KatniSingrauli Doubling

Status as on 05.09.2017
(EDW/RB Report at 1715 Hrs )

1. Year of Sanction PB Item No. 2. CCEA Approval


10 2015-16
3. Estimated Cost 1762.94 Cr. 4. Sanctioned Cost Rs. 1762.94 Cr.
5. Anticipated Cost 1762.94 Cr. 7. States (Districts) MP (Katni, Umaria,
6. Funding Pattern covered Shahdol, Seedhi and
Singrauli)
8. Target : 2020-21 9. Expenditure till March Rs. 254.10 Cr.
17
10. Expenditure in F.Y. 2017- 17.88 Cr 11. Cumulative Rs. 271.98Cr.
18 till last month expenditure
12. Electrification of Existing 272.53 Cr. 12 Year of Sanction PB Item No. 58 year
Line 2015-16

Land Acquisition details : Provision for acquisition of (1) Private Land 11.21 Hectare (2) Forest Land
7.74 Hectare have been made in DPR
Action Plan for Land
1 Process will be initiated by WCR if required
Acquisition
About 23.45 Km. stretch lies in Sanjay Dubri National Tiger Reserve
2 Forest Clearance and Wild Life Sanctuary. This will require clearance from Forest
Department.

Contracts Finalized
Value Award Dated
Name of Work
(in Cr)
Topographical Survey and Preparation of Index plan &
1 0.15 25.11.2016
Section and Detailed Yard Plan
2 Earth Work &Minor Bridges I(Katni Beohari) 139.79 25.01.2017
3 Earth Work &Minor Bridges -II (Marwasgram Singrauli) 120.38 27.01.2017
4 Geo-tech investigation from New Katni to Beohari section 0.69 17.02.2017
Geo-tech investigation from Marwasgram to Singrauli
5 0.58 08.03.2017
stn.
Geo-tech investigation from Beohari to Marwasgram
6 0.20 31.03.2017
Singrauli stn.
7 GAD &Design of Major and Important Bridges 1.67 31.05.2017
8 Steel Superstructure of major & important bridges, Pkg-I 29.81 Awarded on 22.08.2017
9 Steel Superstructure of major & important bridges, Pkg-II 27.60 Awarded on 28.08.2017
10 Steel Superstructure of major & important bridges, Pkg-III 20.64 Awarded on 29.08.2017
11 NDT for minor bridges 0.06 Awarded on 14.08.2017
Electrical tenders
12 a. 2 TSS 19.0 Awarded on 30.06.3017
b. 2 Tower Wagons 8.0 Awarded on 24.04.2017
Supply of Signalling and Telecom cables for infringement 2.17 Tender awarded on
13
removal and at Gondawali station 31.07.2017
TOTAL 370.74
Status of Contracts yet to be Finalized
Value(in
Name of Work Planning for Award
Cr)
CIVIL WORKS
A NIT already invited
21.28 Combined Tender invited on
02.05.2017, opened on 23.05.2017,
extended to 07.06.2017 but no bid
Foundation & Substructure of Major & important bridges ( 2 received, open tender being
1
pkg.) processed. 2 packages NIT advertised
on 10th August 2017& 04th Sept 2017.
Tender opening on 7th Sept & 25th Sept
2017.
Supply of sleepers & special sleepers for targeted section ( 1 1.26 NIT on 24th August 2017 opening on
2
package) ( 2017-18) 14th Sept. 2017
9.98 NIT on 10th August.2017 opening
3 Ballast supply for targeted section (2 packages( 2017-18))
opened on 01st Sept.2017.
Track Fittings and track linking for targeted section (2 18.61 NIT on 13thAugust 2017 opening on
4
packages) ( 2017-18) 07th Sept.2017
38.09 NIT on 06th Sept..2017 opening on 27th
5 Residential Quarters ( 1 package)
Sept.2017
TOTAL 89.22
B Tenders in the process of invitation
1 Station, Platform, offices and service building 39.55 September 2017
2 E/W , imp. Bridge, drain, retaining wall for Pkg III 100.38 September 2017
3 FOBs & P.F Sheds 27.54 September 2017

TOTAL
167.4
7
C Tenders at Planning Stage
1 Foundation & Substructure of Major & important bridges 83.30 September02017
2 ROBs including girders 3.18 October 2017
TOTAL 86.48
OHE WORKS FOR ELECTRIFICATION
Tenders pertaining to Electrical work.
a. 2 TSS ( Doubling & Existing) 19.0 Opened on 07.08.2017
b. OHE Pack-I Tender (Doubling 40%+Existing 60%) 42.0 Opened on 11.08.2017
1
c. OHE Pack-II Tender (Doubling 40%+Existing 60%) 42.0 Opening on 05.09.2017
d. OHE Pack-III Tender (Doubling 40%+Existing 60%) 37.0 Opened on 10.08.2017

TOTAL 140.0
SIGNAL AND TELECOM WORKS
Tenders pertaining S&T works
a. Design Supply and installation of panel interlocking at 5 15.26 NIT floated on 07.08.2017
stations
1 b. Supply of cables at 4 stations 10.0 NIT by 30.09.2017
c. Provision of 6 Quad OFC communication system 20.0 NIT by 15.09.2017
between Katni and Singrauli

TOTAL 45.26
Present Status MOU with WCR signed on 09.08.2016
48.30 Km section targeted for opening in 2017-18. Katangi Khurd Salhana (18.08 km) and
Deoragram-G\Maihdaiya (30.02 Km). 86.90 Km.from NKJ-KTKD,SLHA-VST & SKBR-SSGJ section
targeted for 2018-19.

1. 8.1 Lakh Cum E/W completed in the targeted sections


2. Track linking for coal siding at Bargawan station completed
3. Geotech investigation is in progress in two packages.
4. GADs for 44 Minor bridges in the targeted section has been submitted to Railway for approval
5. GADs for 31 Major Bridges including targeted section submitted.
6. 7 nos..ESPs for targeted section submitted.
Site Map Enclosed.
Rolling Diagram Will be submitted later in the upcoming Progress Report.
Site Map Katni Singrauli Doubling Project