1) The document is a checklist for inspecting block work on a construction project. 2) It includes items to check for the material, operation, and any other remarks regarding the quality and installation of block work. 3) The checklist will be used by the main contractor and approved by the representative, resident engineer, or resident architect during inspections.

Uploaded by

alfie
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
100% found this document useful (2 votes)
2K views2 pages

Project Title:: Checklist For Block Work

1) The document is a checklist for inspecting block work on a construction project. 2) It includes items to check for the material, operation, and any other remarks regarding the quality and installation of block work. 3) The checklist will be used by the main contractor and approved by the representative, resident engineer, or resident architect during inspections.

Uploaded by

alfie
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 2

Project Title:

Form No:

Ref No:

CHECKLIST FOR BLOCK WORK


Location / Storey:

Structural Element: Drawing No:

Date / Time of Notification: Date / Time Inspection Required:

RE / RA / RTO Inspection Date: Time: To:

Re-Inspection Date: Time: To:

Checked By Approved By
Item Detail Y N NA
Engr / Foreman Date RE / RA / RTO Date
A MATERIAL
1 Properly stacked
2 Block Quality
3 Reinforcement Mesh
4 Block Work tie
5 Follows approved shop drawing
6 Mortar mix
7 Cleaning

B OPERATION
1 Setting Out
2 Openings: Size / Location
3 Mortar mixing
4 Damp Proof Course (if necessary)
5 Bond & ties into structure
6 Bond Type
7 Consistency of joints
8 Overall plumb-ness
9 Overall alignment
10 Clean down

C ANY OTHER

REMARKS:
Purchaser Selection Forms Displayed in Unit

Checked By: Rectification Checked By: Approved By:


Main Contractor Main Contractor RE / RA / RTO

Name / Signature / Date Name / Signature / Date Name / Signature / Date


Project Title:

Form No:

Ref No:

CHECKLIST FOR BLOCK WORK


Location / Storey:

Structural Element: Drawing No:

Date / Time of Notification: Date / Time Inspection Required:

RE / RA / RTO Inspection Date: Time: To:

Re-Inspection Date: Time: To:

REMARKS:
Purchaser Selection Forms Displayed in Unit

Checked By: Rectification Checked By: Approved By:


Main Contractor Main Contractor RE / RA / RTO

Name / Signature / Date Name / Signature / Date Name / Signature / Date