CJI3 User Manual

This document provides instructions for using transaction code CJI3 to generate project line item reports in SAP. It explains that CJI3 shows actual financial postings by cost element and cost settlements to financial and controlling accounts. The transaction code can be used to track project expenses, validate month-end settlements, and confirm settlement reversals. Instructions are provided on search criteria for the report, including a predefined layout, and it is noted that the Project Systems Analysis Area in BI is recommended for larger analyses. Key differences between the two reporting options are also outlined.

Uploaded by

papamba
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
100% found this document useful (3 votes)
5K views9 pages

CJI3 User Manual

This document provides instructions for using transaction code CJI3 to generate project line item reports in SAP. It explains that CJI3 shows actual financial postings by cost element and cost settlements to financial and controlling accounts. The transaction code can be used to track project expenses, validate month-end settlements, and confirm settlement reversals. Instructions are provided on search criteria for the report, including a predefined layout, and it is noted that the Project Systems Analysis Area in BI is recommended for larger analyses. Key differences between the two reporting options are also outlined.

Uploaded by

papamba
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 9

Job Display Actual Cost Line Items for Projects

Aid

Table of Contents

Overview............................................................................................................................... 2
1. What can the t-code do? ....................................................................................................... 3
2. How is the t-code used?......................................................................................................... 3
3. Define user-specific layout..................................................................................................... 7
4. Difference between CJI3 and Project Systems Analysis Area in BI ......................................... 9

[Display Actual Cost Line Items for Projects] Umoja Training 1/9
Job Display Actual Cost Line Items for Projects
Aid

Overview
This Job Aid explains the usage of transaction code or T-code CJI3 to generate Projec t Line Item
Reports. The transaction is assigned to users with the following Umoja Enterprise Roles:

EMPLOY_TO_DISPOSE: PLANT_MAINTENANCE_APPROVER
EMPLOY_TO_DISPOSE: PLANT_MAINTENANCE_PLANNER
FINANCIAL_ACCOUNTING: APPROVER_(AP)
FINANCIAL_ACCOUNTING: APPROVER_(AR)
FINANCIAL_ACCOUNTING: APPROVER_(GL)
FINANCIAL_ACCOUNTING: ASSET_ACCOUNTING_SENIOR_USER
FINANCIAL_ACCOUNTING: ASSET_ACCOUNTING_USER
FINANCIAL_ACCOUNTING: CLOSING_USER
FINANCIAL_ACCOUNTING: SENIOR_USER_(GL/AP/AR/CO)
FINANCIAL_ACCOUNTING: USER_(AP)
FINANCIAL_ACCOUNTING: USER_(AR)
FINANCIAL_ACCOUNTING: USER_(GL)
FINANCIAL_MANAGEMENT: ACCOUNTING_OFFICE_USER
FINANCIAL_MANAGEMENT: BUDGET_APPROVER
FINANCIAL_MANAGEMENT: BUDGET_OFFICE_USER
FINANCIAL_MANAGEMENT: EARMARKED_FUNDS_DOCUMENTS_CERTIFIER
FINANCIAL_MANAGEMENT: FUNDS_COMMITMENT_APPROVER
FINANCIAL_MANAGEMENT: GRANTS_MANAGEMENT_ACCOUNT_APPROVER
FINANCIAL_MANAGEMENT: GRANTS_MANAGEMENT_ACCOUNT_CREATOR
FINANCIAL_MANAGEMENT: GRANTS_MANAGEMENT_ACCOUNT_USER
FINANCIAL_MANAGEMENT: GRANTS_MANAGEMENT_BUDGET_APPROVER_RELEASED
FINANCIAL_MANAGEMENT: GRANTS_MANAGEMENT_BUDGET_APPROVER_UNRELEASED
FINANCIAL_MANAGEMENT: GRANTS_MANAGEMENT_BUDGET_USER_RELEASED
FINANCIAL_MANAGEMENT: GRANTS_MANAGEMENT_BUDGET_USER_UNRELEASED
FINANCIAL_MANAGEMENT: GRANTS_MANAGEMENT_MASTER_DATA_MAINTAINER
FINANCIAL_MANAGEMENT: GRANTS_MANAGEMENT_SUPPORT_USER
FINANCIAL_MANAGEMENT: MASTER_DATA_MAINTAINER
FINANCIAL_MANAGEMENT: SUPPORT_USER
PROGRAMME_PROJECT: PROJECT_MANAGEMENT_APPROVER
PROGRAMME_PROJECT: PROJECT_MANAGEMENT_USER
REAL_ESTATE: FACILITIES_APPROVER
REAL_ESTATE: FACILITIES_PLANNER
REAL_ESTATE: LEASE_CONTRACT_APPROVER
REAL_ESTATE: LEASE_PROCESSOR
SERVICES_DELIVERY: DISPOSAL_PLANNER
SERVICES_DELIVERY: NOTIFICATION_APPROVER
SERVICES_DELIVERY: ORDER_RELEASER
SERVICES_DELIVERY: PLANNER
SOURCE_TO_ACQUIRE: REQUISITIONER
SOURCE_TO_ACQUIRE: REQUISITIONER_DIRECT_PROCUREMENT

[Display Actual Cost Line Items for Projects] Umoja Training 2/9
Job Display Actual Cost Line Items for Projects
Aid

* * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * *

1. What can the t-code do?


The Project Line Item Report shows actual FI postings by Cost Element as well as cost settlements to FI
and/or CO. Please note, that CJI3 does not show any commitments or pre-commitments raised against
WBS elements.

The Project Line Item Report can be run ad-hoc to check and analyse project expenditures within a
defined time frame. Please note that a copy of this ECC report was reproduced as a Project Systems
Analysis Area in BI. For performance reasons, we recommend to go to BI for bigger analysis of project
expenses comprising multiple projects.

Based on the Project Line Item Report you can


track project expenses (e.g., good receipts, service entry sheets, payroll and travel)
validate moth-end settlements to AuCs or Cost Centers
validate full settlements from AuC to the final assets
confirm settlement reversals

2. How is the t-code used?

[Display Actual Cost Line Items for Projects] Umoja Training 3/9
Job Display Actual Cost Line Items for Projects
Aid

[Display Actual Cost Line Items for Projects] Umoja Training 4/9
Job Display Actual Cost Line Items for Projects
Aid

Note
Pre-dfined layout /PJ_AUC includes below dimensions which are relevant to month-end cost settlement;
Business Transaction (=KOAO for all cost settlements to Cost Centers)
Originial Business Transaction (=KOAE for all cost settlements to AuCs)
Reversed (indicator =X for all lines due to settlement reversals)

[Display Actual Cost Line Items for Projects] Umoja Training 5/9
Job Display Actual Cost Line Items for Projects
Aid

Note
Please note that the settlement lines will not show the settlement receiver, i.e. the Cost Center or AuC. To
run a report on settlement rules, please go to
KOSRLIST
KOSRLIST_PR (with Selection Variant)

[Display Actual Cost Line Items for Projects] Umoja Training 6/9
Job Display Actual Cost Line Items for Projects
Aid

3. Define user-specific layout

[Display Actual Cost Line Items for Projects] Umoja Training 7/9
Job Display Actual Cost Line Items for Projects
Aid

Note
! If the Default setting option is checked, the layout created will be defaulted every user

[Display Actual Cost Line Items for Projects] Umoja Training 8/9
Job Display Actual Cost Line Items for Projects
Aid

4. Difference between CJI3 and Project Systems Analysis Area in BI


Please note that the Project Line Item report was reproduced in the Project Systems Analysis
Area in BI to facilitate a more comprehensive analysis of expenditures across projects. To this
end, the below fields from the Poject Builder have only become available in BI;

Thematic Assignment 1 (UN Assignments data tab)


Thematic Assignment 2 (UN Assignments data tab)
External Symbol (User Fields data tab)
External ProjID (User Fields data tab)
IMIS Org Unit (User Fields data tab)
IMIS Prog ID (User Fields data tab)

Revision History (Soft Copy only)


Date Version Prepared by Description
18 March 1 Laura Justus Initial Draft
2016

[Display Actual Cost Line Items for Projects] Umoja Training 9/9