Sl. No. Activity Unit Balance No of Days Start Date Finish Date
Quantati
1 RCC Slab Completed
es
2 Brick Work Sqm 3465 150 1-Sep-17 29-Jan-18
3 Door frame No 560 150 5-Sep-17 2-Feb-18
5 Internal Plaster Sqm 17952 160 1-Sep-17 8-Feb-18
6 Bacony Railing Kg 5612 150 15-Sep-17 12-Feb-18
7 Water Proofing Toilets Sqm 1020 120 10-Sep-17 8-Jan-18
8 External plaster Sqm 27720 150 10-Sep-17 7-Feb-18
9 Wall Tiles Sqm 8430 180 15-Sep-17 14-Mar-18
10 POP Ceiling Sqm 20850 150 15-Sep-17 12-Feb-18
11 POP Wall Sqm 58380 150 20-Sep-17 17-Feb-18
12 Stair case stone/ CladingSqm 3025 150 15-Sep-17 12-Feb-18
13 Stair case Railing Kg 9000 150 20-Sep-17 17-Feb-18
14 Floor tiles Sqm 20100 150 21-Oct-17 20-Mar-18
15 Flush Door Shutter Sqm 3198 120 1-Dec-17 31-Mar-18
16 UPVC D/W Sqm 5139 120 1-Dec-17 31-Mar-18
17 Terrace - Brick Work Cum 300 90 1-Sep-17 30-Nov-17
18 Terrace - ReinforcementM.T. 15 90 5-Sep-17 4-Dec-17
19 Terrace - Shuttering Sqm 950 90 1-Sep-17 30-Nov-17
20 Terrace - RCC Parapet Cum 100 90 7-Sep-17 6-Dec-17
21 Terrace - Plaster Sqm 2600 100 1-Sep-17 10-Dec-17
22 Terrace - M S Work Kg 8400 90 15-Sep-17 14-Dec-17
23 Terrace - Water ProofingSqm 5000 120 15-Sep-17 13-Jan-18
24 Water Tank - ShutteringSqm 4500 120 15-Sep-17 13-Jan-18
25 Water Tank - M.T. 75 120 17-Sep-17
15-Jan-18
Reinforcement
26 Water Tank - RCC Cum 750 120 25-Sep-17 23-Jan-18
27 Water Tank - Water Sqm 1800 130 20-Sep-17
Proofing 28-Jan-18