Notes On Reinforce 00 in Di Rich
Notes On Reinforce 00 in Di Rich
Notes On Reinforce 00 in Di Rich
A. Brebner, C.I.E.
SC
" " *
v
^sfcT**- -ly.
UNIVERSITY OF CALIFORNIA
DAVIS
GOVERNMENT OF INDIA
Technical Paper
NOTES ON
REINFORCED BRICKWORK,
BY
A. BREBNER, C.I.E.,
Under Secretary, Government of India, Public Works Department.
VOLUME I.
Notes.
CALCUTTA'
SUPERINTENDENT GOVERNMENT PRINTING, INDIA
1923
PREFACE.
These notes are based on experience gained during the construction of the
New Capital at Patna, Bihar and Orissa.
I am much indebted to Messrs. Brij Narain, A. K. Datta, Eashid Ahmad
and A. Karim, who helped to conduct the experiments carried out and super-
vise the work done and to Mr, Brij Narain also for much assistance given in
the preparation of these notes.
Volume Volume II contains illustrations, experiment
I contains notes and
comparative tables, plates,
tables, curve tables and plans this arrangement being
;
adopted for facility of reference to any of the latter when reading the letterpress.
A. BEEBNEK,
SIMLA;
24th August 1922.
KY
LQKVERSITY OF CALIFORNIA
DAVIS
TABLE OP CONTENTS.
VOL. I.
Section.
I. Introduction ........ 4
II.
Reinforced brick
......
Description of the various forms of reinforced brickwork
.
4
7
lintels,
...
III.
Centering
Materials
........
Practical execution of reinforced brickwork
.... ....
10
10
11
Workmanship . . . . . . . .13
.15
IV. Results of experiments
Tests of slabs
Tests of cantilevers
.........23
.
.
.
.
.
.
.
.
.
.
.
.
17
Tests of lintels 23
....
.....
. . .
25
25
Tests of R. B. partition walls
26
Compression tests of
...
. . . .
28
30
....
it .
I. Illustrations .........
....
CONTENTS OF VOL. II.
II.
IV.
V.
VI.
Plates
SECTION I.
INTRODUCTION.
Reinforced brickwork construction is in all essential features practically the
same as reinforced concrete construction save that brickwork in cement mortar
is substituted for cement concrete. The principles of reinforcement are similar
and steel is used in various ways where necessary, as in reinforced concrete, to
give the requisite strength to the material.
Structures of all descriptions have now for many years been built in rein-
forced concrete. This form of construction has long passed the experimental
stage and at the present time there is scarcely any project which has to be
tackled by civil engineers for which it cannot be usefully and economically
employed in some way. In India, however, it has not been as extensively used
as elsewhere and the reasons for this are not far to seek. In India the price of
cement is high as compared with what it is in other countries and the price of
bricks, tiles, etc., low, so that in the past it has almost invariably been found
when designing, that some other form of construction was cheaper, to
all intents and purposes as good, and had the further advantage of
being
comparatively simple and therefore more easily and cheaply supervised.
Another very great obstacle to the substitution of reinforced concrete for other
forms of construction in India is undoubtedly the fact that the Indian mason
(mistri) and labourer (coolie) cannot be trusted to do good concrete work, unless
constantly supervised by an efficient staff and to arrange for this, more especially
,
in out-of-the-way places is not always feasible. Every one who has experience
of reinforced concrete construction in this country knows the great difficulty
there always in in getting the labour to understand and put into practice the most
elementary principles of good concrete work, not to mention the various troubles
connected with the construction of centering and the correct placing of the
reinforcement, no matter what detailed drawings may be provided. In rein-
forced brickwork construction all these difficulties very largely disappear and it
will be found almost invariably that the cost of this form of construction is much
lower than that of any other form of construction of a more or less permanent
nature.
For some years now lintels over ordinary door and window openings have
been built of reinforced brickwork this method of construction being simpler,
cheaper, and neater than older methods such as arches and relieving arches, or
T and angles with tiles or bricks between them. Partition walls of brickwork
in cement suitably reinforced have also been used with certain limitations. It
is only recently, however, that reinforced brickwork has been used extensively in
Buildings in the new town being constructed by the Tata Iron and Steel
Company Limited at Jamshedpur.
In all nearly 3,000,000 square feet have been laid in the last three years.
IV. Neat and artistic appearance of the finished work, unlike that of jack
arching or other systems in common use.
V. Cool rooms.
VI. Low cost. It is cheaper than any other form of pakka roofing.
(2) No special materials of any kind are required, all that is wanted are :
(a) Bricks,
(6) Cement,
(c) Sand,
There is, therefore, nothing used which any Indian bricklayer is not well
acquainted with, and there are no heavy charges for specially manufactured
materials or for freight in bringing the same to work site from the
factory.
(5) The Indian bricklayer can do good brickwork though he cannot do good
concrete work, and therefore not only is less supervision required but a less
highly trained supervising staff is sufficient. It has been found that ordinary
bricklayers quickly become expert and can be trusted to do good and rapid work
after a week or ten days' practice.
(6) The reinforcement is inserted as the Work proceeds and experience shows
that it is not nearly so liable to displacement as it is in reinforced concrete
work.
NOTES ON REINFORCED BRICKWORK. 3
attention of any kind. The repair charges are therefore very low, in fact, negli-
gible provided the brickwork is efficiently protected from weathering and from
damp by cement plaster or something similar. It has also been found that roofs
built of reinforced brickwork rarely, if ever, leak. In most cases they have a
through cement joint between the bricks which forms as it were, an efficient
rainproof course even if the terracing be not sound. Further there are no large
steel sections round which cracks are likely to be set up by variation in tempera-
ture as frequently happens in forms of roofing in which rolled steel joists are
commonly used.
can be constructed to take any load.
(2) Floors, roofs, etc.,
(3) After the work has set, holes of a fair size can be cut in it without
detriment.
III. The work is fireproof. This is more or less obvious, but a reference
to experiment 276, table XIX
will show exactly what happens when reinforced
brickwork is subjected to a fierce heat for many hours.*
IV. One of the main drawbacks to jack arch and T and tile floors and
roofs, is their unsightly appearance when viewed from the underside. This
is avoided entirely where reinforced brickwork is used. Ordinary sand lime
plaster adheres readily to the surface of the bricks and a clean plastered ceiling
is therefore easily obtained at a very low cost. This is clearly shown in the
photograph of work done in Patnaf. What is true of roof and floor slabs is
equally true of other work such as cornices, balconies, etc. The whole of
the steel reinforcement is completely concealed and no unsightly supporting
brackets of any kind are required.
VI. The cost of the work varies not only with the market prices of steel,
cement, and bricks, but with varying conditions of design. In most cases it
is found that there are several alternatives, any one of which can be adopted,
and it is therefore not easy to give definite figures showing the extent of
the saving effected by substituting this form of construction for others. In
order to get accurate figures, each case must be considered separately. A
comparison of the cost of reinforced brickwork and other roofs is given in
Section VI. These figures are taken from notes kept of the cost of construction
in Patna and may be considered a fair guide.
* Vide
photograph, Vol. II, page 22.
f TiWe photograph. Vol. II, page 17.
B2
4 NOTES ON REINFORCED BRICKWORK.
SECTION II.
Reinforced brick slabs are eminently suitable for all kinds of floors, roofs
and staircases in buildings and for the decking of bridges. They are simply
and quickly constructed and can be designed to carry any load. In practice
they are supported either on two sides, four sides, or built in on one side
(cantilever).
Slabs constructed of ordinary bricks, which throughout this paper are
taken as nominally 10" X 5* x 3", are limited to certain definite depths,
namely 3", 5", 6" or combinations of these, i.e., 3" slabs are made by laying
bricks flat, 5" by laying bricks on edge, and 6" by laying two courses one
upon another in the ordinary manner. A flat course ^/MS a brick-on-edge course
can be used to make up 8* slabs, 9" to 10" slabs are made of three courses
flat while 10" slabs have also been constructed of bricks on end. Though very
satisfactory from the point of view of strength and appearance of the finished
work, slabs of greater thickness than 6" are generally too heavy and ex-
pensive for ordinary use.
In referring to the depth of slabs it is usual to give the thickness in terms
of brick dimensions neglecting the depth of horizontal mortar joints, e.g., a (>"
slab is made up of two courses of brick laid flat, each therefore 3" deep plus a
joint and has an actual depth of G" plus one joint. A
similar convention is
used as regards the spacing of reinforcing rods, thus the distance apart specified
indicates the brick intervals at which rods should be placed and does not take
into consideration the thickness of the mortar joints as will be seen from the
sketches in tables I to XX.
A
6 NOTES ON REINFORCED BRICKWORK.
CROSS 'SECTION
n
i*
cttoss -SECTION
to
CROSi -SECTION
PLAN
FIGURE 3.
The sketches in figure 4< illustrate various ways in which bricks can be
arranged for 6" slabs. There is a simple break joint between the upper and
lower layers and reinforcement can be spaced 5^" or 10j" apart (called for the
sake of convenience 5" or 10") as in the case of 3* slabs according to require-
ments.
PLAM
'Reinforce mcnf every 5 opart.
K-.o- 1|
UONGITOOINAU SECTION C. 0.
every S opart.
CROSS SCC.TIOM A B
FIGURE 4.
Figures 5 and 6 below indicate how 8" and 9'' slabs may be laid, these in
practice will seldom be used except in special circumstances. They are not
as a rule economical to construct.
30
8 NOTES ON REINFORCED BRICKWORK.
without, holding up the brickwork of the wall or in any way altering the
arrangement of the joints. If in such cases the centering can be conveniently
left up for any length of time, the lime masonry sets and will then act along
Avith the cement masonry, thus considerably increasing the strength of the lintel
and reducing the amount of steel required. Examples of this class of work are
given in plate 7, figures 1 to 4.
Reinforced brickwork beams are very convenient where the loads to be
dealt with are not heavy and AA'here a large number have to be made. Beams
for heavier loads such as may be met Avith in bridges can also be designed, but
they are heavy and somewhat clumsy though much less expensiA e than reinforced
r
concrete beams of similar strength would be. Many such beams, some car-
rying well over 100 tons, have been built and have proved entirely successful.
The results of tests carried out on a 40' span girder are shown in experiment
160, table XI.*
Ordinary rectangular and T beams of reinforced brick, and of combined
reinforced concrete and brick, have been successfully designed in many cases
and are easily constructed. In designing sxich beams ample provision should be
made against shearing stresses, and for this both stirrups, and rods inclined
near the ends, have proved efficient. Plate 5 gives a typical design of a T beam
of reinforced brick only, \vhile plate gives a design for a beam of reinforced
brick and concrete combined. It Avill be noticed that concrete is used only ir
the lower portion of the beam where most of the reinforcement is located, the
reason being that the reinforcement is much more easily arranged and securely
packed in concrete than in brickAVork in such cases. Except in this position
it is not, as a rule, economical to substitute concrete for brickAvork.
imbedded roiled When reinforced brick slabs run continuous over intermediate rolled steel
joist supports, it is possible to connect the joists and the slab rigidly by build-
ing the upper flange of the joists a feAV inches into the slab and casing the
rest of the Aveb and lower flange in cement concrete or cement brickAvork. If this
is done, stirrups, passing round the bottom flange of the
joists and having their
ends well anchored into the slab, should be provided. When so treated the
slab and joist form a sort of T beam. The carrying capacity of the joist
is thereby considerably increased, and hence in most cases a lighter section can
be used than would othenvise be possible. It will be seen from table XII,
experiments 102-103, which give figures of joists so treated, that the loads
carried at failure are in each case considerably in excess of the loads at failure
carried by a plain joist of the same section, vide experiment 101, table XII.
Partition walls. Reinforced brick partition Avails are already Avell knoAvn to most engineers
as a very useful type of structure. Not only are they light, cheap, and easily
constructed, but what is not so commonly kiiOAvn is that they can be made self-
supporting Avith very little extra expenditure. For instance a wall can be con-
structed in the first floor of a tA\ o-storied building Avithout any corresponding
r
the side walls. The sketches for experiments 167-172 in Table XIII show how
such walls are made and reinforced.*
Longitudinal reinforcement in reinforced brick
columns is of little use Columns,
alone, but when combined with hooping at close intervals it is most efficient.
In actual practice reinforced brick columns have not been much used as it has
generally been found simpler and not
much more expensive to construct either
reinforced concrete columns or to provide steel stanchions. The figures
shown in Table XVII(e), experiments 212-265, are, however, very interesting as
showing what can be done.
Arc
Reinf orced brick arches have been tried and tested in Patna and found
in compression but
very useful, not because of the fact that reinforcement aids
because it prevents cracking. If there is any bending action due to concentrated
or unsymmetrical loading in the arch or to an unequal settlement or yielding
in abutments, it is advisable to reinforce symmetrically near the intrados and
extrados and combine the reinforcement together at frequent intervals by
of interest in
hoops. The tests given in Table XVIII, experiments 266-269, are
this connection.
* ride Alto
photographs, Vol II, pago 15.
10 NOTES ON REINFORCED BRICKWORK.
SECTION III.
I. Sound centering.
II. Good materials,
III. Careful work.
Centering.
As in reinforced concrete work, some form of centering is required on
which the work can be constructed and supported, until such time as the mortar
has set. Elaborate and expensive centering and shuttering such as is essen-
tial in reinforced concrete work is, however, not required. In different localities
various suitable materials are available, and it is not proposed therefore to lay
down any hard and fast specification. Typical kinds of centering, which have
been extensively used with success, are illustrated in Plate 1, figures 1 to 5,
and anything of a similar nature will probably be found to serve the purpose
equally well.
The simplest type, and that which is most generally used, consists of a
platform composed of planking or sheeting at the required level, supported
on runners or beams and covered with a thin layer of well-beaten earth finished
off with a sprinkling of fine sand.*
It is essential that whatever centering be used it should possess the
following properties :
1. Rigidity.
2. Simplicity of construction, slackening and removal.
3. Asmooth surface on which to lay the slab.
Rigidity. The centering must be rigid. By this is meant that it should not sag
under the weight of the workmen constructing the slab. It should be tested
beforehand by being jumped on, and if there be anything very perceptible
"
in the nature of a give" about it further stiffening should be provided.
Simplicity of
construction
No special difficulties are likely to be met with in erecting centering.
and removal. The following points should, however, be noted at this stage :
(i) Care must be taken to see that all centering planking is kept clear
of the bearings for the slab and rests on cross beams only.
(ii) planks are used they should not be laid too close to each other
If
as they may jam and thare may 1)3 difficulty in removing them.
(Hi) All cross beams should be carried on the walls, supported at in-
tervals if necessary by rough timbering (bullahs) or temporary
dry brick pillars.
(iv) Cross beams should rest directly on wedges and not on the support-
ing walls themselves. This permits of the centering being easily
and rapidly struck and removed, and does away with any chance
of jarring the finished work.
The length of time for which centering should be left up after construction
depends on many conditions, such as the specification of mortar used, the
season of the year and the span of the beam or slab. It is therefore not possible
to lay down any hard and fast rules on the subject. The practice followed in
Patna, as noted below, may be taken as a guide :
(b) Centering for specially heavily reinforced slabs from 7 days to 15 days.
ic) Centering for ordinary beams 10 to 15 days.
(d\ Centering for important beams carrying heavy loads 28 days.
* Thf:
top surface of the centering should be given a camber as below to allow for initial settlement.
Kor slabs. bout TV' for every foot of span up to a maximum of !'.
For beitms about up to a maximum of li ".
''
R. B. slabs are usually finished Avith lime concrete terracing for root's,
and patent stone for floors. The ten-acini;- may lie done after '21 days, but it
is better to wait fora month. Patent stone should b" done as soon after the
11. B. slab is finished as possible, preferably before removing the centering,
1
unless, perhaps, in the case of slabs continuous over beams, where it should be
laid as soon after the removal of the centering as possible. This aspect of the
question is more fully dealt with on pages 21 and 22. If in the case of continuous
slabs supported on intermediate II. S. joists, it be decided to use the joists them-
selves as supports for centering, care must be taken to see that they are propped
up to prevent excessive deflection during construction, otherwise on removal of
the load due to centering, the slab 'may be damaged when each or any joist
springs back to its normal position.
Where T beams B, are combined with the R. B. slab, several arrange-
of 11.
ing may be very simply hung from the lower member of the supporting trusses
by means of specially constructed clips as show n in Plate 2, figure 6. This
r
method was very successfully employed during the construction of the Secre-
tariat building at Patna where 130,000 square feet of ceiling were laid in a
few months.
Suitable centerings for lintels, beams, and staircases, are illustrated in Plate
2. These are perfectly simple and straightforward and require no explanation.
"\Yhen the time comes to ease and remove centering great, care must be
taken to see that no jarring of any kind occurs. All wedges should first of all
be carefully drawn. This separates the supporting beams and planking from
the R. B. construction and readily permits of the removal of centering and
supports. In fact all operations in connection with the removal of centering
must be gently performed. It is desirable to impress this on everyone connected
with the work at the very outset, otherwise accidents may occur and in any
case centering is
needlessly damaged and
destroyed.
As has been explained above, the simplest and cheapest way to obtain a^^ 6 .
' surface
smooth surface is by spreading earth to a depth of about 1* over the planking requi
or sheeting, as the case may be. This is then beaten flat and finished off with
a thin sprinkling cf fine sand. The earth is required to level up the inequalities
in the planking, to help to distribute the weight of the workers and to admit
of the requisite camber being given, while the addition of sand gives a smooth
surface on which the bricks can be quickly and truly laid and prevents adhesion
of the clay to the bricks Avhich would otherwise occur. Care must be taken
to see that only a fine sprinkling of sand is given, since, if too much be given,
there is always risk of the bricks sinking into it when laid, and in any case
mortar may be sucked from the joints, an evil wluch cannot be over-exaggerated.
Materials.
() Bricks,
(b) Cement,
(c) Sand,
(d) Steel reinforcement.
Only the best bricks complying with the usual 1st class specifications Biicfrs:
(1) Low absorption. If nothing else is obtainable and porous bricks have
to be used working stresses must be correspondingly reduced.
(2) Freedom from saltpetre. Bricks having too much saltpetre are un-
suitable for R. B. and should not be vised.
c 2
12 NOTES ON REINFORCED BRICKWORK.
FIGURE 7.
Saru},
should be clean, well graded, i.e., there should be
particles of all size
from jVdiameter to the very finest grains, and if
possible sharp. Sharpness
is not
absolutely essential if the grading is good and the sand otherwise sound.
It should be free from
organic and vegetable matter, and should also be as
free from clay and mica as
possible. Although some authorities are of opinion
that the presence of small
quantities of clay actually improves cement mortar,
there is always the fear that if too much be allowed the mortar will be
weakened.
The presence of mica in the sand is
objectionable as a mioacious. sand
requires a greater proportion of cement to produce a mortar equal in strength
to mortar made from a sand free from mica and otherwise
equally good, tin-
fortunately, most sands are micacious and the only thing to be done is to deter-
mine by actual experiments the
proportion in which it has to be mixed with
cement to produce a suitable mortar.
Too fine sand should not be used as it
requires extra cement to be added
to produce good mortar.
Ganges sand which is both very fine and micacious was discarded in Patna
in favour of sand
dug from pits in the old bed of the river Son. The latter
was found to be clean,
fairly coarse, sharp and well-graded and entirely free
from mica. It gave
Cement. uniformly satisfactory results.
The cement used must comply in
every way with the standard cement
specification. Both Katni and Buiidi cement were used extensively in Patna
and gave excellent results. It must also be fresh
any cement which shows
signs of staleness should be rejected. Samples of all cement used should be
regularly tested.
Mortar. The mortar used should consist of cement and sand in
proportions varying
according to the quality of sand available. (Throughout work at Patna the
proportions used were 1 of cement to 3 of sand by volume, mixed dry, and
it was found that this
gave very satisfactory results.) Only enough water
should be added to make the mortar of such a
consistency that is easily work-
able, leaves the trowel clean, and can be
readily packed round the reinforce-
ment bars.
NOTES ON REINFORCED BRICKWORK. 13
It will generally be found that 3:1 is a sufficiently rich mixture, hut the
best proportions should he found by experiment whenever possible. Propor-
tions which ensure that the following results are attained should he adopted :
(1) Mortar briquettes made in the usual way should give a breaking
tensile strength of 150 Ibs. per square inch when one week old and not less than
350 Ibs. per sq. inch at an age of six months.
(2) Short columns built of single bricks one upon another set in the mortal-
should have an ultimate breaking stress of not less than 1,200 His. per square
inch after 28 days.
(3) Adhesion sti-ess between bricks and mortar should not be less than 25
Ibs. per square inch. This can be tested by pulling apart bricks, set one upon
another crosswise, with a mortar joint between them. For this test the bricks
should be well soaked with water before the sample is made, and the sample
after being made should be kept under water until the time of test. If the
bricks are dry at the time of construction or soon after, the test is unfair.
(4) Bond stress between a round steel rod and mortar should be at least
about 400 Ibs. per sq. inch of the embedded surface of the rod after 28 days.
It will usually be found that a mortar satisfying the tension test satisfies
all other tests,
For beams and other heavily reinforced work, where the bond stress is
likely to be high, it may be advisable to use a mortar richer in cement than
the mortar usi-d for ordinary slabs where the bond stress is low.
All mortar used in work must first be thorough/ mixed dry and water
should on no account be added except by the masons employed on the work
and then only in small quantities. Too great stress cannot he laid on this
point. If these precautions be ignored there is every likelihood that stale
mortar will be used.
From long experience it has been found that the most suitable method is
to have the mortar mixed dry in some central position where this work can be
easily supervised, and then have it distributed. If this method be adhered to,
each mason need only add water in his iron pan (karai) and there is therefore
no fear that the mortar will be partially set when used. Needless to say, this
method can only be adopted when the sand is really dry. Only clean water
should be used.
Only the best mild steel should be used as reinforcement. As far as possi-
hie only steel of circular section shoiild be used. Square sections may also l>e
used but flats or angles should be avoided. If they have to be used care should
he taken to see that the bond stresses are kept very low.
In floor and roof slabs no section of greater diameter than -|" should he
" "
used, and as far as possible only small sections such as j", f-6 and f should he
xised. Sections in beams should not be larger than 1" diameter for main re-
inforcement and \" for shear reinforcement. Hoop iron although unsuitable
for slabs and beams is suitable for reinforcing partition walls.
A rust on the reinforcement is desirable as it ensures good adhesion,
little
but all loose and scaly rust should be removed prior to use. Hoop iron with a
bluish glazed surface should not be used ;
if it has to be, then it should be
immersed in water for a few days. This produces rusting and effectively
destroys the glaze on the surface.
The ends of all rods should be bent into semi-circular hooks of a diameter
at least six times the diameter of the rod itself with a short length of
straight rod beyond the bend.
As far as possible overlapping should he avoided by ordering rods of proper
lengths, but where this cannot he done and overlapping has to be resorted to, a
lap of 50 diameters should be given with proper hooks at the ends and the two
should be bound with wire along the lap.
Workmanship, etc.
The main points under this heading Avhich require careful attention are :
(a) That all bricks are thoroughly soaked before being used. This hardly
requires any comment ; dry bricks are sure to suck moisture out
of the mortar joints and thus interfere with setting. All bricks
should he soaked for at least six hours in a soaking vat before
being used.
NOTES ON REINFORCED BRICKWORK.
(ft)
That bricks are properly arranged as they are laid. "Where possible,
the arrangement should he shown in drawings, hut it may he laid
down as a general principle that joint should be broken where-
ever possible as this gives increased strength.
(c) That reinforcement is
properly arranged. Before starting work all
rods should be prepared and bent to the correct lengths and shapes
shown in the drawings and where possible laid out in situ. It*
this is done difficulties will be anticipated and cutting and over-
lapping reduced to a minimum. Rods of the correct length shoulu
be used, but where this is not possible overlapping may be resorted
to as detailed above. Welding should not be permitted.
(d) That all joints are well filled and all reinforcement well surrounded
by mortar. This requires careful attention as workmen unless
watched are apt to scamp the work or grout the joints. Both
faults are objectionable and apt to lead to trouble unless checked.
All reinforcement must be thoroughly surrounded by mortar other-
wise slipping and rusting may take place and adhesion, on which
the strength of the structure depends, does not develop fully.
Care should be taken that the bottom rods in slabs have a real
cover of mortar under them and do not touch the centering surface.
The mortar used must be fresh and mixed w et only just before
r
plank and not on the centering itself. Planks should also be laid
so that it will never be necessary to walk over newly finished work.
(e) That the work after completion is properly looked after and watered.
All work should be kept moist by means of w et straw, wet sand,
r
or merely sprinkling water, for the first and part of the next day
after finishing. It should then be profusely watered and kept
Avet until one or two days before the removal of centering. A
low mortar wall or kiari might be made all round the slab to hold
about ^" depth of water on it. A clear day should be allowed
for dry setting before the centering is removed. The work should
be kept wet or moist until it is about a month old.
( /) As far as possible, each structure should be finished in one operation
and in one day, but there will be occasions when this is not
possible and in such cases the following hints may be of use :
SECTION IV.
RESULTS OF EXPERIMENTS.
When the proposal that R. B. should be used for the floors and roofs
of new buildings under construction in Patna, was first put forward by the
Executive Engineer, the Local Government were somewhat averse to its accept-
ance, as they did not consider they were justified in adopting, on a large scale,
a system which had not been thoroughly tested. The rapid rise in the cost of
rolled steel joists and other steel work, however, left them no alternative but
that of stopping work altogether, a course which would have been disastrous
in view of the advanced stage which the work had reached. As the preliminary
experiments which had been carried out had proved successful and had estab-
lished beyond doubt the fact that the cost of work done in this system was
very considerably less than that of any other in common use, it was decided
to introduce it and at the same time to carry out a large number of experi-
ments with a view to testing it thoroughly in every way. Tests, extending over
a period of nearly two years, were accordingly made on practically every kind
of structure likely to be met Avith in ordinary building work, and the final
results of these are given in detail in Tables I to XX in Volume II. The
following are some of the types of structures experimented on
1. Roof and floor slabs of all kinds supported on two sides, generallv Typ es f struc-
*
c. , . ,. .. .,,, fyl . tures experiment-
,
reinforced in one direction only, with or without covering such as cement e a on.
concrete, patent stone, terracing, etc.
2. Roof and floor slabs supported on four sides, generally reinforced in
both directions.'
3. Lintels over doors, windows, etc.
4. Beams.
5. T beams and long-span beams suitable for bridge girders.
G. Brickwork beams reinforced with rolled steel joists.
7. Hanging partition walls with and without door or window openings.
8. Slabs capable of being used over culverts or as decking of road bridges.
9. Columns.
10. Arches.
11. Special experiments.
It was felt from the first that R. B. was a system more or less allied to
reinforced concrete, and the investigations therefore ran on somewhat similar
lines to investigations made in regard to the latter. Generally speaking, enough
steel was embedded in the joints of the brickwork to take the tensile stresses
while the brickwork was relied on to take up the compression. Local conditions
and the abnormal prices of some of the materials of necessity played a large part
in the evolution and development of the practical details.
In Patna the following conditions obtained :
(1) 1st class bricks suitable for the work cost Rs. 12 per thousand at site.
(2) Very good sand for cement mortar was available practically at the
site of the work and cost only about Rs. 2-8-0 per hundred c. ft.
(3) The price of cement varied, but most of it was obtained at Govern-
ment-controlled rates and cost about Rs. 3 per c. ft. at site.
Katni cement was principally used.
(1) The cost of steel rods for reinforcement averaged about Rs. 30 per
cwt.
As one of the chief objects in introducing the system was to effect economy,
the conditions influenced the designs and consequently the lines
above
on which the experiments Avere conducted. The following constructional
principles were evolved to ensure economy in cement and steel which were the
most expensive items :
(1) Mortar was made just rich enough in ceruent to give the requisite
safe adhesion with steel as well as brick.
(2) Joints in which there was no reinforcement were made as thin as
was consistent with strength and good work.
10 NOTES ONT REINFORCED BRICKWORK.
(3) Reinforcement was, as a rule, placed in the joints between the bricks
which therefore naturally ran straight without break. Much brick
cutting and consequent use of a large amount of excess mortar
was thus avoided. The only exception was in the case of heavily
reinforced beams with a lot of steel crowded together near the
bottom, where it was found easier and more economical to use con-
crete instead of brick work on account of the thickness of joints and
the extra labour required to fit the bricks in properly, in the latter.
(4) Joints containing reinforcement were only just thick enough to give
a sufficient coating of mortar all round the reinforcement rods,
i" to Y
depending on the diameter of the reinforcement.
In view high price of steel it was found that it often paid to increase
of the
the depth of the brickwork slightly and decrease the amount of reinforcement.
The experiments were conducted on the most practical lines possible in ;
fact with the exception of certain special tests which were carried out with
special objects in view, it may be said that all experiments carried out were
tests of designs about to be used in construction.
(1) To find the most suitable type of structure and reinforcement for
roof and floor slabs, beams, walls, etc., on various spans, and
under different conditions of loading and fixing such as are met
with in ordinary practice.
(2) To determine the various constants required in analysing the
strength of structures, e.g., safe adhesion between mortar and
steel rods, between bricks and mortar, the tensile and shearing
strength of brickwork, and the compressive strength of brickwork
in slabs, columns, beams, etc. .
loaded to
destruction. For some time the slab remains comparatively stiff and deflections are
small. The bending moment couple is resisted, the tension by the steel rods
and the brickwork below the neutral axis, and the compression by the brick-
work above the neutral axis. This goes on until the appearance of the first
minute crack in' brickwork which appears after the limiting stresses in
tension in the extreme fibres of the brickwork are passed. The position of
the neutral axis now rises. As the load increases more minute cracks appear in
the brickwork and eventually the stage is reached when practically all the
tension is taken up by steel and all the compression by brickwork. The rate
NOTES ON REINFORCED BRICKWORK. 17
of deflection is now more thanit was when the hrickwork was acting in tension.
This stage continues until the steel has reached its yield point and in many cases
even much beyond it. The excessive stress tends towards the deformation of the
steel, but this is resisted by the adhesion between steel and mortar. Ultimate-
ly the stress reaches a point where the adhesion begins to fail. When this
occurs there is a sudden increase in the rate of deflection and soon afterwards
the slab fails.
The failure in ordinary circumstances is very gradual, the slab sinking
down. There is nothing in the nature of a regular collapse. The curve of
deflections if drawn accurately will usually be found to be of the shape
sketched below :
FlGUKE 8
Tables I to VIII and XIV give results of tests of slabs of all kinds,
and also give the calculated stresses at final failure both in masonry
and steel. These stresses have been calculated on the assumption that a theory
similar to that for reinforced concrete holds good for reinforced brickwork.
*
The modular ratio for steel and brickwork has been taken as 40 through-
out the tables and calculations based on experimental results. In all the
D
18 ON REINFORCED BRICKWORK.
tables the loads at failure are shown in Ibs. per square foot of the slab and are
external loads only. They do not include the weight of the slab. The dead
weight has, however, been taken into account in calculating the stresses.
Centerings were seldom removed before the sixth day and most of the tests to
destruction were carried out at the age of about three weeks.
On removal of centering there was usually a very slight deflection.
This varied in amount and had probably something to do with the hardness
of brickwork at the time of removal. In heavily reinforced slabs and slabs
with patent stone over them there was very little deflection and often none
at all. To allow for this settlement some camber was generally given in slabs
at the time of construction.
'
The ' first indication of failure which is also tabulated is somewhat difficult
to define, as failure is very gradual in normal circumstances. It may be
considered as the point at which definite signs of distress appear, e.g., sudden
increased deflection or many and extensive cracks.
Testa of 3* slabs. Table I shows experiments of plain 3" slabs, supported on two sides. The
results obtained are all satisfactory as will be seen from the table. The failures
occurred well after the point when the steel bad passed its elastic limit. The
stresses in steel at failure vary from 46,800 Ibs. per square inch to 55,100 Ibs.
per square inch. It will also be noticed that in experiments 2 and 3 where flat
reinforcement was used the failure stress is lower than in case of experiment 1
where round steel was used. Generally speaking, flat bar reinforcement was found
not to be so good as round bar, while heavier flat sections were proved to be
distinctly unsuitable. The depth to the centre of gravity of steel in 3" slabs is
small, and if big sections of steel are used this is still further reduced. This is a
point to be remembered in designing such slabs. The experiments carried out are
on an 8' span, but the loads taken are all low about 40 Ibs. per square foot being
the maximum. Such a slab would not do for roofs or floors, but makes a cheap
and useful ceiling under a tiled roof. In practice such a slab would only be
used for a floor or a roof on spans up to 5'.
Tests of 5" slabs Table II gives the results of tests of 5" slabs, supported on two sides. Such
with free ends.
slabs have been tried up to 12' span for floors and roofs but it has been found
that unless the ends are well fixed or an inordinate amount of reinforcement is
given the deflection in a span of more than 10' is excessive. The results of the
tests are all satisfactory, failure in most cases being due primarily to the steel
being stressed well beyond its elastic limit. In these cases the stresses in the
slab at failure vary from 43,000 Ibs. per square inch in experiment 12 to nearly
79,000 Ibs. per square inch in experiments 17 and 18. It will be noticed that
"
the stress is high where the steel section used is light, diameter round bar
"
for example, and low where the section is heavy fa" and diameter] round
bar. In experiments 20 and 21 the failure is due to the excessive
compressive stress in bricks. probable that excessive compression is also
It is
probably the failure is due to both tension in steel and compression in masonry.
One unusual factor in this experiment is that the joints were about 2" thick
and were filled not with 3 1 qement mortar as usual, but with
: 1:2:4
cement
concrete. This may explain the high compressive stress taken.
Tests of 5" slabs Experiments 27 and 28 were of slabs which had their ends 'fixed',
with " fixed "
ends,
and were reinforced at the top near the ends to take up the tension in upper
fibres due to the negative bending moment. The ends were fixed by piling up
loads at the ends over the bearings.* The results of these and other experiments
referred to later show that it is extremely difficult, if not impossible, to obtain
perfect fixing. In all cases the ends lifted slightly before failure, t The actual
bending moments at the ends and centre of the span are therefore uncertain.
* Tide
Photograph, Vol. II, pajre 6.
t > Pa 5.
NOTES ON REINFORCED BRICKWORK. 19
External loads at failure of 165 and 151 Ibs. per square foot were taken,
vide experiments 27 and 28 respectively. A
comparison of the latter result
with that of experiment 13 on a slab containing practically the same amount
of reinforcement hut with free ends, which took only 25 Ibs. per square foot
external load at failure demonstrates the great advantage derived by having the
ends of a slab even partly fixed.
In 5" slabs the limit of steel sectional area per foot width of slab after
Mhich the failure occurs by crushing of bricks seems to be about '37 square
inch corresponding to about '75 per cent.
Table III gives tests of 6" slabs, supported on two sides. This particular type Tests of e- slabs
of slab has given the highest results in the matter of strength and should with free end8 '
showing once more the difficulty of getting perfect fixing, demonstrates the
great increase in strength derived by even partially fixing the ends. If there-
fore moderately good fixing can be relied on, it is possible to use slabs on larger
spans than would otherwise be the case.
How easy it is to produce some fixing action is clearly indicated in experi-
ment 63. In this case one of the ends of the slab merely rests on a beam and
the other is butted closely against a wall, yet a very considerable fixing action
was noticeable and the slab took 126 Ibs. per square foot, while an exactly
similar slab with free ends, vide experiment 58, took only 49 Ibs. per square foot.
A
comparison of the loads taken by similarly reinforced free and fixed
slabs, e.g., 58, 61, 62, 64 and 65 further shows clearly the advantage of fixing.
Theoretically if the fixing at ends is perfect the B. M. in the centre of the span
should be -^ as against -^g- in case of free ends, but in practice such a value
cannot be adopted with safety.
S f 8
Table IV contains the results of tests of slabs thicker than 6". The
over e t S.
object in carrying out these tests was to see how far it is feasible to adopt plain
slabs for roofs or floors on biglspaus in cases where it is desirable to have an
absolutely flat ceiling. In actual practice they are not likely to be as economi-
cal as beams and lighter slabs, and will therefore seldom be used, except
possibly in square and approximately square rooms or in residences and offices.
where appearance is the main consideration.
Experiments 68 and 69 are on slabs 8" deep made up of one brick on
edge and one brick flat, the reinforcement being -|" diameter rod and l"x" flat
bar respectively. The results obtained in the case of the round bar are more
satisfactory than in the case of the flat, but both have given quite fair results,
^he steel having passed well beyond the elastic limit before failing.
Experiment 70 on a 9" slab with a span of 20' also gives a fair result, the
failure again being due to tension in steel. The stress at failure in this case is
only about 39,000 Ibs. per square inch. This is rather low compared with other
results obtained when \" diameter rods are used. At the same time it has to be
recognised that the brick stress is fairly high, and if this be limited to say, 300.
Ibs. per square inch, the permissible total load for this slab would be, as the total
weight of the slab is 90 Ibs. per square foot, I? g (258 + 90) about 110 Ibs. per
square foot total, i.e., 110 90=20 Ibs. per square foot external load. This
would correspond to a steel stress of f" X 38,400 or about 12,000 Ibs. per
square inch nearly, so that while bricks would be fully stressed the steel
would be understressed.
Experiment 71 gives figures of a test of a 165" deep slab on a 30' span.
The failure in this case is again due to crushing of bricks. The compressive
stress works out to 1,872 Ibs. per square inch. Here the dead load alone would
ensure a compression stress in the brickwork in the neighbourhood of 350 Ibs.
per square inch and to ensure the stress in the brickwork being kept within the
permissible limits the steel will have to be very much understressed. Another
solution would be to deepen the slab, but this would, of course, add considerably
to its weight.
9" slabs (composed of three courses of bricks laid flat reinforced in both
directions, vide pages 22 and 23) have been extensively used with excellent
results in rooms of large span in the new building for the Allahabad Bank
recently constructed at Patna.
Although more expensive perhaps than 6" slabs with beams at intervals,
9" slabs have undoubted advantages in that :
pared with K. c. beyond doubt that both types of structure behave in a similar manner, the only
difference being that R. C. slabs are staffer owing to their higher modulus of
elasticity. This is what one would expect. It therefore follows that a theory
similar to reinforced concrete theory holds for R. B. structures.
NOTES ON REINFORCED BRICKWORK. 21
with patent stone finishing has exactly the same final strength as a reinforced
concrete slab of the same effective depth. A comparison of the results
obtained in experiments 79 and 87 shows that a R. B. slab finished with 1*
artificial stone takes 259 Ibs. per square foot as against a R. C.slab which
takes 2GO Ibs. per square foot, both baving practically the same reinforce-
ment and effective depth. These results are very close, and it is justifiable to
infer from them that the strengths are the same. The reason is obvious as in
both cases the steel takes the tension, while in the concrete slab all the com-
pression is taken by concrete and in the R. B. and patent stone slab nearly all
is taken
by the patent stone. A glance at the stresses will show that the
failures have all taken place well after the point of elastic limit of the steel and
the tests are therefore satisfactory.
In a similar manner lime terrace on a roof, once it has set also increases
the strength very much (owing to the increase in effective depth). Results of
tests on such slabs are given in table V, experiments 88 to 91. All experi-
ments carried out on slabs finished with lime concrete terracing show that the
slab and the terracing act together and not separately as might have been
expected. No tendency for the two to separate has ever been noticed.
The results of these experiments as noted above show conclusively that the
gain jn strength due to patent stone or terrace is very considerable, provided
always that the slab is not a continuous one. The following precautions are,
however, necessary if this gain is to be made use of in designing :
(1) Patent stone shoiild be laid along with or soon after the slab and
stirrup-shape bindings should be given to join the patent stone to
the slab. If the patent stone is done sometime after the slab is
constructed there is the possibility of the two separating in course
of time.
(2) Terrace takes a long time to set and should be allowed at least three
months before it is stressed ; even then it is not desirable to count
too much on the extra strength. It is better to look on it as in-
creasing the factor of safety. A
reference to experiment 91 table
V
will be of interest in this connection.
In all cases when the slab deflected the corners only lifted slightly from the
bearings.*
The stresses have been calculated on the assumption that the theory adopted
by the French Government, which gives the bending moment reduction coeffici-
ents as -$for the shprt span and jpyj for the long span in the case of slabs
sp
reinforced in both directions is correct ; r being the ratio '." ^ t p n .
FlGUltE 11.
Tests of Cantilevers.
causes, faulty construction in case of No. 122. Other results are fair, the stresses
in steel at failure varying from about 32,000 Ibs. per square inch to about 50,000
Ibs. per square inch.
Perhaps the lower resisting qualities of the cantilever are due to the com-
paratively excessive deflection which naturally takes place. This damages the
brickwork in tension. Although not recommended as a form of construction for
overhanging balconies likely to have to carry loads, it can be used very easily and
cheaply for chhujjas and cornices. Balconies if likely to have to sustain heavy
loads are best constructed by carrying an ordinary slab over B,. S. joists built
into the wall.
"
Experiments 123, 124 and 125 are on stepped" cantilevers the depth of
which increases towards the bearing. These have given good results.
127 the results are rather low owing to the fact that an insufficient covering of
mortar was given to the reinforcement. Experiment 129 is a failure due to the
slipping of reinforcement at the ends, thus again showing that with hoop iron*
nud flat bars adhesion is low.
Experiments 132 to 135 are interesting as showing that brickwork in lime
over a lintel combines with the B. B., once it has set, and increases its strength
immensely, while experiments 136 and 137 show the dangers of relying too early
on the strength of lime mortar as this takes a long time to set.
NOTES ON REINFORCED BRICKWORK.
Tests of R. B.
teams. Acomparison of experiment 138 (free ends) with experiments 139, 140 and
(butted ends) shows the advantages derived by butting which is partly
in the nature of fixing.
Failures of 11. B. beams when due to excessive tension in steel or exces-
sive compression in brick are very similar to slab failures. But there are two
other ways in which failure may occur in beams :
FIGURE 12.
Tests of R. 3.
rectangular
Table X
gives results of tests of rectangular beams. These are all
beams. satisfactory, the failure stresses in steel varying from about 50,000 Ibs. per
square inch upwards.
Experiments 142 and 151 show examples of shear failure, the shear stress
in the case of the former being 78 and in the latter 66 Ibs. per square inch.
There was, however, very little shear reinforcement provided. Tests 146 and
147 are interesting 147 is of a beam entirely composed of R. C., while 146 is of
;
appro nate shearing stress being about 170 Ibs. per square inch. In other
cases where shear- reinforcement was less it may be noted that the failure due
to" shear occurred at about 130 Ibs. per square inch.
Test 154 is of an inverted T beam. This type of construction is sometimes
useful where flat ceilings are essential, and the result shows that it may be
relied on if proper allowances are made for shear and direct tension.
On the whole these "experiments show that stirrups are a sound type of
reinforcement againstSshear, and that if reinforcement has heen given to take
up the whole shear the beam may be relied on to take its full load. The shearing
stress must, however, not exceed about 60 Ibs. per square inch in the masonry.
Experiments 156 to 158 are all on T beams and the results show that
the slab acted along with the rib and that there was no tendency for it to
separate even in experiment 158 when there was a definite horizontal joint
between the slab and the rib.
Experiments 155, 159 and 160 all had bricks arranged in horizontal courses :
there was, however, no tendency towards cleavage. The beam acted as a whole
throughout.
Table XII gives the results of tests of R. S. joists embedded in brickwork. Tests of embed-
'
Joists are often embedded in masonry or concrete, generally for the sake
of appearance but also sometimes to prevent rusting. It is not always realized,
however, that if this be done carefully the strength of the joists is increased
very materially. For instance, if a slab is continous over a joist it increases
the strength of the joist very much if the upper flange is built 2 or 3 inches
into the slab, and its bottom flange covered over with cement concrete or brick-
work, adequate stirrups being also provided for additional binding. The
joist when in conjunction with the slab acts practically as a T beam and its
strength is thereby increased considerably.
Experiment 161 gives the deflections of a plain joist under certain loads.
The results may be compared with experiments ] 62 and 163 which have the
same section of joists boxed up and built into a slab.* The plain joist takes
only 3'39 tons at failure, whereas the structure in expei'iment 162, takes 9 tons
and in experiment 163, 13'65 tons. The load taken on test 162 being less
than that in test 163 shows that it is better to box up the whole joist than
leave the lower flange unboxed.
Other figures in the same table show the results of embedding joists of
larger sections and the loads actually taken when compared with those which
could be expected according to K. C. theory, both being tabulated, thus
showing clearly that the increase of strength is definite, determinable, and often
considerable.
The failures in the case of the lighter sections, viz., 4<" x 3", vide experiments
162 and 163 occur in the ordinary way by tension in steel, but when the section is
heavy there is a tendency for separation to occur between the slab and the joist.
Stirrups are therefore very necessary.
Table XIII gives the results of tests of R. B. partition walls suspended Tests of R.B.
from main walls. Experiments 167 and 168 are tests on 3" walls, the rest on 5* walu
'
avails. These walls were given reinforcement oh both sides to withstand lateral
thrusts, but were tested as beams. The failure in most cases is due to shear,
the great depth being enough to make the tension in the steel very low.
Failure stresses in shear vary from about 60 Ibs. per square inch, in experi-
ments 167 and 170 (not reinforced for shear) upwards. Diagonal rods appear
to play a considerable part in resisting shear action.
Table XIV gives the results of tests of heavily reinforced slabs suit- Tests of slabs
able for decking for road bridges. They have taken most of the customary brldg^'dccking.
road loads and failures have occurred at high stresses. The results are therefore
satisfactory.
Table XV gives the results of tests of lintels and slabs without reinforcement Tests of imtei-,
6
tested transversely. They bring out the general fact that by breaking joint o'n two'sWe's*
in the lower courses the tensile strength of brickwork is increased. The and of siabs
tensile strength of brickwork with straight joints according to the lowest foursiHes, an
results is about 50 Ibs. per square inch after 7 days, but other results give without run-
about 120 Ibs. per square inch after about three weeks, vide experiment 20 I .
* ride
Corrparativc Table 6, Yol, II.
26 NOTES ON REINFORCED BRICKWORK.
non-reinforced slabs are not suitable even for small spans as they might
very well collapse during a severe earthquake.
Adhesion tests. Experiments 210 and 211, table XVI, show the extent of adhesion existing
ordinarily between bricks and mortar. The results are quite low, the average
being about 25 Ibs. per square inch.
Experiment 212 gives the tensile strength of bricks tested like cement
briquettes, the average is about 171 Ibs. per square inch.
Experiment 213 shows the amount of adhesion between steel rods and
mortar. This is a most important point and one which deserves close study as
the whole action of reinforcement depends upon the existence of this adhesion.
The tabulated results show that round rods give better results than flat rods
and that 2 1 mortar gives slightly better results than 3 1 mortar. The
: :
adhesion between round bar and 2 1 cement mortar is 512 Ibs. per square
:
inch at 28 days. In 3 1 mortar it is 276 Ibs. per square inch at 7 days and
:
382 Ibs. per square inch at 28 days. In the case of flat bar the figures are
lower, the adhesion between 2 1 mortar being only 143 Ibs. per square inch
:
after 28 days.
Only a portion of these tests, those of bricks alone shown in table XVII(a),
were carried out at Patua ; most of the others, those shown in tables XVII (b) to
(e) were carried out at Sibpur Engineering College, while some were made
at Delhi.
From most of the compression tests it appears that failure is generally due
to the tensile stresses developed in vertical planes owing to the tendency of the
specimen to bulge sideways when compressed. This was proved by the appear-
ance of vertical cracks at failure.
Tests of bricks In Patna the tests were made on small brick cubes about 2"x2"x2" cut
alone.
out of local first class bricks and although the contrivance employed, in the
absence of a testing machine, sketched on table XVII(a) was rather crude the
results show a surprising degree of uniformity. The tests give a crushing strength
varying from a minimum of about 1,100 to a maximum of about 1,600 Ibs. per
square inch. The actual average of fourteen tests is 1,331 Ibs. per square inch.
Some whole bricks were also sent to Sibpur College and tested there. The
results, although good, are not very uniform. This may be on account of the
irregularity due to the frog mark on the bricks. Experiment 241, table XVII(d),
gives 1,418 Ibs. per square inch as the crushing strength while experiments
239 to 241 and 265 give 2,128, 1,497, 1,418 and 838 Ibs. per square inch
respectively as strength at first sign of cracking and 2,850, 1,900, 1,418, 1,535
at final faikire. It must be admitted that 2,850 is unaccountably high while
838 is low.
In the caseof cubes tested in experiment 241 it was observed that the first
crack appeared at about 85 per cent, of the breaking load. The average crushing
strength of fourteen specimens at total failure was 1,331 Ibs. per square inch.
This would mean an average of 1,331 X $j 6
5
=
1,130 Ibs. per square inch at first
sign of cracking. Combining this result with the above we get an average of
1,172 Ibs. per square inch at first sign of cracking.
From these results it would appear that a good first class brick at Patna
has an average crushing strength of about 1,170 Ibs. per square inch at first sign
of cracking and about 1,400 Ibs. per square inch at final failure.
NOTES ON REINFORCED BRICKWGBK. 2?
Table gives three tests which give an average of 65G Ibs. per square
XVII (a)
inch as the comprcssive strength of lime concrete at six months. As noted
J ^^
e
e
lime
elsewhere, however, lime concrete takes a long time to develop its full strength.
T 8ts * t>ck
Compressive tests of brickwork in cement mortar give a wide range of ?
results. These are shown in tables XVII (b) to (e). Even similar mortlr wit^
reinforcement
specimens when tested gave considerably varying results. There is also a
considerable variation in the ratio of the loads at first sign of cracking to the
final breaking loads.
Tables XVII(b) and XVII(c) give results of tests on brick pillars without
reinforcement and as regards these, speaking generally, it may be said that single
brick pillars without any vertical joints, e.g., experiments 217, 218, 242
and 243 give the highest results. The average of these is 1,407 Ibs. per square
inch at final failure at an age of say, from ten weeks to three months and
about 1,000 Ibs. per square inch at first sign of cracking. The next best
results are given by columns which have vertical joints but in which
the joints are well broken. Experiments in table XVI t(b) give the average
strength of such pillars as about 574 Ibs. per square inch at the age of twenty
days. Experiments 244, 245, 248 and 259, table XVII(c), give the average
strength after ten weeks as 936 Ibs. per square inch at failure and 701 Ibs. per
square inch at first sign of cracking. Experiments
224 to 229 in table XVII (c)
give the strength of similar pillars at fourteen weeks, and here the averages work
out to 1,082 Ibs. per square inch at failure and about 629 Ibs. per square inch at
first sign of cracking. Experiments 230 and 231, table XVII (d), give the
compressive strength at the age of five mouths as about 1,240 Ibs. per square inch
and about 1,002 Ibs, per square inch respectively at failure and first sign of
cracking.
Pillars with unbroken joints give the lowest results in compression. Thus
experiments 246 and 247 give an average strength of 723 Ibs. per square inch at
final failure and 481 Ibs. per square inch at first sign of cracking.
I is evident from the above that in brick columns the real source of weak-
ness is the continuous vertical joint. The bond between brick and mortar is weak
in tension, vide experiments Nos. 210 and 211, table XVI, and columns having
vertical joints fail earlier OAving to the tension developed in vertical planes.
When the vertical joint is not continuous the column takes a somewhat larger
load because of the fact that the tensile strength of the bricks themselves
also comes into play and helps matters.
T BtB of m -
Experiments 255 to 258, Table XVII(e) give some results of tests of com- f
bined brick and cement concrete columns. They do not show any extra strength coScrete^ohf
due to the use of concrete. The explanation of this is again the weakness of the
vertical joint where concrete meets brick. The average strength at ten weeks
is 868 Ibs. per square inch and this is not appreciably higher than the strength
of ordinary columns of brick in cement.
Tables XVII (d) and (e) give some results of tests of reinforced columns. Tests of rein-
(i) Vertical.
Safe compressive stress when the compression is ") 350 to 400 Ibs. per
limited to the thickness of one brick > square inch.
Safe compressive stress when compression is not ~) 250 Ibs. per square
limited to one brick ) inch.
Lime concrete from 60 Ibs. at the age of one month to 150 Ibs. per square
inch at the age of 6 mouths.
about TO of the modulus of elasticity for steel, E, i.e., the ratio 40 at ordi-
j^
fi
nary stresses. It also appears that is not a constant but varies with the in^
jj-
of 60 3ar the crushing
tensity of stress, its value being in the neighbourhood
point of brickwork. It is fortunate, however, that this unknown factor does not
variation in the value of calculated stresses as far as beams and
produce great
slabs are concerned. Even a
per cent, variation in the. value of -g does not
fifty
alter the stresses materially. In any case it does not seem that by adopting
the value m = 40, which appears to hold good for brickwork done at Patna,
calculations would be far out.
Tests of rein- The results of a few tests carried out of arches are shown in table XVIII.
forced arches.
The data obtained are not very valuable from the point of view of determining
the effect of reinforcement on an arch, but it shows the great strength of jack
arches and even of flat arches in lime mortar: The loads taken are high and yet
the failure is due to yielding of abutments, otherwise the loads carried would
have been higher still. Reinforcement is however very useful in places where
unequal settlement or any other action tending to produce bending
moments in the arch is feared.
certain qualities.
Special experiments carried out to test
Special tests. Certain special experiments were carried out to determine certain qualities.
These are referred to below as they do not properly fall under any of
briefly
the headings already discussed.
Table XTX contains tests which are mainly self-explanatory, the following-
deserve passing mention.
experiments in the table
271 shows that slabs may be usefully built of alight brickwork
Experiment
slab jointed to ribs of R. B. spaced at short intervals. The composite slab thus
hollows between ribs.
formed is lightened considerably by the
The application of R. B. walls and roofs as shown by experiment 273 gives
an earthquake-proof building.
Some successful methods of waterproofing R. B. slabs are given by ex-
with cement punning after
periment 274. Flushing the
slab just
is probably the most efficient. It is essential that the punning
completion
should be done at the same time as the construction of the slab, otherwise
off.
it may peel
is not harmful, vide experiment 275.
Exposure of R. B. slabs to the sun
Experiment 276 proves that R. B. slabs are fire-proof.
Shocks due to impacts of heavy weights falling on R. B. slabs are not
harmful, vide experiment 277.
Table XX, experiments 279 to 282, gives some tests which indicate how
illustrate are
failures might occur in practice, the features they
:
(a) Experiment
279 emphasises the dangers of using bad mortar.
Failure on account of non-provision of hooks at the end of lap lengths
(b)
is shown by results of experiment 280.
KOTES ON REINFORCED BRICKWORK. 29
Experiments 281 and 282 show failures due to bad alternatives for a lap
and hooks at ends.
of 50 diameters
(io) The theory accepted by the French Government which gives the
amount of reinforcement, required in cross-miuforced concrete
slabs) may be taken as applying to cross-reinforced brick slabs.
(v) In cantilevers the stress in steel should not exceed 16,000 Ibs. per
square inch.
SECTION V.
t t
Ratio of stresses .
c
n, The ratio ~ .
NOTES ON REINFORCED BRICKWORK. 31
METHOD OF DESIGNING.
(3) Calculate the maximum J5. M. at the centre of slab in inch Ibs.
S M= ml"
o~x 12 for freely supported slabs
or
-^ X 12 for slightly fixed slabs
or -75-
I <G
X 12 for well fixed slabs (not perfectly fixed slabs).
2 2
(5) Calculate the sectional area of steel required per foot width, A t
A
'
_ B. M.
'
30,000 x 86 x d
v
Assuming d slabs, 4|" in case of 5" slabs and 5f" incase of 6"
Z^ in case of 3"
slabs provide suitable reinforcement near the bottom surface of the slabs allow-
ing a cover of about V" so that the area of steel, or as actually given in 12" A e,
At the top of the slab at each end give steel corresponding to an area :
A t
to
-JJ-'
if the ends are well fixed (this is a matter of
judgment).
We now proceed to test the design
and the following steps are taken :
Find p
(i) -JgjA.
(ii) From curve tables II and III find values of a, -and t, corresponding
to this value of p.
**,
This should be about 20,000 Ibs per sq. inch. If appreciably greater than
this, more steel should be provided.
y
=-~.
(iv) Find the maximum compressive stress c from c This should
be less than 350 Ibs. per sq. inch ; if more, the depth of the slab
should be increased.
*"
2
(T) Find s the shearing stress from a = ^g xa X(i this should not
a
a x
Xfefimrter of rods in 12" width
t
(/
This should not exceed about SO. (It islusually very low.)
Tests (0) a;id (ci) are seldom necessary for slabs and are usually omitted.
Freely supported slalxs for any loading may also be designed directly from
curve tables V, VI and VII.
Design of slab supported on all four sides reinforced in two
directions.
In designing a slab supported on all four sides the following steps are
taken :
(2) From curve table IV find oC the factor for long span correspond-
ing to this value of r and also ft the factor for short span.
(3) Find the actual M. on the long span, JJML ,from the following
.
-20,000 x -85 x d
(5) Provide steel according to the values of A determined in (4) on the t
In case of three spans or more ^ x!2 for supports next to the ends, and
72 7 2
~j- X 12 for all others. Incase of two spans nX 12 for the only inter-
mediate support. If the supports are not quite rigid the B. M.. are less.
When R. B. beams (which are fairly wide in the rib) are used as intermediate
mpports it is usual to make the clear span from rib to rib equal. This further
reduces B. M,.
The positive B. M. in the centre of spans is generally taken as ^--XlS.
The reinforcement in the centre of the spans should be near the bottom
surface of the slab and over the intermediate supports near the top surface. It
is usual to provide top reinforcement at the ends to the extent of half of what is
provided in the middle of the spans even though the ends are supposed to be free,
as it has been found from practice that there is nearly always slight fixing.
If possible the bottom and top reinforcement should be connected to each
other.
Design of lintels, rectangular beams, and cantilevers.
"Unimportant should be designed in the same way as fixed slabs, and
lintels
This should be 5" if the spans are up to about 11' centre to centre of
beams but 6" if
up to 14'. Spacing of more than 13' to 14' is
not economical.
(2.) Decide upon the depth of the beam, viz., from top of slab to bottom
of rib as far as the centre of gravity of the steel, i.e., d. This
should be about & of span of the beam but the total
depth
in inches of beam should be about d"+2" for cover.
FlGUKE 13.
1= span of beam.
d= depth of beam.
d, depth of slab.
~
11,000 x d
Now proceed to test the design as before.
Faber and
Bowie's Reinforced Concrete Design, 1919, 2nd Edition.)
(?/) Calculate
Iculate the stress in steel f t
=- *'lf X d
'
SO to 90 Ibs. per sq. inch for round steel and 50 Ibs. per sq. inch
for flat steel.
Some fully worked out examples of designs are given in the following
pages.
Example No. 1.
A slab for a roof 5' span carrying 4" beaten lime concrete terracing and
subject to 25 Ibs. per sq. ft. live load,
supported on walls on both sides with-
out any parapets.
The clear span is 5' and the loads are ordinary and light ; therefore a 3"
slab will be suitable.
say 90 Ibs.
The ends are free, therefore the maximum B. M. in centre of span
ml"
-Q-
X 12 inch Ibs.
= 90x5x5x1-5
= 3,375 inch Ibs.
-.*
-H
J ,
f\
r -*->*
* 6
LONltlTUOIMAL 6E.CTION. CROSS SECTION.
FIGURE 14.
Assume 2'5" as the effective depth, d, to the centre of steel and let A be the
t
A =
" 3,375
'
20,000 x -85x2 -5
= '0794 sq. inch.
* This has been found
bji experiment to be the load of the coolies tamping a roof in the
ordinary manner.
In ordinary circumstances a 3" slab is suitable on spans up to 5' where the ends are freely supported
Ditto ditto 10' ditto
&' ditto 12 ditto
NOTES ON REINFORCED BRICKWOEK, 3."
Now reinforcement can only be arranged nl'trr every 5$"or 10$", termed for
convenience 5" or 10*, owing to the size of bricks, therefore the area required
0794x10-5
every 10$ width is
= ,
'070 sq. inch.
^ = .
From a reference to tables it will be seen that the sectional area of a ,"',
top to guard against cracks due to possible partial fixing action. For this
purpose it will be sufficient to bend up every alternate rod towards the end.
Figure 1, plate 3, gives the design.
b = 12"
d_ q
O /3" j_ & "\
\f TS2 )
3" _i| or 2-5" nearly.
A =
t
'076 X -^
= -0868 sq. inch.
. 100 A t
100 x -076
-
lit x 2 5
= 0-253.
Tests for adhesion and shear may be made as for beams but as the stresses
in ordinary cases are very low, such tests arc really unnecessary.
Example No. 2.
A slab tor a 1st floor, 8' span carrying 1" cement concrete (artificial stone)
and subject to 56 Ibs. per sq. ft. live load.
The clear span is 8' and the loads ordinary, therefore a 5" slab (brick on
edge) will be suitable.
Design. Consider a strip 12" wide.
(1) Weight of 5" R.B. slab . . =48 Ibs. per sq. ft.
The ends will be built into the walls and partially fixed. We may take
the positive B. M. in the centre as an ^ the negative B. M. at the ends
-^-
IS
~2Q
.
(This is a matter of judgment. The positive B. J/. at the centre may be
anything from
~ to
-^ according to the efficiency of fixing. It is
-^
when the fixing is perfect and about
~ when
7*
the fixing is nominal. The
7<jf
Then M, E. =A Xf X a
t t
=A x 20,000 x -85d
t
B. M. =
8,909 inch Ibs. per 12" width.
b = 12"
d = 4-4" (as actually
A,
- '098 x |g = '1176drawn).
sq. inch.
JW^_W)x-1176
6d 12lT4-2~"
= -223 from curve tables II and III we have
a,
= '887
t,
- 76-0
d( x a, x d
_~ 8,909
-11'.'6 x -887 x 4-4"
c __ ft_ _ 20,430
v
t
76
= 269 Ibs. per sq. inch which is within the safe limit
tor slabs.
NOTES OK REINFORCED BRICKWORK. 37
Example No, 3.
Aslab for a roof 11' spaa carrying 4" of lime concrete terracing and 25 Ibs.
as free.
per sq. ft. external live load, ends to be treated
The clear span is 11' and the loads ordinary, a 6" slab will be suitable.
Design. Consider a strip 12'' wide.
The loads are-
Weight of 6" slab . . . =58 Ibs. per sq. ft.
= 37 Ibs. per sq,
Weight
Live load ....
of 4" terracing .
ft.
120 x 11 x 11 x 12
8
Then as before A =- t
a
=
21,780
B,M.
20,000 x -85 x d
102 B< 1
"
From a reference to tables it will be seen that the area of a f rod is '11 sq.
"
inch, hence a f diameter rod every 5|* apart will do. Allow of this at the top
at ends, as before.
The sketches for this design are given in plate 3, figure 3.
- ~~~
100 A* 100 x -24
~ '24 x21,780
-865x5-7
= 18,410 Ibs. per sq. inch which is safe.
Example No. 4.
The loadsare-
Weight of 6'slab . . . . 58 Ibs. per sq. ft.
- in
X 12 X ft inch Ibs.
~g-
120 x 15 x 15
= g
-
X 12 X '39
= 15,795 inch Ibs.
Assume 5'3" as the effective depth on the long span and 5'6" as the effective
depth on short span, then
A t
on long span =
j d
___
"
12,442
^
20,000 x^ -85 x 6-3
= '139 sq. inch.
If reinforcement is
placed after every brick, the spacing centre to centre
will be about 10|".
-
'
9 10 5
Reinforcement required in 10|" width is -
^ -J2 sq. inch,
try
a I" diameter rod the area of which is '11
A t on short span = x x -
sq. inch.
%
-^
f t
_~ ___ 5,7 9 5
= 20,000
a,
J.
x^SSlT^G
'166 sq. inch.
,
(I
_
The joint m tWs case may be assumed f thick, hence area required in
lOf
which
is
is
'166
-jjp
'1503 sq. inch,
= -149 sq. inch. Try a & diameter rod, the area of
-
every 10f" apart.
.
100 A t _ -156x100
Td 12 x 5-4 '194
T '
from CurvR taWes II and III
we get
and = 83-0
X a, X d
~ 12,442
NOTES ON REINFORCED BRICKWORK. 39
S'
= 20,500 Ibs. per sq. inch which is near enough to the allowable
stress to be accepted.
p = -"'
= 247 Ibs. per sq. inch, which is safe.
*t
b = 12"
el = 5'7" (as drawn).
A t
= '1503 X -TTvTT- = J.U /
'168 sq. inch.
1* M,
-At 100 x -108
12 x <r<
- -
'
for |j
= -240 from curve tables II and III we get
a = '882
and t,
- 72-0
J-f 18 700
= 2GO
c
t
- = ',
i
,
-
Ibs. per sq. inch, which is also safe.
*<
Example No. 5.
Design of Slab.
The beams for the sake of appearance might be so arranged that the span*,
clear of the ribs, are equal. This slight alteration will tend to reduce the
B. 31. in the end spans and increase B. M. in the centre span and so will do no
"* '
*)
= 110 x 9 X 9
= 8,910 inch Ibs.
--=/n^l =20,000
40 NOTES ON REINFORCED BRICKTVORK.
The area of two rods J" diameter is '098 sq inch. Hence these might lie
used. Top reinforcement over the T beams will have to be continued for | of
the clear span of the slab on each side of a rib. Top reinforcement at the ends
may also be given to the extent of a quarter of that in span.
The sketches for the slab are given in plate 5.
Design of T Beams.
Take depth of beam about ^ of the span, i.e.,and try a 15 \" deep T
1'4'
beam (including the slab) as it is
very easily made by one brick on end under the
slab.
For purposes of calculating the weight of the beam assume b r the width
of the rib to be about fj, of
spacing of beam, i.e., 11", say 12". The following
are the loads on the beams :
Slab, terrace, and live load =110 Ibs. per square foot, vide page 39 but as
the spans are continuous the actual slab load on the beam is
8
= 350,700 inch Ibs,
Taking effective depth, d = total depth from top of slab to bottom of rib less
2", we get
ft x -85 x d
_= 350,700
16,000 x -85 x!3-5
= 1'91 square inches.
Try nine rods \" diameter, A, = 9 X '1963
= T767 square inches.
To take shearing stresses provide enough stirrups to take up all the shear
in the beam and turn up three of the tension rods towards each end at 45".
= 350,700 Ibs.
.
~ ^
350,700
''
'
11,000 x 13-5
= 2 '34 square inches.
Provide fortyeight verticals each J" diameter rod in each half span
Then A 48 x '49
s =
2'35, i.e., eight sets of 3 double stirrups of \* round sec-
tion, to be distributed as far as possible in accordance with
ordinary practice.
The bricks of the beams might be made to break joint laterally.
The drawings for the design are given in plate 5.
NOTES ON KEINFORCED BRICKWORK. 41
8,910
M.
,
x rf
,
'
.-.
= 4'8 nearly.
,
Hence the neutral axis falls within the slab and all the ordinary rules apply.
a =d a ^
= 13-5 -jp
= 11-9
B. M.
'* At x x d
a,
350,700
'
1-767 x 11-9
= 16,678 Ibs. per square inch, which will do.
from curve table III *,= 72'0
c = -j ~ yg
= 230 Ibs. per square inch, which is also safe,
Shearing force
'" X a
perimeter of rods in tension available at end
8,350 .
Shearing force
lr X a,
8,350
~J5 x 11-9
= 47 Ibs. per square inch, which is safe especially as
stirrups have been given, to take up all shear.
o
42 NOTES ON REINFORCED BRICKWORK.
Example No. 6.
A
T beam joined to a 6" continuous slab to carry on 16' span, a load of
8 tons exclusive of the weight of the rib of the beam.
Take d = & of the span = $' = 20* say, total depth 22" approximately.
Assume 6,
= 10",
then the weight of the rib of the beam = if X if X 16 X 120 = 2,130 Ibs.
Load on beam = 8 tons = 17,920 Ibs.
limit, mz.,
10,000
'.# /j~
CA
" or > "
, ,
= ,n
*""
,,
=
4Q,000
11,000 x 2-0
= 2 18 square
-
inches. Give seven rods of ^
diameter each, used as quadruple stirrups in each half span,
Then A, 7 X 4 X '0767 2*148 =
bend two rods near each end at 45 to ;
give additional shear strength. For simplicity of construction the bottom 4"
or 5" should be done in concrete.
Sketches are given in plate 6.
4
n ^J- = '
^ = 174 Ibs. per sq. inch, which is safe,
t, 84
Shearing forte
8
a, Xd X bf
10,000
-S925 x 20 x 10
== 56 Ibs. per square inch, which is less than 60, and there-
fore safe, as stirrups have been provided to take up all the shear.
Shearing force
a, d x ptrimeter of the ban in tension at end.
10,000
-8925 x 20 x 4 X | x 3'14
= 72 Ibs. per square inch, which is less
k
than 90 Iba. per
SECTION VI.
,,.,,,.
........
First class bricks
Bs.
12 per 1,000
Cement
Steel ......... 3 per cubic foot.
30 per cwt.
......
4" beaten lime concrete
over roof slabs
1" cement concrete
terracing
artificial
(including materials)
81 P, W. D.
NOTES ON REINFORCED B'ilCKYTORK. ir,
Example I.
(I)
Corresponding rou'hly to the usual type of room for class rooms, barracks aiid Lo.spit.ils commonly
met with in India.
Type of roofing.
46 NOTES ON REINFORCED BRICKWORK.
Medium sized, double storied house built for Excise Commissioner. Area of roof 3,037 eq. ft.
(V). Example V.
Comparison of costs of roofs of various sized square rooms commonly met with in practice.
Table of comparative cost in Rs.
Size of room.
4.0 NOTES ON HEINFORCED BRICKWORK.
COST STATEMENT I,
21 a serf on cost of 10,029 sq.ft. of centering erected and dismantled at Patna showing quantities of material and
labour required and east per each 100 so. ft.
This table shows the cost of the brickwork portion of the slab onuMiny the cost of reinforcement which varies
with conditions of span loading, etc.
>
Materials.
50 NOTES ON REINFORCED BRICKWORK.
This table shows the cost of lintels and learns omitting the cost of reinforcement which varies with conditions
of span, etc.
Oil
OOII
0001
oo e
oo
001
OOS
COS
00
oot
00 1
01
RETURN TO the circulation desk of any
University of California Library
or to the
NORTHERN REGIONAL LIBRARY FACILITY
Bldg.400, Richmond Field Station
University of California
Richmond, CA 94804-4698
ALL BOOKS MAY BE RECALLED AFTER 7 DAYS
2-month loans may be renewed by calling
(510)642-6753
1-year loans may be recharged by bringing
books to NRLF
Renewals and recharges may be made 4
days prior to due date.
PSL Annex
Call Number:
725108 TA679
India. Public Works 152
Department.
Notes on reinforced
brickwork.
N9 725108
TA679
India. Public Works 152
Department.
Notes on reinforced
brickwork.
PHYSICAL
SCIENCES
LIBRARY
LIBRARY
UNIVERSITY OF CALIFORNIA
DAVIS
33S
1 **> .-* .