH DENISON BARBERTON
14 VALENTINE (SPOT RESURFACING) STEEL YARD LOOP W 18TH
14 WOODBRIDGE W 32ND INTERSECTION (ADA RAMPS ONLY)