4 Safe Practices For Elec
4 Safe Practices For Elec
4 Safe Practices For Elec
Part A:
The department/person asking permit to work on the equipment, fills this part and sends it to
Control Room. If Production shift- in-charge agrees to release the equipment, he signs and
sends the permit to substation for isolation of power.
Part B:
The Electrical Shift-in-charge/technician isolates power to the equipment mentioned in the Part
A of the permit.
Power is isolated by power switch. Power /control fuses are removed. Lockout tag is tied on the
LT switch handle or the operating switch (on the door) of the breaker panel.
Date & time of isolation are also written. Finally it is signed by the electrical supervisor.
After proper isolation, one copy is given back to the agency taking ELP, along with field tag (to
be tied on the field push button).
PART C:
After job completion, the agency of the job has to certify the completion and that the area is
cleaned, equipment is safe for starting. In this part, name and signature of person returning the
permit and area in charge (Production) are required.
PART D:
After completing Part-C, the permit is sent to substation. Electrical group can lift the lockout
(remove tag). If any other lockout permit is pending on this equipment, power will not be
switched on. If all permits are cleared, power is restored to the concerned equipment.
1.2 While taking or processing LOTO, one should be careful for following:
All boxes in the form are properly filled and individually tick marked carefully
for concerned points.
Each agency working on same equipment, should take separate LOTO
permit.
Part-A
To write equipment Tag number correctly
Part-B
To see that required equipment power is isolated.
To see that isolation is fully done & HT panel door or MCC module door is
closed properly.
Field tag given is tied on the MCC module or breaker panel door and field
push button also.
Part-C
Do not ask to energize equipment by lifting the LOTO Temporarily
Part-D
Equipment tag shall be compared with module on the panel or breaker.
Only required equipment will be energized.
Same fuses shall be inserted in the module, after ELP is returned.
1.3 Many accidents happen, because LC permit is followed partially or not followed at all.
During Safety Audit also, LC permit papers are checked.
3.0 Earthing
Provide double earthing to equipments.
Keep the earth pits wet by adding water at regular time intervals.
Remove paint form the equipment surface, before connecting earthing.
Use proper size of earthing as per type & rating of equipments.
In the cable trench & on the OH cable trays, run two earth strips.
Earth pit chamber size shall be of 500 mm x 500 mm.
Number all earth pits.
Earth pits of lightning protections, DCS system, power electronics (like VFDs) panels
shall not be connected with power system earth pits.
Test the earth pit resistance for each pit regularly (at least once a year).
Earthing system Layout plan (updated drawing)
(a) Substation:
Provide good ventilation for lead acid battery sets.
Maintain good housekeeping in the s/s & cable cellar.
Install smoke detectors & Manual call points (MCPs) at unmanned critical
locations.
CO2 fire extinguishers & dry sand buckets shall be provided in s/s.
(c) Transformers:
Carry out BDV test on transformer oil, twice a year (before & after monsoon). For power
transformers, carry out DGA every year. Get the results interpreted.
Soak pit shall be kept clean/dry
HP water jet spray system or Nitrogen injection system for fire protection
Oil filtration shall be carried out based on oil test results.
Oil leakage shall be attended, as per seriousness of the leakage source & quantity of
leakage. Oil leakage shall never be neglected.
Carry out the on line & off line monitoring for power transformers.
Donts
Do not overload the tool.
Do not leave tools unsecured at elevated place
Do not insert bare wires (inside the socket) to draw power supply.
Do not extend the wire of portable electric tool, by temporary jointing.
Do not use tool if casing is broken.
Do not stand on wet surface while using electric tool.
(B) Welding generator /transformer
Welding machines are a dangerous source of stray current, whenever the ground
return cables of the welding machines are not directly attached to the object on which
welding is being done. Wrongly connected ground return cable can cause fire. Correct
practice eliminate fire hazard, while carrying out welding job.
Carry out preventive maintenance of welding machines & transformer regularly.
Get the welding transformer oil tested regularly. It is safer to change the oil at the
suitable interval depending upon use.
(C) Hand lamps in confined area
In confined areas, 24 volt lamps are to be used. Generally, in plant area, at required locations,
240/24 V lighting transformers with small single phase DBs are installed. Feeders are taken to
the required sections.
Donts
(a) Do not depend on verbal communication for isolation of electrical equipment.
(b) Do not wear metallic ornaments (like ring, lucky chain) while working on electrical
equipment.
(c) Do not use underrated or overrated fuses.
(d) Do not switch without familiarity.
(e) Do not leave removed fuses inside MCC.
(f) Do not overload cable or motor beyond its rated capacity.
(g) No part of capacitors shall be approached, unless it is disconnected, effectively
discharged & properly grounded.
(h) Do not remove the ground connection of equipment, unless it has been detached
from the equipment.
(i) Do not ground any circuit, without making it sure that it is actually dead.