MASS PRODUCTION 2
6th START OF PRODUCTION
Nov 2009, Mumbai TRIAL
KEY FUNCTION AREAS
Produce at High quality
& Lower Cost
PRODUCTION
WHEN ?
WHERE ?
PRODUCTION
ENGINEERING
ENGINEERING
New product design & Process Engineering
Design changes & Facility Preparedness
WHAT ? HOW ?
3
6th Nov 2009, Mumbai
KEY BUSINESS CHALLENGES
Production Engineering
challenges
Increase Speed of
introduction for New
Models/ Minor changes
Process Improvement
(Quality, productivity &
Safety, Environment)
Enhance Capability of
Production Engineering,
Vendors & Suppliers
4
6th Nov 2009, Mumbai
KEY CHALLENGES
How to reduce COST? TIME TO MARKET?
(KEY: Innovation, Waste Elimination..)
CONVENTIONAL NEW AREAS
PRODUCT Product
Components development Time
& Cost
PROCESS Process
Manpower,
Reduction &
Rejection Cost
Stabilization
RESOURCE Robots, Tools, New Plant
Jigs, Conveyors Cost & Time
5
6th Nov 2009, Mumbai
Flexibility ?
Flexibility
7
6th Nov 2009, Mumbai
Model Flexibility..
What is meant by Multi-model manufacturing on single line ?
If we are able to make more than one model on one manufacturing line
Plant G1
Plant G2
Plant G3
Plant M1
Flexi Line
8
6th Nov 2009, Mumbai
FLEXIBILITY Common Platform
OLD- NORMAL CLAMP NEW- PIN WITH CLAMP
UNDER BODY -
12 NS
LOCATION PIN F
U
F
F
U
R
M
F
M
F FOR LOCATION 2 PIN & EXTERNAL CLAMP
CHANGED TO PIN CLAMP
F
R R
U
R F
U
R
NC LOCATOR -300 MM
SHIFT POSSIBLE IN 3
DIRECTION
USED FOR UNDER BODY LOCATION IN UNDER BODY & MAIN BODY LINES 9
6th Nov 2009, Mumbai
Process Driven Product Design
11
6th Nov 2009, Mumbai
12
6th Nov 2009, Mumbai
13
6th Nov 2009, Mumbai
100%
90%
80%
70%
60%
50%
40%
30%
20%
10%
0%
2000-01 2001-02 2002-03 2003-04 2004-05 2005-06 2006-07 2007-08 2008-09
Technical skills
People skills
16
6th Nov 2009, Mumbai
Inhouse Automation
Automated Guided Vehicle
Investment :Rs 4 25 000
Capital Cost Saving :Rs 15 75 000
DIE DESIGN
18
6th Nov 2009, Mumbai
WHY DIGITAL MANUFACTURING
No..
19
6th Nov 2009, Mumbai
WHY DIGITAL ENGINEERING
Virtual Problem Identification
at earlier stage
(Concurrent Engineering) High reworking cost
Higher time to market
Problems
PROBLEM BOMB
21
6th Nov 2009, Mumbai
ASSEMBLY FEASIBILITY STUDY
22
6th Nov 2009, Mumbai
TOOL ACCESS
23
6th Nov 2009, Mumbai
ERGONOMIC SIMULATION CHECK
Vision
Window
Stress
Analysis
25
6th Nov 2009, Mumbai
OPERATOR TRAINING
26
6th Nov 2009, Mumbai
BUILDING VIRTUAL FACTORY
28
6th Nov 2009, Mumbai
LAYOUT EVALUATION
LAYOUT A
LAYOUT B
BEFORE 3D NEW
SWIFT
CAD & DM MODEL
32
6th Nov 2009, Mumbai