N Area Parameters WTG (A) Actual Achmt

The document outlines parameters and weightages for evaluating contractor performance in areas like construction/installation, quality, safety, and claims/disputes. Various metrics are considered such as physical progress, delays, testing facilities, safety compliance, accidents, and dispute resolution.

Uploaded by

Subrata Paul
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
63 views3 pages

N Area Parameters WTG (A) Actual Achmt

The document outlines parameters and weightages for evaluating contractor performance in areas like construction/installation, quality, safety, and claims/disputes. Various metrics are considered such as physical progress, delays, testing facilities, safety compliance, accidents, and dispute resolution.

Uploaded by

Subrata Paul
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
You are on page 1/ 3

Actual

N Area Parameters Wtg(A)


Achmt
Physical progress i.e. Installation of equipment /
CONSTRUCTION item, Civil works (i.e. Excavation, RCC, Piling, etc),
15 95 26.96
/INSTALLATION Structural Works (i.e. Structural Fabrication,
Erection, etc) as per approved L2 network

Number of instances of delay due to inadequate


CONSTRUCTION deployment of equipment and T&P, based on
16 -5 0
/INSTALLATION record maintained in hindrance register, monthly
PRT MoM, contractors MPR, etc.

Number of instances of direct payment by NTPC to


CONSTRUCTION Contractors sub-vendors to expedite supplies /
17 -5 0
/INSTALLATION services / the progress of work at site affected due
to strike / delay in payments to labourers.

CONSTRUCTION
18 Submission of Monthly Report in specified formats. 5 0
/INSTALLATION

Availability of Testing facilities (Available as per


19 QUALITY 25 100
contractual requirement)
20 QUALITY Preventing recurrence of defects/complaints 25 NIL

Proper Storage & Preservation of


21 QUALITY 25 NIL
Equipment/Material
Deployment of Qualified Quality Officers/Manpower
22 QUALITY as per Contract (% deployment w.r.t. contractual 25 100
requirement)
Having safety policy and approved Safety
23 SAFETY Assurance Plan (available as per requirement - 10 100
100%, Not-available - 0%)

Violation of safety requirement as per Safety


24 SAFETY 20 0
Assurance Plan.
No. of incidence of Fatal accidents due to
25 SAFETY 50 0
contractor's negligence
No. of incidence of Non-Fatal accidents due to
26 SAFETY 10 0
contractor's negligence
Deployment of Qualified Safety Officers as per
27 SAFETY contract (% deployment w.r.t. contractual 10 0
requirement)
No. of cases where Contractor stopped work on
28 CLAIMS & DISPUTE account of non-admittance/non settlement of 70 0
claims
No. of arbitration/legal cases resorted to by the
29 CLAIMS & DISPUTE 30 0
Contractor
UM

no.

no.

% Available 100% Not available 0%

Number Up to 5 cases 100% Up to 10 cases 40% more than 10 cases 0%

Number Nil violation 100% Up to 1 case of violation 40% more than 1 cases of violation 0%

% percentage (0-100)

Number 0 violation = 100% Upto 3 violations = 50% more than 3 = 0%


lation 0%