Compltion Program - Low Rise C Block

The document outlines a project plan for constructing 300 flats in C Block. It details 27 activities needed to complete the project, including brick work, plastering, tile installation, and terrace construction. The plan lists the unit of measurement, quantity, estimated number of days, and start and finish dates for each activity. The final activity notes that the project will be ready for possession once shutters, wiring, switches, fixtures, painting and modular kitchens are installed.

Uploaded by

Ritesh
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
71 views1 page

Compltion Program - Low Rise C Block

The document outlines a project plan for constructing 300 flats in C Block. It details 27 activities needed to complete the project, including brick work, plastering, tile installation, and terrace construction. The plan lists the unit of measurement, quantity, estimated number of days, and start and finish dates for each activity. The final activity notes that the project will be ready for possession once shutters, wiring, switches, fixtures, painting and modular kitchens are installed.

Uploaded by

Ritesh
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 1

PROJECT: C Block ( Low Rise - 300 Flats )

Sl. No. Activity Unit Balance No of Days Start Date Finish Date
Quantati
1 RCC Slab Completed
es
2 Brick Work Sqm 3465 150 1-Sep-17 29-Jan-18
3 Door frame No 560 150 5-Sep-17 2-Feb-18
5 Internal Plaster Sqm 17952 160 1-Sep-17 8-Feb-18
6 Bacony Railing Kg 5612 150 15-Sep-17 12-Feb-18
7 Water Proofing Toilets Sqm 1020 120 10-Sep-17 8-Jan-18
8 External plaster Sqm 27720 150 10-Sep-17 7-Feb-18
9 Wall Tiles Sqm 8430 180 15-Sep-17 14-Mar-18
10 POP Ceiling Sqm 20850 150 15-Sep-17 12-Feb-18
11 POP Wall Sqm 58380 150 20-Sep-17 17-Feb-18
12 Stair case stone/ CladingSqm 3025 150 15-Sep-17 12-Feb-18
13 Stair case Railing Kg 9000 150 20-Sep-17 17-Feb-18
14 Floor tiles Sqm 20100 150 21-Oct-17 20-Mar-18
15 Flush Door Shutter Sqm 3198 120 1-Dec-17 31-Mar-18
16 UPVC D/W Sqm 5139 120 1-Dec-17 31-Mar-18
17 Terrace - Brick Work Cum 300 90 1-Sep-17 30-Nov-17
18 Terrace - ReinforcementM.T. 15 90 5-Sep-17 4-Dec-17
19 Terrace - Shuttering Sqm 950 90 1-Sep-17 30-Nov-17
20 Terrace - RCC Parapet Cum 100 90 7-Sep-17 6-Dec-17
21 Terrace - Plaster Sqm 2600 100 1-Sep-17 10-Dec-17
22 Terrace - M S Work Kg 8400 90 15-Sep-17 14-Dec-17
23 Terrace - Water ProofingSqm 5000 120 15-Sep-17 13-Jan-18
24 Water Tank - ShutteringSqm 4500 120 15-Sep-17 13-Jan-18
25 Water Tank - M.T. 75 120 17-Sep-17
15-Jan-18
Reinforcement
26 Water Tank - RCC Cum 750 120 25-Sep-17 23-Jan-18
27 Water Tank - Water Sqm 1800 130 20-Sep-17
Proofing 28-Jan-18

17 Ready for intimation


of Possession :
shutter/wiring/switch
es/CP fiitings &
Chinaware/painting/M
odular Kitchen