Extension of Time Analysis Lucif

This document analyzes a request from a contractor for an extension of time to complete a construction project. It lists 5 reasons for delay in the project and the number of contract days requested for each reason. The consultant evaluated each reason and recommended reduced contract days, totaling 23 days, based on the actual performance and issues on site. Payment delay was not accepted as a valid reason since it was not previously justified in earlier extension requests.

Uploaded by

Mesfin Derbew
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOC, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
166 views4 pages

Extension of Time Analysis Lucif

This document analyzes a request from a contractor for an extension of time to complete a construction project. It lists 5 reasons for delay in the project and the number of contract days requested for each reason. The consultant evaluated each reason and recommended reduced contract days, totaling 23 days, based on the actual performance and issues on site. Payment delay was not accepted as a valid reason since it was not previously justified in earlier extension requests.

Uploaded by

Mesfin Derbew
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOC, PDF, TXT or read online on Scribd
You are on page 1/ 4

Document N: 004

SWS CONSULTANCY
?e wK= ?e cMc=
Extension of Time Analysis Issue N: 004

PROJECT: Construction of Koye Feche Condominium Site Sewerage System (Lot-1)


CLIENT : Addis Ababa Housing Project Office (AAHPO)
CONSULTANT: SWS Consultancy
CONTRACTOR : LUCI ENGINEERING PLC
Consultant
Requested
Evaluated
No Reason For Delay Reference CD Remark
CD
1 Right of way problem Luci/112/344/08
due to surplus guard Dated 14/04/2016,
house, construction SWS/HCPO-KF/LOT-1/012/16
material and water Dated 10/05/2016
Obstructions along main sewer line:
tanker. Luci/145/365/09
Parcel 5 = 150m (Store, Aggregate, HCB
Dated 28/09/2016 and Wood)
Luci/154/365/09 The required days calculated to accomplish
Dated 7/12/2016 35 3 sewer line for the above remaining main
SWS/HCPO-KF/Lot-1/052/16 line is based on the contract period
Dated 13/12/2016 allocated for the contractor to accomplish
Luci/158/365/9 the actual total main line and manhole
works.
Dated 06/03/2017
SWS/HCPO-KF/Lot-1/067/2017
Dated 23/03/2017

_______________________________________________________________________________________
TimeExtensionAnalysissheet
Document N: 004
SWS CONSULTANCY
?e wK= ?e cMc=
Extension of Time Analysis Issue N: 004

Consultant
Requested
Evaluated
No Reason For Delay Reference CD Remark
CD
2 Connection outlet Luci/145/365/09 15 blocks have no sanitary outlets.
problems Dated 28/09/2016 The locations of connection outlet problems:
Luci/154/365/09 Parcel 3, Blocks 162,163,164 and 165.
Dated 07/12/16 Parcel 7, Block 82.
SWS/HCPO-KF/Lot-1/052/16 Parcel 8, Blocks 89 & 90.
Parcel 11, Blocks 126,127,130,131,132 and
Dated 13/12/2016 66 10 133.
Luci/158/365/09 Parcel 12, 2 New Blocks
Dated 06/03/2017 The required days calculated to accomplish
sewer line for the above blocks is based on
SWS/HCPO-KF/Lot-1/067/17 contract period originally allocated for the
Dated 23/03/2017 contractor to accomplish connection work for
the total 191 blocks..
3 Road Finish Level(RFL) Luci/158/365/09
The required days calculated to accomplish
have not been obtained Dated 06/03/2017 extension of manhole to the required road finish
from AACRA SWS/HCPO-KF/Lot-1/067/17 level for maximum of 57 manholes is about 8
Dated 23/03/2017 days and is based on the actual contractor's
66 8 performance on site. This activity can be
accomplished with a separate crew in parallel
with other activities like mainline and sanitary
connection works.

_______________________________________________________________________________________
TimeExtensionAnalysissheet
Document N: 004
SWS CONSULTANCY
?e wK= ?e cMc=
Extension of Time Analysis Issue N: 004

Consultant
Requested
Evaluated
No Reason For Delay Reference CD Remark
CD
4 Land ownership Luci/145/365/09
problem, along Dated 28/09/2016
around the building Luci/154/365/09
sewer lines Dated 07/12/16 There is 1 block of which the around building
sewer line work started but the contractor has
SWS/HCPO-KF/Lot-1/052/16 been forced to halt the construction. Two days
66 2 are required to complete the remaining works
Dated 13/12/2016 thereof provided the right of way problem can
Luci/158/365/09 be solved. This work can also be accomplished
Dated 06/03/2017 by a separate crew.
SWS/HCPO-KF/Lot-1/067/17
Dated 23/03/2017

5 Payment Delay Luci/157/365/09 15 - This claim had not been raised in time
Dated 27/02/2017 extension no.1,2 and 3 and was not justified in
previous time extension requests. Hence, it
Luci/160/365/09 cannot be reason for delay from the beginning
Dated 23/03/2017 of project. For the referred letter
refno.Luci/157/365/09 dated 27/02/2017 and
letter ref.no Luci/160/365/09 dated 23/3/17,
there are two reason pending payment no.3.
The performance bond supplied by the
contractor has been expired and

_______________________________________________________________________________________
TimeExtensionAnalysissheet
Document N: 004
SWS CONSULTANCY
?e wK= ?e cMc=
Extension of Time Analysis Issue N: 004

Consultant
Requested
Evaluated
No Reason For Delay Reference CD Remark
CD
requested to renew in the mean time
and there has been dispute and
consequent discussions for execution of
works to be included or excluded
Total 279 9

Note: The contractor can accomplish the whole activities within 9 days by forming different crews provided that the above mentioned right of
way problems are fully solved. The around building sewer line, main sewer line and the sewer connection works can be executed concurrently by
assigning different crews. Hence, the maximum CD (9) has been taken for the above major activities. However, the contractor should have
accomplished leveling and clearing; channeling; manhole cover placing at some locations; DCI cover supply and installation; flushing and system
testing for all other completed sections and the contractor shall not be excused for these part of works and later liquidated damage will be applied
until these outstanding activities are completed. In the meantime, the Client should solve all above remaining right of way problems and ready
the site to the contractor in short time to avoid further time extension.

CD:-Calendar days.

_______________________________________________________________________________________
TimeExtensionAnalysissheet