Revised Kemess North Pre-Feasibility Project
Revised Kemess North Pre-Feasibility Project
Revised Kemess North Pre-Feasibility Project
KEMESS NORTH
PRE-FEASIBILITY PROJECT
CENTRED ON:
4 June 2004
DISCLAIMER
This report was prepared for Northgate Exploration Ltd. by GR Technical Services Ltd.
The quality of information, conclusions and estimates contained herein are based on
industry standards for engineering and evaluation of a mineral project. The report is
based on: i) information available at the time of preparation, ii) data supplied by outside
sources, iii) engineering, evaluation, and costing by other technical specialists and iv)
the assumptions, conditions and qualifications set forth in this report. Cost models use
extensive information from the existing Kemess South operations, increasing the
probability that actual costs in the near term will fall within the accuracy of a Pre-
Feasibility Study. However, no warranty should be implied as to the accuracy, especially
with longer term estimates of forward looking economic assumptions for the future
operations such as but not limited to, metal prices, exchange rates, labour costs, and
energy, equipment, and supply costs.
EXECUTIVE SUMMARY
The Kemess North deposit is part of the Kemess Property, which is located
approximately 430 km northwest of the city of Prince George, British Columbia, Canada,
at 5702 north longitude and 12647 west latitude. The property includes one active
mining lease (#354991) and 213 surrounding and contiguous mineral claims. At least
four additional mining leases are currently in the application process to cover the
Kemess North area.
Legal surveys have been completed for mining lease #354991. The mineral
claims covering the Kemess North deposit and the area to the north and west of the
proposed mine have been surveyed and it is proposed to convert these claims into
mining leases. The Kemess North deposit and associated occurrences are located on
the New Kemess 1, 2 and 3 claims.
The Kemess Property is owned and operated by Kemess Mines Ltd., a 100%
controlled subsidiary o f Northgate Exploration Limited. Kemess Mines Ltd. holds the
surface rights to the property through their mineral claims and mine lease.
The Kemess South deposit, located on mining lease #354991, currently supplies
mill-feed to a 52 000 tpd mill. In 2001, Northgate announced the discovery of a
significant deposit at Kemess North, which was the focus of major drilling campaigns
during 2002 and 2003.
The Kemess North project site is generally located in three north facing alpine
cirques with original ground surface ranging from 1,500 to 2,000 m elevation all above
tree line. Open pit mining will be located in the centre cirque and eastern cirques. The
southern pit wall will be bounded by the southern headwall of the eastern cirques. The
crusher and other infrastructure will be located at the pit rim in centre cirque. A natural
rock glacier is evident in the western cirque. No surface development has been planned
to date in the western cirque.
The climate is generally moderate, although snow can occur during any month.
Temperatures range from -35 to 30 and average annual precipitation amounts to 890
mm. Since mining will be scheduled for year round operations, 24 hours per day
equipment and procedures will need to be adaptable for the variations of 4 seasons in a
mountain environment. The current Kemess South operations will be suited for Kemess
north with some provision for more extreme weather conditions at the higher elevations
and provision for avalanche monitoring and control.
i
Access to the Kemess North project is provided by both air and road via the
current Kemess Operations. Personnel are from various locations in British Columbia
and Alberta. There are scheduled year-round flights from surrounding communities and
Vancouver. All season road access is from either the town of Mackenzie or Fort St.
James via the Omenica resource access road. A privately owned, 380 km power line
originating in Mackenzie in the south provides power to the mine area via the BC Hydro
grid.
Kemess Mines Ltd. holds surface rights through their mineral claims and mining
leases. Onsite infrastructure for the current operation consists of an office, maintenance
facilities, a camp, a mill, crushers and raw ore stockpile areas, access and service
roads, airstrip, explosives depot, and tailings facilities. The tailings pond capacity is
sufficient to meet the needs of the Kemess South ore body until its completion in 2008.
The Kemess North mining plan is based on utilizing the current facilities for ore
processing, accommodation, and support, plus new facilities for the Mining operation at
Kemess North. These include access roads, potential waste dump sites, a pit side
crusher and conveyor system to the current plant site, a field supervision and equipment
service centre adjacent to the pit and a new tailings pond located at Duncan Lake.
Tailings and waste dump facilities are being designed at Duncan Lake with
sufficient capacity for the Kemess North waste. This includes all mill tailings and mine
waste rock. Much of the mine waste rock is PAG material and is planned to be
deposited sub-aqueously in the tailings pond. Any NAG material within the pit will be
used for construction fill or deposited in waste dumps adjacent to the pit area but in the
area specified within the water management plan.
Property Geology
ii of 138
difficult to ascertain but probably reflects the regional trend of flat lyi ng Mesozoic
assemblages.
Mantling the northern and eastern limits of the Kemess North area is a matrix
supported polylithic fragmental volcanic unit. The Polylithic Fragmental Dacite is an
enigmatic unit as it shows field relations suggestive of both an extrusive and intrusive
emplacement mechanism. The evidence suggests that basement structures and
conduits that allowed extrusion of the local Toodoggone volcanic assemblage underlie
the Kemess North area.
These are intermediate intrusive units do not reach surface. The main quartz
monzonite mass beneath East Cirque hosts the bulk of the Cu-Au mineralization at
Kemess North.
Post-Mineral Dykes
Post-ore dykes, including feldspar porphyry and minor mafic varieties, cross cut
Takla volcanics and outcrop locally in cirque highwalls and along ridges. The feldspar
porphyry dykes also cross cut the Jurassic-Toodoggone fragmental unit and are
generally barren and unaltered. The relationship of the feldspar dykes with the larger
quartz diorite stocks is not clear, however they appear temporally late in the sequence
of events. Mafic dykes are generally thin (<1 m to 4 m), dark green and barren of
sulphides and veining.
Faults
At least three steeply dipping, northwest trending normal faults have been
inferred from surface mapping and drilling to transect the Kemess North property. Fault
spacing ranges from 500 m to 1,500 m and they are generally parallel to the Duncan
and Saunders Faults located west and east respectively.
Broken Zone
A flat-lying zone of intensely broken rock and multiple gouge zones (which
results in poor drilling conditions) occurs above the deposit, and is referred to as the
Broken Zone. The Broken Zone averages about 80 m from surface to competent
bedrock and is comprised of clay, multiple gouge zones and a pyritic-argillic alteration
component. Theories on the formation of the Broken Zone range from the effects of
present day weathering, porphyry related alteration zonation, to the tectonic end
products of shallow faulting and thrusting. The most plausible explanation is that the
Broken Zone and related phyllic alteration are due to pre-Toodoggone weathering
processes.
iii of 138
Mineralization
The highest-grade Au-Cu zones occur at or near the quartz monzonite Takla
volcanic contact. This zone occurs mostly within the quartz monzonite stock and to a
lesser extent within the andesite adjacent to the intrusive stock. The protolith is
commonly completely replaced. The quartz monzonite/quartz diorite stock and
associated quartz-magnetite zone is interpreted as the heat source driving the porphyry
copper-gold system at Kemess North.
Grading outwards from the East Cirque stock into the Takla volcanics,
silicification decreases. Sericitization, commonly from the destruction of matrix and
phenocryst plagioclase, is pervasive in the Takla volcanic rocks. The uppermost
alteration zone is the phyllic or QSP zone, which consists mostly of sericite-chlorite-
quartz +/- pyrite and forms the extensive Broken Zone and bright orange-red outcrops at
surface. Pyrite is common throughout (5-7%), both disseminated and within vuggy
quartz veining. This alteration zone is mostly barren of any significant Cu and will often
show a slight increase in Au with depth. It has been postulated that this zone shows
similarities to an acid leached cap, however it lacks any form of supergene enrichment
in base metals, as occurs at Kemess South.
Moving west of East Cirque to the Nugget Zone, alteration and mineralization
becomes irregular as the intrusive units approximate steeply dipping dykes. The Nugget
Zone alteration is dominated by weak chlorite -biotite altered Takla volcanics commonly
with disseminated magnetite. Substantial gold-copper mineralization is present within
the Takla volcanics but at depths exceeding 400 m. The Nugget Zone generally exhibits
a higher gold to copper ratio than Kemess North, and rare narrow intersections of gold
grades of up to 8 g/t are present.
i v of 138
Exploration
The Kemess North property represents a highly advanced project. The early
exploration work in the area identified a porphyry target but it wasnt until deep drilling in
2001 that significant gold and copper grades were located. Since 2001 exploration has
been directed at expanding the resource base in the proposed pit area by drilling 16
holes in 2001, 41 holes in 2002, and 19 holes in 2003.
Because the target is deep, geological mapping and geochemical techniques add
little value, likewise, surface and airborne geophysical exploration have contributed little.
The procedures followed in the field and through the interpretation stage of
exploration have been professional. Various crews under the supervision of professional
geologists carried out the exploration work. Since 2001 to the present day there has
been continuity in personnel both in the field and with the data interpretation. It is
considered that the reliability of the data obtained with exploration is very high.
Outlier high grade cutoffs were applied to both Copper and Gold. 14 Copper
assays were cut to 1.35% and 16 high grade Gold assays were cut to 4 g/t. The
cut grades were used in compositing.
v of 138
The influence of a few remaining high-grade composites were limited to a
maximum of 50 m during interpolation.
The composites were tagged with a Litho code according to the 3-D solid they
were included with.
Variograms (both grade and directional) using the 5m composites were studied
for Litho codes 5, 6, and 7. Kriging parameters were determined from the
variograms for Litho zones 5, 6, and 7.
A contact analysis was completed indicating that the transition zone across the
Litho boundaries is less than the typical drill spacing. Therefore a hard-boundary
approach was chosen to interpolate each Litho zone separately.
Eighteen drillholes with suspect down-hole surveys were found in the database.
Two models were built, one with all of the drill holes, where the suspect holes had their
down-hole surveys corrected, and the second with the 18 suspect drill holes removed.
The resulting models were very similar in contained resources however subsequent
mine planning work with the two models showed similar economic pit sizes for the two
models were achieved with only a 5% difference in input metal prices. With this
sensitivity it was decided for the mine planning work, to use the model including the
corrected holes since the assays are valid and excluding the holes is less
representative than using the corrected holes.
The grade interpolation method and search distances for kriging were based on
the Geostatistical analysis and variogram parameters. A minimum of 3 and a maximum
of 16 composites were used for the interpolations with maximum 4 composites from
each quadrant. The maximum search for the composites was limited to 200 m. The
general steps were:
Separate 'Ordinary Kriging' (OK) runs were made for AU & CU for LITHO
codes 5, 6, & 7 (6 runs) using the specific interpolating parameters for
each metal by zone. For blocks that meet the selection criteria the
background values were over written.
vi of 138
Resource Classification Criteria Used
1 2 3
Measured Resources Indicated Resources Inferred Resources
DIST = < 30 m DIST = 31-50 m DIST > 150
or and or
NCOMP = < 5 Other blocks that
DIST = 31-50 m or cannot be classified as
and 51 m < DIST < 150 m measured or indicated
NCOMP > = 5 and
NCOMP > = 5
or
51 m < DIST < 200 m
and
LITHO = 5, 6, or 7
Where DIST is the distance to the nearest drill hole from the centre of the block and
NCOMP is the number of composites used in the interpolation of a block.
Mineral Resources
The following Resource tables are based on the total Geological Model. They
only include material within the defined LITHO zones.
vii of 138
Summary of Indicated Resources
Five individual areas were selected from the geologic model as manual checks
for grade and tonnage. The copper and gold grade estimates were calculated by
averaging the assay grades from all of the drill hole intercepts within the block. The
tonnage was calculated by using the averaged bulk density (SG) of the data from within
the block.
The estimated grades are very close to the modeled grades for both copper and
gold ranging from 7.0% to + 8.2% for Copper and 6.5% to +6.8% for Gold. The small
variance indicates the modelling method to be reasonable.
viii of 138
Reserves
Mining recovery is estimated at 95% and mining dilution of 10% is applied at the
contact between ore and waste. The dilution grade is estimated at 0.08 g/t Au and
0.05% Cu which is the average grade of material below the incremental cutoff grade.
Interpolated SG is used.
A NSR cutoff has been determined for the Reserves calculation using the
following factors:
NSP (net smelter price); copper C$0.901/lb and gold C$11.753/g.which accounts
for offsite expense, smelting, and refining.
Mill recovery factor; 88.8% for copper and 61.5% for gold.
The reserves for the final pit limit (P634) based on an NSR cutoff of $2.2 are:
Reserve Estimate
Kemess North, Pit P634
Diluted Cu Au
Mineable (%) (g/t)
(tonnes x 106)
Proven 282.40 0.159 0.306
Probable 131.84 0.160 0.310
Total 414.24 0.160 0.307
The final pit design includes 335.09 million tonnes of waste for a strip ratio of 1:0.81.
Note that the reserve tonnages above are all included in the Resource tonnages listed
earlier.
The overall pit slopes and detailed bench design parameters have been provided
by Knight Pisold for the different sectors of the pit wall based on an aggressive 1.2
Factor of Safety. The slope design parameters used are contingent on certain operating
practices and monitoring as prescribed by Senior review Consultants Will Bawden PhD,
PEng of the University of Toronto, and Chuck Brawner PEng. Knight Pisold have
ix of 138
indicated several design modifications required to the South wall of Pit P634. These
may increase the waste stripping by up to 10% but this is within the accuracy of the
reserves estimate and will not affect the overall economic viability of the design. These
modifications will be made during the Feasibility Design stage.
The LG sensitivity analysis was used to design the pit pushbacks. To enable a
more even annual strip ratio in the production scheduling, the first pushback will mine
the near surface lower grade ore on the west side. The deeper east side is split into 2
stages, a shallower north side and a deeper south side mining to the ultimate pit depth.
The first pushback has been further revised where the initial benches in the Pre-
stripping period are included as a Pre-Production phase. The size of the stages was
roughly determined to ensure that each have a sufficient bench width to enable efficient
mining operations and for all the stages, the design was pushed to the ultimate pit
lateral limit on three walls, with subsequent pushbacks expanding in one direction only.
This will enable much more efficient mining operations when adjacent pushbacks are
being mined at the same time.
The production schedule for Kemess North is run from the Pit Phase reserves.
All production will be from the owners fleet except for minor tonnages for the small
initial benches of each pushback. These will require smaller specialized equipment to
operate on the steep original ground at the top benches. The major mining equipment
from Kemess south will be transferred to Kemess North as ore and waste production is
reduced in Kemess South. To meet the higher strip ratio requirements, additional haul
trucks will be purchased. The ore annual ore targets are adjusted each year to reflect
the ore hardness and anticipated SAG mill through put according to the HARD (BWI)
value in the Pit Reserves.
Milling
The Kemess North ore will be processed in the existing Kemess plant, initially
with integrated co-production with the current Kemess South ore and as a stand-alone
operation after the Kemess South ore is depleted. During the co-production period the
plant capacity will be increased and an ore transportation system from Kemess North
will be installed. This will include an Underground ore conveyor system and pit-side
crushers. The current capacities, costs and metallurgical performance of the plant are
well defined and carry a high level of assurance into the Kemess North project
performance and cost estimates.
The metallurgical test work for Kemess North is based on metallurgical samples
taken from the exploration drillholes. The met samples were well located to represent
the deep ore for the Kemess North deposit. Future testing should also be done on the
shallow ore on the west side of the pit for more detailed prediction of operating
performance during the earlier years of the project.
The ores of Kemess North share a number of favourable characteristics with the
Hypogene ores of the Kemess South deposit:
x of 138
Both deposits carry clean sulphides without surface oxidation.
The sulphides are coarse grained and are adequately liberated for rougher
flotation at a grind of K80 at 145 .
Ball mill work indices are low compared to a majority of porphyry deposits.
The average metal contents of North ores are slightly lower, copper at 0.20% Cu
versus 0.22% Cu and gold at 0.4 g/t Au versus 0.75 g/t for South ores.
The pyrite content of Kemess North averages 4% compared to 1% pyrite for the
South ores. Since pyrite contains finely disseminated gold, higher pyrite carries a
larger portion of gold to tailings.
The near surface ores of the North deposit are of slightly lower grade than those
of deeper zones.
The rougher flotation with Kemess North ores in essence is a bulk sulphide float.
Rougher concentrates have to be re-ground to a K80 of =20 microns for cleaner
flotation to produce quality concentrates.
Existing flotation cell capacity and de-watering equipment are adequate for
treatment of North ores.
The Net Neutralization Potential for all North composites is negative, therefore
the tailings will be acid generating unless stored under water cover.
Subsequent analytical work has been completed on the samples from the
flotation test work and determined that there was a relationship between Ag and Au in
the concentrate for the various pit zones. Silver grades have not been included in the
Mining reserves and have not been used in any of the economic pit limit/reserve
calculations. Small silver credits have been included in the financial modelling.
xi of 138
Environmental
Environmental considerations for the Kemess North project have been integrated
with the Total Kemess property requirements for ongoing operation and final closure.
Klohn Crippen has been retained for this work, which covers Mine Waste Management,
Water Management, Environmental studies, and Mine Closure planning. Klohn
Crippens work involves the base line data studies, evaluations, process design and
costing as required to meet or exceed the regulations. These requirements have been
included in the mining and processing designs and schedules. The capital and
operating costs as determined by Klohn Crippen have also been used in the cost
modelling.
Permitting
The permitting process for the Kemess North Project is being carried out by
Northgate. The project entered the regulatory review process for mine development
approval in October, 2003. This will involve three levels of government: Province of
British Columbia, First Nations (4 Bands) and the Government of Canada and will be
concurrent with the applications for Project Permitting. The provincial permits will
establish the guidelines for environmental protection during the construction and
operating phases of the Kemess North Project.
The formal project review was initiated with the submission of the Kemess North
Project Description to the BC Environmental Assessment Office (EAO) in October,
2003. The EAO has the responsibility to notify all stakeholders and disseminate relevant
project information during the review process. The primary government agencies
involved are as follows:
First Nations: Kwadacha FN, Gitxsan FN, Takla Lake FN, and
Tsay Keh Dene FN.
The target for the approval for all permits is May 2005.
Financial Modelling
The financial modelling for the project was undertaken by Northgate and Hatch to
evaluate the costs, cashflows, and financial returns for the Kemess North Project.
These are based on calculating the cashflow of integrated Kemess South and Kemess
North operations, the stand alone Kemess South operation and determining the
incremental financial impact of the Kemess North project. This is summarized as:
xii of 138
Exchange Rate Cdn$/US$1.45
Metal Prices
Gold US $375/oz
Copper US $1.00/lb
Silver US $5.00/oz
Concentrate Treatment $62/tonne concentrate and
& Refining Charges $0.062/pound accountable
copper
Net Present Value (NPV) US$75 million
at a 5% cost of capital
IRR 8.9%
xiii of 138
TABLE OF CONTENTS
i
(f) Mineral Reserve Estimate .................................................................................58
17. ECONOMIC PIT LIMITS AND MINE PLAN ..............................................................61
(a) Economic Pit Limits............................................................................................61
(b) Detailed Pit Designs...........................................................................................68
(c) Production Schedule ..........................................................................................83
18. INTERPRETATION AND CONCLUSIONS...............................................................85
19. RECOMMENDATIONS.................................................................................................88
(a) For Feasibility......................................................................................................88
(b) For Construction and Detailed design.............................................................88
20. REFERENCES ...............................................................................................................89
21. STATEMENT OF QUALIFICATIONS ........................................................................92
22. ADDITIONAL INFORMATION...................................................................................100
(a) Current Kemess Mining Operations ..............................................................100
(b) Kemess North Development...........................................................................101
(c) Integrated Production ......................................................................................103
(d) Recoverability Metallurgy and Mineral Processing ..................................103
(e) Markets Transportation and Smelting ........................................................104
(f) Contracts ...........................................................................................................104
(g) Environmental Considerations .......................................................................106
(h) Permitting Current Status ............................................................................108
(i) Taxes..................................................................................................................109
(j) Capital and Operating Cost Estimates..........................................................110
(k) Economic Analysis ...........................................................................................111
(l) Regional Potential ............................................................................................112
ii of 138
TERMINOLOGY AND ABBREVIATIONS
Abbreviation Definition
Au Gold
BFP Bladed feldspar porphyry
BQ 1.32 inch diameter core
BMWI Ball Mill Work Index
BWI Bond Work Index
Cat trenching mechanical trenching
CLASS Resource/Reserve classification code in 3 -D Block Model
CoG cutoff grade
Cu Copper
DIST Distance to closest composite during grade interpolation
EDA Exploratory Data Analysis
FoS Factor of safety
g/t grams per tonne
GR Tech GR Technical Services Ltd.
HQ 2.406 inch diameter core
IP Induced Polarization
KN Kemess North
KS Kemess South
LG Lerchs-Grossman Pit Optimization Routine
LITHO Lithology codes used in 3-D Block Model
m Metre
Ma Million years
Mt Million tonnes
Mm3 Million cubic metres
NAG Non-Acid Generating rock
NCOMP Number of Composites used in Grade Interpolation
NPV Net Present Value
Northgate Northgate Exploration Limited
NQ 1.775 inch diameter core
NSP Net Smelter Price
iii
Abbreviation Definition
NSR Net Smelter Return
NTS National Topographic System
PAG Potentially Acid Generating rock
PDC Project Design Criteria document
PROF Net profit calculation per block, inclusive of mining, milling, treatment,
refining
QA/QC Quality Assurance/Quality Control
QSP Quartz-sericite-pyrite
SAG Semi-Autogenous Grinding
SG Specific Gravity
Stripper Smoothed pit with ramps (Mine site terminology)
tpd Tonnes per day
TUC Technical Unit Cost
i v of 138
LIST OF FIGURES
Figure Page
v
Figure Page
vi of 138
LIST OF TABLES
Table Page
5.1 Production History from Kemess South 14
5.2 Summary of Exploration Work 15
6.1 Lithologic Units Comprising Stratigraphic Succession 17
9.1 Exploration Employees/Contractors 28
10.1 Drill Collar Location and Orientation Data 33
15.1 Metallurgy Samples with Drill Hole Reference 45
15.2 Summarized Kemess North Metallurgy 48
15.3 Silver Metallurgy for Kemess North 48
16.1 Resource Model Limits and Dimensions 51
16.2 Resource Classification Criteria Used 54
16.3 Summary of Measured Resources 55
16.4 Summary of Indicated Resources 55
16.5 Summary of Inferred Resources 56
16.6 Model Checks 57
16.7 Reserve Estimate, Proven Category Kemess North Pit P634 60
16.8 Reserve Estimate, Probable Category Kemess North Pit P634 60
16.9 Reserve Estimate, Proven and Probable Kemess North Pit P634 60
17.1 Economic Pit Design Parameters 61
17.2 ePit Slope Angles by Pit Sector 62
17.3 Slope design parameters (From Knight Pisold) 72
17.4 Road Design Parameters 72
17.5 NSR Grade Cutoff Bins for Reserves 78
17.6 Reserves for Pre-Production Pit (P601) 79
17.7 Reserves for Phase 1 Pit (P614) 80
17.8 Reserves for Phase 2 Pit (P624) 81
17.9 Reserves for Phase 3 Pit (P634) 82
17.10 Major Mine Equipment Fleet 84
17.11 Annual ROM Mill Feed 84
22.1 Kemess South Reserves and Resources 97
22.2 Production Summary 99
vii
Table Page
22.3 Metal Recovery Summary 100
22.4 Projected Operating Costs 106
22.5 IRR Sensitivity to Metal Prices 108
22.6 IRR Sensitivities 108
viii of 138
LIST OF APPENDICES
ix
1. Introduction and Terms of Reference
Previous:
1 of 138
Current:
Jim Gray PEng of GR Tech has visited the property three times in the
course of this evaluation, to review the current operations and inspect the project
site. Denis Gaspe PEng visited the site in November 2003 to review the
operations, infrastructure, and operations management with respect to costing
and productivity for use in the Kemess North estimates. Bob Morris visited the
site in October 2003 to review onsite drilling and exploration information and to
review the site. Ongoing meetings with Hatch, Klohn Crippen, and Knight Pisold
have been held to review the results of field, Lab, and Engineering/Environmental
evaluation work these companies are performing for the respective Metallurgy,
Environmental, a nd Geotechnical aspects of the project.
Units of measure in this report are all metric and dollars are Canadian
currency with the exception of the market price of gold and copper which are
$US/oz and $US/lb respectively. These are converted to $Canadian fo r
economic pit limit evaluation and cash flow.
The reserves and resource stated in this report are stated in tonnes with
gold grades in grams per tonne (g/t) and copper grades in %. Gold and copper
equivalent grades have also been calculated for use as cutoff grades (CoG). The
equivalent grades and the economic pit limit designs are based on the following
assumptions:
While these economic parameters are the basis of the ultimate economic pit limit
and the Reserves included in this report, financial models using price and costs
sensitivities are also run for the revised Pre-Feasibility study.
2 of 138
2. Disclaimer
Geology, drill hole, and assay information was provided by Northgate and
has been reviewed GR Tech. Geo-statistical evaluation and Resource modelling
was done under contract to GR Tech by Abdullah Arik a Qualified Person in this
discipline, employed by Mintec Inc of Tucson, AZ. The results of this work were
reviewed and validated by GR Tech by comparing to previous estimates and spot
checking the Resource model.
The Kemess North property is located on the Claims and Mining Lease as
listed in Section 3 - Property Description and Location as provided by Northgate ,
the legal status and ownership of the property has not been verified by GR Tech.
(c) Geotechnical
GR Tech has relied on work by Klohn Crippen for the Tailing Dam design,
water management, and environmental issues for Kemess North.
GR Tech has relied on work by Hatch for the Processing Metallurgy and
Infrastructure design. This includes the capital and operating cost estimates in
these areas.
3 of 138
(f) Permitting and Community Relations
All permitting requirements and Community Relations for the Kemess North
project have been undertaken by Northgate. This Technical Report includes the
Engineering, Environmental and other technical aspects of the Kemess North
project, required to meet the pertinent regulatory requirements. On this basis, it
should be reasonably expected that permits will be granted.
The Kemess North deposit is part of the Kemess Property, which covers
35,312 ha. The property is located approximately 430 km northwest of the city of
Prince George, British Columbia, Canada, at 5702 north longitude and 12647
west latitude (see Figure 1). The property includes one active mining lease
(#354991) and 213 surrounding and contiguous mineral claims, which cover
more than 34,450 hectares. At least four additional mining leases are currently in
the application process to cover the Kemess North area. The claims fall within
the Omenica Mining Division of British Columbia located on NTS map sheets
94D/15, 94E/06, 07, 16 and 17 (see Figure 2).
Figure 3 also shows the Kemess North project area in relation to the
current Kemess South operations, and the overall property position.
Legal surveys have been completed for mining lease #354991. The
mineral claims covering the Kemess North deposit and the area to the north and
west of the proposed mine (New Kemess 1, New Kemess 2, DC 1 to 5, Gap and
Overlap) have been surveyed and it is proposed to convert these claims into
mining leases. The Kemess North deposit and associated occurrences are
located on the New Kemess 1, 2 and 3 claims (see Figure 3).
4 of 138
Figure 1: Kemess Property Location Map
5 of 138
Figure 2: General Claims Outline
6 of 138
The location of the Kemess North project site and the other
operations and infrastructure for the Kemess South Operations, are shown
on Figure 3. The Kemess North project site is generally located in three
north facing alpine cirques with original ground surface ranging from 1,500
to 2,000 m elevation all above tree line. Open pit mining will be located in
shallower lower grade mineralization in the centre cirque and deeper higher
grade mineralization in the eastern cirque. The southern pit wall will be
bounded by the southern headwall of the centre and eastern cirques.
The crusher and other infrastructure will be located at the pit rim in
centre cirque. A natural rock glacier is evident in the western cirque. No
surface development has been planned to date in the western cirque.
7 of 138
OTH00123 Gas Permit issued October 27, 1998, expiry date
October 31, 1999
License to Cut
8 of 138
MX-13-69 Mineral & Coal Exploration Activities & Reclamation Permit
There are no provincial fixed time lines for completion of the closure
plan - however it must be reasonable. Therefore, to propose the plan to be
completed over a 10 year period would likely be viewed as unreasonable.
However, to suggest the closure plan will start within 12 to 24 months and
be completed within 5 years should be acceptable. The BC Ministry of
Energy and Mines are willing to consider a variety of factors that may delay
closure - i.e. economics of "related" mine development (Kemess North),
continued use of various components of the operation, staging various re-
vegetation efforts, to ensure the long-term is successful.
9 of 138
Figure 3: Detailed Kemess Area with Infrastructure Kemess South
& Kemess North
10 of 138
4. Accessibility, Climate, Local Resources, Infrastructure &
Physiography
Broad, open, drift and moraine covered valleys characterize the area,
which also has sub -alpine plateaus and rugged incised peaks and cirques.
Elevations range from 1 ,200 m to 2,000 m, with the tree line occurring at
approximately 1,500 m. All the work completed during the 2002 and 2003
drill programs occurred above tree line in three cirques, which open to the
north forming a common southern headwall. Lower elevations on the
property are moderately vegetated with spruce-willow-birch forest, while
poorly drained areas form peat bogs populated by alder brush, willow, and
stunted spruce trees.
Access to the Kemess North project is provided by both air and road
via the current Kemess Operations. There are scheduled year-round flights
from Smithers, Prince George, Vancouver, Kelowna, Kamloops and
Williams Lakes to Kemess from Monday to Thursday. All season road
access is from either the town of Mackenzie or Fort St. James via the
Omenica resource access road.
11 of 138
schedule while some technical and management personnel work a 4-day in
and 3-day off rotation.
Kemess Mines Ltd. holds surface rights through their mineral claims
and mining leases. Onsite infrastructure for the current operation consists of
an office and maintenance building, a 400-person camp, a mill building,
maintenance and office complex, crushers and raw ore stockpile areas,
access and service roads, airstrip, explosives depot, and tailings facilities.
The tailings pond capacity is sufficient to meet the needs of the Kemess
South ore body until its completion in 2008.
12 of 138
5. History
Pacific Ridge Resources Ltd. (Pacific Ridge) staked the area of the
Kemess South deposit in 1983. Exploration programs were subsequently
carried out by Pacific Ridge Resources Ltd. and Anaconda Canada Ltd.
(Anaconda) in 1984; St. Philips Resources Inc. (St. Philips) in 1988 and the
Kemess South Joint Venture between El Condor Resources Ltd. (El Condor)
(60%), operator, and St. Philips Resources Ltd. (40%) from 1990 to 1993. In
1991, Rio Algom Explorations Inc. (Rio Algom) acquired claims adjoining the
west and south sides of the Kemess South Joint Venture claim holdings.
13 of 138
Table 5.1
Production History from Kemess South
The earliest reports of exploration activity in the area date back to the
discovery of placer gold at the mouth of McConnell Creek in 1889. Several
years later there was a brief staking rush in 1907 and prospecting remained
active in the area through the early 1920s resulting in a placer discovery at
McClair Creek. Cominco Ltd. was active in the area in the 1930s exploring
for base metals. During this period Emile Bronlund discovered and staked
several skarn showings; the Cairn showing is a nearby occurrence from this
era that is located on Duncan Ridge, 6 km west of Kemess North.
14 of 138
Table 5.2
Summary of Exploration Work
15 of 138
6. Geological Setting
This section has been adopted from Edmunds and LaPeare (2002).
Intrusive rocks are prevalent in the area and have been categorized
as late Triassic Alaskan-type ultramafics such as pyroxene diorite,
hornblende gabbro and pyroxenite. Economically more significant are the
early Jurassic intrusives of the Black Lake suite, which are granodiorite,
hornblende diorite, pyroxene quartz-diorite, quartz-monzonite and quartz
monzodiorite. Important plutonic masses are the Duncan Lake stock (197.3
Ma), the Sovereign stock (202.7 Ma) and the Maple Leaf pluton (199.6 Ma).
The latter hosts the Cu-Au deposit at Kemess South.
For the most part the volcanic Mesozoic assemblages are upright, shallowly
dipping to flat-lying sequences crosscut by high angle north to northwest
trending faults. Significant structures are the Finlay-Ingenika and Moosevale
fault systems, which bound the eastern margin of the belt. These structures
are dextral strike-slip features that are related to the terrain bounding faults
between the Intermontane and Omenica belts.
16 of 138
Table 6.1: Regional Stratigraphy (Cope, 1992)
17 of 138
(b) Local Geology
More local to Kemess North are the Duncan and Saunders Faults, which are
north-northwest normal block fault structures. Thrust faulting is present in
the district and is interpreted as Eocene or younger; displacement believed
to be towards the northeast and effects rocks from the Takla up to Sustut
sediments.
18 of 138
Due to the lack of bedding and/or marker horizons, the inclination of
the massive thick succession of Takla volcanics is difficult to ascertain but
probably reflects the regional trend of flat lying Mesozoic assemblages.
Mantling the northern and eastern limits of the Kemess North area is
a matrix supported polylithic fragmental volcanic unit. Sub -rounded angular
coarse fragments of bladed feldspar porphyry, andesite, monzonite and rare
quartz-feldspar porphyry or chert occur within a siliceous (dacite) matrix.
Lithic proportion to matrix is inconsistent ranging from 1-30% volumetrically,
with clast size varying from lapilli to blocks. The matrix is fine-grained, dark
gray comprised of 10-30% medium grained feldspar and diagnostic (5%)
quartz phenocrysts. Magnetite is common as an accessory mineral
occurring as very fine-grained disseminations as is distinctive zeolite-calcite
veinlets. Propyllitic (epidote-calcite-pyrite) alteration is dominant within the
fragmental, however narrow (10-20 m) zones of phyllic (quartz-sericite-
pyrite) alteration are present near discordant contacts with the Takla Group.
The phyllic sections can carry anomalous gold concentrations.
19 of 138
however petrographic work shows that the mineralized granitoid underlying
East Cirque is more correctly classified as a quartz diorite due to the paucity
(< 5% to absent) of alkali feldspars.
The main quartz monzonite mass beneath East Cirque hosts the bulk
of the Cu-Au mineralization at Kemess North.
There are several hypotheses for the formation of the Broken Zone.
The theories range from the effects of present day weathering, porphyry
related alteration zonation, to the tectonic end products of shallow faulting
and thrusting. Key features to consider are that the broken zone underlies
and is adjacent to highly competent, unaltered, siliceous Toodoggone
fragmental rocks. This suggests that the alteration occurred in the early
20 of 138
Jurassic before the emplacement of the dacitic fragmental unit. The most
plausible explanation is that the Broken Zone and related phyllic alteration
are due to pre-Toodoggone weathering processes.
21 of 138
Figure 4: Regional Geology after Massey et al 2003
Minfile Occurrences Plotted by Colour Showing Principal
Commodities as Follows:
Gold Red,
Silver Blue,
Copper Green
22 of 138
Figure 5: Shows the General Property Geology
in the Area around Kemess North (Diakow 2001)
23 of 138
Figure 6: Kemess North Geology - Diakow (2001)
24 of 138
7. Deposit Type
A 3-D Block Model has been used to represent the Kemess North
mineral Resources. Mintecs MineSight software, an industry proven
software system, has been used for the modelling . The geology model area
used is large enough to include drill holes from the Nugget area to the west
and the Kemess East area. It also extends sufficiently outside the drilled off
area to include waste material which will fall within the ultimate pit design.
To restrict the resource estimate to defined geology units, four major
lithology zones were modeled as defined by the drillholes. Although multiple
rock types were recorded in the drill logs these are grouped together into the
four main lithologies. Three of the lithologies represent potential ore
material, while the fourth lithology represents rock types known as barren or
low grade mineralization. Any undefined areas within the model boundaries
are therefore designated as waste since these are areas that do not have
sufficient drill hole assay spacing to delineate a continuous Lithology zone.
Details of the 3-D Block model and Resource/Reserve estimation are
included in Section 16.
8. Mineralization
This section has been adopted from Edmunds and LaPeare (2002).
25 of 138
cross-faulting that have down-dropped the tabular upper contact present in
East Cirque, or the rheologic conditions during intrusion changed going
towards the west whereby steep fracture infilling was preferred over
stopeing.
Grading outwards from the East Cirque stock into the Takla
volcanics, silicification decreases gradually to fine-grained assemblages of
chlorite-biotite-sericite, which volumetrically constitutes the bulk of the
mineralization. This pattern is a broad generalization and there are areas of
either potassic (biotitic) or propyllitic (chloritic) alteration that also have an
irregular and patchy outline in plan and cross section.
26 of 138
Overall, sulphide mineralization throughout the deposit consists of 2-
3% pyrite, with lesser amounts of chalcopyrite and traces of molybdenum.
Pyrite occurs as disseminations, fracture fillings, and veins up to a few
centimetres wide generally associated with quartz-anhydrite-magnetite veins
and zones of quartz-magnetite replacement. The mode of occurrence of
chalcopyrite is similar except that veinlets are rare and significant
disseminations occur in zones of stronger quartz-magnetite stock work and
quartz-magnetite replacements. Gold and copper grades variably diminish
outward into the hanging wall and footwall. Total sulphide content in the core
of the deposit averages 3-5%, rising to 5-7% in the pyrite -rich sericitic
altered upper halo.
9. Exploration
27 of 138
there been any trenching. Surface work has been confined to access road
and drill site construction. A recently completed regional airborne
geophysical program will be of great interest as it may add to the
understanding of the volcanic and intrusive events in the area. It is
suspected that the program will have little impact for the reserve estimate on
the Kemess North project.
Table 9.1
Exploration Employees/Contractors
28 of 138
10. Drilling
Since May 2002, two summer drill programs have been completed on
the Kemess North property. Britton Bothers Diamond Drilling of Smithers,
BC completed this work. In total, 198 holes have been completed for a
cumulative of 77,210 m of drilling. Up to four drill rigs were used on the
property, three on skids and one helicopter portable.
(a) Procedures
All of the drilling on the property has been continuous core diamond
drilling. Because of the broken zone at surface, drilling procedures include
setting surface casing then drilling with large diameter HQ core. Once
through the broken zone, and into more solid rock, the drillers generally
reduced to NQ core to complete the hole. Upon completion of the hole, all of
the drill pipe is removed from the hole, though the surface casing is left to
mark the hole location.
29 of 138
lithologies. The mineralized Takla volcanic and intrusive rocks show
generally vertical contacts. The higher-grade monzodiorite intrusive in the
East Cirque appears to be an inclined tabular body, dipping 20 to the south.
CD-01
CD-02
CD-03
CD-09
CD-10
CD-19
CD-11
CD-12
CD-13B
CD-14B
0 1,000 2,000
meters
30 of 138
(d) Collar Survey
Survey control for the drill hole collars was by GPS using a base
station that provided real-time correction such that sub -centimeter accuracy
was achieved.
In 2003, the Flex-IT down-hole survey tool was used. The Flex-IT tool
records the ambient magnetic field while it determines the orientation of the
drill hole at a certain depth. Errant readings on the Fle x-IT are either
removed from the file when over or under-limit magnetics are encountered,
or their effects are minimized by adjacent readings that are true magnetic
north.
The 2003 down-hole survey data was compiled for the Kemess North
area and plotted by hole deviation (azimuth only) versus hole depth. A
regression between the two variables, azimuth and depth, was determined.
For each of the 2003 holes in the potential pit area the regression equations
were derived and tabulated to determine an average slope constant and Y-
intercept. Using this average figure, the down-hole survey files for the 2000-
2002 drilling were revisited. Holes that exhibited counter-clockwise deviation
or sharp bends were re-calculated. In total 18 suspect drill holes were
considered inconsistent with the hole trends derived from the Flex-IT data.
Plots of these holes and drilling experience also confirm that the down hole
surveys of these 18 holes are suspect.
31 of 138
Because the assays for these holes are valid they have been included as
corrected, with a recommendation to re-run the down hole survey with the
Flex-IT tool, if possible , or twin a few of the more important holes. This hole
twinning can have other benefits with respect to the Geo-Statistical analysis.
32 of 138
Table 10.1: Drill Collar Location and Orientation Data
Survey Coordinates
Hole # Easting Northing Elevation Azimuth Dip Depth
KN-00-01 9,662.980 15,573.870 1,751.070 180.000 -70.000 131.100
KN-00-02 9,659.790 15,960.280 1,702.540 0.000 -90.000 150.900
KN-00-03 9,959.000 15,689.360 1,702.150 0.000 -90.000 399.300
KN-00-04 10,158.770 15,808.870 1,720.120 0.000 -90.000 399.300
KN-00-05 10,162.220 15,963.830 1,719.440 0.000 -90.000 399.300
KN-00-06 9,862.070 15,641.100 1,715.100 0.000 -90.000 113.100
KN-00-07 10,062.730 15,736.210 1,694.330 180.000 -60.000 129.540
KN-00-09 10,126.670 16,069.310 1,700.240 0.000 -90.000 388.620
KN-01-01 10,159.390 16,164.800 1,722.000 176.500 -84.250 585.220
KN-01-02 10,156.080 16,284.980 1,736.980 181.500 -84.750 554.740
KN-01-06 10,411.170 16,139.510 1,710.930 300.000 -80.000 597.710
KN-01-07 10,421.670 16,240.150 1,706.120 0.000 -81.000 600.500
KN-01-08 10,454.830 16,297.370 1,692.060 90.000 -87.000 167.740
KN-01-09 10,467.340 16,381.440 1,672.660 149.250 -88.250 499.900
KN-01-10 10,581.550 16,289.270 1,644.320 118.500 -88.500 554.740
KN-01-11 10,667.020 16,355.750 1,597.530 0.000 -90.000 472.440
KN-01-13 10,664.810 16,271.840 1,624.930 64.000 -88.500 621.800
KN-01-14 10,765.920 16,299.450 1,588.040 101.500 -89.500 281.030
KN-01-15 10,665.790 16,164.710 1,664.270 128.500 -89.500 627.900
KN-01-16 10,569.420 16,473.561 1,603.770 79.500 -88.500 320.040
KN-01-17 10,561.290 16,095.530 1,688.530 0.000 -90.000 756.100
KN-02-02 10,557.000 16,377.650 1,624.710 0.000 -90.000 224.640
KN-02-06 10,159.780 16,341.220 1,750.300 180.000 -85.000 602.590
KN-02-07 10,461.190 15,933.830 1,724.970 0.000 -80.000 737.000
KN-02-10 10,053.570 16,264.580 1,682.710 0.000 -90.000 502.010
KN-02-11 10,157.510 16,489.490 1,784.890 180.000 -85.000 496.820
KN-02-12 10,559.440 15,989.110 1,705.170 0.000 -90.000 688.380
KN-02-14 10,062.020 15,871.370 1,692.160 0.000 -90.000 616.610
KN-02-15 9,960.290 15,904.200 1,687.780 0.000 -90.000 650.000
KN-02-17 10,062.930 15,994.110 1,683.080 0.000 -90.000 703.140
KN-02-18 10,654.110 16,067.110 1,686.400 0.000 -90.000 736.700
KN-02-20 10,456.660 16,361.900 1,677.800 0.000 -75.000 458.700
KN-02-21 10,069.650 16,156.510 1,678.020 0.000 -90.000 621.000
KN-02-22 10,759.920 15,976.200 1,694.260 0.000 -85.000 721.460
KN-02-23 8,845.280 15,091.100 1,831.530 0.000 -75.000 1,011.020
KN-02-24 10,551.960 16,192.210 1,679.130 0.000 -90.000 710.180
KN-02-26 9,858.310 16,050.750 1,672.380 0.000 -90.000 102.720
KN-02-28 9,755.060 15,761.200 1,743.220 0.000 -90.000 623.930
KN-02-29 10,360.950 15,729.460 1,765.960 0.000 -90.000 785.850
KN-02-30 8,355.180 15,596.850 1,726.610 0.000 -70.000 450.190
KN-02-31 9,838.940 16,223.120 1,649.510 0.000 -70.000 325.850
KN-02-32 11,011.570 15,445.360 1,852.170 180.000 -60.000 469.390
KN-02-33 9,960.680 16,120.840 1,663.650 0.000 -90.000 508.100
KN-02-34 8,332.290 15,036.080 1,755.710 0.000 -70.000 815.950
KN-02-35 9,859.200 16,132.860 1,665.290 0.000 -90.000 580.640
KN-02-36 9,929.730 16,218.360 1,653.040 0.000 -90.000 587.000
KN-02-37 10,094.000 15,156.670 1,889.030 180.000 -70.000 488.000
KN-02-38 9,865.100 15,997.100 1,678.210 0.000 -90.000 625.610
KN-02-39 10,161.780 15,878.690 1,723.550 0.000 -90.000 675.740
33 of 138
Survey Coordinates
Hole # Easting Northing Elevation Azimuth Dip Depth
KN-02-40 8,345.980 15,290.020 1,737.580 0.000 -70.000 690.980
KN-02-41 11,459.570 15,760.550 1,803.930 180.000 -70.000 490.730
KN-02-42 9,759.570 16,153.240 1,672.210 0.000 -80.000 480.650
KN-02-43 8,837.710 15,010.310 1,808.590 0.000 -80.000 703.170
KN-02-44 10,055.650 16,363.460 1,688.350 0.000 -90.000 151.490
KN-02-46 10,059.170 16,314.960 1,687.060 0.000 -90.000 570.580
KN-02-47 9,659.200 16,040.680 1,690.490 180.000 -70.000 543.460
KN-02-48 8,962.280 15,087.730 1,875.250 0.000 -90.000 605.640
KN-02-49 9,064.140 15,070.880 1,890.340 0.000 -90.000 669.820
KN-02-50 8,839.970 14,910.030 1,746.570 0.000 -80.000 623.320
KN-02-51 9,069.600 14,969.850 1,877.630 0.000 -90.000 668.290
KN-02-52 8,867.360 14,793.800 1,748.760 0.000 -90.000 660.670
KN-02-55 9,457.770 15,768.000 1,780.310 0.000 -90.000 572.260
KN-02-56 8,751.880 15,005.360 1,758.720 0.000 -80.000 542.070
KN-75-18 9,835.860 16,006.950 1,675.280 0.000 -90.000 75.290
KN-75-19 9,713.910 15,955.330 1,698.940 0.000 -90.000 86.720
KN-75-20 9,535.160 16,019.700 1,697.670 0.000 -90.000 185.010
KN-75-21 9,473.680 16,120.330 1,694.160 0.000 -90.000 215.490
KN-75-22 9,736.490 16,132.800 1,675.920 0.000 -90.000 26.060
KN-76-23 8,647.850 15,340.080 1,848.240 0.000 -90.000 115.210
KN-76-24 8,666.530 15,175.970 1,836.130 0.000 -90.000 118.260
KN-76-25 10,027.500 15,936.360 1,684.270 0.000 -90.000 319.430
KN-76-26 9,871.490 15,754.750 1,695.680 0.000 -90.000 308.460
KN-76-27 9,777.970 15,930.560 1,691.010 0.000 -90.000 210.310
KN-76-28 9,775.940 16,122.090 1,672.980 0.000 -90.000 215.800
KN-76-29 10,062.330 15,813.200 1,688.530 0.000 -90.000 188.370
KN-89-1 10,160.020 16,200.450 1,729.060 173.000 -45.000 152.400
KN-89-2 10,140.980 16,317.830 1,733.400 175.000 -45.000 149.350
KN-89-3 10,423.830 16,127.950 1,707.350 185.000 -50.000 145.080
KN-89-4 10,434.580 16,002.550 1,717.120 185.000 -45.000 152.400
KN-89-5 10,055.860 16,265.770 1,683.750 184.000 -45.000 132.590
KN-90-10 10,181.960 16,048.100 1,728.630 176.000 -46.000 200.250
KN-90-11 10,297.560 15,815.880 1,747.140 140.000 -46.000 200.250
KN-90-12 10,288.760 15,874.850 1,764.270 43.000 -45.000 96.620
KN-90-13 10,441.600 15,881.760 1,727.430 182.000 -45.000 200.250
KN-90-14 10,389.740 15,988.490 1,735.950 223.000 -46.500 123.750
KN-90-15 10,210.270 15,710.740 1,745.790 140.000 -45.000 200.250
KN-90-16 10,166.320 15,868.250 1,725.310 50.000 -46.500 200.250
KN-90-17 9,990.330 15,967.560 1,679.170 180.000 -65.000 163.680
KN-90-6 8,458.150 15,548.390 1,748.260 175.000 -45.000 196.290
KN-90-7 8,453.570 15,694.680 1,699.410 180.000 -45.000 200.250
KN-90-8 8,767.240 15,531.960 1,734.690 152.000 -50.000 203.300
KN-90-9 9,312.490 16,143.020 1,764.960 0.000 -90.000 218.540
KN-91-31 9,857.820 15,963.380 1,682.890 0.000 -90.000 282.550
KN-91-32 9,859.790 15,864.030 1,690.070 0.000 -90.000 306.930
KN-91-33 9,759.210 15,859.790 1,708.040 0.000 -90.000 306.930
KN-91-34 9,956.320 15,852.580 1,692.520 0.000 -90.000 282.550
KN-91-35 10,060.130 15,957.950 1,686.930 0.000 -90.000 282.550
KN-91-36 9,755.770 15,761.670 1,743.190 0.000 -90.000 261.620
KN-91-37 9,653.780 15,859.520 1,736.310 0.000 -90.000 331.310
KN-91-38 9,553.450 15,956.890 1,703.270 0.000 -90.000 297.790
34 of 138
Survey Coordinates
Hole # Easting Northing Elevation Azimuth Dip Depth
KN-91-39 9,858.390 15,960.620 1,683.400 0.000 -90.000 82.300
KN-91-40 9,858.620 15,866.970 1,689.400 0.000 -90.000 79.750
KN-91-41 9,662.400 16,057.610 1,686.120 0.000 -90.000 282.550
KN-91-42 9,754.510 16,058.390 1,682.630 0.000 -90.000 282.550
KN-91-43 9,858.690 16,057.470 1,672.650 0.000 -90.000 273.400
KN-91-44 9,955.170 16,057.730 1,665.760 0.000 -90.000 270.350
KN-91-45 10,057.430 16,058.110 1,678.510 0.000 -90.000 276.450
KN-91-46 9,957.470 15,757.070 1,694.130 0.000 -90.000 340.470
KN-91-47 9,658.470 15,755.950 1,762.700 0.000 -90.000 367.890
KN-91-48 9,559.070 15,857.140 1,743.140 0.000 -90.000 338.940
KN-91-49 9,555.450 15,756.910 1,752.920 0.000 -90.000 431.290
KN-91-50 9,660.940 15,656.020 1,741.060 0.000 -90.000 443.480
KN-91-51 9,757.670 15,657.320 1,738.500 0.000 -90.000 337.410
KN-91-52 8,873.880 15,756.100 1,626.500 0.000 -90.000 154.530
KN-91-53 8,897.850 15,568.100 1,652.500 0.000 -90.000 154.530
KN-91-54 8,908.830 15,426.090 1,710.500 0.000 -90.000 212.450
KN-91-55 9,109.860 15,578.060 1,666.500 0.000 -90.000 169.770
KN-91-56 9,062.890 15,764.070 1,640.500 0.000 -90.000 154.530
KN-91-57 9,088.910 15,891.060 1,638.500 0.000 -90.000 54.250
KN-92-63 8,837.110 15,189.310 1,853.700 0.000 -90.000 165.500
KN-92-64 8,836.860 15,010.230 1,807.600 0.000 -90.000 199.700
KN-92-66 8,293.980 15,116.580 1,707.400 0.000 -90.000 151.800
KN-92-67 8,287.820 15,264.650 1,690.910 0.000 -90.000 148.700
KN-92-68 9,014.490 14,914.230 1,857.200 270.000 -60.000 132.300
KN-92-69 9,050.530 14,756.210 1,844.900 0.000 -90.000 125.900
KN-92-70 9,163.050 14,605.680 1,764.560 0.000 -90.000 150.000
KN-92-75 10,492.890 16,102.470 1,700.720 0.000 -90.000 252.400
KN-92-76 10,695.130 16,108.760 1,678.160 0.000 -90.000 197.500
KN-92-77 10,501.790 15,954.890 1,711.340 0.000 -90.000 228.000
KN-92-78 10,728.350 15,979.310 1,695.610 0.000 -90.000 203.300
KN-92-79 10,934.760 16,021.320 1,695.610 0.000 -90.000 172.800
KN-92-80 10,714.270 15,838.950 1,710.970 0.000 -90.000 118.000
KN-92-81 10,450.720 16,197.050 1,699.120 0.000 -90.000 294.700
KN-92-82 9,040.850 15,058.270 1,887.170 0.000 -90.000 90.500
KN-92-83 9,559.320 15,647.800 1,772.560 0.000 -90.000 264.300
KN-92-84 9,430.490 16,065.500 1,722.400 0.000 -90.000 166.700
KN-92-85 9,449.940 15,973.580 1,731.900 0.000 -90.000 181.700
KN-92-86 10,596.850 16,109.640 1,683.900 0.000 -90.000 252.100
KN-92-87 10,551.380 16,194.700 1,679.300 0.000 -90.000 316.100
KN-00-08 10,261.630 15,897.930 1,776.900 0.000 -80.000 454.200
KN-00-10 10,225.930 15,790.360 1,747.940 0.000 -80.000 521.210
KN-00-11 10,398.410 15,944.160 1,733.800 340.000 -80.000 509.020
KN-00-12 10,282.240 16,018.290 1,794.380 340.000 -80.000 674.000
KN-01-03 10,265.770 16,117.460 1,787.190 0.000 -80.000 600.500
KN-01-04 10,268.010 16,207.840 1,792.530 2.000 -80.500 597.410
KN-01-12 10,259.500 16,276.930 1,803.180 0.000 -72.500 548.640
KN-02-01 10,458.930 16,139.050 1,699.050 0.000 -80.000 623.930
KN-02-03 10,460.780 16,033.030 1,707.690 0.000 -80.000 770.230
KN-02-04 10,578.570 16,289.420 1,645.410 0.000 -75.000 451.000
KN-02-05 10,356.230 16,236.270 1,736.820 0.000 -85.000 590.400
KN-02-08 10,249.180 16,367.610 1,818.000 0.000 -70.000 423.700
35 of 138
Survey Coordinates
Hole # Easting Northing Elevation Azimuth Dip Depth
KN-02-09 10,358.300 16,320.290 1,736.580 0.000 -85.000 578.210
KN-02-13 10,360.320 16,046.030 1,738.060 0.000 -85.000 691.000
KN-02-16 10,362.250 15,844.150 1,740.970 0.000 -85.000 804.000
KN-02-19 10,364.550 16,440.961 1,729.900 0.000 -85.000 469.390
KN-02-25 10,759.920 15,976.200 1,694.260 180.000 -75.000 764.130
KN-03-01 9,070.000 14,876.030 1,864.930 0.000 -90.000 643.430
KN-03-02 9,253.790 14,997.170 1,895.900 0.000 -80.000 648.300
KN-03-03 9,266.120 15,184.130 1,916.510 0.000 -90.000 695.000
KN-03-04 8,843.880 15,209.740 1,857.830 0.000 -75.000 657.500
KN-03-05 8,563.900 14,930.060 1,706.270 0.000 -90.000 524.300
KN-03-06 9,471.260 15,337.630 1,930.280 180.000 -80.000 650.500
KN-03-07 9,430.930 15,546.520 1,852.760 180.000 -85.000 570.500
KN-03-08 8,759.960 15,218.760 1,850.950 0.000 -85.000 566.000
KN-03-09 8,985.790 16,591.539 1,493.290 0.000 -50.000 349.600
KN-03-10 8,859.810 15,694.450 1,632.790 0.000 -65.000 449.000
KN-03-11 9,245.500 15,667.670 1,747.510 0.000 -80.000 572.100
KN-03-12 9,076.040 15,381.490 1,719.840 0.000 -90.000 558.400
KN-03-13 9,662.070 15,835.470 1,741.570 180.000 -85.000 475.500
KN-03-14 10,162.700 16,006.150 1,718.370 0.000 -90.000 518.200
KN-03-15 10,456.500 16,033.400 1,707.700 80.000 -45.000 153.920
KN-03-16 9,960.540 15,998.020 1,672.500 0.000 -85.000 442.600
KN-03-17 10,456.500 16,033.400 1,707.700 260.000 -45.000 406.300
KN-03-18 10,062.130 16,088.180 1,678.180 0.000 -90.000 457.200
KN-03-19 10,763.430 16,081.770 1,683.830 90.000 -45.000 397.100
KN-03-20 10,760.230 16,078.360 1,683.700 0.000 -82.000 438.000
KN-03-21 9,960.450 16,307.870 1,653.300 0.000 -90.000 151.500
KN-03-22 10,020.430 16,211.880 1,666.230 0.000 -90.000 148.400
KN-03-23 9,651.100 16,150.800 1,674.770 0.000 -90.000 90.000
KN-03-24 9,681.410 16,251.370 1,653.230 0.000 -90.000 102.700
CD-03 8,527.670 17,171.221 1,416.860 0.000 -90.000 294.700
CD-04 8,985.970 16,594.449 1,493.250 180.000 -65.000 340.500
CD-05 9,540.200 16,640.859 1,554.490 0.000 -70.000 313.000
CD-06 8,984.280 16,087.570 1,608.130 180.000 -70.000 305.100
CD-07 8,299.440 16,629.980 1,558.450 0.000 -70.000 316.100
CD-18 10,764.390 16,682.180 1,547.000 0.000 -80.000 451.100
DH-03-14 10,701.100 16,772.520 1,541.000 0.000 -90.000 16.750
KN-02-53 8,538.420 15,115.090 1,809.550 180.000 -80.000 40.040
KN-02-57 10,939.800 16,023.930 1,695.890 93.000 -60.000 429.000
KN-02-58 10,059.820 16,310.460 1,687.420 6.000 -60.000 591.000
KP-03-01 10,395.320 16,224.400 1,717.120 260.000 -50.000 688.100
KP-03-02 10,402.090 16,302.830 1,711.260 330.000 -65.000 529.600
KP-03-03 10,501.840 16,302.050 1,672.980 30.000 -60.000 551.800
KP-03-04 10,615.180 16,177.830 1,673.080 90.000 -65.000 499.090
KP-03-05 10,499.580 16,106.070 1,699.320 130.000 -60.000 480.800
KP-03-06 10,355.000 16,095.750 1,737.090 200.000 -60.000 501.520
KP-03-07 9,860.270 15,942.360 1,683.900 230.000 -65.000 453.200
KN-02-54 10,162.410 15,915.340 1,718.710 180.000 -55.000 557.010
36 of 138
11. Sampling Method and Approach
Samples from the Kemess North project are totally drill core based,
there are no trench or grab samples in the database. Sample intervals were
determined by a geologist, according to lithology, and ranged from 0.3 to 2.0
m, with the average length of samples being 1.8 m. Core was split using a
diamond saw. Because of the low-grade nature of the mineralization, and
difficulty determining potential ore from non-ore material, the entire drill hole
is sampled. Once in a uniform rock type, the sample spacing was generally
2.0 m. The maximum 2 m-sample length was chosen so that more detail
could be gained concerning the distribution of grade. As well, the 2 m core
length provides a representative sample weight for NQ core. For HQ core, a
maximum sample length of 1.5 m was applied.
The current database contains 198 drill holes with an average length
of 390 m, with the majority in the 200 m to 600 m range. There are a few
short holes less than 100 m, while the deepest hole is 1 ,011 m.
37 of 138
mm core) to act as casing for NQ (48 mm core), which usually was used to
complete the hole, has solved the problem. In rare instances reduction to
BQ (37 mm core) was necessary to reach target depth. The core recovery is
very high with an average of ~70% in the Broken Zone, and ~100% in the
remainder.
A test was conducted to compare assay results from holes with steep
angles to holes with shallow angles. In total 29 holes were drilled at shallow
angles (less than -60) so that oriented core could be obtained to assist with
the geotechnical program. It was found that there is no significant grade
variation between the two data sets. Because the angle holes tested various
different directions, it appears likely that there is no preferred vein
orientation in the deposit that could be missed with steep drilling.
It is our opinion that the sampling and assay program was carried out
with the reasonable care and skill expected of the engineering profession.
Drilling since 2001 has been the most important exploration carried
out on the Kemess North property. This new drilling forms the basis of the
mineable resource as the pre-2001 drilling was not deep enough to test the
higher-grade zones. As well, more than of the assays have been
completed since 2001. The evaluation of the sample Preparation, Analysis,
and Security has therefore been focused on the 2001 and later activities.
The drill core was logged by a small team of geologists, split using a
rock saw, and then samples were passed through primary crushing. During
the 2002 program, a portable sample preparation lab was leased from ALS
Chemex. For the 2003 program, a sample -bucking facility was built near the
mill area.
The core samples were dried then crushed to 80% passing 10 mesh
at the mine site. Each sample is riffled twice with one split being retained at
38 of 138
the mine, and a 250 g sample sent to the lab. The remainder of the sample
was discarded.
The portion of sample retained at the mine site is kept in a plastic bag
with a sample tag and stored in a plastic pail. The portion of the sample sent
to the lab was placed in a plastic bag with a sample tag, shipped in a plastic
pail with two security tags, the pail top was sealed and taped. A submission
sheet was sent along with each pail of samples that included the name of
the sample preparation person, the date, the sample numbers, the number
of samples, and the numbers of the security tags.
Chemex Labs carried out more than 76% of the total assays for this
project. The lab is widely used by the mining and exploration industry and
carries the highest certification as registered assayers, including ISO 9002,
ISO:9001:2000, and they are working towards ISO 17025.
The remaining 24% of the assay work was carried out by various
other labs for the earlier exploration companies including Kennco, Getty,
Shell Oil, and El Condor. Historical records of the Sampling, Analysis, and
Security of this earlier work are not available. Most of this work is for shallow
drilling and the project is sensitive to the deeper part of the deposit.
It is our opinion that the sampling and assay program was carried out
with the reasonable care and skill expected of the engineering profession.
39 of 138
13. Data Verification
In total, three days were spent at the Kemess mine site verifying the
geological database, as well as at least three days doing verification in the
office. During the field check, six drill holes were visited, the holes have
been left with the surface casing in place; the collars are marked with pieces
of 4x4 wood stuck into the casing pipe and metal labels nailed to the posts.
As well as the six holes visited, many more collar markers were visible. The
area has many roads that have been built to access drill sites.
The second step with the field verification was to visit the core
storage area. All of the core is stored in racks, which are well built, marked
and mapped out. A legend is available showing where each hole is stored
by rack number. All of the core is split with a diamond saw and weather
resistant sample tags have been used to mark sample intervals. The tags
are stapled to the edge of the core box at the beginning of the sample
interval. Depth markers have been converted to metric. Sample numbers
correspond with core logging sheets. Sample lengths were between 1.5 m
and 2.0 m. It was observed that there have been samples taken for SG
testing and metallurgical testing; both sample sets were well marked in the
core boxes.
40 of 138
that the work completed by the exploration group has been diligent and has
been carried out with care and skill expected of the engineering profession.
Nugget Zone
Duncan Ridge
41 of 138
Other Areas of Interest
The Bear Claims were staked, to the south of and adjacent to the
existing Kemess claim block. The oxidized Toodoggone volcanic rocks that
originally covered the south area of the Kemess South open pit hindered
exploration in this area at the time of discovery and delineation of the
deposit because induced polarization geophysical surveys were unable to
detect the covered part of the deposit. The company will integrate the results
of this years airborne geophysical survey with a deep penetrating ground
geophysical survey, to be carried out in 2004, in order to identify conductive
argillic alteration zone that may be associated with any other hidden
porphyry deposits.
42 of 138
Figure 9: Kemess Claim and Surrounding Properties
43 of 138
Au prospect to host 160 Mt grading 0.50 g/t Au and 0.20% Cu defined by 34
drill holes of 7,889 m. Exploration work planned for 2004 by Stealth includes
6,000 m of drilling on a series of epithermal gold and silver occurrences
located to the north and east of the map area. Stealths extensive land
holdings in the Toodoggone District cover 288 km 2.
44 of 138
This indicates that the met samples were well located to represent the deep
ore for the Kemess North deposit. Future testing should also be done on the
shallow ore on the west side of the pit for more detailed prediction of
operating performance during the earlier years of the project. Since the
project viability is dependant on the performance of the deep, higher grade
ore, and during the earlier schedule periods plant feed will also be provided
from Kemess South, these shallower samples are not considered to be
critical to the project viability.
Sample
Drill Holes
#
1 KN-00-12 KN-02-01 KN-02-04 KN-02-05 KN-02-09
2 KN-02-01 KN-02-03 KN-02-05 KN-02-07 KN-02-09 KN-02-13 KN-02-16 KN-02-24
3 KN-02-01 KN-02-03 KN-02-05 KN-02-13 KN-02-16 KN-02-18 KN-02-24
4 KN-01-17 KN-02-01 KN-02-03 KN-02-07 KN-02-13 KN-02-16 KN-02-24
5 KN-02-0102-03 KN-02-06 KN-02-07
6 KN-02-01 KN-02-04 KN-02-05 KN-02-06 KN-02-09
7 KN-02-05 KN-02-06 KN-02-09
8 KN-02-05 KN-02-08 KN-02-09
9 KN-02-01 KN-02-03
10 KN-02-01 KN-02-04 KN-02-06
11 KN-02-01 KN-02-05 KN-02-06 KN-02-09 KN-02-10 KN-02-21
12 KN-02-01 KN-02-05 KN-02-06 KN-02-08 KN-02-09 KN-02-21
13 KN-02-16 KN-02-18 KN-02-24
14 KN-02-13 KN-02-16 KN-02-24
15 KN-02-13 KN-02-24
16 KN-02-14 KN-02-17 KN-02-21
17 KN-02-14 KN-02-17 KN-02-36 KN-02-39
18 KN-02-10 KN-02-17 KN-02-21 KN-02-39
19 KN-02-03 KN-02-07 KN-02-24
20 KN-02-03 KN-02-07 KN-02-13 KN-02-24
21 KN-02-03 KN-02-07 KN-02-13 KN-02-16 KN-02-24
22 KN-02-03 KN-02-13
23 KN-02-03 KN-02-07 KN-02-13 KN-02-15
24 KN-02-15 KN-02-33 KN-02-36
25 KN-02-10 KN-02-14 KN-02-15 KN-02-17 KN-02-21 KN-02-46
26 KN-02-14 KN-02-15 KN-02-17 KN-02-21 KN-02-39
27 KN-02-14 KN-02-15 KN-02-17 KN-02-38 KN-02-39
28 KN-02-15 KN-02-33
29 KN-02-01 KN-02-13 KN-02-14 KN-02-15 KN-02-15 KN-02-16 KN-02-17 KN-02-33 KN-02-39
30 KN-02-14 KN-02-15 KN-02-17 KN-02-39
45 of 138
Figure 10: Pit 634 with Met Sample Drill Holes
46 of 138
Additional metallurgical reports referenced are Amtel Ltd.s Kemess
North Preliminary Metallurgical Testing June 2001, Characterisation of
Copper and Gold occurrences in Composites of the Kemess North Deposit,
Summer 2002 and Gold Deportment in Copper Cleaner Scavenger
Tailings, May 2003.
The sulphides are coarse grained and are adequately liberated for
rougher flotation at a grind of K80 at 145 .
Ball mill work indices for samples of two recent plant surveys were
13.8 and 15.0 kWh/t. The BMWI for the sample used in laboratory
testing was only 12.5, well below average. The samples of Kemess
North averaged 13.8 kWh/t.
The average metal contents of North ores are slightly lower, copper
at 0.20% Cu versus 0.22% Cu and gold at 0.4 g/t Au versus 0.75 g/t
for South ores.
The near surface ores of the North deposit are of slightly lower grade
than those of deeper zones.
47 of 138
The Net Neutralization Potential for all North composites is negative,
averaging -50 tons CaCO3/1000t of tailings. The tailings will be acid
generating unless stored under water cover.
48 of 138
16. Mineral Resource and Mineral Reserve Estimates
4.0 g/t Au was used as an outlier cutoff grade for gold; 16 assays are
higher than the cutoff for gold.
Outlier high grade cutoffs were applied to both Copper and Go ld. 14
Copper assays were cut to 1.35% and 16 high grade Gold assays
were cut to 4 g/t. The cut grades were used in compositing.
49 of 138
Dilution effects of composites were studied. Dilution was calculated to
range, depending on litho type, between 5.4% and 13.5% for the 5 m
composites and 8% and 18.5% for the 15m composites. Metal losses
were calculated to be between 1.5% and 11.7% for the 5 m
composites, and 1.4% and 16.7% for the 15m composites, again
depending on litho type. The 5m composites were chosen which is
reasonable for this type of deposit.
0 = undefined lithologies;
5 = Hypogene monzodiorite;
7 = Takla BFP.
3-D solid wire frame models based on the drill hole intercepts were
provided by Northgate for the above Litho types. The composites
were then tagged with a Litho code according to the 3-D solid they
were included in on a majority (length) basis.
50 of 138
Since it was not possible to correct or re-survey the 18 suspect holes,
two models were built, one with all of the drill holes, where the suspect holes
had their down hole surveys corrected, and the second with the 18 suspect
drill holes removed (see Section 10, Down Hole Survey). The intention was
that these holes would be added back in later, after the corrected surveys
were verified. Subsequent mine planning work with the two models, using
the project base economic parameters, showed a significant reduction in the
economic pit size with the model with the holes missing. Similar pit sizes for
the two model were achieved with only a 5% difference in price. With this
sensitivity it was decided for the mine planning work, to use the model
including the corrected holes since the assays are valid and excluding the
holes is less representative than using the corrected holes.
The modelling process was identical for the 2 models. The 3 -D block
models included the following dimensions. The block height was chosen to
match the bench height for the mining equipment being used in the mine
plan.
51 of 138
The 3-D Block models for Kemess North include the following items:
52 of 138
CU Interpolated from 5 m composites using geology
matching based on LITHO code. CUKRG uses kriging,
CUIDW uses inverse distance weighting, and CUPLY
uses the polygonal method. The interpolation steps are
listed below.
CUEQ Calculated from the kriged copper and gold grades and
the project base design parameters.
AUEQ Calculated from the kriged copper and gold grades and
the project base design parameters.
The grade interpolation method and search distances for kriging were
based on the Geostatistical analysis and variogram parameters. A minimum
of 3 and a maximum of 16 composites were used for the interpolations with
maximum 4 composites from each quadrant. The maximum search for the
composites was limited to 200 m. The general steps were:
Separate IDW runs were made for AU & CU for LITHO codes 5, 6, &
7 (6 runs) using the specific interpolating parameters for each metal b y
zone. For blocks that meet the selection criteria the background values were
over written.
Separate Ordinary Kriging (OK) runs were made for AU & CU for
LITHO codes 5, 6, & 7 (6 runs) using the specific interpolating parameters
for each metal by zone. For blocks that meet the selection criteria the
background values were over written.
53 of 138
NCOMP - Number of composites used in the interpolation of a
block
The distances used in the resource CLASS item were deduced from
the ranges of the global indicator variogram determined for CU within L ITHO
5, 6, and 7 zones. These are listed in Table 16.2. The 50 m-distance used in
the measured classification was deduced from the range of the first structure
of the indicator variogram. The 150 m-distance used for the indicated
resource category was derived based on the range of the same variogram
corresponding approximately to 80% of the sill. The variogram range for the
second structure extends up to 285 m, but the correlation between
composites beyond 200 m is not significant.
1 2 3
Measured Resources Indicated Resources Inferred Resources
DIST = < 30 m DIST = 31-50 m DIST > 150
or and or
NCOMP = < 5 Other blocks that
DIST = 31-50 m or cannot be classified as
and 51 m < DIST < 150 m measured or indicated
NCOMP > = 5 and
NCOMP > = 5
or
51 m < DIS T < 200 m
and
LITHO = 5, 6, or 7
The following Resource and Reserve tables are based on the All Drill
Hole model and summarize the measured, indicated, and inferred
resources for the total Geological Model.
54 of 138
Table 16.3: Summary of Measured Resources
55 of 138
Table 16.5: Summary of Inferred Resources
The variation between the two models is considered very minor and it
falls within the margin of error for the resource calculation. The difference is
more pronounced when the effects of the economic design parameters are
applied in the ultimate pit limit qualification. This is discussed in Section (c)
below.
A great deal of effort has gone into the determination of the b ulk
density (referred to as SG) for the deposit. In total, more than 2,200
measurements have been performed and a weighted mean SG of 2.70 has
been determined. Four different sets of data are available, pre-1999
samples, as well as samples from 2000, 2002, and 2003. Sample material
has ranged from whole core samples 15 cm to 20 cm long for the 2003
work, quartered core for the 2000 and 2002 samples, and crushed coarse-
reject material for the pre-1999 samples. The 2003 lab work was by
Lakefield Research using their wax immersion method.
56 of 138
The range of SG values by bench was from 2.63 to 2.72 showing a weak
trend of increasing SG with depth.
As shown the estimated grades are very close to the modeled grades
for both copper and gold. The estimated tonnage is consistently lower than
the model but the variance is well within the margin of error for the resource
calculation.
(e) Reconciliation
57 of 138
original copper analyses are supported by production history (as reconciled
between the geologic model to blast hole and milled ore). Generally good
agreement for average grade copper values were observed while gold
exceeded expectations by an average of 15%. Annual reconciliation and
comparison of milled production to the block model showed good agreement
for copper.
The Reserves within the P634 pit design are generated from 3-D
block model incorporating the following steps:
58 of 138
Figure 11: Ultimate Pit Limit (P634)
Mill recovery factor; 88.8% for copper and 61.5% for gold.
59 of 138
Table 16.7: Reserve Estimate, Proven Category
Kemess North, Pit P634
The final pit indicates a strip ratio of 1:0.81 (tonnes ore to tonnes
waste).
60 of 138
17. Economic Pit Limits and Mine Plan
The entire mine planning for the Kemess North mineral property is
based on work done with MineSight a suite of software well proven in the
industry. This includes the 3-D block model described in Section 16, as well
as pit optimization, detailed design, and production scheduling.
In addition to the geology information used for the block model, other
data used for the mine planning includes the base economic parameters,
costs data from the February 2003 pre-feasibility study, Geotechnical slope
design parameters, metallurgical recoveries, and project design through put
targets. All design work is based on using the existing mining equipment
from Kemess South.
The economic pit limit was determined using the ePit optimization
routines in MineSight which are based on the Lerchs-Grossman algorithm
(LG) and have been run to account for time value discounting. The LG runs
against the 3D Block model evaluating the costs and revenues of the blocks
within potential pit shells. The routine expands downwards and outwards
from economic surface mineable mineralization, until the last increment is at
break-even economics.
The Base Design criteria for the ePit routine are listed in Table 17.1.
The mine costs were also increased by $0.02 per bench below 1,615
elevation to account for increased haulage and pit dewatering costs as the
pit deepens. The Net Minesite Price is the market price minus all offsite
charges for concentrate transportation, smelting, refining etc.
61 of 138
Slope parameters
Block Discounting
The economic effect of the time delay of ore revenues versus the cost
of stripping the over-lying waste is accentuated in the Kemess North ore
body because of the deep high grade zone and its effect on the economic pit
limits. This is often evaluated using the Whittle 4d or 4x analysis but an
equally effective method is to apply a discount factor to each block. In this
way for each sector of the pit wall, for each incremental shell, the time
discounted revenues from ore grade blocks are evaluated against the time
discounted overlying waste. For example , while examining the next
incremental skin or pit shell the LG at any point on the pit wall may show
that the revenues from the ore in the next block in that pit sector may be
greater than the cost overlying waste up to surface. However, when the time
delay between the revenues and the stripping costs are considered, the next
pit incremental expansion may not be economic. Although the actual years
that the revenues and costs are incurred is not known when the LG is
evaluating each incremental expansion, it is the difference between the two
time periods that determines if the sector is a cash positive expansion. The
discount rate for this LG analysis is 8% and assuming the final pit
pushbacks will be designed to keep the bench advance rate to 10 benches
per year.
Resource Class
62 of 138
Ultimate Pit Limit by Lerchs-Grossman Pit Optimization
The ultimate economic limit, pit shells are shown in Figure 12 & 13 on
an undiscounted and discounted basis and in section view in Figure 14. Ore
grade material from the Block model (NSR > 2.2) is also shown as a 3-D
solid in these figures.
Sensitivities
A series of LG pit designs were run keeping the costs the same but reducing
the metal prices. At low prices only low cost mineralized material is mineable
(high grade &/or low strip ratio) and as the prices are increased the pit limits
expand. These sensitivity cases are shown in Figure 15.
From the sensitivity graph the following points are noted:
In the undiscounted cases deep ore is mined in Pit 8 (or greater),
which is based on 96% of base prices. This gives a small downside
price cushion.
The deep ore is only mined with full Base Case pricing (Pit 10) or
greater in the discounted cases.
After opening up the deep pit, the pit expands fairly evenly as the
price increases.
From this analysis, the detailed pit designs were based on the
discounted P10 pit shell which corresponds to the full project base case
prices. A discount rate less than 8%, a bench advance greater than 10 per
year, or lower costs/higher prices than the project base parameters will
improve the economics within this pit shell. However the opposite is also
true.
63 of 138
Figure 12: Ultimate Pit Limits - Undiscounted
64 of 138
Figure 13: Ultimate Pit Limits - Discounted
65 of 138
Figure 14: Ultimate Pits Section View
66 of 138
Figure 15: Lerchs-Grossman Sensitivities
LG Sensitivity
(Pit 10 is Base Case Prices)
350000
300000
250000
50000
0
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15
-50000
Pit Number
Note: Net$ value is relative. Full cash flow analysis is required to determine
project NPV.
67 of 138
(b) Detailed Pit Designs
Selection of Pushbacks
68 of 138
Figure 16: Lerchs-Grossman Pit Low Prices
69 of 138
Figure 17: Lerchs-Grossman Pit Split Final Stage
70 of 138
Figure 18: Lerchs-Grossman Pit Base Price
71 of 138
Table 17.3: Slope Design Parameters (From Knight Pisold)
Included in the detailed designs are the high wall access roads.
These are designed at a maximum grade of 10%. The road allowance has
been made for haulage lanes and lateral berms suitable to meet regulatory
road width requirements for the Euclid R260 haul trucks in the mine fleet.
The majority of the roads are design as two way but for the bottom 2
benches of the ramp in each push back this has been reduced to single
lane. This will be suitable since traffic is reduced as the work space
becomes restricted. Ramp access is not designed for the last 2 benches of
Stage 2 & 3 under the assumption that internal ramps can be used for the
majority of the material and then the ramp is excavated upon retreat with a
backhoe and smaller salvage equipment from the ancillary fleet. The details
of the ramp design parameters are given Table 17.4 .
# of Width Grade
lanes
Main Ramp 2 30m. 10%
Last 2 benches of Ramp 1 22.6m. 10%
Last 2 benches of Pit Phase None NA NA
72 of 138
Subsequent to the pit design Knight Pisold reviewed the final P647
design with the combined designed overall slope angles and the high wall
ramps (see Appendix D). This review continues to indicate that the pit wall
slopes as designed, are aggressive but achievable with effective controlled
excavation techniques and groundwater depressurization with the exception
of the South slope. Because of the increased slope height with the current
design, the Factor of Safety (FoS) drops below 1.2 for a narrow sector of the
pit where the south pit wall cuts through the mountain peak. Design changes
will be required for the Feasibility Study to address this shortfall. Possible
solutions are to reduce the overall slope angle in this sector or to reduce the
overall slope height by excavating the top off the mountain peak. In the
worst case, reducing the slope by 100 m vertically, by removing the total
mountain peak will require 32 million tonnes of excavation. This would
increase the pit waste by 10%, which is within the accuracy of the Pre-
feasibility. A more thorough design will likely be able to reduce this extra
waste requirement. This design work will need to be addressed in the
Feasibility Study; however at this stage the Pre-feasibility pit design and
reserves are reasonably valid.
Phase Designs
The resultant 3 pit phase designs are given in Figures 20 to 22. The
upper benches in Phase 1 are shown as a separate Pre-strip phase which is
mined in the pre-production period to expose ore. This is shown in
Figure 19.
The reserve reports have the ore broken into grade bins for
production schedule optimization. These grade bins are based on the NSR
value of each block, which is calculated from the ore grades in each block,
the net smelter metal price, and the plant recovery for gold and copper. The
net smelter price is base on the base project parameter market price and
$US exchange rate, and offsite transportation, smelting, and refining
charges, etc. The NSR cutoff values ($/Tonne) used in the reserve reports
are set to report ore grade bins which cover full and incremental ore cost.
The incremental cutoffs are based on the fact that the LG only expands the
economic pit limit if the ore grade blocks can cover all costs (Decision
Blocks). Any blocks that are internal in the pit (Internal Blocks) will be mined
anyway to get to the decision blocks so they can still contribute positively to
cash flow if their metal content can cover costs downsteam of mining.
Different levels of downstream costs were considered to cover the overhead
costs and other high grade bins are also defined. The NSR cutoffs also
include a rehandle cost to allow for stockpiling. The Table 17.5 describes the
NSR cutoffs used in the reserve reports.
73 of 138
Figure 19: Pre-Strip Phase (P601)
74 of 138
Figure 20: Pit Phase 1 (P614)
75 of 138
Figure 21: Pit Phase 2 (P624)
76 of 138
Figure 22: Pit Phase 3 (P634)
77 of 138
Table 17.5: NSR Grade Cutoff Bins for Reserves
Phase Reserves
Pit reserves for these designs were calculated using the 3D block
model. The mining losses and dilution included in these reports are the
same as described in Section 16. The following tables include the material
by class, and Diluted grade values. Grades are based on the kriged value in
the Block Model and are in % for Copper and g/t for Gold. The HARD value
is the Bond Work Index (BWI) and is used in scheduling to vary the annual
ore production through the mill. Tables 17.6, 17.7, 17.8 and 17.9 list the
reserves for each mining phase.
78 of 138
Table 17.6: Reserves for Pre-Production Pit (P601)
In situ In situ Run of
Zone Zone Ore Ore Mine Diluted Grades
Name No. Cutoff (BCMS) (Tonnes) (Tonnes) NSR CU AU KRG Hard
KRG
PROV 1 0.0 2.38 90,840. 245,906. 236,743. 2.276 0.0604 0.1658 13.90
2.38 3.38 521,400. 1,379,737. 1,327,976. 2.873 0.0787 0.2036 14.23
3.38 4.03 239,580. 632,398. 605,476. 3.648 0.1025 0.2522 14.42
4.03 5.00 103,680. 268,863. 260,118. 4.380 0.1175 0.3114 14.15
>= 5.00 30,000. 76,920. 73,074. 5.408 0.1390 0.4092 14.70
Totals: 985,500. 2,603,824. 2,503,387. 3.235 0.0885 0.2290 14.25
PROB 2 0.0 2.38 57,240. 150,376. 145,989. 2.266 0.0506 0.1873 14.32
2.38 3.38 356,101. 952,520. 929,950. 2.957 0.0809 0.2066 14.05
3.38 4.03 132,960. 350,431. 339,173. 3.696 0.1037 0.2522 14.27
4.03 5.00 100,680. 262,046. 253,642. 4.470 0.1233 0.3104 14.37
>= 5.00 29,520. 75,962. 79,994. 5.329 0.1366 0.3515 13.26
Totals: 676,501. 1,791,335. 1,748,748. 3.371 0.0915 0.2355 14.13
Summary 0.0 2.38 148,080. 396,281. 382,731. 2.272 0.0567 0.1740 14.06
79 of 138
Table 17.7: Reserves for Phase 1 Pit (P614)
In situ In situ Run of
Zone Zone Ore Ore Mine Diluted Grades
Name No. Cutoff (BCMS) (Tonnes) (Tonnes) NSR CU AU Hard
KRG KRG
PROV 1 0.0 2.38 1,151,040. 3,050,816. 2,907,671. 2.291 0.0696 0.1466 14.36
2.38 3.38 8,361,240. 22,229,232. 21,161,620. 2.2905 0.0908 0.1800 14.69
3.38 4.03 5,503,920. 14,656,754. 13,974,028. 3.702 0.1185 0.2219 14.46
4.03 5.00 9,423,780. 25,117,896. 23,882,362. 4.518 0.1447 0.2714 14.43
>= 5.00 13,851,360. 37,573,680. 35,745,112. 5.995 0.1932 0.3571 14.46
Totals: 38,291,340. 102,628,376. 97,670,792. 4.526 0.1448 0.2722 14.50
PROB 2 0.0 2.38 338,700. 896,144. 868,563. 2.296 0.0691 0.1468 14.19
2.38 3.38 3,033,540. 8,051,396. 7,723,994. 2.917 0.0889 0.1848 14.34
3.38 4.03 2,401,800. 6,418,572. 6,124,266. 3.708 0.1142 0.2330 14.35
4.03 5.00 3,736,440. 10,059,201. 9,562,505. 4.519 0.1437 0.2743 14.32
>= 5.00 4,249,380. 11,568,613. 11,019,937. 5.767 0.1853 0.3441 14.30
Totals: 13,759,860. 36,993,924. 35,299,264. 4.363 0.1377 0.2662 14.32
Summary 0.0 2.38 1,489,740. 3,946,960. 3,776,234. 2.292 0.0695 0.1467 14.32
2.38 3.38 11,394,780. 30,280,628. 28,885,614. 2.908 0.0903 0.1813 14.59
3.38 4.03 7,905,720. 21,075,326. 20,098,294. 3.704 0.1172 0.2253 14.43
4.03 5.00 13,160,220. 35,177,096. 33,444,868. 4.518 0.1444 0.2722 14.40
>= 5.00 18,100,740. 49,142,292. 46,765,048. 5.941 0.1913 0.3540 14.42
Totals: 52,051,200. 139,622,304. 132,970,048. 4.483 0.1429 0.2706 14.45
80 of 138
Table 17.8: Reserves for Phase 2 Pit (P624)
In situ In situ Run of
Zone Zone Ore Ore Mine Diluted Grades
Name No. Cutoff (BCMS) (Tonnes) (Tonnes) NSR CU KRG AU KRG Hard
PROV 1 0.0 2.38 1,840,560. 4,858,974. 4,622,290. 2.284 0.0608 0.1675 12.87
2.38 3.38 12,158,041. 32,365,262. 30,795,542. 2.864 0.0780 0.2056 12.80
3.38 4.03 6,395,820. 17,037,772. 16,209,376. 3.700 0.1083 0.2472 12.81
4.03 5.00 10,825,404. 28,724,876. 27,321,516. 4.528 0.1416 0.2804 12.83
>= 5.00 21,917,108. 57,991,944. 55,159,684. 6.906 0.2197 0.4183 13.79
Totals: 53,136,932. 140,978,816. 134,108,400. 4.947 0.1523 0.3120 13.22
PROB 2 0.0 2.38 1,094,100. 2,893,205. 2,762,639. 2.284 0.0588 0.1720 13.17
2.38 3.38 5,155,500. 13,722,186. 13,064,263. 2.840 0.0753 0.2088 12.97
3.38 4.03 2,102,220. 5,656,791. 5,377,084. 3.699 0.1134 0.2349 13.06
4.03 5.00 4,215,780. 11,245,503. 10,689,494. 4.544 0.1429 0.2797 12.84
>= 5.00 10,933,680. 28,903,346. 27,511,422. 7.031 0.2236 0.4255 13.90
Totals: 23,501,280. 62,421,032. 59,404,904. 5.139 0.1588 0.3225 13.40
Summary 0.0 2.38 2,934,660. 7,752,179. 7,384,929. 2.284 0.0600 0.1692 12.99
2.38 3.38 17,313,540. 46,087,448. 43,859,804. 2.857 0.0772 0.2065 12.85
3.38 4.03 8,498,040. 22,694,564. 21,586,460. 3.700 0.1096 0.2441 12.87
4.03 5.00 15,041,184. 39,970,380. 38,011,008. 4.532 0.1420 0.2802 12.83
>= 5.00 32,850,788. 86,895,288. 82,671,104. 6.948 0.2210 0.4207 13.83
Totals: 76,638,208. 203,399,840. 193,513,296. 5.006 0.1543 0.3152 13.27
81 of 138
Table 17.9: Reserves for Phase 3 Pit (P634)
In situ In situ Run of
Zone Zone Ore Ore Mine Diluted Grades
Name No. Cutoff (BCMS) (Tonnes) (Tonnes) NSR CU KRG AU KRG Hard
PROV 1 0.0 2.38 649,560. 1,729,989. 1,643,489. 2.277 0.0729 0.1371 12.77
2.38 3.38 3,219,300. 8,555,371. 8,130,735. 2.839 0.0977 0.1543 12.83
3.38 4.03 1,718,700. 4,572,714. 4,351,908. 3.692 0.1313 0.1896 12.98
4.03 5.00 2,849,580. 7,468,683. 7,101,512. 4.522 0.1608 0.2328 12.89
>= 5.00 10,616,931. 28,251,538. 26,881,244. 8.599 0.2817 0.5005 13.54
Totals: 19,054,072. 50,578,296. 48,108,888. 6.364 0.2120 0.3619 13.24
PROB 2 0.0 2.38 1,157,400. 3,055,086. 2,913,293. 2.274 0.0635 0.1593 13.17
2.38 3.38 3,166,020. 8,312,042. 7,902,706. 2.796 0.0908 0.1652 12.96
3.38 4.03 1,701,480. 4,410,786. 4,190,247. 3.690 0.1293 0.1950 12.58
4.03 5.00 2,039,940. 5,367,272. 5,098,908. 4.521 0.1620 0.2301 12.89
>= 5.00 6,006,480. 16,069,363. 15,294,082. 8.881 0.2862 0.5285 13.69
Totals: 14,071,320. 37,214,548. 35,399,236. 5.736 0.1878 0.3345 13.24
Summary 0.0 2.38 1,806,960. 4,785,074. 4,556,782. 2.275 0.0669 0.1513 13.03
2.38 3.38 6,385,320. 16,867,414. 16,033,441. 2.818 0.0943 0.1596 12.89
3.38 4.03 3,420,180. 8,983,500. 8,542,155 3.691 0.1303 0.1923 12.78
4.03 5.00 4,889,520. 12,835,954. 12,200,420. 4.521 0.1613 0.2317 12.89
>= 5.00 16,623,411. 44,320,900. 42,175,328. 8.701 0.2833 0.5107 13.59
Totals: 33,125,392. 87,792,840. 83,508,120. 6.098 0.2017 0.3503 13.24
82 of 138
In Situ In Situ Run of Waste Grades
Bench Ore Ore Mine Total ROM Diluted CU KRG AU KRG
Toe (BCMS) (Tonnes) (Tonnes) (Tonnes) S/R NSR Hard
1390.0 1,762,440. 4,645,725. 4,421,268. 1,325,403. 0.30 4.580 0.1596 0.2435 12.39
1375.0 1,783,379. 4,750,944. 4,519,660. 1,110,662. 0.25 4.819 0.1710 0.2489 12.65
1360.0 1,724,031. 4,632,754. 4,402,684. 957,892. 0.22 5.363 0.1920 0.2733 12.92
1345.0 1,686,000. 4,506,998. 4,286,347. 932,493. 0.22 5.618 0.1969 0.2959 13.09
1330.0 1,562,640. 4,206,172. 4,006,825. 756,573. 0.19 6.308 0.2219 0.3284 13.25
1315.0 1,581,120. 4,304,193. 4,101,512. 438,931. 0.11 7.283 0.2545 0.3824 14.42
1300.0 1,527,660. 4,104,676. 3,907,272. 229,999. 0.06 8.489 0.2887 0.4675 14.70
1285.0 1,481,820. 3,971,514. 3,776,070. 216,457. 0.06 9.140 0.2974 0.5377 14.55
1270.0 1,229,040. 3,301,376. 3,142,572. 164,271. 0.05 10.745 0.3290 0.6819 14.44
1255.0 1,347,780. 3,622,258. 3,447,409. 191,753. 0.06 12.741 0.3838 0.8242 14.31
1240.0 963,720. 2,607,249. 2,476,886. 169,731. 0.07 13.436 0.4058 0.8686 14.26
1225.0 753,540. 2,050,034. 1,956,928. 157,767. 0.08 11.845 0.3627 0.7483 14.17
1210.0 484,980. 1,320,256. 1,263,639. 65,798. 0.05 8.760 0.2811 0.5204 13.68
1195.0 380,280. 1,035,709. 983,924. 75,626. 0.08 8.806 0.2882 0.5149 13.44
1180.0 112,320. 305,762. 290,474. 18,799. 0.06 9.856 0.3291 0.5605 13.36
1165.0 62,280. 163,472. 155,299. 27,935. 0.18 9.424 0.3098 0.5478 13.30
Total 33,125,392. 87,792,840. 83,508,112. 107,500,072. 1.29 6.098 0.2017 0.3503 13.24
Basic Criteria
The production schedule for Kemess North is run from the Pit reserve
files listed above. All production will be from the owners fleet except for
minor tonnages for the small initial benches of each pushback. These will
require smaller specialized equipment to operate on the steep original
ground at the top benches. The major mining equipment from Kemess
South will be transferred to Kemess North as ore and waste production is
reduced in Kemess South. The full integrated Kemess South, Kemess North
production schedule is included in Section 22C. To meet the higher strip
ratio requirements additional haul trucks will be purchased. The production
equipment fleet used in the Life of Mine Production schedule is listed in
Table 17.10. This schedule is based on the annual Mill Feed ore production
listed in Table 17.11. The ore targets are adjusted each year to reflect the
ore hardness and anticipated SAG mill through put according to the HARD
(BWI) value in the Pit Reserves. The mill feed in some years includes
material from stockpiles and Mined ore in some years is sent to stockpile.
The full Kemess North production schedule is given in Section 22C as part
of the Integrated Kemess South/Kemess North Schedule .
83 of 138
Table 17.10 Major Mine Equipment Fleet
Unit # of Location
Units
Shovels P&H 2800 1 Moves Kemess South to Kemess North 4 th
Qtr 2006
P&H 2300 1 Moves Kemess South to Kemess North
early 2010
Hit 5500 1 Moves Kemess South to Kemess North
start of 2006
Drills P&H XP100 1 Moves Kemess South to Kemess North
start of 2010
IR Viper 1 Moves Kemess South to Kemess North
start of 2006
Haul Trucks Euclid R260 13 Existing Fleet in Kemess South start
of 2004
3 Add 3 new trucks in 2005 for
Kemess South
5 Move 5 trucks to Kemess North start
of 2006
4 Add 4 new trucks start of 2006 for
Kemess North
7 Move 7 trucks to Kemess North 4 th
Qtr 2006
1 Add 1 new trucks start of 2016 for
Kemess North
Total 19,072 19,115 14,949 5,248 29,942 31,003 30,961 28,784 29,489 32,010 36,490 35,510 33,610 30,710
Mill ktonnes
Feed
Cu % 0.217 0.224 0.265 0.195 0.159 0.182 0.169 0.144 0.119 0.120 0.122 0.133 0.162 0.177
Au g/t 0.691 0.669 0.777 0.544 0.440 0.451 0.409 0.280 0.260 0.256 0.256 0.270 0.314 0.333
84 of 138
18. Interpretation and Conclusions
85 of 138
statistics analysis, grade interpolation, and mineral quantity
calculations were done by Abdullah Arik of Mintec a Certified Geo-
Statistician and a Qualified Person. GR Tech confirms that this
method of modelling is appropriate for the Kemess North deposit and
that resultant Resource and Reserve quantities are to an acceptable
industry standard.
Economic Pit Design The ultimate economic pit limit is based on the
Lerchs-Grossman (LG) pit optimization routine with time value
discounting assigned to the blocks. The price, cost, and recovery
inputs to the LG are reasonable and overall slope angles have been
deemed to be adequate by Geotechnical specialists, provided proper
wall control measures are taken during operations. The time
discounting of the blocks is an important aspect since parts of the
mineralized zone are deep. Sensitivity analysis a round the Base
Price parameters for the Project show little upside potential and
considerable downside risk. If prices are dropped to 85% of the target
level the lower parts of the ore body are not economic. The LG pit
optimization algorithm is an industry standard for evaluation of
economic pit limits and the method used to time discount the blocks
adequately addresses the economic impact of the deep
Mineralization.
Detailed Pit Design The Detailed pit design includes a Pre-stripping
phase plus three pus hbacks to mine out to the ultimate pit limit
determined by the LG. These pushbacks have been designed
following the Geo-technical consultants design criteria. The final pit
limit design (P634) has been reviewed by Knight Pisold. A sector of
the South pit wall has been found to have an inappropriate Factor of
Safety and will need to be redesign for the Feasibility Study. The
effect of this redesign will be limited but will increase the waste
mining costs. The magnitude is within the accuracy of the Pre-
Feasibility Study and is not likely to affect the economic viability of the
pit design. This assumption will need to be confirmed in the
Feasibility Study.
Milling Metallurgical test work was performed on drill hole samples
taken from within or in close proximity to the pit limits. The mill feed
from Kemess North will be similar to Kemess South Hypogene. Hatch
has confirmed that the test work on the met samples is representative
and accurate and the resultant process performance design criteria
for gold and copper recovery and plant throughput are reasonable for
project planning purposes.
Production Schedule The production schedule is based on the
detailed pit designs and the specified mining equipment to meet the
ore production targets in the plan. Mining production levels are varied
year to year to defer waste cost into the future. While this makes
86 of 138
operations management difficult it is possible. GR Tech confirms that
this operating schedule is achievable with the equipment as specified.
Capital and Operati ng Cost estimates The basis of most of the
operating costs are the current operations at Kemess South. The
capital cost of much of the existing equipment types also comes from
Kemess South experience. As such, these estimates have a high
level of assurance. Capital estimates for much of the facilities and
infrastructure for the Kemess North area have been provided by
others to a Feasibility level of accuracy as well. However additional
geo-technical information and condemnation drilling is still needed for
the underground conveyor way. Until these are completed, the costs
are only submitted as Pre-feasibility accuracy. Other aspects of the
mining costs such as truck cycle times, waste dumping details, and
capital and replacement costs for the mining equipment are also only
at Pre-feasibility study level. For these reasons the current Kemess
North project cost estimates are being called a Pre-Feasibility Study
estimate. Design revisions will increase the waste mining costs and
the subsequent cost of releasing ore.
Environmental and Permitting The Environmental planning for the
project is well advanced. The operating criteria and costs to meet
sound environmental operating practices and to meet or exceed
regulatory requirements have been included in the Kemess North
plan. With this the required operating permits should be granted.
The future estimates of metal prices, the US exchange rate, and
future cost for goods and services beyond the control of Northgate are as
stated. Accurate prediction of these future financial parameters is beyond
GR Techs capability. The values used in this evaluation are not un-
reasonable.
87 of 138
19. Recommendations
Upgrade the estimate for the underground ore conveyor from Kemess
North to the existing mill. This will require drilling for condemnation
and geotechnical analysis.
Run detailed truck haul simulations for the truck haul cycles for ore
and waste hauls.
Obtain vendor budgetary quotes for a wall control drill and for
ongoing maintenance and repair parts and rebuild costs for the
existing mining fleet.
Re-design details of the pre-stripping requirements and seek
contractor budgetary quotes.
If possible re-survey with the Flex-IT tool, as many of the 18 holes
with suspect down hole surveys, as possible.
(b) For Construction and Detailed design
88 of 138
20. References
Cann, R.M., Summary and Review of 1987 and 1988 Exploration Results
Kemess Property; private report for El Condor Resources, November 1988
Diakow, L.J., Panteleyev, A., Schroeter, T.G., Geology of the Early Jurassic
Toodoggone Formation and Gold Silver Deposits in the Toodoggone River
Map Area, Northern British Columbia, B.C. Geological Survey Branch
Bulletin 86, 1993
89 of 138
Diakow, L.J., Geology of the Southern Toodoggone River and Northern
McConnell Creek Map Areas, North-Central British Columbia; BCEM, Map
2001-1, 1:50000 Scale
Klohn Crippen, Kemess North, Tailings and Waste Rock Management. 2003
Massey, N.D.W., MacIntyre, D.G. and Desjardins, P.J. Digital Map of British
Columbia: Tile NO9 North Central B.C., B.C. Ministry of Energy and Mines,
Geofile 2003-18, - BC Geological Survey
Monger, J.W.H., The Triassic Takla Group in McConnell Creek Map Area,
North Central British Columbia, Geological Survey of Canada Paper,
76-29, 1977
90 of 138
Northgate Exploration Limited 2003 Annual Report, April 2004
Rebagliati, C.M., Bowen, B.K, Copeland, D.J., Niosi, D.W.A., Kemess South
and North Porphyry Gold-Copper Deposits Northern British Columbia, in
Porphyry Deposits of the Northwestern Cordillera of North America, CIM
Special Volume 46, pp 377-397, 1995
91 of 138
21. Statement of Qualifications
_____________________
J.H. Gray PEng
92 of 138
93 of 138
Robert J. Morris PGeo
_____________________
R.J. Morris, MSc, PGeo
94 of 138
95 of 138
Kenneth W. Major; PEng
_____________________
K.W. Major; PEng
96 of 138
97 of 138
Abdullah Arik
_____________________
Abdullah Arik
98 of 138
99 of 138
22. Additional Information
The Kemess Mine currently operates from one open pit. The pit is
mined on 15 m benches and is split into three phases. The final wall is
designed with a combined single - and double -bench configuration. The wall
angles range from 40-51 degrees and the pit ramp widths are 35 m and
exceed the design width as defined by the Health, Safety and Reclamation
Code for Mines in British Columbia for the equipment utilized at the
operation. All roads have been designed for a maximum grade of 10%.
100 of 138
380 km via gravel road to a trans-loading facility located in Mackenzie, BC
next to a rail spur. The concentrate is then loaded into covered gondola
railcars and transported to Norandas Horne smelter in Rouyn-Noranda,
Quebec.
101 of 138
of 12 years beyond the current life-of-mine plan for the current Kemess
operations.
The current mining and milling levels will continue through mid 2006
with all ore being produced from the Kemess South pit to feed the plant. To
meet the future needs of the Kemess South pit, three more haul trucks will
be added to the fleet in 2005. As the Strip ratio declines in Kemess South
mining equipment will be released and will be transferred to Kemess North.
Kemess North pre-stripping will begin in the second half of 2005 with small
scale contract development equipment preparing large enough initial
working areas to accommodate the large mining equipment from Kemess
South .The first shovel will be transferred at the start of 2006 along with a
blast hole drill and 5 trucks from the existing fleet. Initial mine waste will be
used for construction of pads for the crusher stockpile site and infrastructure
required for the Kemess North operations. This initial material will be NAG
material from the northern pit limit on Douglas Ridge. Mine waste will also
be used to fill a haul road to the waste dump site at Duncan Lake.
Power line and road link from Kemess North to Kemess South.
102 of 138
The waste rock and tailings impoundment facilities at Duncan Lake
will be developed during 2005 and 2006 and a tailings pipeline will be
constructed to connect the expanded Kemess South mill to the facility.
In the fourth quarter of 2006 the first ore from Kemess North will be
delivered to the Kemess South mill and ore production from the Kemess
South pit will be reduced to 11 million tonnes per year until reserves are
exhausted in early 2010 at which point Kemess North production will be
ramped up to fill the additional mill capacity.
2004-2009 2010-2020
KS KN Total KN
Ore & Waste Mined (MM tonnes) 27.5 30.3 57.9 57.1
103 of 138
Table 22.3: Metal Recovery Summary
(f) Contracts
104 of 138
Concentrate Treatment
Kemess is in the last year of a three year contract with Noranda Inc. for the
sale of its full production of copper concentrate. Negotiations for a contract
extension have begun and the company is also looking at other destinations
for the Kemess concentrate.
Electricity
Concentrate Trucking
Kemess has a long term contract with Lomak Bulk Carriers who
provide truck transportation services to the mine. Concentrate is trucked to
the MacKenzie trans-loading facility and mill grinding media, diesel fuel and
other supplies are backhauled to the mine.
Explosives
Kemess has a long-term supply with BXL Explosives who supply explosives
and related products to the Kemess mine.
Tires
Kemess has a long-term agreement with Fountain Tire who supply tires for
Kemess fleet of 13 haul trucks as well as various other vehicles.
Collective Agreement
105 of 138
between the company and its employees. The current three year agreement
expires on December 31, 2004.
Closure Bonding
Kemess Mines Ltd. has posted a Cdn$13 million dollar closure bond
with the Province of British Columbia to fund the eventual closure of the
Kemess South mine. The agreement with the province calls for Northgate to
add $1 million dollars to the bond on December 31st of each year until the
estimated $19 million dollar cost of closing the mine has accrued. For the
purposes of the Kemess North development it has been assumed that the
full amount of this bond will remain in place until the conclusion of the
Kemess North mine life.
Kemess South
The current reclamation bond for the Kemess Mine has been set at
Cdn $12 million and is in good standing. Reclamation and remediation are
ongoing at the mine site and are budgeted items.
Kemess North
106 of 138
under water in a saturated environment. Over sixteen alternative tailings and
waste rock disposal options were assessed by Klohn Crippen. The
recommended alternative is to store all of the tailings and potentially acid
generating waste rock below water in Duncan Lake, with construction of a
90 m high dam at the north end of the lake, a 35 m high dam at the
southwest end and 10 m high dam at the southeast end.
Geotechnical drilling and site investigations were carried out for the
Duncan Lake option and design studies have been carried out to the
feasibility study level. A corresponding Bill of Quantities and Engineers Cost
Estimate have been prepared for the study and submitted to Kemess.
Water Management
Environmental Considerations
Closure
107 of 138
The earth fill dams are designed to maintain the free water pond
(Duncan Lake) at least 300 m upstream of the dam. The dams are also
designed with low gradient core zones and robust fill sections to reduce long
term dam safety and erosion concerns.
The open pit will infill with water over a period of up to 100 years. The
water could become acidic due to oxidation of rock in the remaining pit
walls. If the acidity and metal loading exceeds the pre-mining conditions (the
area currently generates acid drainage and metal loadings) it will be
necessary to treat the water in the open pit lake with a lime dosage system.
The formal project review was initiated with the submission of the
Kemess North Project Description to the BC Environmental Assessment
Office (EAO) in October, 2003. The EAO has the responsibility to notify all
stakeholders and disseminate relevant project information during the review
process. The primary government agencies involved are as follows:
First Nations: Kwadacha FN, Gitxsan FN, Takla Lake FN, and Tsay
Keh Dene FN.
108 of 138
The Reclamation & Closure Plan, and
(i) Taxes
Property Taxes
During the mining of Kemess South and Kemess North under the metal
price and foreign exchange rate assumptions used in this report, Kemess
Mines Ltd. will not pay federal or provincial income taxes due to the large
109 of 138
quantity of tax shields currently available to the Corporation and the shields
that will result from future capital expenditures.
Mining and milling costs for the Kemess North and Kemess South
operations have been estimated using actual 2003 costs incurred at the
Kemess South complex as well as a detailed analysis from first pri nciples of
the activities that will take place in each year of the pre-feasibility study mine
plan from 2004 through 2020. Site G&A costs are fixed costs that have been
estimated based on 2004 budget projections and adjusted in each year for
the tonnes of mill throughput. Table 22.5 summarizes the mine operating
costs during the period of combined operation and the period during which
the Kemess North pit is the only source of ore for the mill.
110 of 138
Project capital to develop Kemess North totals US$165 million dollars
and sustaining capital over the combined Kemess North/Kemess South
mine life totals US$88 million dollars. Project capital will be spent in 2005
and 2006 and sustaining capital for replacement and rebuilding of capital
equipment and construction of tailings and waste rock impoundment
facilities will be spent over the combined 17 year life of the mine.
Exchange Rate
Cdn$/US$1.45
Metal Prices
Gold US $375/oz
Copper US $1.00/lb
Silver US $5.00/oz
111 of 138
Table 22.6: IRR Sensitivity to Metal Prices
Copper Price
Two specific areas within the Kemess claims that have already
showed promise are the Nugget Zone and the area to the southwest to the
112 of 138
existing Kemess South pit. At the Nugget Zone, one drill hole, only 0.5
kilometers from the proposed Kemess North pit boundary, contained 420
metres of porphyry mineralization at 0.13% copper and 0.38 gr/mt gold
starting at a depth of 25 meters. To the southwest of the current Kemess
South pit there are over 25 million tonnes of indicated resources grading
0.49 gr/mt gold and 0.16% copper and a geologic setting that has the
potential to host additional higher grade porphyry mineralization. Both these
areas have the potential to add ore to the Kemess operation in the future.
113 of 138