Bim 1 PDF

Download as pdf or txt
Download as pdf or txt
You are on page 1of 102

How To Measure the Benefits of BIM

A Case Study Approach

by

Kristen Barlish

A Thesis Presented in Partial Fulfillment


of the Requirements for the Degree
Master of Science

Approved July 2011 by the


Graduate Supervisory Committee:

Kenneth Sullivan, Chair


Dean Kashiwagi
William Badger

ARIZONA STATE UNIVERSITY


August 2011
ABSTRACT

As a term and method that is rapidly gaining popularity, Building

Information Modeling (BIM) is under the scrutiny of many building professionals

questioning its potential benefits on their projects. A relevant and accepted

calculation methodology and baseline to properly evaluate BIM's benefits have

not been established, thus there are mixed perspectives and opinions of the

benefits of BIM, creating a general misunderstanding of the expected outcomes.

The purpose of this thesis was to develop a more complete methodology to

analyze the benefits of BIM, apply recent projects to this methodology to quantify

outcomes, resulting in a more a holistic framework of BIM and its impacts on

project efficiency. From the literature, a framework calculation model to

determine the value of BIM is developed and presented. The developed model is

applied via case studies within a large industrial setting where similar projects are

evaluated, some implementing BIM and some with traditional non-BIM

approaches. Cost or investment metrics were considered along with benefit or

return metrics. The return metrics were: requests for information, change orders,

and duration improvements. The investment metrics were: design and

construction costs. The methodology was tested against three separate cases and

results on the returns and investments are presented. The findings indicate that in

the tool installation department of semiconductor manufacturing, there is a high

potential for BIM benefits to be realized. The evidence also suggests that actual

returns and investments will vary with each project.

i
DEDICATION

To my amazing family and friends and my wonderful mentors, you may not know

who you are, but I do. Ive learned that people will forget what you said, people

will forget what you did, but people will never forget how you made them feel.

Maya Angelou

ii
ACKNOWLEDGMENTS

I would like to take this opportunity to thank Dr. Sullivan, my committee chair,

for assisting me from the conceptual beginnings of my thesis to its final revisions.

Without Dr. Sullivans amazing guidance and industry knowledge, my thesis

would be incomplete. Dr. Kashiwagi and Dr. Badger were also generous in

devoting their time and consideration to be on my committee and available for

assistance.

I would also like to thank those who will remain nameless that were instrumental

to my case studies and industry data. I am thankful to those who provided me raw

data and assisted in assuring its soundness.

Lastly, I would like to thank those researchers out there that are striving to report

project data and create valuable frameworks for BIM. I am grateful for your data

and valuable insights into future research.

iii
TABLE OF CONTENTS

Page

LIST OF TABLES.................................................................................................... viii

LIST OF FIGURES .................................................................................................... ix

CHAPTER

1 INTRODUCTION.................................................................................. 1

Overview ............................................................................................. 1

Definitions........................................................................................... 1

Problem Statement .............................................................................. 5

Objective ............................................................................................. 6

Research Methodology Summary ...................................................... 6

Research Scope ................................................................................... 7

Summary of Thesis ............................................................................. 8

2 LITERATURE REVIEW .................................................................... 10

Introduction ....................................................................................... 10

Classifications ................................................................................... 10

Main Sources .................................................................................... 12

Source #1........................................................................................... 12

Source #2........................................................................................... 13

Source #3........................................................................................... 13

Source #4........................................................................................... 14

Summary ........................................................................................... 15

Determining Proper Metrics ............................................................. 18

iv
CHAPTER Page

3 RESEARCH METHODOLOGY ........................................................ 21

Overview ........................................................................................... 21

Challenges ......................................................................................... 22

Measurement Strategies for this Research ....................................... 23

Scope of this Thesis .......................................................................... 27

4 DATA COLLECTION ........................................................................ 30

Overview ........................................................................................... 30

Description of Case Studies.............................................................. 30

Metrics............................................................................................... 31

Characteristics ................................................................................... 34

5 DATA ANALYSIS .............................................................................. 35

Overview ........................................................................................... 35

Validation .......................................................................................... 35

Testing ............................................................................................... 35

6 RESULTS ............................................................................................. 37

Case 1: Returns ................................................................................. 37

Case 2: Design and Construction Investments ................................ 37

Case 3: An Areas Returns and Investments.................................... 38

Project Manager Surveys and Interviews......................................... 40

7 DISCUSSION....................................................................................... 42

Limitations: Literature ...................................................................... 42

Limitations: Case Studies ................................................................. 43

v
CHAPTER Page

8 ORGANIZATIONAL CONSIDERATIONS ..................................... 45

Overview ........................................................................................... 45

Level 1: Executive ............................................................................ 47

Corporate Strategy ............................................................................ 47

Stakeholders ...................................................................................... 48

Legal Aspects .................................................................................... 49

Level 2: Communication .................................................................. 50

Positive and Negative Effects........................................................... 51

Changing Roles and Responsibilities ............................................... 53

Unanswered Questions ..................................................................... 55

Level 3: Risk Management and Strategic Planning......................... 55

Preconstruction ................................................................................. 56

Technical Risks ................................................................................. 56

Alignment.......................................................................................... 57

Level 4: Change Management.......................................................... 58

Pace ................................................................................................... 58

Paradigms .......................................................................................... 58

Contracts ........................................................................................... 59

Summary ........................................................................................... 60

9 CONCLUSIONS .................................................................................. 62

Outcomes .......................................................................................... 62

Recommendations............................................................................. 64

vi
CHAPTER Page

Future Research ................................................................................ 67

REFERENCES ........................................................................................................ 71

APPENDIX

A LITERATURE REVIEW TABLES ................................................ 76

B FUTURE TRACKING METRICS .................................................. 91

vii
LIST OF TABLES

Table Page

1. Return Metrics ...................................................................................... 32

2. Investment Metrics ............................................................................... 33

3. Case 1: Returns from 2D to 3D .......................................................... 37

4. Case 2: Investments from 2D to 3D ................................................... 38

5. Case 3: Returns from 2D to 3D .......................................................... 39

6. Case 3: Investments from 2D to 3D ................................................... 40

7. PM Interviews ...................................................................................... 41

8. Literature Review Codes ................................................................. 77

9. Literature Review Top 21 Sources .................................................. 78

10. Literature Review Summary of Classifications ............................. 88

11. Literature Review Summary of Source Types ............................... 89

12. Literature Review Top Mentioned Benefits ................................... 90

13. Future BIM Tracking Metrics ............................................................ 92

viii
LIST OF FIGURES

Figure Page

1. Process of Measuring IT Benefits ....................................................... 24

2. Business Case of an Information System ........................................... 24

3. Business Case for this Thesis .............................................................. 25

4. Framework Development for this Thesis ........................................... 27

ix
Chapter 1

INTRODUCTION

Overview

As many have done before, a clear definition of the term Building

Information Modeling (BIM) must be established prior to discussions about the

benefits of BIM. The sheer quantity of definitions of BIM in circulation in

publications hints at the assortment and tendency for misinterpretation by readers.

In fact, most publications attempt to define BIM in their own terms and, with over

1,000 publications on this topic, BIM takes on a variety of definitions.

Technology is not new to the building industries; however, the specific

software, programs, and applications have evolved over the years, becoming

manifested as different systems. Referred to in different publications as BIM, VC

3D CAD, IS, CIC, and IT (Building Information Modeling/Management, Virtual

Construction, 3 Dimensional AutoCAD, Information Systems, Computer

Information Construction, and Information Technology, respectively), all of these

systems help to integrate the many functions of the building industries to create a

more interactive information sharing space.

Definitions

According to Jung and Gibson, CIC (Computer Information Systems) is

the integration of corporate strategy, management, computer systems, and IT

throughout the projects entire life cycle and across different business functions.

Computerized information systems (IS) are widely recognized as an enabler, not

1
only for effective project management, but also for automation of engineering and

construction tasks (1999).

Originally invented to streamline labor-intensive tasks, IS (information

systems) have become deeply interrelated with business processes and expanded

further to supporting or molding corporate strategy (Jung and Gibson, 1999). The

involvement of IS in the higher-level management structure should be measured

in order to make sure it is utilized effectively and for the correct purpose(s).

Despite the specific naming convention, computer-aided integration in

construction has recently manifested itself in the form of BIM applications and is

causing much discussion about its costs and benefits.

As noted in their evaluation of the business sense of BIM, Aranda-Mena et

al. found that, For some, BIM is a software application; for others it is a process

for designing and documenting building information; for others it is a whole new

approach to practice and advancing the profession which requires the

implementation of new policies, contracts and relationships amongst project

stakeholders (2008). There are various stakeholders that interact when BIM is

utilized, thus their perspectives must be taken into consideration when defining

BIM and establishing its benefits. In order to determine if BIM has the potential

to provide positive quantifiable project benefits, a common definition of BIM

must first be accepted.

Entire journal articles have been dedicated to surveying building

professionals, from contractors to architects and engineers, for their perceptions of

BIM and their definitions (McGraw Hill, 2009; Zuppa, 2009; Becerik-Gerber and

2
Rice, 2010; FMI and CMAA, 2007), focusing on their differences rather than

similarities. The McGraw Hill The Business Value of BIM Report, a

commonly referenced document by contractors, defines BIM as, The process of

creating and using digital models for design, construction and/or operations of

projects (2009). In The Business Value of BIM Report, the contractors

perspective is the dominant reference for BIM, putting BIM in terms of its

technical aspects as a model or documentation tool (2009). Another definition of

BIM as, an intelligent 3D virtual building model that can be constructed digitally

by containing all aspects of building information into an intelligent format that

can be used to develop optimized building solutions with reduced risk and

increase value before committing to a design proposal, focuses on the design

perspective (Woo et al., 2010). Zuppa, et al. found that, BIM was most

frequently perceived of as a tool for visualizing and coordinating AEC work and

avoiding errors and omissions (2009). The literature fails to define BIM more in

terms of the owner, another important stakeholder. There is no agreement on the

definition of BIM nor a consensus of the outcomes multiple stakeholders

(contractors, architects, engineers, and owners) will receive from its utilization on

a construction project.

For the purposes of this paper, the definition credited to the National BIM

Standard (NBIMS) is used as, A Building Information Model (BIM) is a digital

representation of physical and functional characteristics of a facility. As such it

serves as a shared knowledge resource for information about a facility forming a

reliable basis for decisions during its life-cycle from inception onward. The BIM

3
is a shared digital representation founded on open standards for interoperability

(2006). This definition focuses solely on BIM containing adequate life-cycle

building information and does not refer only to one group of stakeholders, thus it

is used as the underlying definition and purpose of BIM for this paper.

Furthermore, the mention of 3D is used interchangeably with BIM unless

otherwise noted, and 2D is used to denote non-BIM or standard construction

procedures that do not utilize BIM or 3D as a tool.

The frequency and variety of the definitions of BIM illustrate the

confusion in defining and quantifying BIM and putting it in terms of potential

benefits. This deficiency not only prohibits the collaborate process between

stakeholders, but it also makes the measurement of BIMs effectiveness too

general and qualitative. For example, architects are more likely to see the benefits

of BIM as enhancing coordination, productivity, and business operations; whereas

contractors see improvements in scheduling, estimating, and drawing processing

(Zuppa, 2009). Furthermore, as the perceived benefits differ across stakeholders,

comparisons of benefits across projects becomes exponentially difficult to obtain

and non-uniform. Despite the industry-perceived potential for BIM, most

construction organizations do not utilize a formal methodology to evaluate its

benefits (Becerik-Gerber and Rice, 2010). There is a need for a relevant

methodology to evaluate the expected benefits of BIM on any type of project,

from a business perspective, in conjunction with a valid baseline.

4
Problem Statement

The utilization of BIM has not been empirically and clearly established to

be beneficial to the overall outcome of a construction project. Owners are faced

with the dilemma of making a decision of whether or not to utilize BIM based on

speculated benefits. The largest barriers to BIM implementation and acceptance

across the building industries are recognition and enforcement by owners and a

balanced framework for implementation that considers both monetary and

managerial outcomes (Succar, 2010). In fact, the latter is a prerequisite for the

former, as owners are looking to adopt BIM as a tool once it has been proven

effective.

Some of the challenges with establishing BIMs effectiveness are the

varying nature of partial frameworks and case studies presented by the literature

regarding BIM. The literature presents results that are qualitative and not easily

compared. Many frameworks focus on the general implementation, rather than an

analysis of the choice to implement (Jung and Joo, 2011 and Taylor, 2007).

Furthermore, the proof in existence does not appeal to an executive or someone at

the business level that is prepared to make a decision such as whether or not to

employ BIM as a tool. At the executive level, a proper BIM business case

would need to be established that contains some of the vocabulary and relevance

to upper level management in the particular company, as well as a plan or

framework for implementation.

5
Objective

The objective of this thesis is to empirically measure BIM data from 2D

and 3D projects to determine if the utilization of BIM can be beneficial in

construction projects. Furthermore, it is the goal of this thesis to provide case

studies of BIM benefits via an examination of 2D versus 3D projects at a

particular organization.

As highlighted by Succar, it is as equally important to establish metrics

and benchmarks to assess overall performance and benefits derived from BIM as

it is that those metrics are to be consistently accurate and adaptable to different

industry sectors and organizational sizes (2010).

Research Methodology Summary

Prior research methodologies found in the review of past literature were:

case studies, surveys, interviews, and individual analyses and theories. According

to Bakis et al., a case study is the most appropriate investigation method for the

business benefits of new information technologies, when compared to the formal

experiment and the survey (2006). Case studies present the information in the

context of a particular project, inclusive of the projects characteristics and give

actual project data. Experimentation and surveys are ineffectual because the

impact of a new system has variables and factors that cannot be extracted out of

the original context. Furthermore, the business benefits of a new system are

commonly a victim of subjectivity, perception, and general estimation via surveys

and interviews (Bakis et al., 2006). Another commonly used method is for an

individual to assign a weight to each of the potential benefits of the system,

6
especially those that are intangible, to determine its importance. Then a rating of

impact could be assigned based on the magnitude of the impact the benefit could

have on a particular business process. Once again, these are subjective

determinations (Bakis et al., 2006). The subjectivity of methods to assign value to

BIM, from interviews to surveys, makes quantification and comparisons of

benefits across projects ineffectual. Furthermore, a benefit and measure of

success can also have different meanings depending on the individual. This

thesis sought to present data in the least-subjective and most quantifiable context.

The research for this thesis involved two parts:

Part 1: An analysis of the literature regarding BIM and its potential

benefits

Part 2: Case studies of a particular organizations 2D versus 3D projects

and resultant benefits analysis

Research Scope

The scope of this thesis is to provide a business case for BIM utilization

for project stakeholders faced with the decision of whether to employ BIM in

their construction projects, most commonly referred to as owners. As

evidenced by the literature, the owners perspective is rarely conveyed in

estimation of BIMs benefits, thus this thesis focuses on that perspective.

This thesis has limitations due to the nature of the project data available

with regards to BIM. The first limitation is on the metrics as quantifying cost and

benefits of IT investments will produce results that are immeasurable, such as:

efficiency, effectiveness, and performance (Andresen, 2000). The second


7
limitation is on the variety of methods in which historical project measurements

could have been recorded. This is a challenge that can be mitigated via project

review meetings, where stakeholders are present to review the data. Lastly, the

chosen method (i.e. case studies, surveys, experiment, etc.) will have limitations

and associated challenges. These are discussed in Sections 2.2, 7.1, and 7.2.

Summary of Thesis

This thesis documents and seeks to measure the benefits resulting from the

utilization of BIM in construction projects. The following is a summary of the

thesis.

Chapter 2 presents a review of the literature regarding BIM and potential

benefits, with an analysis of the data presented from the top four sources.

Chapter 3 describes the research methodology including discussions on

the challenges, general methods, measurement strategy, and scope of this

thesis.

Chapter 4 demonstrates the data collection conducted and metrics

established for the measurement of the benefits of BIM utilized in the

subsequent Cases as described.

Chapter 5 provides more detail on the data analysis methods employed.

Chapter 6 presents the results of the said Cases, and quantifies the benefits

of BIM according to the metrics set forth in Chapter 4.

Chapter 7 initiates discussion of the results presented.

8
Chapter 8 delves into organizational, intangible precedents and outcomes,

specifically: executive, communication, risk management, and change

management.

Chapter 9 concludes with final thoughts on the case studies as well as

identifies future implications and research concerning BIM and benefits

analysis.

9
Chapter 2

LITERATURE REVIEW

Introduction

A review of the literature was performed to analyze the current

information available with regards to benefits derived from BIM utilization, with

the goals of: 1) determining the proper metrics for measurement of BIM benefits;

2) seeking the results or data of those metrics from a variety of projects; 3)

assisting in the further development and insight into an applicable benefits

framework model to be applied to the case studies in this thesis as well as to

future projects.

After analyzing over 600 sources of information including: journal

articles, conference proceedings, published case studies, press releases,

professional presentations, and online articles, there remained twenty-one sources

that had some information regarding the benefits gained from BIM utilization, but

in general terms. These twenty-one sources were publicized and/or published

within the past ten years, thus representing recent data with respect to BIM. The

twenty-one sources obtained were organized according to a system that assigned a

classification of data presented. For comparisons of the twenty-one sources,

please see Tables A1-A4 in Appendix A Literature Review.

Classifications

The first classification of the literature was case study and quantifiable

findings, this represented studies that contained quantified measurements of the

benefits of BIM presented from a case study. The second classification was case

10
study, in which a BIM project was analyzed, but no numerical benefits or

measurements were presented. The third classification was case study and

model or process, this type presented a case study and a model about how the

benefits of BIM were obtained excluding any quantifiable savings as a result of

BIM utilization. The fourth classification was model or process, in which a

framework or suggested evaluation process was put forth, and, was either (1) not

used on a BIM project or (2) if claimed to be utilized on a project, no quantifiable

results were presented. The fifth classification, survey, contained independent

surveys that were carried out, asking various questions of different individuals,

soliciting their opinions or perceptions of the concepts and benefits obtained from

BIM utilization. The sixth classification, survey and case studies, contained a

survey from a specific project and, in some cases, interviews of team members of

a project in which BIM was utilized. The seventh and final classification, theory

and general assumptions, contained publications that presented a framework or

suggested benefits ungrounded in actual BIM project data. No one source had a

framework model, applied it to a project to be made into a case study, and

presented quantifiable case study data.

As stated previously, each type of data classification (case study,

experiment, survey, and interview) has various constraints and barriers to

establishing a universal benefits analysis of BIM (Bakis et al., 2006). See

Appendix A for summary tables of the literature review that presents general

findings, sources, and issues related to utilizing the data for comparisons on other

BIM projects. Overall, there were the most classifications of: 01 case studies

11
and quantifiable findings; and 07 theories and general assumptions. The

highest frequency of source type was 01 journal article.

Main Sources

From these twenty-one sources, there remained four sources with some

quantifiable results based on case study data. These four sources were carefully

examined to extrapolate any usable data. Below, a summary is provided for these

sources and the data they presented.

Source #1

In Garrett and Garsides case study, a new semiconductor fab is

constructed, termed as basebuild, and 3D modeling was utilized six months

after design commenced (2003). Garret and Garside found that this pilot program

represented slightly less than 1 percent of the total project cost, with conversion of

the 2D model accounting for approximately 75 percent of the total pilot cost, and

the model saved more than the cost of implementation. The analyses classified

savings as: identified physical conflicts (clash reports) saved $0.75M; schedule

conflicts (scheduling interface) saved $1.2M; and data conflicts (attribute

management) saved $0.5M (2003). Furthermore, Garrett and Garside estimate

that in the future, BIM could have the outcomes of, Overall reduction in design

time would be on the order of 20 percent to 50 percent, possibly greater. In their

article, they state that construction management and finance management teams

were able to jointly define a method of measuring the relative value of savings

and avoidances, a third party Quantity Surveyor was hired to assign values to

other savings and avoidances, and subcontracts were developed with highly

12
detailed scope (Garret and Garside, 2003). The calculation methodology of

project returns and investments for BIM is unclear in this source.

Source #2

J.C. Cannistrato, a Plumbing, HVAC, and Fire Contractor in the

Massachusetts area, utilized data from 408 projects over 6 years totaling

$558,858,574 to quantify how much BIM saved them (2009). In their company

press release, they reportedly found that change orders for 2D projects

represented 18.42 percent of base contract, change orders for 3D projects

represented 11.17 percent of base contract, and change orders for Collaborative

BIM projects represented 2.68 percent of base contract (Cannistrato, 2009).

These results are taken from the Mechanical Contractors perspective and are

limited in their application to other case studies. Additionally, the results are

published in a general company press release and are not subject to peer review.

Source #3

Khanzode et al. presented a case study of fast track project for a new

$96.6M Medical Office Building (MOB) facility and parking garage (2008). In

their analysis of BIM on this project, Khanzode et al. reported, MEP systems

include labor savings ranging from 20 to 30 percent for all the MEP

subcontractors, 100 percent pre-fabrication for the plumbing contractor, only one

recorded injury throughout the installation of MEP systems over a 250,000 square

foot project area, less than 0.2 percent rework for the whole project for the

mechanical subcontractor, zero conflicts in the field installation of the systems

and only a handful of requests for information for the coordination of the MEP

13
systems between contractors and the designers, 6 months savings on the

schedule, and about $9M savings in cost for the overall project (2008).

Furthermore, via project team member interviews and stated opinions, they found

zero change orders related to field conflicts on this project (compared with an

estimated 1-2 percent of the cost of MEP systems) and 2 RFIs relating to field

conflict and construction related issues. According to Khanzode et al., the

project team compared this fast track project delivery to a traditional Design-Bid-

Build project delivery to compare how much savings accrued due to the use of

VDC tools and a fast track project approach that hedged the effects of inflation.

This study indicates a savings of $9M and 6 months to the owner due to the use of

the BIM / VDC tools and a collaborative project delivery approach (based on

escalation of: 2004 = 3.4 percent, 2005 = 10.5 percent, 2006 = 7.5 percent)

(2008). Some distinct variables include: the costs and savings are only related to

MEP systems and those contractors opinions, the designer did not participate, no

formulas are presented, and estimates of costs and benefits are based on opinions

of project team members.

Source #4

Kuprenas and Mock utilized a BIM case study of Central Los Angeles

Area New Learning Center #1 (2009). In this 685,000SF facility with an

elementary school and middle school, the Intra-trade BIM model benefits and

cost savings realized were: (coordination-inserts) reduced rework - $50,000 and

shortened construction durations - $10,000; and (visualization - underground

electrical) sequencing - $250,000; (sequencing-MEP and FP systems)

14
preassembly - $25,000, bundling - $10,000, and shop fabrication - $25,000

(2009). Furthermore, the Inter-trade BIM model benefits and cost savings

realized were: (coordination) conflict checking (between trades) - $4,000,000 and

(visualization-underground electrical) bulletins - $250,000 (2009). These results

are taken from the contractors perspective, not founded in background

calculations or methodology, and are limited in their application to other case

studies.

Summary

From these four sources, no data existed on the methodology with which

to calculate returns on other projects and how to form a valid comparison of 2D

vs. 3D methods to extract benefits. Additionally, from the four sources, only one

remained that was specifically applicable to the background metrics set forth by

this paper. Upon further analysis of the most applicable journal article, Source

#1, it was discovered through communications that the past project team members

disagreed with the findings presented. Source #2, while it provided some

quantifiable findings, was taken from a company newsletter, thus the source

credibility can be in question. In Source #3, the data was based on a narrow scope

and a smaller project, making it difficult to generalize the findings. Source #4

was limited to the contractors perspective and was from a specialized project.

Furthermore, all sources case studies suggested different measurements, focused

on new construction, and had varying definitions of BIM.

The results of the literature review performed here are in agreement with

other literature reviews carried out on the topic of BIM and BIMs expected

15
outcomes, asserting that both case studies and academic research fail to analyze

and quantify universal benefits and costs of BIM on a project (Becerik-Gerber and

Rice, 2010; Succar, 2009). Unfortunately, in FMI and CMAAs eighth annual

survey of owners they found that, Nearly 25 percent of survey respondents do

not know how much information technology (IT) related spending takes place

on individual projects to support achieving project objectives (2007). Thus, the

current methods for the evaluation of BIM and information systems related

benefits are not sufficient as they do not promote a dominant framework

methodology and visibility to comparable data on other projects. Participants in

FMI and CMAAs survey of owners agree that there has to be a strong business

case focused on ROI and value added, for all parties involved, to commit to BIM

use (2007). The need for a proper business case, consisting of a framework

methodology and baseline, to evaluate the benefits of BIM has gone unmet.

The outcome of the literature review proved that there is neither a

consistent approach within individual organizations nor a consistent approach

across organizations to evaluate BIM or similar information systems benefits

(Andresen et al., 2000; Succar, 2009). Furthermore, current frameworks are

ineffective as they show a fragmentation in the very core of BIMs goals, such as,

Scheduling, estimating, and design are the most demanding areas where the

discrepancy between the practitioners needs versus actual exploitation was found

to be significant (Jung and Joo, 2011). When the system is not meeting the very

intent, such as project efficiency, it becomes clear that the initial process and

framework were not clearly defined. In order for a framework to be effective, the

16
strategies for implementation via the framework should be examined and

evaluated (Jung and Joo, 2011). The system cannot stand on its own; it needs

consistent measurement and evaluation.

The dilemma faced by owners regarding BIM utilization is due to a lack of

dominant and transparent performance information that establishes BIM as being

beneficial in construction projects. Information Management Theory (IMT), as

established by Dr. Dean Kashiwagi, holds that, when the key information is

available, no decision is required (2011). However, when choosing whether or

not to employ BIM on a particular project, owners do not have information to

substantiate their decision in a transparent fashion. That is, the literature has

illustrated that projects have determined potential benefits of BIM, but few

quantifiable measurements and sparse framework methodologies for benefits

calculation are present. Therefore, no conclusive information can be stated and

owners are left to make a decision without a business case.

With BIM being promoted as a coordination tool and a way to align

resources, it is quite contradictory that the resources BIM is alleged to conserve

are not measured themselves. As such, IMT theory would predict that a

convoluted perspective of BIM will result in a further complex implementation of

BIM, should an owner decide to implement without a business case. The lack of

measurements prior, during, and after BIM utilization in a company on a

particular project hint at the lack of a framework to alleviate this void for owners.

17
Determining Proper Metrics

The determination of what to measure and who to measure in construction

projects are challenges in quantifying changes and benefits. The terms Key

Performance Indicator (KPI) and productivity are common terms, but authors

identify them as lacking consistency. Models such as: lost productivity method,

measured mile analysis, baseline productivity analysis, system dynamic modeling,

earned value analysis, sampling methods, and comparison methods are commonly

referred to (Ibbs et al., 2007), but inconsistently used across case studies. More

commonly, construction projects are measured via KPIs. However, KPIs are

often not uniform across projects and result in confusion regarding: what should

be measured, how it should be measured, what are the sources of change, and how

to evaluate project success or failure. Furthermore, with these suggested models

and KPIs, few studies utilize internal and external project data with measurable

results to validate them. Productivity is a popular measure (Ibbs et al., 2007;

McEniry, 2007; Thomas and Napolitan, 1995), but is based on a subjective,

observable quantity.

According to Cox et al., KPIs are compilations of data measures used to

assess the performance of a construction operation or a particular task (2003).

Generally, these measures have comparisons of estimated or planned and actual or

completed quantities. Furthermore, the measures are often of both the intangible

and tangible types. These generalizations make comparisons of KPIs quite

challenging across projects and organizations. Cox et al. identifies that current

models fail to recognize which indicators will accurately portray the changes in

18
performance (2003). This thesis holds that the quality, rather than the quantity, of

measurements should be upheld. There is a void regarding the measurement of

project changes and outcomes with respect to BIM utilization.

The KPI suggested by the majority of the literature are not incorrect,

rather, they are not precise enough and result in an overload of subjective

measurements. Examples of qualitative KPI suggested by the literature are:

safety, turnover, absenteeism, and motivation (Bassioni et al., 2004; Cox et al.,

2003; Ibbs et al., 2007). In contrast, examples of quantitative KPI suggested by

the literature are: units/man-hours, dollars/unit, cost, on-time completion, resource

management, quality control, percentage complete, earned man-hours, lost time

accounting, and punch list (Bassioni et al., 2004; Cox et al., 2003; Ibbs et al.,

2007). A survey and analysis revealed top rated KPIs in order of: on-time

completion, no preference, units/MH, safety, and quality control/rework (Cox et

al., 2003). A common and concise list of KPI would be beneficial for proper

project comparisons of change.

Two common references for quantification of KPIs and comparisons are

industry studies or databases and construction productivity claims made in court;

however, both have limitations of application. Industry studies and databases can

be misleading, as Thomas found a range of error in predicting the inefficiency for

a single project to be 10-40% differential (Thomas, 2010). Loss claims can

become a comparison and source of data for other projects, as contractors file and

attempt to quantify cumulative impact of multiple change orders and productivity

(Jones, 2001; Gulezian and Samelian, 2003). However, there are challenges in

19
utilizing these measurements due to their litigious nature and highly project-

specific variables. Furthermore, once KPI are established, a range or level of

success and failure must be established.

Zuppa et al. assert that, The main success measures of construction

projects are cost, schedule, quality, productivity, and safety (2009). Others see

quality control, on-time completion, cost, safety, dollars/unit performed, and units

per man hour (Suermann and Issa, 2008). Aranda-Mena et al. see similar

technical, operational, and business benefits (2008). Furthermore, surveys such as

the McGraw Hill The Business Value of BIM Report, survey individuals

perceptions of value of BIM based on a predetermined list of success criteria such

as cost, schedule, scope, changes, etc. (2009). The term KPI is commonly

utilized; however, these metrics and their calculation methodology vary across

projects and individuals as seen in the literature review. The varying definitions

of success and value complicate the evaluation of BIMs benefits. Sebastian

highlights the importance of defining KPIs in terms of quantifiable added values

to build the business case for BIM (2010).

To this end, a key list was compiled of the top mentioned benefits of BIM

based on the literature review. From those, units were derived and a master list

was developed. The most quantifiable benefits were: schedule, change orders,

and RFIs. Please see the Appendix, Table A5 Literature Review Top

Mentioned Benefits from the Literature Review for complete information.

20
Chapter 3

RESEARCH METHODOLOGY

Overview

After a thorough review of the literature, it became evident that a value-

based methodology and framework for the presentation of the benefits obtained

from BIM utilization was necessary. In the development of this thesis, it became

necessary to develop a framework methodology to quantify the benefits of

employing BIM by:

Establishing metrics or KPI to collect to quantify the costs and

benefits of BIM

Testing the metrics against case studies, specifically projects that

are in 2D versus 3D in the same organization in order to minimize

variables

Evaluating the resultant information from the case studies to

quantify benefits and costs associated with BIM utilization

Providing conclusions from the data

Validating the resultant framework model established to evaluate

the net benefit or lack thereof from BIM

Both the framework and the case study data could provide industry

information on the benefits from the utilization of BIM and promote like

comparisons of benefits measured on other related BIM projects to build the

business case for BIM utilization. Existing publications and case studies are

inadequate for a large amount of owners to justify BIM utilization, thus until
21
there is an agreement on the benefits and costs, adoption of BIM will be a great

challenge to many organizations (Aranda-Mena et al., 2008; FMI and CMAA,

2007).

Challenges

FMI Management Consulting and the Construction Management

Association of Americas (CMAA) eighth annual survey of owners (2007) ranked

BIM hurdles, with Unclear business value and ROI coming in at seventh

place out of eleven owner-identified barriers to BIM adoption. The business

value of any computer aided collaboration or information systems comprises

both monetary and intangible outcomes. The difficulties with the evaluation of

the business benefits of information systems can be best categorized into six

areas: (1) some of the business benefits may be intangible; (2) organizational

changes may occur as a result of the introduction of a new system; (3) business

benefits are evolutionary over the life-cycle of the system; (4) diverse

stakeholders involved will subjectively evaluate the system and may have

conflicting opinions; (5) users may feel intimidation or fear of the new system and

how it will affect their jobs negatively; and (6) practical difficulties such as

improper utilization, interconnected systems, and inability to divide related

systems and benefits (Bakis et al., 2006). In the construction industry, some

examples of quasi-tangible benefits are: productivity, information availability, and

enhanced decision making; with intangible benefits being: better risk

management, competitive advantage, and gained market access (Becerik, 2006).

Intangible considerations are challenging to quantify in monetary terms and are

22
outside the scope of this paper, as their analyses are prone to subjectivity and

estimation. Some intangible benefits are listed in Appendix A. Additionally, the

extraction of these benefits from the business objectives and processes the system

aims to support cannot be expressed independently, or in a universal manner

(Andresen et al., 2000; Bakis et al., 2006). The lack of a formal methodology or

process for establishing a business case for BIM encourages speculation and

improper estimation of its benefits. Methods have been proposed of how to

evaluate the benefits of information systems in general, but they are reactive and

prescriptive in nature, relying on individuals perceptions of value.

Measurement Strategies for this Research

The framework methodology is in line with the problem statement of this

thesis, to fill the void of a balanced framework for BIM implementation that

considers both monetary and managerial outcomes. The general IT measurement

process proposed by Andresen and Baldwin was also taken as inspiration in this

thesis. Please see Figure 1. Process of Measuring IT Benefits below. For this

thesis; however, a value-based framework is proposed in which monetary and

managerial outcomes are analyzed. Monetary outcomes will be established via the

metrics set forth in chapter 4 and managerial outcomes will be evaluated and

discussed in section 6.4 and chapter 8.

23
Figure 1. Process of Measuring IT Benefits (Andresen and Baldwin, 2000)

In the literature review, general models were taken for inspiration to form

the more qualitative portions of the framework with respect to the managerial

outcomes of BIM. Specifically, organizational factors needed to be taken under

consideration and BIMs resultant impact analyzed. A complete business case

would appropriately take into consideration executive, communications, risk

management/strategic planning, and change management factors. Bakis et al.

correctly formed this link in their Evaluating the business benefits of information

systems (2006). Please see Figure 2 Linking the Business Case of an

Information System below for more detail.

Figure 2. Business Case of an Information System (Bakis et al., 2006)

24
For the monetary side of the framework, both current and historical project

data was utilized for the Non-BIM and BIM data sets. Data was analyzed and

percentages computed by comparing 2D to 3D projects, with a differential

computed. To properly quantify and represent these returns and investments,

metrics were developed to share this information without compromising

confidentiality. In accordance with the objective of this paper, the metrics were

also devised to create a calculable comparison to other projects by establishing the

percentage comparison of Non-BIM data to BIM data.

From this managerial and monetary analysis, a mapping of the business

case for this thesis was developed. The business case for BIM takes into account

key tangible and intangible outcomes. Please see Figure 3 - Business Case for

this Thesis below for a map of the process.

Figure 3. Business Case for this Thesis

Based on the findings of the literature review and the preceding analysis,

the monetary and quantifiable outcomes of BIM need to more clearly established.

25
This was carried out in this thesis via establishing quantifiable metrics and

applying them to case studies. Please see Figure 4 Framework Development for

this Thesis below. The basic methodology for the computation of the returns and

investments of BIM in this paper consisted of:

Gathering background information on the case studies

Collecting historical Non-BIM data for the case studies

Capturing and reviewing recent BIM data for the case studies

Determining the metrics to utilize

Reviewing the metrics with the project team members

Analyzing the data in accordance with the chosen metrics

Drawing conclusions from the data

Reviewing findings with the project teams and various

stakeholders

26
Figure 4. Framework Development for this Thesis

Scope of this Thesis

Based on the literature review, the data that attempts to quantify BIMs

benefits is highly contextual, most prevalent for new construction, and from the

contractors perspective, making other facilities, such as existing manufacturing

buildings, difficult to analyze and compare. In alignment with the objective of

this paper, projects with a high potential for receiving the benefits of BIM must be

carried out as case studies to test the soundness of the proposed methodology.

The construction of semiconductor manufacturing facilities is very expensive and

complex, with costs around roughly $1 billion in the 300mm fab environment

(Chasey and Merchant, 2000). Additionally, costs see an exponential increase

with every new process. The processes keep evolving on a regular basis with

27
Moores Law, originally stated in 1965, testifying that every 18 to 24 months the

capabilities of integrated circuits double and the price of such chips is cut in half

(Intel 2008).

This rise in costs has made any strategy for cost reduction quite attractive

and worthy of a pilot or test. Nevertheless, as Gil et al. assert, Four main factors

contribute to the challenges in managing fab projects: complex designs, speed,

reducing costs, and frequent but hard to anticipate changes (2005). Indeed, the

semiconductor manufacturing environment presents many unique challenges and

opportunities for BIM to reduce costs. Few BIM enthusiasts have tried to

implement BIM-related processes in a semiconductor environment, notably

Garrett and Garside, touting such benefits as, not only showing the factory and

how it will look, but also providing detailed cost estimates based on the material

data extracted from the Multi-Dimensional CAD design including labor rates,

bills of materials and construction and install/qual schedules (2003). While these

benefits seem to be an expected outcome of BIM in most construction

environments, in the semiconductor manufacturing areas, these benefits and

others have yet to be stated as metrics and a baseline established.

As a building sector with high potential for benefits derived from BIM, a

leading semiconductor manufacturer, Company 1, was utilized for case studies to

best test the methodology of BIM benefits evaluation. Company 1 was seeking to

improve efficiencies and become leaner through the utilization of BIM in its

design, construction, operations, and updating of facilities. Company 1 completed

a series of pilot projects in its efforts at deploying the 3D modeling phase of BIM

28
for design and construction in its tool installation process. A series of pilots were

carried out in Company 1s fabrication facilities (fabs) which are defined as high-

tech facilities that contain the manufacturing tools required for the production of

semiconductors (Gil et al., 2005). For Company 1, tool installation consists of

construction of equipment inside the existing fab manufacturing space, with

mechanical, electrical, plumbing, and some structural activities taking place. Due

to Company 1s employment of BIM in only the 3D modeling stage at the time

these case studies were performed, to simplify terms, 2D and 3D will be the

terms used to represent Non-BIM and BIM.

The BIM business process for Company 1 was to develop the 3D design

and construction models in parallel with the 2D models, acting as a supplement

rather than a replacement. The 3D models were utilized in the tool installation

department in three specific functional areas, which are areas of a fab that carry

out a specific process on the silicon wafers, such as lithography (Gil et al., 2005).

These three functional areas were selected for various reasons and represent the

most complex tool installations. Gil et al., note that certain design characteristics

make a particular functional area more stringent, thus they are indicative of the

most difficult case (2005). The case studies at Company 1 provided this thesis

with an opportunity to properly examine the benefits of BIM utilization garnered

by a large owner, under multiple projects.

29
Chapter 4

DATA COLLECTION

Overview

Company 1 decided to first employ the 3D process in 2001 and utilized it

on subsequent projects. Therefore, there is an array of data, both current and

historical, with regards to the case study data set forth in this thesis. Additionally,

the objective of this thesis requires that both 2D and 3D project metrics are

compared in order to build the benefits business case regarding BIM utilization.

Each project comparison carried out at Company 1 is assigned as a case.

There are three BIM case studies at Company 1:

Case 1 returns

Case 2 investments

Case 3 returns and investments of a particular functional area

Description of Case Studies

Each case study was carried out with the intent to present a valid

comparison of 2D versus 3D project metrics. It is essential that the cases are

described and background information relating to the data presented. As

previously described, the cases at Company 1endowned this thesis with an

opportunity to appropriately examine the benefits of BIM utilization as seen by a

large owner, under multiple projects.

Case 1 is based on two 2D historical projects and two 3D pilot projects in

similar functional areas. This Case was carried out at no additional costs to the

30
owner and was not a competitively bided scope of work, thus could not be used to

accurately portray 3D investments.

Case 2 is based on a current project that is utilizing both 2D and 3D in the

same three functional areas. This Case provides a baseline for the 3D design and

construction investments portion.

Case 3 is a study on one particular functional area, based on two historical

2D projects, two historical 3D projects, and the current 2D and 3D project. The

data were compared as total 2D vs. total 3D metrics for the specific cases

functional areas.

Metrics

A proper benefits analysis, in line with the objective of this thesis

measures not only returns, but also calculates the investments required for BIM.

As discussed in the review of the literature, a matrix of the potential benefits

derived from BIM was composed. From this matrix, it was determined that the

most quantifiable returns were: schedule, change orders, and RFIs. Investment

metrics were: project cost and pilot cost. Please see the Appendix, Table A5

Literature Review Top Mentioned Benefits from the Literature Review for

complete information. The return metrics are in accordance with the objective of

this paper to create a quantification of BIM benefits. These were quantified from

a comparison of 2D projects to 3D projects. Values were reported with respect to

2D projects, 3D projects, and percent change or differential in units of: quantity

per assembly, cost of change per cost of total project, and actual versus standard

duration in order to promote a valid comparison with other projects in the future

31
that will utilize this framework. Percentage values are given in lieu of dollar

values comply with agreements on confidentiality. Please see Table 1 Return

Metrics below.

Table 1

Return Metrics

Criteria Calculation Unit


RFIs Quantity of RFIs / assembly or tool quantity #
Change Orders Cost of change / total cost of project %
Schedule Actual duration / standard duration %

The costs for the 3D design investment category are best separated out

into two distinct sub-categories: A&E costs and 3D background model creator

costs. The A&E costs were based on the costs incurred as a result of the 3D

design of the three specific functional areas. They were a summation of the

items: design, assembly non-variable costs, and an allowance for the 3D design.

The 3D background model creator costs were a summation of the items: laser

scanning, background model creation, 3D block creation, an allowance,

hardware/server for storage, collaboration software, surveying, and training. The

3D background model creation was carried out for the entire factory and not

solely the functional areas that would be receiving 3D design. Thus, the 3D

background model creator costs are higher as they are applicable to all functional

areas, not just those three receiving 3D design. 3D modeling is an additional step

for Company 1s designers and is thus a cost. However, in some cases this

background model may already be created and just need updating or it could be

further extended and used on future projects, thus representing a future savings.
32
The investment metrics were carefully devised in accordance with the

objective of this paper to create a universal comparison. The metric A&E costs

as a percentage of total awarded A&E scope represents how much of the A&E

costs are due to the costs incurred as a result of completing both 2D and 3D

design packages. The metric 3D background model creator costs represents

how much of the total factory design costs are represented by the 3D tools. The

metric contractor costs represents the cost if these areas were in 2D versus cost

if these areas were in 3D, and reveals that contractors would provide savings if

these areas were in 3D. The metric overall savings with 3D scope awarded

represents the addition of the costs of design and savings of construction in these

areas utilizing 3D.

Table 2

Investment Metrics

Metric Calculation Unit


Design Cost
A&E Costs 3D cost of A&E services/ cost of total $/$=%
design 2D and 3D scope awarded
3D Background Model 3D cost of 3D Background Model $/$=%
Creator Costs Creation / cost of total design 2D and
3D scope awarded
Construction Cost
Contractor Costs 3D Contractor Costs / cost of total $/$=%
construction 2D and 3D scope awarded
Design + Construction Costs
Overall Savings with 3D Design Cost + 3D Construction Cost $/$=%
3D in Design and / cost of total construction 2D and 3D
Construction scope awarded + cost of total design 2D
and 3D scope awarded

33
Characteristics

The data from the Cases was collected utilizing Company 1s database of

project information as well as via numerous project meetings with stakeholders.

Data could only be reported in formats agreeable to Company 1, as the

organization was generous enough to allow access and comparisons of their data.

The data was originally recorded during the construction of the project

Cases. Access to Company 1s databases of information as well as project

stakeholders (especially Project Managers) was critical to the proper collection of

all, representative data. All data was first collected in U.S. dollar (USD) values

and quantities. All calculations were carried out in USD, validated in USD, and

percentages were derived. Due to the confidentiality requests of Company 1 and

assertions to maintain a competitive advantage, dollar values could not be

reported in this thesis. Instead, Company 1 allowed the reporting of ratios or

comparisons of costs to derive percentage values.

34
Chapter 5

DATA ANALYSIS

Overview

The case study data was collected via metrics that Company 1 had already

recorded or was in the process of capturing on each project. The involvement of

key stakeholders, such as Project Managers, was paramount to ensuring data was

accurately captured. Change order data was recorded as work orders were

received and final reconciliations were performed by the project finance group.

RFI data originated from an owner-driven system for the tracking and

classification of these requests. Schedule information was obtained via a

scheduling software and owner Project Managers reconciliations.

Validation

Reliability of the data was ensured and validated by project team members

from the construction and finance departments, as well as various stakeholders

throughout the case studies via monthly update meetings. At these meetings

stakeholders would be present and demonstrate their concerns, if any, with the

data and the steps to take to ensure its quality. All steps were taken to ensure the

quality of the data and involvement of the project team members that originally

recorded the data. Both 2D and 3D data were validated.

Testing

Excel spreadsheets were utilized as the main tool for computations.

Returns and investments were captured via either historical or current data, then

entered into a basic excel spreadsheet. Much care was taken to ensure values

35
were correctly transferred and were validated against the original data for

accuracy. Original dollar-values were utilized to compute percentage values

relative to totals. In line with the methodology of this thesis, projects were carried

out under the same owner, Company 1, allowing a more closed-system approach

to the case studies. Thus, external factors were held more constant than

comparable case studies.

36
Chapter 6

RESULTS

Case 1: Returns

As previously mentioned, Case 1 served as a historical account of the

returns experienced from BIM utilization at Company 1 on the projects described.

The data shows a positive differential or a net gain from 3D projects. For

complete data, please see Table 3 Case 1 Returns from 2D to 3D below.

Table 3

Case 1 Returns from 2D to 3D

Metric Unit 2D 3D (2D vs. 3D)


RFIs Quantity/tool 6 3 3
Change Orders % of standard project costs 12% 7% 42%
Schedule % behind standard schedule 15% 5% 67%

Case 2: Design and Construction Investments

Case 2 was established to illustrate the investments or cost of 3D on a

current project. The data shows that costs are incurred due to 3D Design and a

savings is experienced due to 3D Construction. The RFP for Case 2 required that

the electrical, mechanical, and process piping contractors submit their bids in two

different formats. The first format required was the cost of the entire scope of

work for their discipline in 2D (standard). The second format was the cost of

three identified functional areas to be performed in 3D (BIM). Upon comparing

the 2D bids for the three functional areas with the 3D bids for the same three

functional areas, they revealed that the contractor would pass down a savings of

five percent to the owner with the utilization of 3D in those areas.


37
To reiterate, percentage values are a comparison of 3D costs for that

particular metric versus the cost of total 2D and 3D scope awarded for that metric.

For example, Construction Costs are calculated as 3D Contractor Costs / cost of

total construction 2D and 3D scope awarded. Construction savings suggest that

contractors are experiencing a savings due to the utilization of BIM in key areas.

This is significant as Company 1 has the opportunity to maintain those contractors

that experience this savings with ongoing work. For complete Case 2 data please

see Table 4 Case 2: Investments from 2D to 3D below.

Table 4

Case 2: Investments from 2D to 3D

Metric Unit Differential (2D vs. 3D)


Design Costs
A&E Costs % of total awarded design 31%
scope
3D Background Model % of total awarded design 34%
Creator Costs scope
Construction Costs
Contractor Costs % total awarded (-5%) (savings)
construction scope
Design + Construction Costs
Overall Savings with 3D in % total awarded design and (-2%) (savings)
Design and Construction construction scope

Case 3: An Areas Returns and Investments

As a check to provide another data set, a specific functional area was

focused on and the returns and investments were analyzed. This area had the

most precise tool-to-tool comparisons across projects. Consequently, it is also

deemed the most complex functional area. Company 1 sees cost savings and

benefits adequate to merit this areas total utilization of the 3D process.


38
Therefore, a case study of this area is highly indicative of typical benefits. Using

the same metrics as Case 1, the returns of Case 3 were calculated and can be seen

in Table 5 Case 3 Returns from 2D to 3D below. The results show a change

order savings as a significantly higher percentage than Case 1, which contains this

functional area as well as two others. The percentage suggests that this functional

area is receiving the highest returns from change orders.

Table 5

Case 3: Returns from 2D to 3D

Metric Unit 2D 3D (2D vs. 3D)


RFIs Quantity/tool 2 3 -1
Change Orders % of standard project 23% 7% 70%
costs
Schedule % behind standard 15% 7% 53%
schedule

Using the same metrics as Case 2, the returns of Case 3 were calculated

and can be seen in Table 6 Case 3 Investments from 2D to 3D below. As

previously stated, it is difficult to separate out the 3D background model creator

cost, as it is the model of the entire factory and not just a functional area.

Consequently, design the costs are slightly higher than would be applicable to the

specific functional area. In contrast, the contractor savings are higher than for

Case 2.

39
Table 6

Case 3: Investments from 2D to 3D

Metric Unit Differential (2D vs. 3D)


Design Costs
A&E Costs % of total awarded design 29%
scope
3D Background Model % of total awarded design 47%
Creator Costs scope
Construction Costs
Contractor Costs % of total awarded (-6%) savings
construction scope
Design + Construction Costs
Overall Savings with 3D in % of total awarded design and (-1%) savings
Design and Construction construction scope

Project Manager Surveys and Interviews

Individual interviews of tool area Project Managers and Coordinators were

conducted in order to provide insight into individual perspectives and gauge their

experiences and overall atmosphere of the BIM environment at Company 1. Raw

data from interviews did not contribute to the calculation of benefits; rather it

served as contextual information. Utilizing the same series of questions for the

interviews, the individuals were asked if BIM caused an increase, decrease, or

stayed the same in the following categories: accountability, verification,

software/hardware costs, learning curve, and coordination meeting attendance.

Overall, they reported: an increase in attendance by the contractors at the

coordination meetings, a diminishing BIM software learning curve, and decreased

contractor accountability as a result of BIM utilization. Please see Table 7 PM

Interviews below for more information.

40
Table 7

PM Interviews

Category Increased Decreased Stayed the Same


Accountability 38% 62% -
Verification 50% 50% -
Software/Hardware 50% 50% -
Learning Curve 38% 24% 38%
Coordination Meeting Attendance 100% - -

Project Managers were encouraged to share their experiences and

comments throughout the interview. From this, it was determined that there were

barriers to BIM utilization at Company 1 in past projects. Project Managers

suggested that the employment of BIM on projects leads to a decreased headcount

on site during construction, which is one of their main goals. It was conveyed

that both safety and cost are affected by the number of workers on site. BIM has

the perceived potential at Company 1 to reduce on site headcount by enabling

prefabrication and visualization.

41
Chapter 7

DISCUSSION

Limitations: Literature

As evidenced by Table A3 Literature Review Summary of Source

Types in Appendix A, there are a variety of suggested benefits of BIM in the

literature review. However, these benefits do not have a proposed calculation

methodology and have not been quantified nor a baseline established. Garrett and

Garside presented a case study and findings similar to the case studies in this

paper; however, with very different project scope, methodologies, visibility, and

quantification (2003). Koo and Fischer presented a study that examined the

utilization of 4D (scheduling) modeling; however, the case study is retrospective

and did not utilize 4D modeling during the actual construction process, was based

loosely on interviews and post-mortem analyses, and did not present a

classification of the monetary benefits or metrics to evaluate (2000). Tillotson et

al. found generic benefits of intelligent 3D design in an environment similar to

Cases 1, 2, and 3 in their paper. However, the calculation and background

methodology of these generic benefits is not presented, and some distinct

variables for these case studies became evident that may not occur in other case

studies such as: additional field design hours were allowed and different designers

were selected for the pilot projects (Tillotson et al., 2002). These variables and

missing calculation methodologies are barriers to comparing data presented by

these sources with other case studies. In their publication, BIMs Return on

Investment, Autodesk suggested a basic calculation for the return on investment

42
of BIM, but no data quantified via their methodology was validated (2007). The

literature review did; however, suggest potential areas of benefits of BIM. These

potential top benefits are classified in Appendix A. As this thesis sought to

quantify and provide a value-based framework, units were derived with respect to

these potential benefits. These units are a result of careful consideration and were

not directly suggested by the literature.

The literature presented a variety of hierarchies and theoretical models for

the first implementation of BIM at an organization, which was beyond the scope

of this thesis. Such theories and relationship-based models serve more as

suggestions and lessons learned than a value-based framework. For more

information regarding how to implement BIM with these qualitative hierarchies,

such as phases and execution strategies, see Appendix A Table A1 Literature

Review, codes 17-21.

Limitations: Case Studies

The case studies presented in this paper were based on an owners

perspective and had less visibility to details regarding third party savings, such as

from the contractor or designer. Additionally, some of the data available was

historical, thus an ideal state would be proper tracking of metrics by the team

while the project is in progress. Please see Appendix B Future Tracking

Metrics for suggested ongoing tracking metrics for Company 1.

The ideal setting for this methodology would be a case study in which

both BIM and Non-BIM were carried out under not only the same owner, but also

the same contractors; similar scopes of work, the findings were shared among

43
project stakeholders, and with numerous representative projects. The ideal setting

described would provide both consistency and uniformity for future comparisons.

There are limitations in every project associated with the individual stakeholders

varying degree of visibility, how much information can be obtained, and under

what conditions. For example, an owner is less likely to have a contractors field

labor productivity rates and will have a lower degree of visibility to their

contractors actual savings. The contractor alone knows how much they spend or

save as a result of BIM and how much of that savings they choose to pass on to

the owner. Furthermore, contractor costs for generating 3D shop drawings,

reduced headcount (in the field and in the office), reduction in insurance rates,

offsite fabrication savings, and safety rates may not be highly visible to all parties.

Actual savings become proprietary due to the business nature of these

transactions. Nevertheless, the business case presented here is predicated on

benefits that are quantifiable and realized by the owner.

The scope of this thesis does not cover a learning curve associated with

being seen as proficient or able to provide adequate BIM support (Zuppa et al.,

2009 and Becerik, 2006). No methodologies for the learning curve are proposed,

thus they are not in the purview of this thesis.

44
Chapter 8

ORGANIZATIONAL CONSIDERATIONS

Overview

The frameworks suggested by the literature for implementation regarding

BIM and analysis of its benefits provided little attention to monetary gains or

losses as an outcome. The quantitative framework developed thus far in this

thesis is expanded upon based on more organizational and project management

results, which tend to have intangible precedents and outcomes. The precedents

and outcomes can be evaluated to ensure they meet the prerequisites of the

framework and overall BIM implementation.

In their analysis, Building information modeling (BIM) a framework for

practical implementation, Jung and Joo propose that organizational strategies and

policies can affect the success or failure of BIM implementation in an

organization (2011). In this light, the organization itself can be a barrier to BIM

implementation, regardless of the potentially quantified benefits BIM is posed to

offer. Jung and Gibson suggest corporate strategy, management, computer

systems, and information technology as the four main concerns of IS [information

systems] (1999). Furthermore, Talyor suggests social and organizational

contexts need to be taken into consideration to understand the adoption of this

BIM technology (2007).

There is a large need for managerial effectiveness as an antecedent of BIM

success (Jung and Joo, 2011). Organizational and project management functions

45
will be affected by the implementation of BIM and they should be analyzed with

respect to the four (4) different levels suggested here:

Executive Level

o Corporate strategy

o Stakeholders

o Legal aspects

Communications Level

o Positive and negative effects

o Changing roles and responsibilities

o Unanswered questions

Risk Management/Strategic Planning Level

o Preconstruction

o Technical risks

o Alignment

Change Management Level

o Pace

o Paradigms

o Contracts

The importance of appropriately and directly formalizing a BIM

framework for the proper executive, organizational and managerial functions is

paramount to the future implementation of BIM in the building industries and its

overall sustainability.

46
Level 1: Executive

At the executive level, BIM strategies should be concerned with:

understanding the corporate strategy, clearly identifying and communicating with

key stakeholders, and the legal aspects. Commonly referred to as a business case,

the concept is that the strategy utilizes proper business language and is effective

to the business in that it can affect the value chain and promote a more complete

representation of the supply chain, allowing a more integrated approach (Jung and

Joo, 2011). BIM must operate across disciplines and is not exclusive to one

entity; rather, the sharing of information is critical to its success.

Corporate Strategy

The corporate strategy sets both the stage for the organizations

performance and any external event or change in process that could impact the

company. In their, Planning for computer integrated construction, Jung and

Gibson propose various areas to evaluate BIM, in their effort to create a

framework (1999). For example, corporate strategy assesses the opportunity that

can be improved or created by using IS. This is accomplished by prioritizing

corporate strategies of an organization, and then assessing each business function

to determine how it supports such strategies. It is also emphasized that executives

within a company should be involved in this analysis because they have

exemplary insight to represent the companys strategy (Jung and Gibson, 1999).

As recognized by Sebastian, Most clients struggled to translate their ambition

and objective of BIM into effective project implementation strategies, (2010). It

is not enough to have a goal of moving towards BIM, rather the strategy is

47
paramount. Furthermore, not only should key executives be involved, but key

future users should also be engaged.

Stakeholders

BIM is more than software; its an active process that engages

stakeholders that could be impacted by its utilization. As suggested by Jung and

Joo, practical BIM implementation effectively incorporates BIM technologies in

terms of property, relation, standards, and utilization across different construction

business functions throughout project, organization, and industry perspectives

(2011). BIM crosses business functions of: planning, sales, design, estimating,

scheduling, material management, contracting, cost control, quality management,

safety management, human resources management, financing, general

administration, and research and development (Jung and Joo, 2011). The sheer

quantity of business functions hints at the importance of involving those key

stakeholders and decision-makers in each business function that can contribute to

both the implementation and sustainability of BIM; thus reinforcing their role in

the framework before, during, and after BIM utilization.

Some of the essential questions to consider for key stakeholders are

presented by Sebastian in his Breaking through business and legal barriers of

open collaborative processes based on Building Information Modeling (BIM).

For example, in order to be effective, a framework must consider the economic

gain of open collaboration for the stakeholders in the building industry (Sebastian,

2010). The issue of openness is not exclusive to the construction industry. Often

seen as a barrier to BIM adoption by owners are the current regulations that,

48
Many building permit-issuing agencies are not yet ready to review digital

information and require paper-based submissions (Sebastian, 2010). Authors

have noted that, despite the recognition of the importance of key stakeholder

involvement, current BIM proof does not warrant buy-in from executives.

Legal Aspects

BIM also has some very important legal and regulatory considerations for

its implementation framework and as a direct result of openness. Sebastian

further discusses the legal consequences of having such openness of information

and intellectual property rights, raising some important questions, such as: Are

there any regulatory impediments to BIM Standards proceeding? What new

regulation needs to be put in place? Who is liable for the information in the digital

model? How are the users protected? (Sebastian, 2010). Currently, there is no

universal BIM legal framework or guide, with the National BIM standards

(NBIMS) appearing to be the most commonly cited source for project

development in the literature (Succar, 2009). There is a need for a more universal

model, one in which the benefits and costs are clearly delineated. Sebastian

analyzed the benefits associated with BIM from the business and legal

perspectives as being: consistent information resulting from the integration of all

data in a centralized model; efficient and fast design and engineering, as drawing,

analyzing, verifying and decision-making are done through simultaneous

processes involving all disciplines; efficient planning and production based on

accurate quantity estimation and coordination; high quality buildings due to the

elimination of design errors; sustainable solutions through continuous validation

49
of the design alternatives against the client requirements; and effective facility

management using the data contained in the model for managing, remodeling, and

maintaining the building over time (2010). Similar to the benefits suggested in

other sections in which surveys and interviews were conducted , the quantification

of these benefits is not direct and is based more on subjectivity than a monetary

value.

As quantifying the benefits of BIM is a challenge for everyone with

changing KPIs and metrics, so too is the measurement of the barriers. According

to Sebastian, these barriers can be organized into five main issues: lack of

immediate benefits of BIM for the stakeholders; changing roles, responsibilities,

and payment arrangements; uncertainty of the legal status and intellectual

property of the model; inadequacy of the existing contractual frameworks,

including the agreements on liability and risk allocation; and lack of consensus on

the protection of information in conversion and interoperability, and against loss

and misuse of data (2010). Benefits and barriers should be held to the same

standards of quantification. A monetary as well as an intangible organizational

and project management value should be established. Some of these risks are

discussed in the following sections.

Level 2: Communication

At the communication level, BIM strategies should be concerned with: its

effects (positive and negative), its impact on changing roles and responsibilities,

and remaining unanswered questions. These communication factors must be

carefully analyzed prior, during, and after BIM implementation in an

50
organization, as they are key intangible aspects that could affect the overall

success of the BIM framework posed here.

Positive and Negative Effects

Through the proper framework, BIM is poised to result in positive effects

in the area of communications. By encouraging the sharing of information, BIM

is a tool that fosters exchange of information, schedule communication, and

organizational transformation. BIM enthusiasts believe, BIM is a tool that can

foster integration because it not only improves project communication and

information exchange, but also creates a platform that serves as a framework for

collaboration (Ospina-Alvarado and Castro-Lacouture, 2010). By themselves,

frameworks function as a tool to communicate the means and goal to achieve an

objective, such as the utilization of BIM.

The schedule, a critical tool in project management, can be positively

affected by BIM. Accordingly, Using BIM for scheduling purposes can help to

generate and control the schedule for the project team from the design model that

can be automatically updated as the project evolves. Therefore the schedule will

reflect more accurate the duration of the project and will serve as a decision

making tool (Ospina-Alvarado and Castro-Lacouture, 2010). In this light,

merely the capabilities of BIM to promote communication of schedule for

example, it can be seen that the emphasis is that a Project Manager uses the

information beyond the original intent and for their unique purposes. Sebastian

has a very positive outlook overall on the effects that BIM could have on

improving communications for an organization, he comments, Although a

51
certain participant holds the coordinating role, a complex hierarchy is not

required. An attention should be given to build the trust that guarantees the open

book philosophy and the ethics of collaboration regarding the sharing and

integration of information (2010). BIM can promote open exchange of

information both across multiple disciplines and individuals.

Timeliness, if capitalized, can have a positive impact as well with BIM

utilization. The early-design stage is vital for adoption of BIM because in this

stage, when merely 1% of the project cost is used, the key decisions that commit

70% of the life-cycle cost of the building are taken (InPro, 2009). Furthermore,

critical documents are created at this time, and BIM would be well poised to

positively impact tools such as project execution plans, procedures, and manuals

(Jung and Joo, 2011). While these efforts have the potential to have good results,

with each positive also comes a negative.

As with any new system, negative impacts may be equal to or greater than

the positive impacts. Compared to other industries, information systems utilized

in construction are not very advanced and often applications exist independently

and have little or no capacity for communications with each other (Jung and

Gibson, 1999). Interoperability is a hotly debated issue for BIM; however, there

are various guides from the NBIMS and AIA if this kind of tool is desired.

In fact, A report by the National Institute of Standards and Technology in

the United States described inadequate interoperability of technology in the

design and construction industry in the United States alone as a $15.8 billion

problem annually (Gallaher et al. 2004). Outside of the technical and

52
interoperability issues, rests the main change agent or inhibitor, the individual

stakeholder. Unfortunately for BIM, Not all stakeholders can easily share

information and not all stakeholders want to disclose all information (Sebastian,

2010). There is undoubtedly a very large organizational force running through

these stakeholders in their various job roles.

Changing Roles and Responsibilities

The main beacons of change for BIM implementation will be those leaders

and managers with an understanding of the framework presented here, potentially

fostering new roles and responsibilities. Sebastian identified an emerging role of

Model Manager on BIM projects, along with the usual roles of Project Manager

and Process Manager (2010). More specifically, The model manager needs both

ICT and construction process competencies. The model manager deals with the

system as well as with the actors. He provides and maintains the technological

solutions required for BIM functionalities, manages the information flow, and

improves the ICT skills of the stakeholders. The model manager does not take

decisions on design and engineering solutions, nor the organizational processes,

but he holds a supporting role in the chain of decision-making (Sebastian 2010).

While these responsibilities may seem similar to those of a project manager, they

are quite distinct.

Further defining the model managers responsibilities, Sebastian

enumerates that they must have a commanding role in the development of BIM

and relevant tools by: defining the configuration and level of details of the model,

checking and merging, clash detections, contributing to collaboration methods by

53
facilitating decision-making and communication protocols, integration of task

planning and risk management; management of the flow and storage of

information, identification of communication errors, and decision or process (re-

)tracking (Sebastian, 2010). It is important to delineate the differences among

project management, process management, and model management.

A project managers main focus is maintenance of cost, time, and quality;

whereas process managements center of attention is creating tactics for

communication, collaboration, and decision-making among team members.

According to Sebastian, The new role of a model manager is not necessarily

conflicting with the existing roles of a project manager and a process manager

(2010). Instead, there are numerous opportunities for collaboration. As the

clients representative, the project manager executes the management of project

scope, objectives, resources, and schedule in the clients best interest. Seen as a

decision-maker, the PM is also in charge of assuring all stakeholders fulfill their

contractual obligations. When it comes to the more technical aspects of the

project, such as design and engineering, the model manager can provide the PM

with the needed information from BIM (Sebastian, 2010).

Promoting collaboration among project stakeholders on a more strategic

level, the process managers role is complementary to that of the project manager,

and also depends on the model manager. The process manager forms the inter-

organizational processes to accomplish an effective collaboration that will benefit

the projects lifecycle (Sebastian, 2010). In collaboration with the client and

model manager, the process manager can foster the strategies for communication

54
and decision-making into the BIM based collaboration methods, protocols, and

risk management plans. It is important to emphasize the early and frequent

involvement of the project manager, process manager, and model manager in the

framework understanding and implementation to further promote the lifecycle of

BIM in the particular company.

Unanswered Questions

Despite the best efforts to clearly delineate the communication strategies,

roles, and responsibilities, confusion may still persist in this area. Among the

most debated questions are: Is the architect still the leading designer in the

integrated design and engineering? Who is in charge of the total quality of the

design? Who assures that all interface problems (clashes) are solved and that the

model is full-proof? Which new agreements on responsibilities and input-output

workflows should be made if every discipline is involved almost simultaneously

in the process? Since a new role of model manager has come to place, what are

the general and specific tasks of the model manager with respect to the project

manager and the process manager? (Sebastian, 2010). These questions are

common and should not be seen as a deterrent to BIM, rather, they should be

viewed as essential areas to address in the very early stages of BIM

implementation to ensure a smooth framework. Communication should be open

and transparent.

Level 3: Risk Management and Strategic Planning

For the risk management and strategic planning level, BIM strategies

should be concerned with: preconstruction, mitigation of technical risks, and

55
alignment. These key preliminary areas lay the foundation not only for successful

BIM implementation, but also for proliferation across the projects life-cycle.

Preconstruction

A major appeal for the utilization of BIM in construction is the

management and prediction of risks prior to construction. The concept that risks

are discovered early can save both time and money, as the costs to resolve risks

rises after design is complete escalate. In their study of eight projects, Kiziltas

and Akinei found that during preconstruction, general contractors used BIM

mainly for constructability analysis and design consistency check to eliminate

unexpected problems and rework during the construction phase (2010). In the

early days of BIM proliferation, clash detection was touted as a main benefit to

BIM, as stakeholders would meet to review clashes between building assemblies

and across disciplines, posing solutions based on their expertise. As it has gained

momentum and utilization across projects, BIM has the increasing potential to

reduce both risks across project life-cycles and amongst team members.

Technical Risks

Risks can occur in both design and construction phases, but BIM

encourages pre-planning by looking at the design, constructability issues, and

operations prior to construction. Effective pre-planning and risk mitigation

efforts prior to the initiation of construction are paramount to effective risk

management (Kashiwagi, 2011). However, the key is to get early involvement by

all stakeholders, not just designers. Contractors must also be involved and

participate in the clash detection sessions where solutions are formed. As

56
Sebastian noted, BIM-wise collaboration is believed to be able to reduce the

traditional project risks. BIM simplifies the risk management in a project through

a more accurate estimation of cost, time, and quality (2010). A tool, such as

BIM, is only successful as the individuals that take advantage of its benefits, with

proper training and encouraged collaboration between all individuals on the

project team.

Alignment

While BIM guides and frameworks do not specifically list alignment as a

requirement, the outcomes of alignment such as collaboration and pre-planning

are necessary prerequisites. Just as the model crosses the phases of a project, so

teamwork should cross disciplines. On a strategic level, the model should be

created in an environment that encourages participation from designers and

contractors alike. Both the need and barriers of alignment of designers and

contractors for successful BIM implementation have been referenced in multiple

sources: Aranda-Mena, 2008; Homayouni et al., 2010; Ospina-Alvarado and

Castro-Lacouture, 2010; Taylor, 2007. This alignment should be upheld across

organizations and individuals within these organizations alike. Risks that need to

be further investigated in this realm are, the scarce availability of BIM

experienced personnel for the formation of a highly qualified team, and the

challenges to integrate the new expertise in the sustainable business strategy of

the organization (Sebastian, 2010).

57
Level 4: Change Management

On the level of change management, BIM strategies should be concerned

with: pace, paradigms, and contractual implications. These transformations

parallel changes experienced in the past with the first implementations of 2D

CAD. Taylor specifically addresses the similarities between the initial

proliferation of 2D CAD and the current introduction of BIM or 3D CAD in his

Antecedents of successful three-dimensional computer-aided design

implementation in design and construction networks (2007). Any paradigm shift

will have change management implications.

Pace

BIM invokes a very fast-paced and early change environment.

Furthermore, any change can experience resistance, as quick changes are

increasingly difficult to implement. As identified by Sebastian, Model-based

decision-making will result in the changes to the internal processes of the project

stakeholders. The analyses performed through the multidisciplinary collaboration

at an early stage must be emphasized in order to achieve the benefits of using the

models to support decision-making and to make the comparison between

available design alternatives (2010). The model itself cannot realize its full

potential and move forward without the stakeholders operating at the same pace.

Paradigms

In many ways, the challenges associated with BIM represent a

quintessential paradigm shift. The normal way of doing things will be

challenged by new processes (Lu and Li, 2011). For example, BIM is more

58
technology-based, with less utilization of physical drawings. Often, individuals

will compare the movement from blueprints to CAD as a shift similar in

difficulty and importance as the current shift to 3D CAD or BIM. However,

BIM has been reported to have a slower rate of acceptance than 2D CAD, as this

requires a fundamental change in perspective of the previously accepted silos of

design and construction (Taylor, 2007). Instead of keeping these silos separate,

BIM promotes integration of common concerns and needs across design and

construction. Taylor identifies the top concerns of designers as: liability and

contractual issues; and concerns of contractors as: the cross-pollination of ideas

and technology competence (2007). From these concerns, it can be seen that BIM

requires more of a paradigm shift than its predecessor technology shift from

blueprints to CAD.

Contracts

The culmination of these implications at the various levels that will affect

BIM implementation must be properly accounted for in the contractual and

liability arenas. Sebastian (2010) and Taylor (2007) both discuss contractual

changes and new liabilities that are a result of collaboration and open sharing of

the relevant information. In the area of contracts, it has been observed that

projects have added at least one paragraph, to multiple pages of requirements and

rules due to BIM utilization on a particular project (Taylor, 2007). However,

some projects may require more detail or contractual obligations for their BIM

standard. Entire models for project delivery, such as Integrated Project Delivery

(IPD) have been proposed in response to these concerns. IPD is stated to specify

59
the roles, activities and required contributions of the stakeholders in each project

stage, thereby encouraging early contribution, experience, and proactive

involvement of key participants (Sebastian, 2010). On a more technical level,

BIM carries an additional liability concern by designers since printed plans are

not traditionally drawn to scale, but a BIM is required to be more accurate, with

contractors making adjustments to the model prior to field work (Taylor, 2007).

Contractual and liability concerns with BIM should be properly understood and

accounted for prior to BIM implementation, as BIM represents a modification or

change to existing processes and methods.

Summary

With research and applications of computer-aided integration in

construction being touted starting around 1999 in the literature, its a wonder that

despite all the concerns raised over the years and intangibles, there is still a

positive attitude towards BIM in the literature (El-Mashaleh et al., 2006).

According to Homayouni et al., Researchers have found successful collaboration

that spans organizational boundaries enhances the productivity of the design and

construction process. Researchers and practitioners alike argue that using BIM

should lead to tighter collaboration and closer communication among project

participants working in cross-organizational environments (2010). A framework

for proper assessment is increasingly critical. Thus, benefits do not come without

a price, as lessons learned, We find that inter-organizational BIM-enabled

projects and successful inter-organizational collaboration have shared theoretical

categories: fostering integrated teams; implementing tools and strategies to

60
encourage clear communication across the team; and developing transparent

technology use (Homayouni et al., 2010). With BIM proliferation comes some

areas of challenges. As Bakis et al., 2006 and Homayouni et al., 2010 assert,

without an organizational environment that promotes collaboration and the open

and freely exchange of information, such as partnering, the full potential and

implementation of integrated systems cannot be realized.

Organizational and project management functions will be affected by the

implementation of BIM and they should be analyzed with respect to the four (4)

different levels suggested here: 1) Executive, 2) Communications, 3) Risk

Management/Strategic Planning, and 4) Change Management. The framework

presented here ensures that organizations read and respond to these four levels,

carefully considering the benefits and costs associated at each level. While the

factors presented do not have a direct numerical quantification, the

organizational-specific responses to these levels, when coupled with the previous

quantified benefits provide an organization seeking an analysis of whether they

should utilize BIM with a realized framework for decision-making.

61
Chapter 9

CONCLUSIONS

Outcomes

The calculation methodology and findings of the Cases 1-3 present a valid

evaluation for the utilization of BIM. The success of BIM depends on many

factors such as the size of the project, team members BIM proficiencies, the

communication of the project team, as well as other organizational external

factors. The Cases in this analysis do not quantify these aspects or other

intangible benefits since their quantification is subjective in nature. Therefore,

BIMs success is relative to the project and the organization.

While the literature did portray a positive outlook and future for BIM,

quantified results and metrics used to measure its proposed benefits were not

consistently applied. Therefore, this thesis concludes that BIM has not definitely

been proven to have positive benefits, measured under a value-based framework.

This thesis did, however, provide quantifiable project data via three Cases

of BIM utilization through established return and investment metrics and laid

down a framework for benefits measurements. The benefits framework involved:

Return Metrics: Change Orders, RFIs, and Schedule

Investment Metrics: Design Costs and Contractor Costs

Organizational Considerations: Executive, Communication, Risk

Management and Strategic Planning, and Change Management

At Company 1, calculated returns were: change orders saw a savings of

five percent of standard costs in Case 1, RFIs decreased 50 percent per tool or
62
assembly, and duration reduction was a savings of 9 percent based off the

standard duration. Calculated investments were: 31 percent increase in design

costs due to A&E costs, 34 percent increase in design costs due to 3D background

model creation, and a contractor savings of 5 percent of contractor costs. When

totaled in dollar value and percentages computed, investments in both design and

construction resulted in a savings of 2 percent of combined awarded design and

construction scope. Thus, the contractor savings outweighed the design costs as a

percentage of the scope awarded. A more complete portrayal of the savings

experienced at Company 1 could be conveyed if a dollar value is derived for the

returns. Nevertheless, the findings of the Case Study at Company 1 indicate that

in the tool installation department of semiconductor manufacturing, there is a high

potential for BIM benefits to be realized. Moreover, contractors experienced a

realized savings that they passed on to the owner.

The data provided by Case 3 held that in specific areas of semiconductor

manufacturing, such as those that are more complex, may have increasing returns

as compared to less-complex areas. More testing on specific areas can be carried

out in a particular project environment; however, this provides some insights as

there are numerous areas of this type in semiconductor manufacturing.

For a project trying to determine if BIM has or will benefit them, this

paper presents a valid framework methodology and baseline. The metrics for

collection presented in this paper provide a starting point for the stakeholders to

begin their analysis. The methodology of this thesis is consistent in a closed

system, such as Company 1. However, variables in other organizations or

63
projects that are exterior to this system must be analyzed if this framework is to

be utilized.

Additionally, it is critical that all perspectives are represented in the

metrics, from contractor, designer, to owner. This can be best established via

project stakeholder meeting in which metrics are validated. Obtaining proper

baseline data on the Non-BIM (2D) metrics is essential for a proper analysis of

BIM (3D) benefits and an apples to apples comparison. Lastly, ongoing project

performance measurement is critical to benefits realization. The metrics in this

paper should first be quantified, and then other potential metrics can be addressed

as listed in Appendix A.

Since these metrics are based off of a standard, they are very easily

employed across projects and sectors by companies that have Non-BIM

performance metrics to insert as their standard and BIM pilot projects as their

comparison data set. With this framework analysis of benefits, companies utilize

their own standard as a basis of comparison. Innovations progress with time or

become obsolete, thus the utilization of BIM beyond 3D will be a good indicator

of the benefits that companies may be receiving as a result of a more complete

BIM utilization.

Recommendations

With change orders seeing a savings of five percent of standard costs in

Case 1, this resultant savings could be substantial with a large scope of work. An

RFI decrease of 50 percent per tool or assembly may have an impact in savings if

processing time and resources are scarce, as is generally the case in the

64
manufacturing environment. Duration reduction is critical, thus a savings of 9

percent based off the standard duration can have a tremendous impact, especially

if the critical path is affected.

As stated by Chasey and Merchant, Because of restrictive construction

schedules, sequencing and coordination of different construction activities will

also become a big issue. Constructors will need to develop new ideas and

methods to be able to design and construct a fab that ramps up quickly and works

efficiently in an uncertain and changing environment (2000). Those in a

semiconductor manufacturing environment will have to decide if the upfront

investment costs of BIM are worth the potential returns later in the project. For

Gil et al., Designers and customers argue that benefits and cost savings of a

flexible product design in the long term outweigh its up-front cost and risk of

rework (2005). The challenges of the semiconductor manufacturing

environment make strategies for reducing costs, such as BIM, quite attractive.

The calculation methodology in Cases 1-3 could be further refined on

future projects, depending on the availability of information. For Case 1, in future

measurements, a cost associated with the creation and responding to the RFI or

cost avoidance may be a useful measure depending on the objectivity of the

analysis. Also, a classification of a type of RFI specifically related to BIM would

be useful to a future analysis. Schedules should be more diligently tracked,

milestones should be uniform, and actual versus planned dates should be more

carefully compared. As a semiconductor manufacturer, certain schedule

constraints exist outside the control of the project at hand. For example, Gil et al.

65
found that, more than eighty percent of the requested tool arrival dates were

changed at least once, if not more frequently for times around sixty days. This is

a common occurrence, with the tool suppliers premature commitment to a date

(2005). These factors should be taken under consideration when comparisons are

created. For Case 2, an ideal state would be to have the cost incurred only as a

result of the 3D scope of work, only in the areas that will utilize this process and

not the entire factory. Additionally, as actual costs could not be revealed in this

thesis due to the proprietary nature of the bidding information of Company 1,

comparisons where actual costs are able to be reported would provide increased

visibility.

As Company 1 seeks the returns associated with the full utilization of

BIM, consideration should be given to its future opportunities for savings and

reduced cost over the full life-cycle of the BIM process. In the manufacturing

setting, BIM has the potential to further impact factory layouts, with a more

flexible model that can keep the pace with its dynamic environment. Garrett and

Garside note exponential benefits if the BIM layout analysis could includes space

usage changes, utility loadings and routings, tool pedestal changes, labor and

material costs, and also highlight potential physical interferences of equipment

and facility systems (2003). An analysis and metric for these industry-specific

types of potential future applications should be developed.

In particular, Company 1 should evaluate the potential benefits for BIM in

dimensions beyond 3D (modeling), and to assist in and provide information

regarding: planning scenarios and site information, architectural program, floor

66
plans, layouts, engineering calculations, specifications, contract documents, legal

description, change orders, supporting documentation for litigation, shop

drawings, procurement documents, progress photographs, alarm diagrams,

warranty data, purchase requests, cost estimates, organizational occupants,

personnel lists, handicap designation, hazardous materials (reduction in airborne

molecular contaminants), Operating manuals, maintenance records, inspection

records, simulations, continuation of operations plans, disaster recovery plans,

contingency plans, asset inventory, energy analysis, project closeout

documentation, proper lean implementation, electronic document transfer, supply

chain management (internal and external), forecasting, risk management, and

safety applications (NBIMS, 2006). Future research on the measurement of the

benefits of BIM could utilize more sector-specific metrics, such as those listed

above, to provide a sector-specific representation and level of detail in accordance

with the calculation methodology presented.

Future Research

The literature suggests that the full potential of BIM has not been realized,

as it was noted full implementation is hindered by a lacking business case for

owners. Nevertheless, there are many articles and publications related to the

future potential of BIM in dimensions beyond 3D; notably scheduling,

sustainability, and facilities management. Furthermore, some suggest that a more

formal review and certification system of BIM could lead to increased adoption.

As Succar postulates, Also, a valid set of BIM metrics will lay the foundations

for a formal certification system which can be employed by industry leaders,

67
governmental authorities and large facility owners/procurers to pre-select BIM

service providers and attest to the quality of their deliverables (2010).

Applications of BIM regarding scheduling (4D) hold potential beyond

visualization to a greater assessment of innovations and to evaluate construction

alternatives. Jongeling et al. present 4D content quantitatively via workspace

areas, work locations, and distances between concurrent activities (2008).

Furthermore, Homayouni et al. 2010; Krigsvoll, 2008; Kang et al., 2007; Koo and

Fischer, 2000, provide many insights into the other dimensions of BIM and their

possible implications on the investments and returns of BIM projects.

Organizations seeking to employ BIM beyond 3D are encouraged to conduct

further analysis prior to employment of BIM; ensuring metrics are established for

data collection to evaluate if the other dimensions are truly beneficial.

The literature is beginning to identify how the BIM model can be used in

broader applications, such as extracting data needed for a sustainability

assessment of design (Nguyen et al., 2010).

McGraw Hills Green BIM: how building information modeling is contributing to

green design and construction report identified, Because of the way BIM

facilitates green design, construction, and sustainable outcomes, the growth of

green building as an accepted, widespread practice is helping to accelerate BIM

adoption (2010). The report further provides case studies and data to support

this topic. In their efforts at establishing relationships between Greening

Strategies, Lean Principles, and BIM, Enache-Pommer et al. found the utilization

of all three approaches resulted in efficient healthcare buildings (2010).

68
BIM is very frequently portrayed in the Design and Construction phases;

however, the entire lifecycle should be in the purview of BIM implementation.

As Lewis et al. asserts, The lifecycle cost of the operational life of a building is

about 60 to 85 percent of the total lifecycle cost, whereas the design and

construction is about five to ten percent (2010). Among various tasks to be

performed after construction is complete, companies would like to use BIM for

punch-list administration, keeping up to date manufacturing and installation

information about maintenance items, which are needed during repair and

replacements (Kiziltas, Akinci, 2010). However BIM is not viewed by some to be

limited to those applications, The use of building information modeling (BIM)

promises to part of the solution to reducing interoperability and integration

challenges for facility management (Lewis et al., 2010). Facilities Management

has much to gain if similar benefits are realized due to BIM implementation, as,

Viewed over a 30-year period, initial building costs account for approximately

just two percent of the total, while operations and maintenance costs equal six

percent, and personnel costs equal 92 percent (Public Technology Inc., U.S.

Green Building Council, 1996). Operations and Maintenance as a cost is quite

substantial and any advancements or promise of reducing that cost, albeit BIM,

should be properly investigated and follow a framework metric to evaluate its

impacts.

As BIM is more than just 3D modeling, other applications of BIM may

have benefits not under the purview this thesis. Additionally, sector-specific

benefits may arise and should be evaluated for each project and organization as

69
deemed necessary. The benefits framework established by this thesis can be

further developed as BIM reaches new dimensions. However, the literature, to

date, does not provide quantifiable metric suggestions nor a baseline for a

comparison of investments and returns. Until BIM is accepted as beneficial and

adopted by owners, measurements and estimates beyond 3D are premature.

70
REFERENCES

Andresen, J., Baldwin, A., Betts, M., Carter, C., Hamilton, A., Stokes, E., Thorpe,
T. (2000). A framework for measuring IT innovation benefits, ITcon, 5, 57-72.

Aranda-Mena, G., Crawford, J., Chevez, A., and Froese, T. (2008). Building
information modeling demystified: does it make business sense to adopt BIM?
CIB W78 2008 International Conference on Information Technology in
Construction Santiago, Chile.

Autodesk. (2007). BIMs return on investment . Retrieved from:


http://static.ziftsolutions.com/files/8a7c9fef2693aa1e0126d282571c02c7

Bakis, N., Kagioglou, M., Aouad, G. (2006). Evaluating the business benefits of
information systems. 3rd International SCRI Symposium, Salford Centre for
Research and Innovation, University of Salford, Salford, Retrieved from:
http://www.irb.fraunhofer.de/CIBlibrary/search-quick-result-
list.jsp?ALLE=evaluating+the+business+benefits+of+information+systems&Res
ultCount=10&start=1&Title=&Contributors=&Source=&ConfData=&CIBPT=&
PubType=&PubDateFrom=&PubDateUntil=&PubCodes=&uebergeord=&SortSp
ec=jahr+desc+sort1+desc+sort2+asc&idSuche=CIB+DC10146&detailed=true&S
earchtype=universal

Bassioni, H. A., Price, A. D. F., Hassan, T. M. (2004). Performance measurement


in construction. Journal of Management in Engineering, 20, 2, 4250.

Becerik, P. (2006). Computer aided collaboration in managing construction.


Cambridge: Harvard University Graduate School of Design, Retrieved from:
http://scholar.google.com/scholar?q=Computer+Aided+Collaboration+in+Managi
ng+Construction&hl=en&as_sdt=0&as_vis=1&oi=scholart (2006).

Becerik-Gerber, B., Rice, S. (2010). The perceived value of building information


modeling in the U.S. building industries, AECBytes, Retrieved from:
http://www.itcon.org/2010/15

Cannistrato, J.C. LLC. (2009). How much does BIM save. Shop Talk, a quarterly
newsletter, Retrieved from:
http://bimworkx.com/index.php?option=com_content&view=article&id=47:how-
much-can-bim-saveq-cannistraro-quarterly-newsletter--fall-2009-
&catid=34:bim101&Itemid=56

Cox, Robert F. Issa, R. R. A., Ahrens, D. (2003). Managements perception of key


performance indicators for construction. Journal of Construction Engineering and
Management, 142-151.

71
Chasey, A.D. and Merchant, S. (2000). Issues for construction of 300-mm fab.
Journal of Construction Engineering and Management, 451-457.

El-Mashaleh, M., OBrien, W.J., Minchin, R. E. Jr. (2006). Firm performance


and information technology utilization in the construction industry. Journal of
Construction Engineering and Management, 132, 5, pp 499-507.

Enache-Pommer, E., Horman, M.J., Messner, J.I., Riley, D. (2010). A unified


process approach to healthcare project delivery: synergies between greening
strategies, lean principles and BIM. Construction Research Congress: Innovation
for Reshaping Construction Practice, 2, 1376-1385.

FMI Management Consulting and the Construction Management Association of


America (CMAA). (2007). Eighth annual survey of owners. Retrieved from:
http://www.fmiresources.com/pdfs/FMIEighthAnnualOwnersSurvey.pdf

Gallaher, M., OConnor, A., Dettbarn, J., and Gilday, L. (2004). Cost analysis of
inadequate interoperability in the U.S. capital facilities industry. Gaithersburg:
U.S. Department of Commerce Technology Administration, National Institute of
Standards and Technology.

Garrett, T., Garside, M. (2003). Fab pilot of a multi-dimensional CAD system.


Future Fab International, 14.

Gil, N. D., Tommelein, I.D., Stout, A., Garrett, T. (2005). Embodying product
and process flexibility to cope with challenging project deliveries. Journal of
Construction Engineering and Management, 439-448.

Gulezian, R., Samelian, F. (2003). Baseline determination in construction labor


productivity-loss claims. Journal of Management in Engineering, 19, 4, 160165.

Homayouni, H., Neff, G., Sturts Dossick, C. (2010). Theoretical categories of


successful collaboration and BIM implementation within the AEC industry.
Construction Research Congress, 1, 778-787.

Ibbs, W., Nguyen, L.D., Seulkee, L. (2007). Quantified impacts of project change.
Journal of Professional Issues in Engineering Education and Practice, 45-52.

Intel, Press. (2008). Moores law continues. Retrieved from


http://www.intel.com/technology/mooreslaw/index.htm.

Jones, R. M. (2001). Lost productivity: claims for cumulative impact of multiple


change orders. Public Contract Law Journal, 31, 1, 146.

72
Jongeling, R., Kim, J., Fischer, M., Mourgues, C., and Olofsson, T. (2008).
Quantitative analysis of workflow, temporary structure usage, and productivity
using 4D models. Automation in Construction, 17 (6), 780-7981.

Jung, Y. and Gibson G. E. Jr., (1999). Planning for computer integrated


construction. Journal of Computing in Civil Engineering, ASCE 13, 4, 217-225.

Jung, Y. and Joo M. (2011). Building information modeling (BIM) a framework


for practical implementation. Automation in Construction, 20, 126-133.

Kang, J. H., Anderson, S. D., and Clayton, M. J. (2007). Empirical study on the
merit of web-based 4D visualization in collaborative construction planning and
scheduling. Journal of Construction Engineering Management, 133, 6, 447-461.

Kashiwagi, D. (2011). PIPS/PIRMS: the best value standard. Performance Based


Studies Research Group, Kashiwagi Solution Model Inc., Mesa, AZ.

Khanzode, A., Fischer, M., Reed, D. (2008). Benefits and lessons learned of
implementing building virtual design and construction (VDC) technologies for
coordination of mechanical, electrical, and plumbing (MEP) systems on a large
healthcare project, ITcon, Special Issue Case studies of BIM use, Retrieved from:
http://www.itcon.org/2008/22 13, 324-342.

Kiziltas, S. and Akinei, B. (2010). Lessons learned from utilizing building


information modeling for construction management tasks. Construction Research
Congress, 1, 318-327.

Koo, B., Fischer, M. (2000). Feasibility study of 4D CAD in commercial


construction. Journal of Construction Engineering and Management, 251-278.

Krigsvoll, G. (2008). Life cycle costing as part of decision making - use of


building information models. Conference Proceedings World Conference SB08.

Kuprenas, J.A., Mock, C.S. (2009). Collaborative BIM modeling case study
process and results, Computing in Civil Engineering, Proceedings of the 2009
ASCE International Workshop on Computing in Civil Engineering, 1, 431-441.

Lewis, A., Riley, D., Elmualim, A. (2010). Defining high performance buildings
for operations and maintenance. International Journal of Facilities Management,
1, 2.

Lu, W.W.S., Li, H. (2011). Building information modeling and changing


construction practices. Automation in Construction, 20, 99-100.

73
McEniry, G. (2007). The cumulative effect of change orders on labour
productivity: the leonard study reloaded. The Revay Republic, 26, 1.

McGraw Hill. (2009). The business value of BIM: getting to the bottom line.
Retrieved from: http://www.bim.construction.com/research/

McGraw Hill. (2010). Green BIM: how building information modeling is


contributing to green design and construction. Retrieved from:
http://www.mcgraw-hill-
sales.com/MHC%20Green%20BIM%20SmartMarket%20Report%20(2010).pdf

NBIMS. (2006). What is the NBIMS. Retrieved from: http://cic.vtt.fi/projects/vbe-


net/data/What_is_the_NBIMS.pdf

Nguyen, T.H., Shehab, T., Gao, Z. (2010). Evaluating sustainability of


architectural designs using building information modeling. The Open
Construction and Building Technology Journal, 4, 1-8.

Ospina-Alvarado, A.M. and Castro-Lacouture, D. (2010). Interaction of processes


and phases in project scheduling using BIM for A/E/C/FM integration.
Construction Research Congress: Innovation for Reshaping Construction Practice,
2, 939-948.

Public Technology Inc., U.S. Green Building Council. (1996) Sustainable


Building Technical Manual. Green Building Design, Construction, and
Operations, U.S. Department of Energy, U.S. Environmental Protection Agency.
Retrieved from:http://www.wbdg.org/ccb/EPA/sbtm.pdf

Sebastian, R. (2010). Breaking through business and legal barriers of open


collaborative processes based on building information modeling (BIM). TNO
Built Environment and Geosciences, Delft, The Netherlands; Proceedings: W113
- Special Track 18th CIB World Building Congress, May 2010, Salford, UK.
166-186.

Succar, B. (2010). The five components of BIM performance measurement.


University of Newcastle, NSW Australia; Part of Proceedings: W096 - Special
Track 18th CIB World Building Congress (combined with W104), May 2010,
Salford, UK.

Succar, B. (2009). Building information modeling framework: a research and


delivery foundation for industry stakeholders. Automation in Construction, 18,
357-375.

Suermann, P.C. and Issa, R.R.A. (2008). Case studies: evaluating building
information modeling impact on United States army corps of engineers

74
construction. CIB W78 2008 International Conference on Information
Technology in Construction.

Taylor, J.E. (2007). Antecedents of successful three-dimensional computer-aided


design implementation in design and construction networks. Journal of
Construction Engineering and Management, 933-1002.
Thomas, H. R. (2010). Why are loss of labor efficiency damages so difficult to
recover? Journal of Legal Affairs and Dispute Resolution in Engineering in
Construction, 190-193.

Thomas, H. R., Napolitan, C. L. (1995). Quantitative effects of construction


changes on labor productivity. Journal of Construction Engineering
Management, 121, 3, 290296.

Tillotson, J., Espitalier-Noel, P., Huddleston, D. (2002). New design approaches


to counteract change costs and impacts on schedules. Future Fab International,
13.

Woo, J., Wilsmann, J., and Kang, D. (2010). Use of as-built building information
modeling. Construction Research Congress, 1, 538-547.

Zuppa, D., Raja, R., Issa, A., and Suermann, P.C. (2009). BIMs impact on the
success measures of construction projects, Computing in Civil Engineering, 503-
512.

75
APPENDIX A

LITERATURE REVIEW TABLES

76
Table A1

Literature Review Codes

Source Reference Type Classification


Code
01 Garrett and Garside,
01 01
2003
02 J.C. Cannistrato, LLC
04 01
2009
03 Khanzode et al., 2008 01 01
04 Kuprenas and Mock,
02 01
2009
05 Koo and Fischer,
01 02
2000
06 Tillotson et al., 2002 01 02
07 Woo et al., 2010 02 02
08 Aranda-Mena et al.,
02 03
2008
09 Andresen, et al., 2000 01 04
10 Bakis and Aouad,
01 04
2006
11 Autodesk, 2007 05 04
12 El-Mashaleh et al.,
01 05
2006
13 Zuppa et al., 02 05
14 Becerik-Gerber and
06 05
Rice, 2010
15 FMI/CMAA. 2007 07 05
16 McGraw Hill, 2009 03 06
17 Becerik and Pollalis,
03 07
2006
18 Krigsvoll, 2008 02 07
19 Suermann and Issa,
01 07
2008
20 Gil, et al., 2005 02 07
21 Homayouni et al.,
02 07
2010

77
KPIs analyzed or
Code suggested Issues Data
Table A2

Total project cost New construction, base-build Cost less than 1% of the total project
Total pilot cost only scope, new facility, cost ; Conversion of the 2D model
Sequencing issues cost implementation of the pilot began approximately 75% of the total pilot
Physical conflicts approximately six months after cost ; Identified and resolved
(clashes) detailed design began in 2D, no sequencing issues that avoided nearly
01
Schedule conflicts calculations or methodology, past $2M ; Physical conflicts (clash
project team members disagreed reports) saved $0.75M ; Schedule
with the findings presented conflicts (scheduling interface) $1.2M
; Data conflicts (attribute
management) $0.5M
Literature Review Top 21 Sources

Change orders Not much detail on the Change orders representing % of base
calculations, specific to MEP contract: 2D projects = 18.42%; 3D

78
industry, not peer-reviewed only = 11.17%; Collaborative BIM =
02
journal (press release) 2.68%
(Data is based on 408 projects over
past 6 years, totaling $558,858,574)
KPIs analyzed or
Code suggested Issues Data

Labor savings New construction, MEP systems include labor savings ranging from
Pre-fabrication savings hospital project, MEP 20 to 30 % for all the MEP subcontractors ; 100%
Safety systems only, pre-fabrication for the plumbing contractor
Field conflicts contractor opinions, no One recorded injury throughout the installation of
RFIs formulas or backup MEP systems over 250,000SF ; Less than 0.2%
Schedule data presented rework for the whole project for the mechanical
03
Overall project costs subcontractor ; Zero conflicts in the field
installation of the systems ; A handful of requests
for information for the coordination of the MEP
systems between contractors and the designers ; 6
months savings on the schedule
About $9M savings in cost for the overall project.

79
Coordination New construction, Reduced rework - $50,000; Shortened construction
Rework 685,000SF facility, durations - $10,000; Visualization (underground
Durations did not have electrical); Sequencing - $250,000 (MEP and FP
Conflict checking involvement of systems); Preassembly - $25,000; Bundling -
Visualization designer, instead $10,000; Shop fabrication - $25,000; Conflict
04 Sequencing contractor, subs, and checking (between trades) - $4,000,000; Bulletins -
Preassembly and construction manager $250,000; Other changes - $250,000
prefabrication developed model
elements and then
combined into one
model
Code KPIs analyzed or Issues Data
suggested

Schedule Retrospective case study, does Retrospective case study that determined if 4D
not list actual quantified could have helped overall project execution. Stated
savings, just general that the results show that 4D models are effective in
05
statements determining the feasibility of the construction
schedule. Some discussions in opposition were
carried out after.

Engineering Illustrates 3D design with 2 Generic benefits of intelligent 3D design and


Design examples: (1) hookups and quantified them as: Engineering (reduce redundant
Field installation labor saved (2) FM on pumps, efforts) 15% decrease; Design (increased effort for
Change orders LCCA, and estimate of $ accuracy, planning, detail) 5% increase; Installation
Design labor saved on alternative vacuum (reduced field engineering, man hours) 5-20%
pump. Only describes decrease; Change orders (reduced through

80
06 approach, highly contextual, improved accuracy) 35% ; Case study saw Design
only 1 project, management labor to issue a 3D design package, although
strategies are differential, not sometimes greater, is comparable to that for
a good model for beginners, detailed 2D packages. Secondly, the installation
older model 1999-2000, labor hours are typically significantly lower for the
allowed additional field tools installed with 3D design packages
design hours and cost).
Code KPIs analyzed or Issues Data
suggested

Business outcomes Data is solely based on Presents general findings and implications obtained from
Communicate interviews and public interviews and research from five case studies to suggest
alternatives information, no real the generally accepted benefits of BIM and expected
07 Client satisfaction metric exists, based on outcomes. It also suggests that there cant be one
Risk expected outcomes, business case for BIM, applicable to all projects and
and no financial data organizations.
is presented

08 Fully coordinated model Case studies are very Utilized 3 case studies to illustrate the general options of
Visualization brief and no implementation of BIM, non-quantified benefits of
Simulation (mock ups) quantifiable data is implementation, and lessons learned
Schedule presented, benefits are
Accurate as-builts stated in general terms

81
Asset management
visualization
Maintenance scheduling
Lifecycle project
information
Code KPIs analyzed or Issues Data
suggested

Typical IT benefits (such Subjectivity in Proposed a framework to evaluate the benefits of an IT


as reduced assigning the type of investment by first assigning the type of benefit
communication costs and benefit and populating (efficiency, effectiveness, or performance), and then
reduced staff) the table, especially filling the appropriate table with data relating to: business
09
Efficiency with assigning an process, specific benefits, implications, metrics,
Effectiveness impact, not directly ownership, likelihood, resultant benefit, and assigning an
Performance applied to BIM impact. Assert that this method is more viable than ROI
and term it as "information economic analysis."

Typical IT benefits (such Suggests only a Good background and framework for determining the
as intangibles and method and is not value of information systems, limitations, intangibles, and
10 achieving business directly applied to methods. Suggests gathering information via the methods
initiatives) BIM of individual ranking of intangible benefits and case

82
studies.

Labor Focuses on the first Suggests a simple formula for BIM ROI
Productivity year's ROI and is a
simple model, not
taking into account
11
specific project
variables, formula is
presented without case
studies or applications
Code KPIs analyzed or Issues Data
suggested

Firm performance, Survey, received from 74 firms, no


schedule owners represented. Suggests increases
performance, cost of: firm performance (2%), schedule
performance, performance (5%), and cost performance
12
customer (3%)
satisfaction, safety
performance, and
profit

Cost Survey was more concerned A survey was distributed to gain an


Schedule with background/demographic understanding of the prevalent definition
Quality and asked only 1 technical of BIM, and to identify BIM perceived
Productivity question relating to how BIM is impact on the success measures of

83
Safety defined (subjective), results construction projects (202 AEC
were analyzed on a level of the professional respondents) - responses:
13
individual and not the company's "1) BIM is an open standards based
practices, and no performance information repository for facilities'
metrics were given. lifecycles 2) BIM is a tool for visualizing
and coordinating AEC work and
avoiding errors and omissions (most
selected response); and 3) Other
Code KPIs analyzed or Issues Data
suggested

A list, resultant from General assumptions, subjectivity, Survey, frequently referenced findings resultant
the survey, with top distributed in multiple channels and of a BIM survey (~400 respondents) of opinions
results of: response rate is unknown, 99% U.S. and ideas, spring 2009
14 Visualization based, mostly commercial and retail
Field Errors
Building Design
As-builts

Communication Data related to IT in general (not Found that the largest segment of owners (44%)
Quality specifically BIM), have a budget for job related IT spending
Documentation between 0%-0.4% of their construction budget,
Schedule who has utilized BIM, ranking of a list of

84
Quality results benefits, and ranking of hurdles
15
Productivity
Consistency
Labor
Safety
Business benefits
Code KPIs analyzed or Issues Data
suggested

RFIs Survey questions are General questions on the perceived value of BIM
Constructability based on "perceived" and its ROI, sample is limited to survey
Rework value, no common respondents and highly cited in BIM articles, Study
Budget method of to assess adoption of BIM across the construction
Mock-ups calculation/estimation industry and to gauge the perception of value that
16
Visualization of benefit is suggested, firms are receiving by implementing BIM.
Simulation case studies are all new
Schedule buildings and less-
complex facilities, not
peer-reviewed

Typical OCPM Not directly applied to Classifications of benefits of ICT (tangible, quasi-
benefits, tangible, BIM tangible, intangible), focused mainly on online

85
17
quasi tangible, and collaboration and project management (OCPM)
intangible technology to the design and construction industry
Code KPIs analyzed or Issues Data
suggested

Life-cycle cost Benefits are not quantified and Suggests alternate uses of BIM models
analysis focus on stages of BIM in LCCA, benchmarking, energy data
18 Supply chain implementation beyond 3D and modeling, O&M data, performance
effects metrics, and forecasting; highlighting
Benchmarking potential benefits

Rework Not current (some surveys Qualitative data collected via a survey
Schedule from 2007), survey data was to assess perceptions about BIM
Safety taken over an extended period impacts on 6 key performance
Performance of time, multiple surveys, indicators (quality control, on-time
inconsistent respondents and completion, cost, safety, dollars/unit
response rate, respondents performed, and units per man hour.
19
were from a limited audience, There is a positive correlation between

86
based on "perceptions" of a BIM-based approach and construction
value management productivity, established
by the USACEs utilization of internal
tracking metrics and performance
comparisons.
Code KPIs analyzed or Issues Data
suggested

Design Basebuild only scope, Overall reduction in design time would


Layout modeling implementation of the pilot be on the order of 20% to 50%, possibly
20 Automated began approximately six greater.
estimation months after detailed design
began in 2D

Productivity Model is and observations are Gives a general methodology and steps
Communication based on a single scientific and theory to implementing BIM.
research lab project in the U.S. Came up with a typology of how the
and through interviews from collaboration process is implemented in
21
70 professionals across the inter-organizational BIM integration.
U.S., findings are general
categories and suggestions for

87
implementation
Table A3

Literature Review Summary of Classifications

Code Source Classification Frequency


01 Case study and quantifiable findings 4
02 Case study 3
03 Case study and model or process 1
04 Model or process 3
05 Survey 4
06 Survey and case studies 1
07 Theory and general assumptions 5
Total 21

88
Table A4

Literature Review Summary of Source Types

Code Source Type Frequency


01 Journal article 8
02 Conference proceedings 7
03 Report 2
04 Press Release 1
05 Internet article, report 1
06 Survey and internet article 1
07 Survey/report/press release 1
Total 21

89
Table A5

Literature Review Top Mentioned Benefits

Benefit Frequency Unit


Schedule 11 Days
Sequencing coordination 7 N/A
Rework 5 N/A
Visualization 5 N/A
Productivity 5 N/A
Project cost 5 $ or %
Communication 4 N/A
Design/engineering 4 N/A
Physical conflicts 4 N/A
Labor 3 N/A
RFIs 3 #
Safety 3 N/A
Change orders 2 $ or %
Maintenance applications 2 N/A
Prefabrication 2 N/A
Quality 2 N/A
Simulation 2 N/A
As-Builts 1 N/A
Pilot cost 1 $ or %

90
APPENDIX B

FUTURE TRACKING METRICS

91
Table B1

Future BIM Tracking Metrics

Metric Reporting Frequency Suggested Source


Change orders as a % of Quarterly Owner/Contractor
standard costs
Avoidance log and associated Quarterly Contractor
costs
RFI quantities in 2D versus 3D Quarterly Owner
Offsite prefabrication man-hours Monthly Contractor
from Contractors

OCIP insurance headcount Quarterly Owner


dollar savings % off site hours

Reconciliations of savings from End of Project Contractor


Contractors using BIM

Reconciliations of savings from End of Project Designer


Designer using BIM

Actual durations as a % of End of Project Contractor/Owner


standard duration

92

You might also like